U.P. COOPERATIVE FEDERATION LTD. Vs M/S. THREE CIRCLES
Case number: C.A. No.-002732-002732 / 2001
Diary number: 10925 / 2000
Advocates: RANI CHHABRA Vs
MANJULA GUPTA
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
U.P. COOPERATIVE FEDERATION LTD. v.
M/S. THREE CIRCLES (Civil Appeal No. 2732 of 2001)
SEPTEMBER 10, 2009 [TARUN CHATTERJEE AND HARJIT SINGH BEDI, JJ.]
[2009] 14 (ADDL.) S.C.R. 310
The Judgment of the Court was delivered by
TARUN CHATTERJEE, J. 1. On or about 14th of December, 1983, a tender was floated by the U.P. Cooperative Federation
Ltd. (hereinafter referred to as “the Federation”) for construction of
4000 Metric Ton cold storage at Vashi, New Mumbai. The tender
document mentioned the time of completion as twelve months. M/s
Three Circles – the respondent herein, submitted a tender to get
the contract. In the year 1984, a contract was executed with M/s
Three Circles. Clause 10[f] of the Contract Agreement reads as
follows:
“It is further agreed that all disputes or differences arising
out of the provisions as contained in the preceding
paragraphs, [a] to [f] of Clause 10 shall be referred to the
Managing Director of Employer, whose decision shall be final,
conclusive and binding and shall not be referred to arbitration
or to any court of law.”
Clause 11 of the contract reads as follows:
“All disputes and differences between the parties
regarding the construction or interpretation of any of the terms
and conditions herein contained or conditions of contract being
the integral part of this contract [except those which are
subject matter of the decision of Managing Director of the
Employer or/are expressly forbidden and excluded from being
referred to arbitrator under any clause by the contract
documents and such decision shall be final, conclusive and
binding upon the parties hereto] or determination of and
liability or any disputes of whatever nature whether during the
course of progress or work or thereafter or after recession of
the contract, shall be referred to the arbitration as provided in
the condition No.51 of the Heading “scope and performance”
in the Tender documents and shall be deemed to be reference
within the relevant provisions of the Indian Arbitration Act,
1940, and or any statutory modification of enactment there
under.”
Clause 51 of the General Conditions of contract provided for
arbitration. This clause reads as follows:
“51. The contractor will become nominal member of the
Federation and will abide by the rules and regulation laid down
from time to time. Except where otherwise provided for in the
contract all questions and disputes relating to the meaning of
the specifications, designs, drawings and instructions herein
before mentioned and as to the quality of workmanship or
materials used on the work or as to any other questions, claim,
right, matter or thing whatsoever in any way arising out of or
relating to the contract, designs, drawings, specifications,
estimates, instructions, order or these conditions or otherwise
concerning the works, or the execution or failure to execute the
same whether arising during the progress of the work or after
the completion or abandonment thereof shall be referred to the
sole arbitration of the Registrar Cooperative Societies Uttar
Pradesh and if the Registrar is unable to or unwilling to act, to
the sole arbitration of some other person appointed by the
Managing Director, willing to act as such arbitrator. There will
be no objection if the arbitrator so appointed is an employee of
Federation and that he had to deal with the matters to which
the contract relates and that in the course of his duties as such
he had expressed views on all or any of the matters in dispute
or difference. The arbitrator to whom the matter is originally
referred being transferred or vacating his office or being unable
to act for any reason, such Managing Director as aforesaid at
the time of such transfer vacation of office or liability to act
shall appoint another person to act as arbitrator in accordance
with the terms of the contract. Such person shall be entitled to
proceed with the reference from the stage at which it was left
by his predecessor. It is also a term of this contract that no
person other than a person appointed by such Managing
Director as aforesaid should act as arbitrator and if for any
reason, that is not possible the matter is not to be referred to
arbitration at all. Cases where the amount of the claim in
dispute is Rs.25,000/- [Rupees twenty five thousand] and
above, the arbitrator shall give reasons for the award. Subject
as aforesaid the provisions of the Arbitration Act, 1940 or any
statutory modification or reenactment thereof and the rules
made there under and for the time being in force shall apply to
the arbitration proceeding under this clause.
It is a term of the contract that the party invoking
arbitration shall specify the dispute or disputes to be referred to
arbitration under this clause together with the amount or
amounts claimed in respect of each such dispute.
The arbitrator[s] may from time to time with consent of the
parties enlarge the time, for making and publishing the award.
The work under the contract shall, if reasonably possible,
continue during the arbitration proceedings and no payment
due or payable to the contractor shall be withheld on account
of such proceedings.
The Arbitrator shall be deemed to have entered on the
reference on the date he issues notice to both the parties fixing
of the date of the first hearing.
The Arbitrator shall give a separate award in respect of
each dispute or difference referred to him.
The venue of arbitration shall be such place as may be
fixed by the Arbitrator in his sole discretion.
The award of the Arbitrator shall be final, conclusive and
binding on all parties to this contract.”
2. The respondent was given extension of time for execution
and completion of the project pursuant to Clause 13 of the General
Conditions of Contract. It may be kept on record that Clause 32
clearly postulates that the extended time was also to be the
essence of the contract. After the expiry of stipulated period of
time, the respondent submitted certain claims to the Managing
Director of the appellant in terms of Clause 10 of the Contract. A
compensation of Rs.87,000/- was awarded to the respondent. In
this connection, it may be stated that the respondent had also
suspended work for some time.
3. The respondent thereafter filed a suit being Arbitration Suit
No.3212 of 1986 before the High Court of Bombay under Section
20 of the Arbitration Act, 1940 [in short ”the Act”] praying for
appointment of an Arbitrator. By an order dated 7th of January,
1988, the High Court appointed one Shri N.N. Shrikhande as the
sole Arbitrator to decide the disputes raised by the parties.
Subsequently, the appellant filed a notice of motion praying for
setting aside the order of appointment dated 7th of January, 1988
and also prayed for stay of the arbitration proceedings. The said
notice of motion was, however, dismissed by the High Court. The
appellant filed an appeal which was also dismissed on the ground
of delay.
4. The appellant, feeling aggrieved, filed a special leave
petition being SLP [C] No.11703 of 1988 in which this Court
granted leave, which came to be registered as Civil Appeal
No.3585 of 1988. By an order dated 4th of October, 1988, this
Court had set aside the order dated 7th of January, 1988 and
remanded the matter to the High Court for nominating another
Arbitrator. Again by an order dated 2nd of November, 1988, the
High Court appointed one Shri S.N. Mishra as the sole Arbitrator.
On 1st of March, 1989 the learned Arbitrator entered upon the
reference. On 2nd of March, 1989, statement of claim was filed by
the respondent. Various claims were made, inter alia, for
escalation, purchase of additional material and transport charges.
Reply to show cause notice was filed on 16th of March, 1989 by
the appellant and rejoinder to the same was also filed by the
respondent. The learned Arbitrator thereafter by a reasoned award
dated 20th of October, 1989 directed the appellant to pay a sum of
Rs.32,68,805.80 to the respondent along with interest at the rate of
15% till the date of final payment. On or about 14th of December,
1989, the appellant filed an application for setting aside the said
award before the High Court. By a judgment and order dated 19th
of October, 1994, a learned Judge of the High Court dismissed the
said petition of the appellant, inter alia, on the following findings:
[1] The claim of the appellant that they were entitled to deduct
certain amounts from the final payment to the respondent on
account of his having consumed extra cement was rejected.
[2] The Arbitrator did not have any jurisdiction in rejecting the
claim in view of Clause 10 of the agreement.
[3] The claim of the appellant that it was entitled to deduct
certain amount from the final bill on account of non utilization
of steel was rejected.
[4] The Arbitrator awarded escalation price to the respondent
on account of increase in prices even after the stipulated time
of completion.
[5] The Arbitrator disallowed the claim of the appellant for
deduction of amounts from the final bill on account of poor
workmanship.
[6] The claim towards purchase of surplus wood by the
respondent was allowed along with the claim for filling of earth.
[7] The claim of the respondent towards transport charges for
carrying wood was allowed despite the fact that the contract
provided for local wood to be used.
[8] Expenses towards litigation and interest at the rate of 18%
prior to the reference were also allowed.
5. Feeling aggrieved, an appeal was carried to the Division
Bench of the Bombay High Court and by a judgment and order
dated 11th of February, 2000, the Division Bench partly allowed
the appeal limited to the question of interest but rejected all other
contentions of the appellant. Feeling aggrieved by the aforesaid
order of the Division Bench of the High Court, a special leave
petition was filed, which on grant of leave was heard in the
presence of learned counsel for the parties.
6. We have heard the learned counsel for the parties and
examined the impugned order of the High Court as well as the
application for setting aside the award passed by the Arbitrator
filed at the instance of the appellant and other materials on record.
On behalf of the appellant, Mr. Rakesh Dwivedi, learned senior
counsel, contended at the first instance that there was an error
apparent on the face of the award on the issue of ‘balance steel
recovery’. Mr. Dwivedi contended that the respondent was having
balance steel with it which was not consumed or returned and the
respondent should, therefore, pay interest on it as per penal rates
in terms of Clause 15[2][6] of the Contract. At this stage we may
refer to Clause 15 [2][6] which runs as under :-
“if on completion of work, the contractor fails to return surplus
materials out of those supplied by the Federation, then, in
addition to any other liability which the contractor would incur,
the Engineer In-charge may, by a written notice to the
contractor, require him to pay within a fortnight of receipt of
notice, for such unreturned surplus materials at double the
issue rates.”
7. On this score, the finding of the Arbitrator was that there
was no clear evidence put forward by either of the parties as to
what happened to the balance steel and under that circumstances
the claimant, namely, the respondent was directed to pay at the
issue rates and not at the penal rates. However, though this was
the observation in the body of the award, in Appendix ‘C’, the
Arbitrator had given certain deductions based on balance steel
under three heads. Mr. Dwivedi, therefore, contended that the
appendices were part of the award itself which is to be interpreted
in conjunction with Appendix ‘C’ and, therefore, in the light of
Appendix ‘C’ where a finding of unutilized steel under three heads
lying unutilized the Arbitrator should have awarded the respondent
to pay at penal rates and by not doing so and directing the
payment at issue rates it was against the express terms of the
contract and liable to be interfered with. In response to this
argument, the learned counsel for the respondent, however,
contended that Appendix ‘C’ could not be construed to be a part of
the award, since, in the award the observation was that there was
no clear evidence as to the balance steel, payment at penal rates
could not have been awarded. It was further contended by learned
counsel for the respondent that if anyone, it was the respondent
who should be aggrieved and at any rate, the appendix did not
give the appellant to contend that there was a finding of unutilized
balance steel. The Arbitrator in his award clearly stated that in the
absence of a positive finding of the same, the penal rate cannot be
awarded. The Court, therefore, rightly held that Appendix ‘C’ did
not mean to be a positive finding by the Arbitrator that such steel
was unutilized and had been appropriated by the respondent.
Accordingly, we do not find any infirmity either in the award of the
Arbitrator or in the findings of the Division Bench as well as of the
learned Single Judge on this ground.
8. It was next contended by the learned senior counsel for the
appellant that there was inferior quality of workmanship as a result
of which it was entitled to make deduction from the bills. The
learned Arbitrator had refused to accept this submission from the
side of the appellant that under the contract the respondent was
obliged to use local materials including local bricks, that the bricks
in the Bombay region were of inferior quality and further that all the
bills presented had been passed by the Architect of the appellant
without any objection, therefore, the appellant was estopped from
raising the issue and no recovery could be allowed. We do not find
any infirmity in the aforesaid findings of the Arbitrator as well as
the findings arrived at by the High Court. Mr. Dwivedi had drawn
our attention to the fact that under the contract this was an issue
which was left to the sole discretion of the Managing Director of
the appellant and, therefore, was not within the jurisdiction of the
Arbitrator to arbitrate upon. In this connection, Mr. Dwivedi placed
reliance on Clause 10[b], [c] and [f] and Clause 11 of the Articles of
Agreement. The learned Single Judge as well as the Division
Bench, after examining the Clauses, as indicated hereinabove,
held that these Clauses did not include within their purview ‘bad
workmanship’ and, therefore, it was beyond the jurisdiction of the
Arbitrator to decide it. In respect of Clause 10 [c], the Court, in our
view, has rightly rejected the argument of the appellant that
‘negligence or lack of proper care’ was synonymous to bad
workmanship. Accordingly, we do not find any ground to interfere
with the findings of the High Court in rejecting the submissions of
the learned counsel for the appellant on this ground. In any view of
the matter, the Arbitrator had considered the entire materials on
record and the rival submissions of the parties and then came to
the conclusion of fact, which was accepted by the courts below, it
is not open to this Court to interfere with such conclusions until and
unless it is manifest that such conclusions are perverse or
arbitrary. That apart, we are of the view that this would not be a
ground for setting aside the award under the Arbitration Act, 1940.
9. That apart, in our view, the High Court was justified in
holding that the poor workmanship did not fall under any of the
sub-clauses of Clause 10 of the Articles of Agreement, which
enumerates the matters in which the Managing Director will have
the exclusive authority to decide the dispute as per Clause 11 of
the Agreement. Clause 10(b) provides that all special losses and
damages suffered by the Employer, as certified by the certificate of
the Engineer-in-charge, shall be final, conclusive and binding.
Clause 10(c) of the agreement makes “losses suffered by the
employer or damages due to negligence or lack of proper care” on
the part of the contractor shall be liable to be reimbursed and the
certificate of the Engineer-in-charge as to the extent of damage
and its value is declared to be final, conclusive and binding upon
the contractor. Clause 11 provides that all disputes and differences
arising out of the contract as contained in the proceedings in
paragraphs (a) to (f) of Clause 10 shall be referred to the
Managing Director of Employer whose decision shall be final,
conclusive and binding and shall not be referred to arbitration or to
any Court of law. In this connection, as noted herein earlier, the
High Court was fully justified in holding that “lack of proper care or
negligence” appearing in Clause 10(c), was not synonymous to
bad workmanship by which the respondent had based its claim.
Workmanship refers to skill or talent displayed in the performance
of a work and is not related to the care or diligence showed in the
work or choosing the materials. Accordingly, this submission of
Mr.Dwivedi, learned senior counsel appearing for the appellants is
not worthy of consideration and, therefore, it is rejected.
10. We also find from the impugned judgment of the High
Court that both the parties had admitted before the Arbitrator that
the format to be used for analysis of extra items shall be the
CPWD Format and that both the parties had indicated to the
Arbitrator that there was no difference between them as to the
format used by them in analyzing the extra items. However, the
parties are not at ad idem on the actual rates to be taken for labour
and material, referred to in the format. It also appears from the
judgment of the High Court that while the appellant insisted that
the rates prescribed by CPWD in respect of the labour and
material had to be used, the respondent insisted that local rates
would have to be used. Considering the resolution approved in a
meeting on 6th of March, 1986, where the Architect approved extra
items 1 to 6 at the rates that were put forward by the respondent
and with regard to extra items 7 and 8 the rates analysis put
forward by the appellant was not even contested by the
respondent. With regard to the analysis of item No.9 pertaining to
transportation and wages, the Arbitrator denied the claim of the
respondent. With regard to item No.10, the rate put forward by the
appellant was accepted by the Arbitrator. In these circumstances,
it is no longer open to hold the contention that there was any
requirement that the CPWD rates must be accepted and that no
deviation therefrom was permissible under the Contract. In this
view of the matter, it is difficult to agree that the Arbitrator had
acted beyond the terms and conditions of the contract while
coming to the findings of fact relating to the extra items on rates
other than the CPWD rates also.
11. The next ground of attack of the impugned judgment rests
on payment of interest. From the impugned judgment, it appears
that three limbs of the argument of the parties were dealt with by
the Division Bench of the High Court. It is not in dispute that the
learned Arbitrator entered upon the reference on 1st of March,
1989. The Arbitrator having found that the appellant was liable to
pay a total sum of Rs.32,68,805.80 p. directed that if the said
amount is not paid by the appellant to the respondent on or before
15th of December, 1989, the same would carry interest @ 15% per
annum till the payment was made. The total sum of
Rs.32,68,805.80 as found by the learned Arbitrator included the
following three claims :-
Claim No.1 : Rs.17,36,994.97
Claim No.2 : Rs.2,40,615.96
Claim No.8 : Rs.2,68,000.000
So far as Claim No.1 was concerned, the Arbitrator found that
what was due was Rs.13,62,349/- to which he added interest from
January 1987 to October, 1989 @ 15% which worked out to
Rs.3,74,645.97. Thus the total amount in respect of Claim No.1 as
mentioned above worked out to Rs.17,36,645.97 (there is an
apparent inconsistency in the figures of claim No.1 reproduced
with this figure), but the thing remains that the learned Arbitrator
calculated interest @ 15% for the period from January 1987 to
October, 1989 and added it to make up the claim No.1. Similar
was the exercise carried out by the learned Arbitrator in regard to
claim No.2 in which the Arbitrator having found that a total sum of
Rs.1,88,718.40 p. was due, added interest for the period from
January 1987 to October, 1989 again @ 15% which amounted to
Rs.51,897.56 making the total under the head of CPWD as
Rs.2,40,615.96 p. So far as Claim No.8 as mentioned by the
learned Arbitrator is concerned, it appears that the learned
Arbitrator re-calculated the amount of interest and awarded
Rs.2,68,000/- as interest on delayed payment. It is not in dispute
that the learned Arbitrator in his final analysis had allowed interest
@ 15% per annum. So far as the payment of interest is concerned,
the Division Bench of the High Court after analyzing the decisions
of this Court, namely, Executive Engineer, (Irrigation) Balimela &
Ors. vs. Abhaduta Jena & Ors. [1988 (1) SCC 418], Secretary,
Irrigation Department, Government of Orissa & Ors. vs. G. C. Roy
[1992 (1) SCC 508] came to the conclusion of law which was that
the Arbitrator has power to award pendente lite interest and where
the contract was silent as to the awarding of interest, the Arbitrator
has the power to award interest for the pre-reference period if
there is a substantive law which empowers him to do so or if there
is a usage of trade for payment which has the force of law. In our
view, the High Court was perfectly justified in holding that the
Arbitrator has the power to award interest for the pre-reference
period. It needs to be repeated at this juncture that the arbitration
in question was governed not by the present Act of 1996 but by the
provisions of Arbitration Act, 1940. However, as this power
emanates from Section 3 of the Interest Act, 1978, the High Court
noted that the rate of interest cannot be more than ‘the current rate
of interest’ as stipulated by the said Section. Accordingly the High
Court had reduced the rate of interest for pre-reference period
from 18% to 15%. It was, however, argued on behalf of the
appellant that the High Court was not justified in awarding interest
for pre-reference period in view of Section 3 of the Interest Act,
1978 which was pursuant to a special clause in the Contract. As in
the present case there was no such clause in the agreement and
hence it was not within the power of the Arbitrator to make an
award with respect to interest.
12. In our view, this argument lacks substance. The position of
law, as found by the High Court in its impugned judgment on
consideration of various other judgments of this Court, would
clearly show that in those judgments the High Court relied on also
did not stipulate any express agreement with respect to interest as
a precondition to the authority of the Arbitrator to award interest for
the pre-reference period. The matter would have a different issue
altogether if there had been a specific provision prohibiting grant of
interest which was, of course, not the case of the appellant.
13. In the case of State of Rajasthan and Anr v. Ferro
Concrete Construction Pvt. Ltd, [2009 (8) SCALE 753], the same
work was advanced in which this Court observed:
“But this Court has held that in the absence of an express bar,
the arbitrator has the jurisdiction and authority to award
interest for all the three periods - pre reference, pendente lite
and future (vide decisions of Constitution Bench in Secretary,
Irrigation Department, Government of Orissa vs. G. C. Roy -
1992 (1) SCC 508, Executive Engineer, Dhenkanal Minor
Irrigation Division vs. N. C. Budharaj - 2001 (2) SCC 721 and
the subsequent decision in Bhagawati Oxygen vs. Hindustan
Copper Ltd -2005 (6) SCC 462). In this case as there was no
express bar in the contract in regard to interest, the Arbitrator
could award interest.”
14. In view of the above decision in law now settled by this
Court, we are unable to hold that the Arbitrator was not entitled to
award interest on the pre-reference period because there was no
clause in the agreement prohibiting such awarding of interest.
However, the High Court had reduced the rate of interest to the
‘current rate of interest’ and, therefore, it is not open for us to
interfere with such rate of interest at this stage in this appeal.
Therefore, there is no substance in this argument, accordingly it is
rejected.
15. Now the question comes which is related to awarding of
‘interest on interest’. According to the appellant, they have to pay
interest on an amount which was inclusive of interest and the
principal amount and, therefore, this amounts to a liability to pay
‘interest on interest. This question is no longer res integra at the
present point of time. This Court in McDermott International Inc. v.
Burn Standard Co. Ltd, & Ors. [2006 (11) SCC 181] has settled
this question in which it had observed as follows :
“The Arbitrator has awarded the principal amount and interest
thereon upto the date of award and future interest thereupon
which do not amount to award on interest on interest as
interest awarded on the principal amount upto the date of
award became the principal amount which is permissible in
law.”
16. The High Court on this question has also rightly relied on a
decision of this Court in the case of Oil and Natural Gas Commission vs. M/s. M .C. Clelland Engineers S.A. [1999 AIR
SCW 1224]. That being the position, we are unable to find any
ground to set aside the judgment of the Division Bench of the High
Court while considering the ground of ‘interest on interest’. So far
as the ground relating to the power of the Arbitrator to award
interest on the cost of arbitration is concerned, we are of the view
that we do not find any infirmity in the said findings of the High
Court relating to that ground. Since the legislature by way of an
amendment in the year 1956 deleted Section 35(3) of the Code of
Civil Procedure which empowered the court to award interest, the
Arbitrator, on analogy, cannot have the power to award interest on
costs. Therefore, the High Court has failed to justify in holding that
the powers of the Arbitrator are not effected by changes made to
the Code of Civil Procedure. The power of the Arbitrator, if any,
shall be located from the act itself. We may note that awarding
costs is a matter of discretion of the Arbitrator under the 1940 Act.
Sir Mohd. Akbar Khan vs. S.Attar Singh (deceased) [AIR 1945 PC
170] is an answer to the aforesaid ground. Paragraph 8 of the First
Schedule to the Arbitration Act, 1940 which contains “Implied
Conditions of Arbitration Agreements” lays down that –
“the costs of the reference and award shall be in the discretion
of the arbitrators or umpire who may direct to, and by, whom,
and in what manner, such costs or any part thereof shall be
paid, and may tax or settle the amount of costs to be so paid or
any part thereof and may award costs to be paid as between
legal practitioner and client.”
17. A plain reading of this paragraph would show that there is
a provision in this clause which does not permit or prohibit the
imposition of interest on costs of arbitration.
18. The High Court has also observed in the impugned
judgment that the principles in relation to payment of interest on
interest will apply in this context as well and that there is no
principle or precedent prohibiting award of interest on cost. It may
be noted that the Law Commission of India in its 55th Report
submitted in 1973 discussed the rationale behind grant of interest
on interest and on costs. Though the Commission found it fit not to
disturb the position of law that emerged after the deletion of
Section 35(3) of the Code of Civil Procedure, but Law Commission
had expressed its opinion in favour of grant of interest on costs.
The logic behind it was that the cost incurred in the litigation were
actually and rightfully incurred by the successful litigant which he
would have invested but for the lengthy litigation proceedings.
Interest, which is damages for wrongful retention of money that
rightfully belonged to one, thus can be paid on costs as well. This
may also be considered that costs of arbitration are actually
incurred by the respondent and it is only that it becomes payable
only with the award in its favour. Accordingly, we do not find any
infirmity in the judgment of the Division Bench except in that we
are of the view that the rate of interest from 15% should be
reduced to 7%. In McDermott International vs. Burn Standards
(supra), it had summarized the practice of this Court on this issue
in the following words :-
“The 1996 Act provides for award of 18% interest. The
arbitrator in his wisdom has granted 10% interest both for the
principal amount as also for the interim. By reason of the
award, interest was awarded on the principal amount. An
interest thereon was upto the date of award as also the future
interest at the rate of 18% per annum.
However, in some cases, this Court was resorted to exercise
its jurisdiction under Article 142 in order to do complete justice
between the parties.
In pure Helium India (P) Ltd. [2003 8 SCC 593] this Court
upheld the arbitration award for payment of money with
interest at the rate of 18% p.a. by the respondent to appellant.
However, having regard to long lapse of time, if award is
satisfied in entirety, respondent would have to pay a huge
amount by way of interest. With a view to do complete justice
to the parties, in exercise of jurisdiction under Article 142 of the
Constitution of India, it was directed that award shall carry
interest at the rate of 6% p.a. instead and in place of 18% p.a.
Similarly in Mukand Ltd. vs. Hindustan Petroleum Corpn. [2006
(4) SCALE 453], while this Court confirmed the decision of the
division bench upholding the modified award made by the
learned single Judge, the court reduced the interest awarded
by the learned single judge subsequent to the decree from
11% per annum to 7% per annum observing that 7% per
annum would be the reasonable rate of interest that could be
directed to be paid by the appellant to the respondent for the
period subsequent to the decree.
In this case, given the long lapse of time, it will be in
furtherance of justice to reduce the rate of interest to 7%.”
19. Following the aforesaid decision and considering the fact
that there was a long lapse of time and for the ends of justice, we
are, therefore, of the view that the judgment of the Division Bench
can be modified only to the extent that the rate of interest should
be reduced from 15% to 7%. As we also find in this case that such
reduction of interest is warranted because the award was passed
on 20th of October, 1989, now 20 years have passed since then.
20. This Court in Mcdermott International Inc. vs. Burn
Standard Co.Ltd. & Ors. (supra) S.B.Sinha,J., (as His Lordship
then was), following the two earlier decisions of this Court in the
case of Pure Helium India (P) Ltd. vs. ONGC [(2003) 8 SCC 593]
and Mukand Ltd. vs. Hindustan Petroleum Corpn. Ltd. [(2006) 9
SCC 383] and considering the fact that due to long lapse of time if
the entire award is satisfied, the appellant would have to pay a
huge sum of money by way of interest. Therefore, in that decision,
this court directed reduction of rate of interest in order to do
complete justice between the parties in the exercise of its
jurisdiction under Article 142 of the Constitution of India and that is
the reason we also reduce the rate of interest from 15% to 7%.
21. Before parting with this judgment, we may refer to two
decisions of this Court which were cited at the bar in the case of
T.N. Electricity Board vs. Bridge Tunnel Constructions & Ors.
[1997 4 SCC 121] and Trustees of the Port of Madras vs.
Engineering Constructions Corpn. Ltd. [1995 5 SCC 531]. So far
as the case of T.N. Electricity Board is concerned, we have no
quarrel with the principle laid down in the aforesaid decision. In
that decision, it was held that one of the question that was decided
was that the Arbitrator cannot clothe himself conclusively with the
jurisdiction to decide or omit to decide the arbitrability of a
particular item or the claim made by the parties. It was held that
when a specific reference has been made to the Arbitrator and the
parties raise the dispute of arbitrability, with the leave of the
court/by a direction of the court in a proceeding under Section 33,
he is to decide the arbitrability of the dispute and make a decision
while giving reasons in support thereof. It was further held that the
decision of the Arbitrator in granting a particular sum by a non-
speaking award, therefore, hinges upon the arbitrability of a
dispute arising under the contract or upon a particular item claimed
thereunder. It was further observed that he was required to give
the decision thereon. Therefore, it was held that the question of
decision by implication does not arise since his jurisdiction to
decide the dispute on merits hinges upon his jurisdiction to decide
the arbitrability of the dispute.
22. The aforesaid decision of this Court, therefore, in our view
cannot come to help the appellant.
23. So far as the decision in the case of Trustees of the Port of
Madras vs. Engineering Constructions Corpn. Ltd. (supra) is
concerned, this case also has no application in the facts of this
case. In that case, the principles have been laid down in the case
of a reasoned award and the court can interfere if the award is
passed upon a proposition of law which is unsound in law. The
error apparent on the face of the award contemplated by Section
16(1)( c) as well as Section 30 (c ) of the Arbitration Act is an error
of law apparent on the face of the award and not an error of fact.
Therefore, this decision, in our view, is also of no help. The
Arbitrator has passed his award on the basis of the conditions of
the clauses in the agreement and passed an award and nothing
could be shown from which it could be held that the court could
interfere with the award if the same was passed upon the
proposition of law which is unsound in law.
24. For the reasons aforesaid and subject to the modification as noted
hereinabove, this appeal has no merit and the same is hereby dismissed.
There will be no order as to costs.