T.NADU HOUSING BOARD Vs SERVICE SOCIETY
Bench: R.V. RAVEENDRAN,A.K. PATNAIK
Case number: C.A. No.-002320-002320 / 2011
Diary number: 15131 / 2008
Advocates: T. HARISH KUMAR Vs
V. BALACHANDRAN
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 1
TAMIL NADU HOUSING BOARD v.
THE SERVICE SOCIETY & ANR. (Civil Appeal Nos. 2320 of 2011)
MARCH 04, 2011 [R.V. Raveendran and A.K. Patnaik, JJ.]
[2011] 6 SCR 1
The Order of the Court was delivered by
O R D E R
R. V. RAVEENDRAN J.
1. Leave granted.
2. The first respondent (‘Society’ for short) requested the state
government (second respondent) to provide a Low Income Group housing
scheme for the benefit of its members who were the employees of Tamil
Nadu Electricity Board. The state government directed the Tamil Nadu
Housing Board, the appellant herein (‘The Board’ for short) to execute the
said scheme. To meet the requirements of the employees of the Electricity
Board as also the staff of the appellant, the state government acquired an
extent of 8.38 acres of land in Singanur Village, Coimbatore. The Board
formulated a scheme for development of the said land and construction of
145 LIG Houses and 120 LIG flats therein. In pursuance of it, in the year
1976, the Board allotted to several members of the society, LIG Houses, each
house comprising a plot measuring about 40’ x 26’ (1040 sq.ft.) and a
proposed construction measuring 316 sq.ft. Though the standard
measurement of the proposed plots was 1040 sq.ft, the actual extents of
some of the plots were different, that is 1000 sq.ft, 1021 sq.ft, 1150 sq.ft,
1235 sq.ft etc. For convenience we will refer to the facts relating to the
allottee of LIG House No.49 which comprised a plot measuring 1000 sq.ft.
and a house measuring 316 sq.ft.
Page 2
3. The tentative allotment price was fixed by the Board as Rs.18,000/-
(made up of cost of plot, cost of development and cost of house) and each
allottee was required to make an initial deposit of Rs.3000/- and pay the
balance in agreed monthly instalments. The Board also entered into a lease-
cum-sale agreement in November 1977 with the allottee containing the terms
and conditions of lease and the option for sale. Clause 17 of the said
agreement providing for sale of the LIG House to the allottee is extracted
below:
“The lessor agrees to sell the property more particularly described in the
schedule hereunder to the lessee for such price as the Administrative
Officer of the lessor may at any time in his sole discretion fix and at which
time the Administrative Officer of the lessor is entitled to consider details
regarding development charges, cost of amenities, cost of buildings etc.,
and whether the price of the land acquired under the Land Acquisition Act
together with suitable modifications thereto by the local laws become final
by a conclusive adjudication thereon by the concerned tribunals and
courts. The final decision of the Administrative Officer of the lessor are to
be the final price of the property as determined under these presents is
conclusive and binding on the lessee and the lessee agrees to purchase
the property from the lessor as the said price on the terms and conditions
hereinafter mentioned.
Excepting the fixation of price with reference to the claim of compensation
adjudicated or awarded by courts finally and conclusively with regard to
the lands acquired under the scheme, the lessor shall fix the price of the
property after taking into consideration the development charges, cost of
amenities and buildings etc. within a period of three years from the date
of allotment and which price is subject only to a revision on account of
excess compensation if any awarded by the courts for the lands as
aforesaid.”
Page 3
Clause 24 of the agreement required the allottee-cum-lessee to pay interest
on the amounts outstanding, at the rate of 9% per annum. The Board did not
disclose to the allottees, the break-up of the tentative cost, as to how much
for the land, and how much for the development cost and construction.
4. Though clause 17 contemplated the final price being fixed within three
years from the date of allotment, the Board did not fix the final price within
that period. The Board determined the final price only in the year 1988, nearly
12 years after the allotment and sent a demand letter dated 21.5.1988
informing the allottee that the final cost of the LIG House No.49 was
Rs.34,770/- as against the tentative price of Rs.18,000/- and called upon the
allottee to remit the difference in cost of Rs.16,770/- (plus Rs.351 payable to
the municipal corporation) on or before 30.06.1988. The allottee was required
to pay the said amounts on or before 30.06.1988, failing which the amount
due would carry interest at 14%/13% per annum from 1.7.1988. The Board
also clarified that the increase in the cost was mainly on account of payment
of increased compensation for the acquisition of land.
5. Feeling aggrieved, the society, acting on behalf of its members who
were the allottees of the LIG houses, filed an appeal before the state
government challenging the said demand. The appeal was dismissed by
order dated 31.10.1991. The society thereafter filed WP No.15635 of 1991 for
quashing the appellate order dated 31.10.1991 of the state government and
sought a direction to the Board not to demand from its members, any
increase in price as demanded in May 1988. The society contended that
having regard to clause 17 of the lease-cum-sale agreement, the final cost
had to be determined within three years from the date of allotment; that such
a determination not having been done, the tentative price of Rs.18,000/-
should be deemed to be the final price; and that the Board could not make a
demand for increase in price, after expiry of 12 years. Alternatively, it was
submitted that in the event of the court holding that the Board could demand
the increase in cost, that should be only in respect of the land cost
Page 4
component and not with reference to the components relating to cost of
development and cost of construction. It was lastly contended that the
amount determined and demanded by the Board as the final cost was
excessive and the Board had failed to justify the final cost demanded by
giving any break up or particulars of the claim.
6. The Board resisted the petition contending that the final price was
determined with reference to the cost of the acquisition of the land and the
cost of development and cost of construction. It stated that the delay in
finalizing the final cost was on account of the pendency of dispute raised by
the land owners in regard to increase in compensation for the acquired land
and on account of encroachments over part of the acquired land. It contended
that the final cost was based on actuals and it was not excessive. It was
submitted that only a few of the LIG Houses and flats were allotted to the
members of the society and the remaining houses were allotted to its own
employees and to members of public; and that except 55 allottees, all others
had remitted the amount demanded.
7. A learned single judge of the High Court by order dated 29.4.1999
allowed the writ petition and quashed the appellate order dated 31.10.1991 of
the state government and the demand by the Board for increase in price. The
Board filed a writ appeal challenging the order of the learned Single Judge.
8. During hearing before the division bench, both sides filed calculation
sheets showing the cost of acquisition and the consequential increase in the
cost of the LIG house. As per the calculation sheet filed by the society, the
balance payable by each allottee towards increase in land cost was Rs.8634/-
per plot of 1040 sq.ft. (after adjusting Rs.3000/- paid as initial payment and
Rs.500/- paid as EMD) and the interest payable thereon from 17.4.1985 to
6.11.1991 was Rs.5148/- in all Rs.13,782/- towards increase in land cost and
interest as on 30.11.1991. The society alleged that the Board had indicated at
the time of allotment, that the tentative price of Rs.18000 was made up of
Page 5
Rs.3000/- towards land cost and the balance towards development cost and
construction; and that as no increase in regard to development
cost/construction was notified to the allottees, within three years of allotment,
the price component towards development/construction (which according to
the society was Rs.15,000/- out of a total price of Rs.18,000/-) attained finality
under clause 17 of the agreement. It was submitted that the amount payable
by an allottee to the Board on account of the increase in cost of land was
Rs.13,782/- plus interest at 9% per annum on Rs.8,634/- from 1.12.1991 to
date of payment.
9. On the other hand, the calculation sheet filed by the Board showed the
total acquisition cost of the land (8 acres 38 cents) including interest upto
31.3.1987 was Rs.35,02,727.24. The Board contended that on that basis, the
cost of land and development per ground (an area of 2400 sq.ft) was
Rs.40,400/- and each allottee should pay the proportionate cost based on the
actual sital area of the LIG House allotted to him and interest in addition.
10. The division bench its judgment dated 7.8.2007, held after referring to
the two calculation sheets, that the interests of justice would be met if each
allottee is directed to pay an additional sum of Rs.13,780/- towards the
increased cost of the plot and Rs.5,148/- towards interest in all Rs.18,928/- as
on 30.11.1991 with further interest at 9% per annum. The High Court
assumed that all plots measured 1040 sq.ft. It did not indicate any reasons for
arriving at the said amount nor did it record any finding as to the correctness
of the calculations by the society and the Board.
11. Feeling aggrieved, the Board and the society have filed these two
appeals. On the contentions urged, the following questions arise for our
consideration :
(i) Whether the Board is barred from fixing the final price on the expiry
of three years from the date of allotment, resulting in the tentative
price becoming the final price?
Page 6
(ii) Even if the Board could fix the final price beyond three years,
whether only the land cost component could be increased out of the
tentative price and not the cost of development or cost of
construction?
(iii) Whether the Board failed to justify the increase demanded by it?
Re. question (i)
12. The letter of allotment and the lease-cum-sale agreement enable the
Board to take note of the cost of land, cost of development and amenities,
and cost of the building to determine the final price. It is not in dispute that
when the allotment was made in the year 1976, the layout was yet to be
developed, the construction had not yet begun and the compensation for the
acquired land was yet to be determined by the Land Acquisition Collector.
The price indicated at the time of allotment was therefore purely tentative.
The Board did not undertake the scheme as a commercial venture but on ‘no
loss-no profit basis’, with a loan from HUDCO. Therefore obviously it has to
pass on the liability for the entire cost to the allottee who opted to buy the LIG
house under the scheme. The allotment was on lease-cum-sale basis and
until the LIG House was conveyed in favour of the allottee, he continued as a
lessee of the Board and does not acquire any ownership rights.
13. The reference to the period of three years in clause 17 was not
intended to be prohibition upon fixation of final price thereafter. The work of
development of an acquired land into a residential layout and construction of
houses therein were expected to be completed within three years, but final
determination of the claims for increase in compensation for acquired land
was expected to take much longer. Clause 17 therefore provided that the final
price will be decided within three years, subject however to further revision
with reference to the land cost. If the Board completed the development of the
layout and construction of houses within three years and if there are no
pending claims, it is bound to fix the final price of the LIG house within three
Page 7
years from the date of allotment (even if the land acquisition cost had not
been finalized) and if necessary, revise the final cost subsequently, after
determination of land acquisition cost.
14. But where the development of the layout and construction of houses
were not completed within three years from the date of allotment, the Board
obviously could not determine the final cost within three years as neither of
the three components (cost of land, cost of development and cost of
construction) would be known to the Board. There is no term or provision in
the contract that if the Board does not determine the final price within three
years from the date of allotment, the Board would lose the right to determine
the final price thereafter or that the tentative price would become the final
price. If on account of delay in determination of compensation for land
acquisition or delay on the part of the contractors in completing the
development works or construction, or if there are any encroachments or if
there are pending claims of contractors regarding development or
construction, the Board would not be able to determine the final cost within
three years. But that did not mean that the tentative cost would become the
final cost in the absence of such a provision in the letter of allotment or lease-
cum-sale agreement.
Re :question No.(ii)
15. The alternative submission of the society is that even if the price could
be increased after three years, having regard to clause 17 of the lease-cum-
agreement, what could be increased after three years is only the land cost
component and not the cost of the development or building. Clause 17 states
that except the fixation of price with reference to the compensation finally
awarded by the courts, the board should fix the price of the LIG house after
taking into consideration the development charges, cost of amenities and cost
of buildings within three years from the date of allotment. If the final price is
so fixed, thereafter what could be increased is only the land cost component
Page 8
on account of any increase in compensation that may be awarded by the
courts. If the board had earlier fixed the final price, the society’s contention
might have merited acceptance as the component of price with reference to
cost of development and amenities and cost of building would have attained
finality on account of such final determination and only the increase on
account of award of compensation for land could be demanded after such
determination of final price. But where the final price has not been determined
at all, for whatsoever reason, and the final cost was being determined for the
first time, the allottee cannot contend that only the increase on account of the
land, and not the increase on account of development cost and construction
cost, could be demanded. Where the final price has not been fixed, the Board
could, after ascertainment of various costs, determine the final price even
after three years, and the finality in regard to cost of development and
amenities and the cost of construction, referred under clause 17, would not
apply.
16. It is not in dispute that the compensation in regard to the land was
pending in courts and was finally determined in or about 1985. It is also not in
dispute that development work could not also be completed as a portion of
the acquired land was under encroachment. Therefore it is not possible to say
that when the final price was fixed in the year 1988, it could be only with
reference to increase on account of land and not with reference to increase in
the development cost or construction cost. The demand letter dated
21.5.1988 of the Board clearly states that the increase in price demanded
was mainly due to increase in compensation for the land paid by the Board
and only a small portion of the increase was under the other heads.
Re: question No.(iii)
17. The High Court, we find, has not appreciated the controversy in the
correct perspective nor decided the matter in issue. The finding of the learned
single judge that the Board is not entitled to any increase is contrary to the
Page 9
terms of allotment. The letter of allotment and the lease-cum-sale agreement
make it clear that the price mentioned in the letter of allotment was only
tentative and final price was to be determined taking into account, the final
cost of acquisition, cost of development and amenities, and cost of the
building. The fact that, subsequent to the allotment of the LIG Houses and
execution of lease-cum-sale agreements, the land acquisition cost increased
substantially was not in dispute. Similarly, if there was any increase in the
actual cost of development/construction the allottees had to bear it. The
Board could not be made liable to bear the extra cost as it was operating on
‘no-profit, no-loss basis’ and had obtained a loan from HUDCO to execute the
scheme. The division bench referred to the contentions of the parties and
extracted the calculation sheets filed by both parties, but did not pronounce
upon the correctness of the same. It neither accepted nor rejected the
calculation sheets filed by the Board and the Society. The sum of Rs.13,780/-
found by it to be increase in cost and Rs.5,148/- as interest, were apparently
borrowed from the calculation sheet filed by the Society. But as per the
calculation sheet of the society the increase in land cost (over and above the
deposit of Rs.3500/-) was Rs.8,634/- and interest upto 30.11.1991 was
Rs.5148/-, the total being Rs.13,782/-. The High Court however wrongly
assumed that as per the calculation sheet of the Society, the increase in the
cost of the plot itself was Rs.13,782/- (rounded of to Rs.13780/-) and the
interest of Rs.5,148/- was in addition to Rs.13,782/- and direct such payment.
This is without any acceptable basis.
18. The cost of a house constructed by a development authority or
Housing Board has the following three components: (a) the cost of the plot;
(b) the proportionate share in the cost of development and amenities (like
water, electricity, sewage disposal etc.) and (c) cost of construction of the
house. Where the construction is taken up in a developed layout, and not in
an undeveloped land, item (b) will not be an independent component, but be
a part of item (a).
Page 10
19. If a development authority or board acquires a large tract of land and
develops it for residential purposes and forms plots in a portion thereof for
construction of houses, utilises another portion for construction of multi-
storeyed apartment buildings and uses the balance for development works
like roads, drains, parks, open spaces apart from earmarking some areas for
site office/electrical sub-station/police station, etc., then what is chargeable to
the allottee of a plot or a house, is not only the cost of the plot area, but also
the cost of the proportionate share in the common areas, used for
development and amenities and the cost of the development.
20. We may illustrate. If 5 Hectares (50000 sq.m.) of land is acquired for
formation of residential plots each measuring 250 sq.m., it is not possible for
the authority to carve out 200 plots (each measuring 250 sq.m). This is
because, not less than 25% to 30% of the total sital area will be used up for
forming roads, footpaths and drains. Another 10% to 20% may be used for
common facilities and amenities like park, playground, community hall etc.
The common/service areas are not saleable and the board will have to
recover the cost thereof by loading the proportionate cost thereof, on the cost
of the residential plots. Therefore if 40% is the area used for roads, drains,
parks, playgrounds etc., the saleable area or area that can be used for
forming plots would be only 60% and the cost of the total land 50000 sq.m.
will have to be recovered from the sale of the said 60% area (30,000 sq.m.)
which can be carved into 120 plots of 250 sq.m. If the total value of 5
hectares is Rs.60 lakhs, the value of a plot of 250 sq.m. will not be
Rs.30000/- (that is Rs.60 lakhs divided by 200) but Rs.50,000/-(that is Rs.60
lakhs divided by 120). An allottee of a plot measuring 250 sq.m. cannot
therefore contend that he is liable to pay only the actual proportionate cost of
250 sq.m. of land out of 50000 sq.m. The proper method is to calculate the
total common/service area (used for roads, drains and common amenities)
and include the proportionate cost thereof in the price of the plot.
Page 11
21. When a large undeveloped tract is acquired by a development
authority or a Board, considerable amounts will have to be spent for
developing it, to make it suitable for residential use. This will include the cost
of levelling the land, forming plots, laying roads and drains, drawing electrical
lines, laying water and sewerage pipes, providing electricity and water etc.
This cost also will have to be proportionately borne by the allottee as
development cost. Some authorities even load the cost with reference to its
overheads, that is, a proportionate cost, depending upon the norms, rules and
regulations. In Preeta Singh vs. Haryana Urban Development Authority –
1996 (8) SCC 756, this Court held :
“It is to be remembered that the respondent HUDA is only a statutory
body for catering to the housing requirement of the persons eligible to
claim for allotment. They acquire the land, develop it and construct
buildings and allot the buildings or the sites, as the case may be. Under
these circumstances, the entire expenditure incurred in connection with
the acquisition of the land and development thereon is required to be
borne by the allottees when the sites or the buildings sold after the
development are offered on the date of the sale in accordance with the
regulations and also offered on the date of the sale in accordance with
the regulations and also conditions of sale.”
The calculation sheet of the Society which works out the cost of land with
reference to the actual size of the plot ignoring the proportionate share in the
cost of the common/service areas (roads, drains, etc.) and the development
cost, is therefore liable to be rejected.
22. Whenever allotments are made even before the completion of the
development of land and construction, necessarily the cost that is shown by
the authority or the board will be tentative. In regard to the land cost, there
may be claims for enhancement of compensation before the reference court
with appeals to high court and this court. Sometimes the entire process may
Page 12
take 10 to 15 years and till that process is concluded the final cost of the land
cannot be determined. An allottee cannot therefore say that the authority
cannot increase the cost after 12 years. Similarly cost of developing of land
into residential area requires coordination with different contractors engaged
for laying roads, laying drains, developing parks and playgrounds, drawing
electricity lines, water lines, sewerage lines etc. Many times, disputes with the
contractors lead to delays and litigation. Sometimes though the work may be
completed within three years, the settlement of bills and ascertainment of cost
may take several years. There may also be encroachments, which will have
to be removed which apart from being time consuming and involving litigation,
delay the development and finalization of cost of development. As a
consequence, the development cost may also shoot up beyond the estimate
on account of delays, additional claims of contractors, litigations and other
factors. The same applies to the cost of construction of the houses also.
Therefore an allottee cannot contend that the increase, if any, should be
determined within three years and if the increase is not so determined, the
tentative cost would itself become the final cost. Such an interpretation of
clause 17 would be illogical and unreasonable. If the Board is able to show
that there was sufficient cause for the delay in deciding the final price and that
it was beyond its control to determine the final cost earlier (or within three
years) it will be entitled to final cost even if the claim is delayed by a few
years. The allottee cannot refuse to pay it merely on the ground of delay.
23. On the other hand the authority or Board should also be diligent.
Allottees belonging to low income groups should not be made to suffer for the
defaults or negligence on the part of the staff of the authority. They should
take prompt steps to settle claim regarding compensation. They should also
be prompt in executing the development works and construct work. They
should ensure that the cost is kept to the minimum. If any allottee approaches
court and is able to demonstrate that the development and construction work
was completed within three years, but the authority failed to fix a final cost, it
Page 13
may be possible to infer that there was no increase from the tentative cost
and therefore the final cost was not fixed and therefore the tentative cost
should be the final cost. Be that as it may.
24. In view of the complex nature of acquisition, development,
construction and allotment, it is necessary to safeguard the interests of the
allottees and at the same time ensure that there is no loss to the public
exchequer or the authority by making it to bear any part of the cost of
development or cost of the plot or cost of construction. Normally a claim by
the authority or the board for increase should be accepted if the authority or
board certifies that what is claimed is the actual final cost, and supports it by
a certificate from an independent chartered accountant or its own Accounts
Department showing the break up of the cost. A standard certificate should
furnish the following :
(a) break up of the tentative allotment price in regard to the plot,
development and construction;
(b) break up of the final cost in regard to the plot, development and
construction;
(c) a table showing total area, area used for plots, area used for
common/service areas like roads, drains, parks and open spaces;
(d) a table showing the acquisition cost; and
(e) a table showing the construction cost.
It is open to the allottee to apply for the particulars and have it verified
independently, before rushing to court.
25. Let us now examine whether the amount claimed by the board in this
case is excessive. As noticed above in regard to a plot measuring 1000 sq.ft.
with a residential house measuring 361 ft. the board had indicated the
tentative price as 18000 in the year 1976. After the compensation for land
was decided by courts and after carrying out the development work and
Page 14
construction, the board determined the final cost as Rs.34,770 in the year
1988 and demanded the difference of Rs.16,770/-. The question is whether
this claim is excessive.
26. We find that the allottees/society do not dispute that the cost of the
land increased considerably on account of enhancement of compensation.
The board showed that the total cost of land inclusive of interest upto
31.3.1987 was Rs.35,02,727 for 8 acres and 16422 sq.ft. The said figure was
broadly accepted by the society, in its calculation sheet. The society arrived
at the cost of a plot measuring 1040 sq.ft. as 3500 (paid as deposits) plus
Rs.8634/- which aggregates to Rs.12,134. But as noticed above, this is the
proportionate cost worked out for 1040 sq.ft. out of the total cost of an extent
of 33,64,902 sq.ft. (8 acres and 16422 sq.ft.). It is not possible for the allottee
to contend that he will pay only the proportionate actual cost of his plot. If the
cost of the plot has to be worked out, the cost relating to proportionate share
in the common/service areas (roads, parks, playgrounds etc.) should be
added. That means at least addition of another 40% to the price worked out
for the actual extent of the plot. With reference to the cost worked out by the
society, if 40% is added, the increased cost of plot would be around
Rs.16,987.60. According to the society the original tentative cost for the plot
was Rs.3,000. Therefore the increase in cost would be around 14,000. What
is demanded as additional amount is Rs.16,770. The difference is hardly
2770 which may be attributable to the increase in the cost of development/
construction. It cannot therefore be said that the amount claimed under the
demand notice dated 21.5.1988 is excessive or unreasonable. Neither party
has given the full data or facts or accounts. The allotment was made 35 years
back. No purpose would be served by remitting the matter for re-examination.
On the facts and circumstances, we are satisfied that the demand is not open
to challenge.
27. The only aspect that required to be corrected is the rate of interest.
The demand notice dated 21.5.1988 claims interest at the rate of 13% or 14%
Page 15
per annum on the outstanding with effect from 1.7.1988 which is contrary to
the provisions of contract. The board will be entitled to only simple interest at
9% per annum. The Division Bench of the High Court has already held that
the interest should be only at 9% per annum.
28. We accordingly allow the appeal filed by the Board in part and dismiss
the appeal filed by the society. We uphold the demand for increase in price
on account of final cost made by the board but confirm that the interest
payable on the increase should be only 9% per annum as directed by the
High Court. The Board will now calculate the amounts due accordingly and
after giving credit to the amounts already paid, demand only the balance due.
The respective allottees who are members of the society, shall be permitted
to pay the same in six quarterly instalments. If there is any error in
arithmetical calculations, it is open to the respective allottee to point out the
same to the Board for its consideration.