04 March 2011
Supreme Court
Download

T.NADU HOUSING BOARD Vs SERVICE SOCIETY

Bench: R.V. RAVEENDRAN,A.K. PATNAIK
Case number: C.A. No.-002320-002320 / 2011
Diary number: 15131 / 2008
Advocates: T. HARISH KUMAR Vs V. BALACHANDRAN


1

Page 1

TAMIL NADU HOUSING BOARD v.

THE SERVICE SOCIETY & ANR. (Civil Appeal Nos. 2320 of 2011)

MARCH 04, 2011 [R.V. Raveendran and A.K. Patnaik, JJ.]

[2011] 6 SCR 1

The Order of the Court was delivered by

O R D E R

R. V. RAVEENDRAN J.  

1. Leave granted.

2. The first respondent (‘Society’  for short) requested the state  

government (second respondent) to provide a Low Income Group housing  

scheme for the benefit of its members who were the employees of Tamil  

Nadu Electricity Board. The state government directed the Tamil Nadu  

Housing Board, the appellant herein (‘The Board’  for short) to execute the  

said scheme. To meet the requirements of the employees of the Electricity  

Board as also the staff of the appellant, the state government acquired an  

extent of 8.38 acres of land in Singanur Village, Coimbatore. The Board  

formulated a scheme for development of the said land and construction of  

145 LIG Houses and 120 LIG flats therein. In pursuance of it, in the year  

1976, the Board allotted to several members of the society, LIG Houses, each  

house comprising a plot measuring about 40’  x 26’  (1040 sq.ft.) and a  

proposed construction measuring 316 sq.ft. Though the standard  

measurement of the proposed plots was 1040 sq.ft, the actual extents of  

some of the plots were different, that is 1000 sq.ft, 1021 sq.ft, 1150 sq.ft,  

1235 sq.ft etc. For convenience we will refer to the facts relating to the  

allottee of LIG House No.49 which comprised a plot measuring 1000 sq.ft.  

and a house measuring 316 sq.ft.

2

Page 2

3. The tentative allotment price was fixed by the Board as Rs.18,000/-  

(made up of cost of plot, cost of development and cost of house) and each  

allottee was required to make an initial deposit of Rs.3000/- and pay the  

balance in agreed monthly instalments. The Board also entered into a lease-

cum-sale agreement in November 1977 with the allottee containing the terms  

and conditions of lease and the option for sale. Clause 17 of the said  

agreement providing for sale of the LIG House to the allottee is extracted  

below:

“The lessor agrees to sell the property more particularly described in the  

schedule hereunder to the lessee for such price as the Administrative  

Officer of the lessor may at any time in his sole discretion fix and at which  

time the Administrative Officer of the lessor is entitled to consider details  

regarding development charges, cost of amenities, cost of buildings etc.,  

and whether the price of the land acquired under the Land Acquisition Act  

together with suitable modifications thereto by the local laws become final  

by a conclusive adjudication thereon by the concerned tribunals and  

courts. The final decision of the Administrative Officer of the lessor are to  

be the final price of the property as determined under these presents is  

conclusive and binding on the lessee and the lessee agrees to purchase  

the property from the lessor as the said price on the terms and conditions  

hereinafter mentioned.  

Excepting the fixation of price with reference to the claim of compensation  

adjudicated or awarded by courts finally and conclusively with regard to  

the lands acquired under the scheme, the lessor shall fix the price of the  

property after taking into consideration the development charges, cost of  

amenities and buildings etc. within a period of three years from the date  

of allotment and which price is subject only to a revision on account of  

excess compensation if any awarded by the courts for the lands as  

aforesaid.”

3

Page 3

Clause 24 of the agreement required the allottee-cum-lessee to pay interest  

on the amounts outstanding, at the rate of 9% per annum. The Board did not  

disclose to the allottees, the break-up of the tentative cost, as to how much  

for the land, and how much for the development cost and construction.  

4. Though clause 17 contemplated the final price being fixed within three  

years from the date of allotment, the Board did not fix the final price within  

that period. The Board determined the final price only in the year 1988, nearly  

12 years after the allotment and sent a demand letter dated 21.5.1988  

informing the allottee that the final cost of the LIG House No.49 was  

Rs.34,770/- as against the tentative price of Rs.18,000/- and called upon the  

allottee to remit the difference in cost of Rs.16,770/- (plus Rs.351 payable to  

the municipal corporation) on or before 30.06.1988. The allottee was required  

to pay the said amounts on or before 30.06.1988, failing which the amount  

due would carry interest at 14%/13% per annum from 1.7.1988. The Board  

also clarified that the increase in the cost was mainly on account of payment  

of increased compensation for the acquisition of land.  

5. Feeling aggrieved, the society, acting on behalf of its members who  

were the allottees of the LIG houses, filed an appeal before the state  

government challenging the said demand. The appeal was dismissed by  

order dated 31.10.1991. The society thereafter filed WP No.15635 of 1991 for  

quashing the appellate order dated 31.10.1991 of the state government and  

sought a direction to the Board not to demand from its members, any  

increase in price as demanded in May 1988. The society contended that  

having regard to clause 17 of the lease-cum-sale agreement, the final cost  

had to be determined within three years from the date of allotment; that such  

a determination not having been done, the tentative price of Rs.18,000/-  

should be deemed to be the final price; and that the Board could not make a  

demand for increase in price, after expiry of 12 years. Alternatively, it was  

submitted that in the event of the court holding that the Board could demand  

the increase in cost, that should be only in respect of the land cost

4

Page 4

component and not with reference to the components relating to cost of  

development and cost of construction. It was lastly contended that the  

amount determined and demanded by the Board as the final cost was  

excessive and the Board had failed to justify the final cost demanded by  

giving any break up or particulars of the claim.

6. The Board resisted the petition contending that the final price was  

determined with reference to the cost of the acquisition of the land and the  

cost of development and cost of construction. It stated that the delay in  

finalizing the final cost was on account of the pendency of dispute raised by  

the land owners in regard to increase in compensation for the acquired land  

and on account of encroachments over part of the acquired land. It contended  

that the final cost was based on actuals and it was not excessive. It was  

submitted that only a few of the LIG Houses and flats were allotted to the  

members of the society and the remaining houses were allotted to its own  

employees and to members of public; and that except 55 allottees, all others  

had remitted the amount demanded.  

7. A learned single judge of the High Court by order dated 29.4.1999  

allowed the writ petition and quashed the appellate order dated 31.10.1991 of  

the state government and the demand by the Board for increase in price. The  

Board filed a writ appeal challenging the order of the learned Single Judge.  

8. During hearing before the division bench, both sides filed calculation  

sheets showing the cost of acquisition and the consequential increase in the  

cost of the LIG house. As per the calculation sheet filed by the society, the  

balance payable by each allottee towards increase in land cost was Rs.8634/-  

per plot of 1040 sq.ft. (after adjusting Rs.3000/- paid as initial payment and  

Rs.500/- paid as EMD) and the interest payable thereon from 17.4.1985 to  

6.11.1991 was Rs.5148/- in all Rs.13,782/- towards increase in land cost and  

interest as on 30.11.1991. The society alleged that the Board had indicated at  

the time of allotment, that the tentative price of Rs.18000 was made up of

5

Page 5

Rs.3000/- towards land cost and the balance towards development cost and  

construction; and that as no increase in regard to development  

cost/construction was notified to the allottees, within three years of allotment,  

the price component towards development/construction (which according to  

the society was Rs.15,000/- out of a total price of Rs.18,000/-) attained finality  

under clause 17 of the agreement. It was submitted that the amount payable  

by an allottee to the Board on account of the increase in cost of land was  

Rs.13,782/- plus interest at 9% per annum on Rs.8,634/- from 1.12.1991 to  

date of payment.  

9. On the other hand, the calculation sheet filed by the Board showed the  

total acquisition cost of the land (8 acres 38 cents) including interest upto  

31.3.1987 was Rs.35,02,727.24. The Board contended that on that basis, the  

cost of land and development per ground (an area of 2400 sq.ft) was  

Rs.40,400/- and each allottee should pay the proportionate cost based on the  

actual sital area of the LIG House allotted to him and interest in addition.

10. The division bench its judgment dated 7.8.2007, held after referring to  

the two calculation sheets, that the interests of justice would be met if each  

allottee is directed to pay an additional sum of Rs.13,780/- towards the  

increased cost of the plot and Rs.5,148/- towards interest in all Rs.18,928/- as  

on 30.11.1991 with further interest at 9% per annum. The High Court  

assumed that all plots measured 1040 sq.ft. It did not indicate any reasons for  

arriving at the said amount nor did it record any finding as to the correctness  

of the calculations by the society and the Board.

11. Feeling aggrieved, the Board and the society have filed these two  

appeals. On the contentions urged, the following questions arise for our  

consideration :  

(i) Whether the Board is barred from fixing the final price on the expiry  

of three years from the date of allotment, resulting in the tentative  

price becoming the final price?

6

Page 6

(ii) Even if the Board could fix the final price beyond three years,  

whether only the land cost component could be increased out of the  

tentative price and not the cost of development or cost of  

construction?

(iii) Whether the Board failed to justify the increase demanded by it?

Re.     question     (i)   

12. The letter of allotment and the lease-cum-sale agreement enable the  

Board to take note of the cost of land, cost of development and amenities,  

and cost of the building to determine the final price. It is not in dispute that  

when the allotment was made in the year 1976, the layout was yet to be  

developed, the construction had not yet begun and the compensation for the  

acquired land was yet to be determined by the Land Acquisition Collector.  

The price indicated at the time of allotment was therefore purely tentative.  

The Board did not undertake the scheme as a commercial venture but on ‘no  

loss-no profit basis’, with a loan from HUDCO. Therefore obviously it has to  

pass on the liability for the entire cost to the allottee who opted to buy the LIG  

house under the scheme. The allotment was on lease-cum-sale basis and  

until the LIG House was conveyed in favour of the allottee, he continued as a  

lessee of the Board and does not acquire any ownership rights.  

13. The reference to the period of three years in clause 17 was not  

intended to be prohibition upon fixation of final price thereafter. The work of  

development of an acquired land into a residential layout and construction of  

houses therein were expected to be completed within three years, but final  

determination of the claims for increase in compensation for acquired land  

was expected to take much longer. Clause 17 therefore provided that the final  

price will be decided within three years, subject however to further revision  

with reference to the land cost. If the Board completed the development of the  

layout and construction of houses within three years and if there are no  

pending claims, it is bound to fix the final price of the LIG house within three

7

Page 7

years from the date of allotment (even if the land acquisition cost had not  

been finalized) and if necessary, revise the final cost subsequently, after  

determination of land acquisition cost.  

14. But where the development of the layout and construction of houses  

were not completed within three years from the date of allotment, the Board  

obviously could not determine the final cost within three years as neither of  

the three components (cost of land, cost of development and cost of  

construction) would be known to the Board. There is no term or provision in  

the contract that if the Board does not determine the final price within three  

years from the date of allotment, the Board would lose the right to determine  

the final price thereafter or that the tentative price would become the final  

price. If on account of delay in determination of compensation for land  

acquisition or delay on the part of the contractors in completing the  

development works or construction, or if there are any encroachments or if  

there are pending claims of contractors regarding development or  

construction, the Board would not be able to determine the final cost within  

three years. But that did not mean that the tentative cost would become the  

final cost in the absence of such a provision in the letter of allotment or lease-

cum-sale agreement.  

Re     :question     No.(ii)   

15. The alternative submission of the society is that even if the price could  

be increased after three years, having regard to clause 17 of the lease-cum-

agreement, what could be increased after three years is only the land cost  

component and not the cost of the development or building. Clause 17 states  

that except the fixation of price with reference to the compensation finally  

awarded by the courts, the board should fix the price of the LIG house after  

taking into consideration the development charges, cost of amenities and cost  

of buildings within three years from the date of allotment. If the final price is  

so fixed, thereafter what could be increased is only the land cost component

8

Page 8

on account of any increase in compensation that may be awarded by the  

courts. If the board had earlier fixed the final price, the society’s contention  

might have merited acceptance as the component of price with reference to  

cost of development and amenities and cost of building would have attained  

finality on account of such final determination and only the increase on  

account of award of compensation for land could be demanded after such  

determination of final price. But where the final price has not been determined  

at all, for whatsoever reason, and the final cost was being determined for the  

first time, the allottee cannot contend that only the increase on account of the  

land, and not the increase on account of development cost and construction  

cost, could be demanded. Where the final price has not been fixed, the Board  

could, after ascertainment of various costs, determine the final price even  

after three years, and the finality in regard to cost of development and  

amenities and the cost of construction, referred under clause 17, would not  

apply.

16. It is not in dispute that the compensation in regard to the land was  

pending in courts and was finally determined in or about 1985. It is also not in  

dispute that development work could not also be completed as a portion of  

the acquired land was under encroachment. Therefore it is not possible to say  

that when the final price was fixed in the year 1988, it could be only with  

reference to increase on account of land and not with reference to increase in  

the development cost or construction cost. The demand letter dated  

21.5.1988 of the Board clearly states that the increase in price demanded  

was mainly due to increase in compensation for the land paid by the Board  

and only a small portion of the increase was under the other heads.  

Re:     question     No.(iii)   

17. The High Court, we find, has not appreciated the controversy in the  

correct perspective nor decided the matter in issue. The finding of the learned  

single judge that the Board is not entitled to any increase is contrary to the

9

Page 9

terms of allotment. The letter of allotment and the lease-cum-sale agreement  

make it clear that the price mentioned in the letter of allotment was only  

tentative and final price was to be determined taking into account, the final  

cost of acquisition, cost of development and amenities, and cost of the  

building. The fact that, subsequent to the allotment of the LIG Houses and  

execution of lease-cum-sale agreements, the land acquisition cost increased  

substantially was not in dispute. Similarly, if there was any increase in the  

actual cost of development/construction the allottees had to bear it. The  

Board could not be made liable to bear the extra cost as it was operating on  

‘no-profit, no-loss basis’ and had obtained a loan from HUDCO to execute the  

scheme. The division bench referred to the contentions of the parties and  

extracted the calculation sheets filed by both parties, but did not pronounce  

upon the correctness of the same. It neither accepted nor rejected the  

calculation sheets filed by the Board and the Society. The sum of Rs.13,780/-  

found by it to be increase in cost and Rs.5,148/- as interest, were apparently  

borrowed from the calculation sheet filed by the Society. But as per the  

calculation sheet of the society the increase in land cost (over and above the  

deposit of Rs.3500/-) was Rs.8,634/- and interest upto 30.11.1991 was  

Rs.5148/-, the total being Rs.13,782/-. The High Court however wrongly  

assumed that as per the calculation sheet of the Society, the increase in the  

cost of the plot itself was Rs.13,782/- (rounded of to Rs.13780/-) and the  

interest of Rs.5,148/- was in addition to Rs.13,782/- and direct such payment.  

This is without any acceptable basis.

18. The cost of a house constructed by a development authority or  

Housing Board has the following three components: (a) the cost of the plot;  

(b) the proportionate share in the cost of development and amenities (like  

water, electricity, sewage disposal etc.) and (c) cost of construction of the  

house. Where the construction is taken up in a developed layout, and not in  

an undeveloped land, item (b) will not be an independent component, but be  

a part of item (a).

10

Page 10

19. If a development authority or board acquires a large tract of land and  

develops it for residential purposes and forms plots in a portion thereof for  

construction of houses, utilises another portion for construction of multi-

storeyed apartment buildings and uses the balance for development works  

like roads, drains, parks, open spaces apart from earmarking some areas for  

site office/electrical sub-station/police station, etc., then what is chargeable to  

the allottee of a plot or a house, is not only the cost of the plot area, but also  

the cost of the proportionate share in the common areas, used for  

development and amenities and the cost of the development.  

20. We may illustrate. If 5 Hectares (50000 sq.m.) of land is acquired for  

formation of residential plots each measuring 250 sq.m., it is not possible for  

the authority to carve out 200 plots (each measuring 250 sq.m). This is  

because, not less than 25% to 30% of the total sital area will be used up for  

forming roads, footpaths and drains. Another 10% to 20% may be used for  

common facilities and amenities like park, playground, community hall etc.  

The common/service areas are not saleable and the board will have to  

recover the cost thereof by loading the proportionate cost thereof, on the cost  

of the residential plots. Therefore if 40% is the area used for roads, drains,  

parks, playgrounds etc., the saleable area or area that can be used for  

forming plots would be only 60% and the cost of the total land 50000 sq.m.  

will have to be recovered from the sale of the said 60% area (30,000 sq.m.)  

which can be carved into 120 plots of 250 sq.m. If the total value of 5  

hectares is Rs.60 lakhs, the value of a plot of 250 sq.m. will not be  

Rs.30000/- (that is Rs.60 lakhs divided by 200) but Rs.50,000/-(that is Rs.60  

lakhs divided by 120). An allottee of a plot measuring 250 sq.m. cannot  

therefore contend that he is liable to pay only the actual proportionate cost of  

250 sq.m. of land out of 50000 sq.m. The proper method is to calculate the  

total common/service area (used for roads, drains and common amenities)  

and include the proportionate cost thereof in the price of the plot.

11

Page 11

21. When a large undeveloped tract is acquired by a development  

authority or a Board, considerable amounts will have to be spent for  

developing it, to make it suitable for residential use. This will include the cost  

of levelling the land, forming plots, laying roads and drains, drawing electrical  

lines, laying water and sewerage pipes, providing electricity and water etc.  

This cost also will have to be proportionately borne by the allottee as  

development cost. Some authorities even load the cost with reference to its  

overheads, that is, a proportionate cost, depending upon the norms, rules and  

regulations. In Preeta Singh vs. Haryana Urban Development Authority –  

1996 (8) SCC 756, this Court held :  

“It is to be remembered that the respondent HUDA is only a statutory  

body for catering to the housing requirement of the persons eligible to  

claim for allotment. They acquire the land, develop it and construct  

buildings and allot the buildings or the sites, as the case may be. Under  

these circumstances, the entire expenditure incurred in connection with  

the acquisition of the land and development thereon is required to be  

borne by the allottees when the sites or the buildings sold after the  

development are offered on the date of the sale in accordance with the  

regulations and also offered on the date of the sale in accordance with  

the regulations and also conditions of sale.”  

The calculation sheet of the Society which works out the cost of land with  

reference to the actual size of the plot ignoring the proportionate share in the  

cost of the common/service areas (roads, drains, etc.) and the development  

cost, is therefore liable to be rejected.  

22. Whenever allotments are made even before the completion of the  

development of land and construction, necessarily the cost that is shown by  

the authority or the board will be tentative. In regard to the land cost, there  

may be claims for enhancement of compensation before the reference court  

with appeals to high court and this court. Sometimes the entire process may

12

Page 12

take 10 to 15 years and till that process is concluded the final cost of the land  

cannot be determined. An allottee cannot therefore say that the authority  

cannot increase the cost after 12 years. Similarly cost of developing of land  

into residential area requires coordination with different contractors engaged  

for laying roads, laying drains, developing parks and playgrounds, drawing  

electricity lines, water lines, sewerage lines etc. Many times, disputes with the  

contractors lead to delays and litigation. Sometimes though the work may be  

completed within three years, the settlement of bills and ascertainment of cost  

may take several years. There may also be encroachments, which will have  

to be removed which apart from being time consuming and involving litigation,  

delay the development and finalization of cost of development. As a  

consequence, the development cost may also shoot up beyond the estimate  

on account of delays, additional claims of contractors, litigations and other  

factors. The same applies to the cost of construction of the houses also.  

Therefore an allottee cannot contend that the increase, if any, should be  

determined within three years and if the increase is not so determined, the  

tentative cost would itself become the final cost. Such an interpretation of  

clause 17 would be illogical and unreasonable. If the Board is able to show  

that there was sufficient cause for the delay in deciding the final price and that  

it was beyond its control to determine the final cost earlier (or within three  

years) it will be entitled to final cost even if the claim is delayed by a few  

years. The allottee cannot refuse to pay it merely on the ground of delay.

23. On the other hand the authority or Board should also be diligent.  

Allottees belonging to low income groups should not be made to suffer for the  

defaults or negligence on the part of the staff of the authority. They should  

take prompt steps to settle claim regarding compensation. They should also  

be prompt in executing the development works and construct work. They  

should ensure that the cost is kept to the minimum. If any allottee approaches  

court and is able to demonstrate that the development and construction work  

was completed within three years, but the authority failed to fix a final cost, it

13

Page 13

may be possible to infer that there was no increase from the tentative cost  

and therefore the final cost was not fixed and therefore the tentative cost  

should be the final cost. Be that as it may.

24. In view of the complex nature of acquisition, development,  

construction and allotment, it is necessary to safeguard the interests of the  

allottees and at the same time ensure that there is no loss to the public  

exchequer or the authority by making it to bear any part of the cost of  

development or cost of the plot or cost of construction. Normally a claim by  

the authority or the board for increase should be accepted if the authority or  

board certifies that what is claimed is the actual final cost, and supports it by  

a certificate from an independent chartered accountant or its own Accounts  

Department showing the break up of the cost. A standard certificate should  

furnish the following :  

(a) break up of the tentative allotment price in regard to the plot,  

development and construction;  

(b) break up of the final cost in regard to the plot, development and  

construction;  

(c) a table showing total area, area used for plots, area used for  

common/service areas like roads, drains, parks and open spaces;  

(d) a table showing the acquisition cost; and  

(e) a table showing the construction cost.  

It is open to the allottee to apply for the particulars and have it verified  

independently, before rushing to court.

25. Let us now examine whether the amount claimed by the board in this  

case is excessive. As noticed above in regard to a plot measuring 1000 sq.ft.  

with a residential house measuring 361 ft. the board had indicated the  

tentative price as 18000 in the year 1976. After the compensation for land  

was decided by courts and after carrying out the development work and

14

Page 14

construction, the board determined the final cost as Rs.34,770 in the year  

1988 and demanded the difference of Rs.16,770/-. The question is whether  

this claim is excessive.

26. We find that the allottees/society do not dispute that the cost of the  

land increased considerably on account of enhancement of compensation.  

The board showed that the total cost of land inclusive of interest upto  

31.3.1987 was Rs.35,02,727 for 8 acres and 16422 sq.ft. The said figure was  

broadly accepted by the society, in its calculation sheet. The society arrived  

at the cost of a plot measuring 1040 sq.ft. as 3500 (paid as deposits) plus  

Rs.8634/- which aggregates to Rs.12,134. But as noticed above, this is the  

proportionate cost worked out for 1040 sq.ft. out of the total cost of an extent  

of 33,64,902 sq.ft. (8 acres and 16422 sq.ft.). It is not possible for the allottee  

to contend that he will pay only the proportionate actual cost of his plot. If the  

cost of the plot has to be worked out, the cost relating to proportionate share  

in the common/service areas (roads, parks, playgrounds etc.) should be  

added. That means at least addition of another 40% to the price worked out  

for the actual extent of the plot. With reference to the cost worked out by the  

society, if 40% is added, the increased cost of plot would be around  

Rs.16,987.60. According to the society the original tentative cost for the plot  

was Rs.3,000. Therefore the increase in cost would be around 14,000. What  

is demanded as additional amount is Rs.16,770. The difference is hardly  

2770 which may be attributable to the increase in the cost of development/  

construction. It cannot therefore be said that the amount claimed under the  

demand notice dated 21.5.1988 is excessive or unreasonable. Neither party  

has given the full data or facts or accounts. The allotment was made 35 years  

back. No purpose would be served by remitting the matter for re-examination.  

On the facts and circumstances, we are satisfied that the demand is not open  

to challenge.

27. The only aspect that required to be corrected is the rate of interest.  

The demand notice dated 21.5.1988 claims interest at the rate of 13% or 14%

15

Page 15

per annum on the outstanding with effect from 1.7.1988 which is contrary to  

the provisions of contract. The board will be entitled to only simple interest at  

9% per annum. The Division Bench of the High Court has already held that  

the interest should be only at 9% per annum.  

28. We accordingly allow the appeal filed by the Board in part and dismiss  

the appeal filed by the society. We uphold the demand for increase in price  

on account of final cost made by the board but confirm that the interest  

payable on the increase should be only 9% per annum as directed by the  

High Court. The Board will now calculate the amounts due accordingly and  

after giving credit to the amounts already paid, demand only the balance due.  

The respective allottees who are members of the society, shall be permitted  

to pay the same in six quarterly instalments. If there is any error in  

arithmetical calculations, it is open to the respective allottee to point out the  

same to the Board for its consideration.