04 October 2005
Supreme Court
Download

STATE OF RAJASTHAN Vs M/S. NAV BHARAT CONSTRUCTION COMPANY

Bench: S. N. VARIAVA,TARUN CHATTERJEE
Case number: C.A. No.-002500-002500 / 2001
Diary number: 8386 / 2000
Advocates: Vs RESPONDENT-IN-PERSON


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 17  

CASE NO.: Appeal (civil)  2500 of 2001

PETITIONER: State of Rajasthan                                                       

RESPONDENT: M/s Nav Bharat Construction Company                      

DATE OF JUDGMENT: 04/10/2005

BENCH: S. N. Variava & Tarun Chatterjee

JUDGMENT: J U D G M E N T [With Civil Appeal No.2501 of 2001]

S. N. VARIAVA, J.         These Appeals are against the Judgment dated 10th December  1999 of the Rajasthan High Court.         Briefly stated the facts are as follows.         The Appellants invited tenders for construction of Bhimsagar  Dam.  Pursuant thereto, various tenders were received. Ultimately the  tender of the Respondent was accepted. A contract was awarded to  the Respondent on 18th January 1979.  Under the contract, the work  was to be started on 16th November 1978 and to be completed by 15th  May 1981.  The work was not completed within this time and time was  extended.  It appears that the work was not completed within the  extended time also. The Appellants terminated the contract and got  the balance work completed from some other contractor.           The Respondent raised various claims which were rejected by  the Appellants.  The Respondent, therefore, moved an application  under Section 20 of the Arbitration Act, 1940 for referring the claims  mentioned therein to arbitration.  By an Order dated 11th November  1982, the District Judge held that only one claim was referable to  arbitration and refused to refer the other three claims to arbitration.           The Respondent filed an Appeal before the High Court.  The High  Court by its Order dated 7th June 1984 held that it was for the  Arbitrator to decide whether the claims were to be awarded or not.  The High Court held that reference could not be refused and,  therefore, directed that all the four claims be referred to arbitration.            Even before the High Court passed the Order dt. 7th June 1984,  the Respondent had, on 31st March 1983, filed another application  under Section 20 of the Arbitration Act, 1940.  By this application the  Respondent  sought reference of 24 more  claims.  The District Judge  by an Order dated 1st March 1985 allowed the application.         The disputes were referred to two Arbitrators. One Shri M.K.  Gambhir was appointed by the Appellants and Shri Leeladhar Aggarwal  was appointed by the Respondent. The Respondent, however, filed 39  claims amounting to Rs. 42,59,155.56 before the Arbitrators.         Parties led oral and documentary evidence. There was a  difference of opinions between the two Arbitrators.  Therefore, the  Arbitrators referred the disputes to an Umpire viz. one Shri V. K.  Gupta.         The Appellants filed an application under Section 11 of the  Arbitration Act, 1940 for removal of Shri V. K. Gupta as an Umpire on  the ground of bias.  This application was dismissed on 16th November  1993 inter alia on the ground that there was no evidence to show that  there was any bias.  The Appellants filed a Revision which also came to  be dismissed by the High Court in January 1995.         The Umpire entered into the reference and gave an Award on  29th May 1995.  The operative part of the Award reads as follows:- "...... And having carefully considered the oral

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 17  

evidence, the documents, site topographical  conditions, analysis of rates, technical  specifications, other exhibits filed by the  parties, the operations required for various  items of existing B.S.R. and newly approved  rates for Bhim Sagar Dam, Schedule ‘C’ the  conditions of the contract, P.W.F.A.R. and  various case laws cited by the parties, I make  the award as under:-  

       I award an amount of Rs. 29,96,060/-  (Rupees Twenty nine lacs Ninety-six thousand  and sixty only) payable by the Respondents to  the Claimants against claim Nos. 1 to 39  except Claim No. 30 (as awarded below  separately) and enumerated under paras 15  and 16 of the statement of claims of the  Claimants.                    I further award refund/release of the  Bank F.D.R.S. amounting to Rs. 2,84,000/-  (Rupees two lacs eighty-four thousand only)  being security deposit by the Respondents in  favour of Claimants as claimed under para 17  of the Claim statement.                  I award an interest difference of (18% -  F.D.R. interest rate on F.D.R. amount w.e.f.  15.12.82 till released to the Claimants or  decreed whichever is earlier however the  interest already accrued from 17.11.78 upto  14.12.82 is to be reduced from the final  calculated sum.

       I also award an interest @ 18% per  annum from 15.12.82 to 14.7.83 on total  amount of claims except F.D.R. amount  payable to Claimants as prior to reference.

       I further award an interest @ 18% p.a.  from 15.7.83 to 29.5.95 on total amount of  Claims except F.D.R. amount payable to  Claimants as pendente lite interest.

       I further award an interest @ 18% p.a.  on total amount of Claims except F.D.R.  amounts beyond 29.5.95 upto the date of  payment or decree of the Court whichever is  earlier.

       I further award that the Respondents  shall pay a part of the cost of arbitration and  part of fees of arbitrator and Umpire to the  extent of Rs.20,000/- to the Claimants."           

       The Appellants filed objections under Sections 30 and 33 of the  Arbitration Act 1940, which were dismissed by the Trial Court on 16th  July 1996.      The Appellants filed an Appeal before the High Court and  the Respondent filed a Cross-Appeal claiming compound interest.   The  High Court by the impugned Judgment dismissed both the Appeals.    Civil Appeal No.2500 of 2001 is by the Appellants who are aggrieved  by the dismissal of their objections.  Civil Appeal No.2501 of 2001 is  by the Respondents against dismissal of their claim for compound  interest.         Mr. Mohta has assailed the Award on five grounds:

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 17  

(1)     that the Umpire was biased against the Appellants inasmuch  as he was  person, who regularly appeared for the  Respondent in arbitration matters and assisted the  Respondent in their arbitration cases;  (2)     that the Court had referred only 28 claims yet all the 39  claims have been allowed by the Umpire.  It was submitted  that in respect of the claim which had not been referred to  arbitration the Umpire had no jurisdiction to arbitrate and the  Award in respect of those claims had to be set aside;  (3)     that as there had been a difference of opinion between the    two Arbitrators and, one of the Arbitrators namely, Mr.  Gambhir, had given a speaking and reasoned Award, the  Umpire was also bound to pass a reasoned Award.  It was  submitted that by not giving a reasoned Award the Umpire  had misconducted himself;  (4)     that the Umpire had misconducted himself inasmuch as he  had  not applied his mind to the terms of the contract and  had awarded contrary to the terms of the contract; and  (5)   that the interest awarded is very high and that in an identical  matter between the same parties, reported in (2002) 1 SCC  659, this  Court has reduced interest to 6%. Mr. Mohta first submitted that the Umpire was biased against the  Appellants inasmuch as he was the person, who regularly appeared for  the Respondent in arbitration matters and assisted the Respondent in  their arbitration cases. Mr. Mohta relied on the case of Ranjit Thakur  vs. Union of India & Ors. reported in (1987) 4 SCC 611. In this case  it has been held that the test of real likelihood of bias is whether a  reasonable person in possession of relevant information would have  thought that bias was likely and whether the authority concerned was  likely to be disposed to decide the matter only in a particular manner.  It is held that what is relevant is the reasonableness of the  apprehension in that regard in the mind of the party. Mr. Mohta also  relied on the case of Jiwan Kumar Lohia & Anr. Vs. Durga Dutt  Lohia & Ors. reported in (1992) 1 SCC 56 wherein also the same  principles have been reiterated.   We see no substance in this first  ground of challenge.  On the   ground now urged the Appellant had  earlier filed an application for removal of the Umpire.  That application  came to be rejected on 16th November 1993 and an Appeal against  that Order was also dismissed in January 1995.   Having failed in their  attempt to remove the Umpire, in our view, this ground is no longer  available to the Appellants.   Even otherwise except for making bare  averments no proof has been produced to substantiate the averments.  If, as claimed, this Umpire was appearing for and/or regularly assisting  the Respondents there would be documents showing his name/  appearance. None have been produced.   So far as the second ground is concerned, we have seen the two  applications made by the Respondent.  It prima facie appears that the  two applications were for referring, in all, 28 claims to arbitration.  The  Respondent then made 39 claims before the Arbitrators. The Umpire  has awarded in respect of all the 39 claims.  If claims not referred to  Arbitration have been dealt with and awarded the Umpire would have  exceeded his jurisdiction. However Mr. Moolchand Luhadia, partner of  the Respondent who appeared in person, contended that all the claims  were referred to the Arbitrators by the Order dt. 1st March 1985. He  submitted that this is clear from the directions to the Arbitrators to  decide all disputes arising between the parties. We are unable to  accept this submission. The Order dt. 1st March 1985 allows  "application dt. 9th April 1983 as part of application dt. 5th October  1981". It is in the context of claims raised in these two applications  that the Arbitrators are instructed to decide all disputes between the  parties. Mr. Lohadia then submitted that all claims were  included in  the two applications made by them.   It was submitted that in the  applications some of the claims were clubbed together but whilst filing  the statement of claims they were segregated and separated.  As we  are proposing to refer the matter back to an Umpire, we do not

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 17  

propose to go into the question as to whether or not the 39 claims  were part of the two applications filed by the Respondent.   In our  view, this is a question which can be decided by the Umpire.  All that  we need to clarify is that if any claim did not form part of the two  applications the same cannot be arbitrated upon and the Umpire will  confine the reference   to the claims made in the two applications. It  must be mentioned that in the case of Orissa Mining Corporation  Ltd.  Vs. Prannath Vishvanath Rawlley reported in (1977) 3 SCC  535 this Court has held that when an agreement is filed in Court and  an order of reference is made, then the claim as a result of the order  of reference is limited to that relief and the arbitrator cannot enlarge  the scope of reference and entertain fresh claims without a further  order of reference. It must also be mentioned that Mr. Lohadia had  relied upon the case of H. L. Batra & Co. vs. State of Haryana &  Anr. Reported in (1999) 9 SCC 188. In this case the award of the  arbitrator was set aside and a new arbitrator was appointed. The order  stated that the new arbitrator was appointed "for settling disputes  between the parties". Before the new arbitrator 7 additional claims,  over and above the 30 claims originally made, were made. It was held  that the award was not vitiated as the terms of reference did not  confine the second reference to only 30 claims. This authority is of no  assistance to the Respondent as it does not lay down that the  arbitrator can entertain claims not referred to him.          We, however, see no substance in the third ground i.e. that  reasons should have been given by the Umpire.  It is settled position  that under the Arbitration Act 1940, unless the contract so required,  reasons were not required to be given.  A Constitution Bench of this  Court in the case Raipur Development Authority & Ors. vs. M/s  Chokhamal Contractors & Ors., reported in (1989) 2 SCC 721, has  held that it is not necessary to give reasons and that an Award cannot  be set aside merely because it is a non-speaking Award.  The mere  fact that two Arbitrators had differed and that the matter was required  to be dealt with by an Umpire does not mean that the Umpire should  give reasons for his Award. We further clarify that the Umpire now  being appointed by us need not give reasons.         Mr. Mohta had next contended that the Umpire has  misconducted himself inasmuch as he had ignored the terms of the  contract and awarded contrary to the terms of the contract.  To this  objection, the Respondent had submitted that such a point had neither  been urged before the District Judge nor before the High Court.  We,  however, find that this point has in fact been urged both before the  District Judge as well as before the High Court.  This point, therefore,  requires to be considered.         In order to consider this point, some of the terms and conditions  of the tender documents and the contract are required to be set out.   The Respondent has given a declaration which inter-alia reads as  follows: "1. I/We have visited the Site and fully acquainted  myself/ourselves the local situation regarding  materials, labour and other factors pertaining to  the  work before submitting this order.

2.      I/We carefully studied the N.I.T. conditions  of contract, specification, additional instructions,  general rules and directions and other  documents related to this work and I/We agree  to execute the work accordingly.

......................................................................

I/We do hereby tender for the execution for the  Rajasthan Government of the work specified as  above within the time specified in Schedule ‘F’  and at the rates entered in Schedule ‘G’.  The

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 17  

work will be carried out in accordance in all  respects with the detailed specifications, designs,  drawings and instructions referred to in the  attached Schedule sheet."

The relevant terms of the tender document (which is part of the  contract) and the contract reads as follows;

"7. HOUSES:- No local housing is likely to be available and the  contract should arrange for suitable housing for  the staff and labour.  Land for the same will be  granted free of charge for temporary use during  the period of contract.

......................................................................

12. SUPPLY OF PETROL AND DIESEL:- The contractor has to make his own arrangements  for the supply of petrol and diesel and lubricants.   The nearest place from where it can be obtained  is Jhalawar.  

......................................................................

Clause 12\027The Engineer-in-Charge shall have  power to make any alterations in or additions to  the original specifications, drawings, designs and  instructions, that may appear to him be necessary  or advisable during the progress of the work and  the contractor shall be bound to carry out the  working in accordance with any instruction which  may be given to him in writing signed by the  Engineer-in-Charge and such alteration shall not  invalidate the contract and any additional work  which the Contractor may be directed to do in the  manner above specified as part of the work shall  be carried out by the contractor on the same  conditions in all respects on which he agreed to  do the main work, and at the same rates as are  specified in tender for the main work.  The time  for the completion of the work shall be extended  in the proportion that the additional work bears to  the original contract work, and the certificate of  the Engineer-in-Charge shall be conclusive as to  such proportion.  And if the additional work  includes any class of work for which rate is  specified in this contract then such class of work  shall be carried out at the rates entered in the  schedule of rates of the district  if it exists and  such last mentioned class of work is not entered  in the schedule of rates of the district, then the  contractor shall, within seven days of the date of  this receipt of the order to carry out the work,  inform the Engineer-in-Charge of the rate which it  is his intention to charge for such class of work  and if the Engineer-in-Charge does not agree to  this rate he shall, by notice in writing, be at  liberty to cancel his order to carry out such class  of work and arrange to carry it out in such  manner as he may consider advisable, provided  always if the contractor shall commence work or  incur any expenditure in regard thereto before the  rates shall have been determined as lastly herein

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 17  

before mentioned, then and in such case he shall  only be entitled to be paid in respect of the work  carried out or expenditure incurred by him prior  to the date of the determination of the rate as  aforesaid according to such rate or rates as shall  be fixed by the Engineer-in-Charge.  In the event  of a dispute, the decision of the Chief Engineer  will be final.

......................................................................

Clause 23\027Except where otherwise specified in  the contract the decision of the Chief Engineer of  the Government of Rajasthan for the time being  shall be final, conclusive, and binding on all  parties to the contract upon all questions relating  to the meaning of the specifications, designs,  drawings and instructions herein before  mentioned and as to the quality of workmanship,  or materials used on the work or as to any other  question, claim, rights, matter, or thing  whatsoever in any way arising out of, or relating  to, the contract, designs, drawings, specifications,  estimates, instructions, order, these conditions or  otherwise concerning the works, or the execution  or failure to execute the same, whether arising  during the progress of the work, or after the  completion or abandonment thereof, or the  contract by the contractor shall be final,  conclusive and binding on the contractor.   

......................................................................

Clause 36\027The Sales Tax or any other tax on  materials issued in the process of fulfilling  contract payable to the Government under rules  in force will be paid by the contractor himself.

......................................................................

Clause 38\027Fair Wages Clause:--(a) The  contractor shall pay not less than fair wage to  labourers engaged by him on the work.

Explanation:-- ‘fair wages’ means minimum  wages for time on piece work fixed or revised by  the State Govt. under the minimum Wages Act,  1948.

(b) The contractor shall not withstanding the  provisions of....................contract to the  contrary cause to be paid fair wages to labourers  indirectly engaged on the work including any  labour engaged by him, his sub-contractors in  connection with the said work as if the labourers  has been immediately or directly employed by  him.

(c) In respect of all labourers indirectly or directly  employed on the work for the purpose of the  contractor’s part of this agreement, the contractor  shall comply with or cause to be complied with  the P.W.D. contractor’s labour regulation made  way of that be made by the Government from  time to time in regard to payment of wages

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 17  

period, deductions, maintenance of wages  register, wage card, publications and submission  of wages periodical returns in all other matters of  like nature.

(d) The Executive Engineer-in-Charge shall have  the right to deduct from the money due to the  contractor may sum required to estimate to be  required for making good the loss suffered by a  worker by reasons of non-fulfillment of the  conditions of the contract for the benefit of the  worker or workers non-payment of wages or  deductions made therefor which are not justified  by the terms of contract or as a result of non- observance of the aforesaid regulations.

(e) Vis-‘-vis the Government of Rajasthan the  contractor shall be primarily liable for all  payments to be made and for the observance of  the regulations aforesaid without prejudice to his  right to claim indemnity from his sub-contract.

(f) The regulations aforesaid shall be deemed to  be part of this contract and breach thereof shall  be deemed to be breach of contract."

Special Conditions of the contract inter-alia provide as follows:

"31 LABOUR CONDITIONS:- (a)     The contractor shall comply with the  labour laws viz. Contractor Labour  Regulation Act, Minimum Wages Act.   Workman’s Compensation Act, Industrial  Disputes Act, etc. as may be current and  shall furnish the returns and information  as any required and be specified from time  to time.   The contractor will have to carry  out registration with the office or Regional  Labour Commissioner, and obtain a valid  licence for employing labour.

(b)     The contractor shall as far as possible,  obtain his requirements of labour, skilled  and unskilled from the local area.  No  person below the age of 12 years shall be  employed as labour.

(c)     The contractor shall pay fair and  reasonable wages (whether or not such  wages are controlled by any Laws existing  at the time) to the workmen employed by  him for the work.  In the event of any  disputes arising between the contractor  and his workmen on the grounds that the  wages paid are not fair and reasonable the  dispute shall in the absence of legal or  other relief to the workmen, be referred to  the Engineer who shall decide the same  the decision of the Engineer shall be  conclusive and binding on the contractor  but such decision or any decision in this  behalf that the contractor’s workmen may  obtain by resource to law or other legal  means available to them, shall not, in any  way, affect the condition in the contract

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 17  

regarding payment to be made by Govt. to  the contractor only at the rate accounted  in this contrtact.

(d)     The contractor shall not employ animals  suffering from source, lameness, or  emaciation or which are immature nor  shall treat them in a way that may be  considered in human.

(e)     The Engineer shall have the authority to  remove from the work any animal or  workmen that, in his opinion which shall  be conclusive, he may consider unfit or  undesirable and no responsibility shall be  accepted by the Government for any delay  or extra expenses caused towards the  completion of the work such removal.

(f)     While employing skilled or un-skilled  labourers piece workers the contractor  shall be first preference to the person  certified to him by the Engineer, or his  duly authorized representative as persons  who are adversely affected by the  Bhimsagar submergence and are suitable  for employment and shall be minimum fair  wages not below the minimum which has  been fixed to this implementation of this  work sited by the Engineer, whose  decision shall be final, binding on the piece  worker/contractor.

(g)     The contractor shall employ any famine,  convict or other labour of a particular class  or kind if ordered in writing to do so by the  Engineer.

(h)     Should Government declare a state of  famine to exist in any village within 10  miles of the work, the contractor shall  employee upon such parts of the works  are suitable for unskilled labour, any  persons certified to him by the Engineers  or by a duly authorized agent of the  Engineers, in writing to be in need or relief  and the contractor shall pay to such  persons wages not below the minimum  which the Government may have fixed in  this behalf.  Any disputes which may arise  in the implementation of this provision  shall be decided by the Engineer whose  decision shall be final and binding on the  contractor.  

(i)     The contractor shall provide reasonable  facilities to the satisfaction of the  Engineer, for the labour employed by him,  where no such natural facilities exists.   The usual facilities are weather proof  shelter for rest and supply or whole some  drinking water, facilities for obtaining food  reasonable washing and sanitary facilities  special facilities for women workers,  suitable residential accommodation,

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 17  

recreation and cultural activities, general  sanction and health measures etc.

(j)     The implementation of any provision of  this clause shall, in no way, entitle the  contractor to claim compensation or rates  higher than tendered in his contract.

....................................................................

57) The quantities given in Schedule ‘G’ are  approximate and payments will be made on  measurement of actual quantities of different  items of work executed by the contractor.

       The rates quoted shall be for the  committed item in the schedule.  The contractor  is advised to see the site fully and investigate in  detail as to the source of materials availability of  labour means of approach and carrying quarries  to be put stocking of materials putting tools and  plants in use and other site conditions such of  flood levels etc.  He is expected to have  investigated as site the execution of work and  quote his tender accordingly.  No claim on his  account shall be accepted.  It shall be assumed  that his rates quoted in ‘G’ Schedule cover all  possible eventualities that may be not within the  course of execution of this work.

....................................................................

60.  Owning to difficulty in obtaining certain  materials in the open market the Government  has undertaken to supply materials specified in  the schedules of the tender form.  There may be  delay in obtaining materials by the Department  and the contractor is therefore required to keep  in touch with the day to day position of supply of  material from the Engineer-in-Charge need to so  adjust the progress of the work that their labour  may not remain idle not there may be no other  claim due to or arising from delay in obtaining  materials.  It should be clearly understood that  no monetary claim whatsoever shall be  entertained by the Government on account of  delay in supplying way.

61.  Under no circumstances shall any claim for  compensation from the Government on any  account be considered unless the contractor  shall have informed the reasons for the claim in  writing to the Engineer-in-Charge within 7 days  of occurrence of cause of such claim.  Similarly  any hindrances to the work which may cause  extension of period of completion of work shall  be immediately informed in writing to the  Engineer for his consideration."    

Schedule ‘G’ to the contract lists the estimated quantities of items of  work and the rates payable for such work. At the end of this Schedule  a lead statement and some notes appear, the relevant portion of which  reads as follows:

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 17  

"LEAD STATEMENT S.      Items             Source         Lead in        Total  No.                                              Kms.            Km. __________________________________________

1.     Stone Ballast    Local            1 km.          1 km. 2.     Sand               Piplia river   46 km.       46 km.

1) Any extra items if involved will be paid on the  basis of the B.S.R. 1975 of Ajmer Irrigation on  which ‘G’ Schedule is prepared plus the  tendered premium of the Contractor.

2) If any construction material is not available at  the sources indicated in the Lead Statement and  has to be obtained from other sources intimated  in writing by the Executive Engineer and if such  other sources are nearer or further than the  original source indicated recovery or extra  payment will accordingly be made for the leaser  or greater distance involved as per B.S.R. on  which ‘G’ Schedule is based plus the premium  tendered by the contractor."(emphasis supplied)

Thus the Respondents had fully acquainted themselves with the local  conditions and had agreed to execute the work as per specifications  and at the rates specified in Schedule ‘G’. It is only in respect of  additional work that the Respondents were entitled to be paid at rates  set out in B.S.R. 1975. Clause 12 provides that the Respondents  had  to make their own arrangements for petrol, diesel and lubricants.  Clause 31 of the special conditions provides that the Respondent shall  pay fair wages and comply with labour laws. The contract provides  that the fact that the contractor had to pay fair/minimum wages and  comply with labour laws would not entitle the contractor to claim  compensation or rates higher than those tendered in the contract.  Clause 57 of the special conditions provides that the rates quoted in  Schedule G cover all possible eventualities and that no claim can be  made in respect of items like source of material, availability of labour,  means of approach etc.          At this stage it becomes necessary to set out a summary of the  claims made by the respondent. They are as under:            S. No Claim No. Claim Amount  (Rs.) 1 Claim No. 1 Amount of Final Bill 2,00,000.00 2 Claim No. 2 (1) For Chisel Dressed Face Stone 2,78,737.92

(2) Cost of C.R. Stone

3 Claim No. 3 Cost of R. R. Stone 2,71,282.00 4

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 17  

Claim No. 4 Rehandling of Sand 1,18,559.82 5 Claim No. 5 Rehandling of Stone    15,743.59 6 Claim No. 6 Extra lead of stone    15,743.59 7 Claim No. 7 Extra lead of Rubble Stone    11,123.19 8 Claim No. 8 Preparation of Foundation for  slides 1,49,955.00 9 Claim No. 9 Final excavation of sides    18,556.57 10 Claim No. 10 Carriage of porus pipes      2,662.90 11 Claim No. 11 Finishing of the concrete      5,861.16 12 Claim No. 12 R.C.C. in inspection gallery and  sluice    32,000.00 13 Claim No. 13 Rock cutting by line drilling  chiseling    25,947.31 14 Claim No. 14 Mechanical mixing of cement  mortar 1,82,990.72 15 Claim No. 15 Cleaning of surface by air & water  daily    66,079.74 16 Claim No. 16 Shuttering of stair case in  Galleries      2,231.60 17 Claim No. 17 Cement concrete in saturated  condition    29,223.81 18 Claim No. 18 Shuttering at the junction of the

12

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 17  

Dam heel and the Down stream  protection     5,126.49 19 Claim No. 19 Mechanical mixing of cement  concrete     2,463.26 20 Claim No. 20 Carriage of Air vent pipe     2,497.50 21 Claim No. 21 Crusher broken aggregate    33,669.00 22 Claim No. 22 Cleaning the foundation surface  handed over by the department    28,092.00 23  Claim No. 23 Increased in rates of royalty    17,216.87 24 Claim No. 24 Increased in rates of Diesel 1,22,604.36 25 Claim No. 25 Increased in minimum labour  wages 5,27,638.60 26 Claim No. 26 Increased in minimum labour  wages and increase in price in the  rates  10,52,797.30 27 Claim No. 27 Loss of profit 3,07,038,00 28 Claim No. 28 Due to unlawful withdrawl of the  running work 1,58,904.85 29 Claim No. 29 Over establishment and overheads  beyond 16.5.81 (stipulated date of  completion)  4,33,347.00 30 Claim No. 30 Difference of interest of F.D.R.    56,800.00 31 Claim No. 31 Wrong recovery from bills for sand  department & extra carriage  (6364.71 + 23206.90    29,571.61

13

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 17  

32 Claim No. 32 Recovery of labour     2,730.30 33 Claim No. 33 Recovery of Storage charges    22,549.30 34 Claim No. 34 Material remain unused      5,856.00 35 Claim No. 35 Electric charges    10,205.20 36 Claim No. 36 Excess charges of hire charges of  machine

37 Claim No. 37 Recoveries to be final

38 Claim No. 38 For screening of sand     4,165.00 39 Claim No. 39 Royalty charges on departmental  material     6,243.30            

       Mr. Mohta relied upon the case of Bharat Coking Coal Ltd. vs.  L. K. Ahuja & Co. reported in (2001) 4 SCC 86, wherein it has been  held that if an Arbitrator has not applied his mind to important terms  of the contract between the parties and has not applied such terms in  making his award, then, even though the award is a non-speaking  award.  This error is apparent on the face of the award, the entire  lump sum award is required to be set aside.   He also relied upon the  case of Continental Constructions Co. Ltd. vs.  State of M. P.  reported in (1988) 3 SCC 82.  In this case also it has been held that if  an Arbitrator awards extra costs on account of changes in  circumstances such as price rise, in spite of a provision in the Contract  to the contrary, it would amount to the Arbitrator mis-conducting  himself and that such an award would be required to set aside.            Mr. Mohta took us through a number of claims and pointed out  that under most of the claims additional/higher  amounts were being  claimed in respect of works covered by the Contract. He submitted  that  there were a number of claims where, for doing the contracted  work during the extended period, higher rates were claimed and the  Umpire has awarded those claims not on the basis of contracted price  but on basis of rates given to the new contractor who was appointed to  complete the work left unfinished by the Respondent. Mr. Mohta  submitted that the letters extending time categorically provided that  the work would be done at the contracted rate. He submitted that this  had been accepted by the Respondent. As we propose to remit the  matter back to an Umpire we do not deal with each instance pointed  out by Mr. Mohta. Only by way of example we refer to two claims. As set out hereinabove claim no. 2 is in a sum of Rs.2,78,737.92  and  it is for chisel dressed face stones.  Under this claim, the

14

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 17  

Respondents have claimed extra amounts for chiseling the stones on  all four sides when, under the Contract, they are supposed to do this  work at the rates specified for such work in Schedule G.   Mr. Mohta  pointed out Clause 5.11(iii) of the Technical Specifications the relevant  portion of which reads as follows: "       xxx                     xxx                     xxx Dressing:- The face stone shall be squared on all joints  and beds.  The beds shall be hammer dressed true and  square for at least 7.5 cms.  Back, from the face and the  side joints for atleast 7.5 cms.  The faces of the stones  shall be single line chisel dressed and bushing shall not  project by more than 3.75 cms.  No pinnings will be  allowed on the face.   All side joints shall be vertical and  beds horizontal and no joint shall be more than 12 mm. in  thickness.  Stones shall break joints in courses above and  below by at least half the height of the courses.  The joint  in face work shall not be thicker than 12 mm. for single  line chisel dressed stones.   

       xxx                     xxx                     xxx"

He submitted that this was the work which was required to be done  under the Contract at the rate specified in Schedule G and yet the  claim had been made at higher rates.  He submitted that the Umpire   had not rejected the claim. He submitted that even though the award  was a lump sum award it  was also in respect of claim No. 2.    Mr.  Mohta also referred to claim No. 26 which was for Rs. 10,52,797.30 for  increase in minimum labour/wages and increase in prices.   He pointed  out that this claim was contrary to Clause 38 of the Contract and  Clause 31 of the Special Conditions of the Contract which specifically  provided that the contractor would not be entitled to claim  compensation or higher rates because he had to implement labour  laws or pay fair wages.            In the same manner, Mr. Mohta took us through a large number  of other claims to show that they were contrary to the terms of the  Contract.  As stated above  it is not necessary, for the purposes of this  Judgment, to set out in detail the submission of Mr. Mohta in respect  of other claims referred to by him.           On the other hand, Mr. Luhadia submitted that this was a non- speaking lump sum award and therefore the grounds on which this  Court can interfere with such an award are very limited. In support of  his submission he relied upon a number of authorities including the  cases of Hindustan Steel Works Construction Ltd. vs. C.  Rajasekhar Rao reported in (1987) 4 SCC 93. In this case it has  been held that it is only in a speaking award that the Court can look  into the reasoning of the award. It is held that it is not open to the  Court to probe the mental process of the arbitrator and speculate,  where no reasons are given, as to what impelled the arbitrator to  arrive as to his conclusions. He also relied on the cases of S.  Harcharan Singh vs. Union of India reported in AIR (1991) SC 945;  Hindustan Constructions Co. Ltd. vs. State of J. & K. reported in  AIR (1992) SC 2192 and Continental Construction Ltd. vs. State of  U. P. reported in (2003) 8 SCC 4. In these cases the question was  regarding interpretation of the terms of the contract. It was held that  the Court cannot substitute its own interpretation to that of the  arbitrator so long as the interpretation of the arbitrator is a possible  one. Reliance was also placed upon the case of M/s. Sudarsan  Trading Co. vs. State of Kerala reported in AIR (1989) SC 890. In  this case also it has been held that  it is for the arbitrator to interpret  terms of the contract and that if the view taken by the arbitrator is a  possible view then the court would not interfere. In the case of  P. M.  Paul vs. Union of India reported in AIR (1989) SC 1034 the  questions referred to the arbitrator were (a) who was responsible for  the delay; (b) what are the repercussions of the delay and (c) how to

15

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 17  

apportion the consequences. The arbitrator gave a reasoned award  holding  the Union of India responsible for the delay and awarded  escalation in costs to the contractor. It must immediately be  mentioned that there was no provision in the contract which permitted  or barred grant of escalation. This Court held that the arbitrator had  not exceeded his jurisdiction nor misconducted himself.   In the case of   Build India Construction System vs. Union of India reported in  (2002) 5 SCC 433 after the contract was entered into it was amended  to provide that in cases where the claim is more than 1 lakh a  reasoned award should be given. The arbitrator gave an unreasoned  award. The challenge to it on the ground that the award was  unreasoned was not accepted as this point was taken for the first time  in the high court and also on the ground that a contract cannot be  unilaterally altered. There can be no dispute to the well established principle set out  in these cases. However these cases do not detract from the law laid  down in Bharat Coking Coal Ltd’s case or Continental  Construction Co. Ltd’s case (supra). An arbitrator cannot go beyond  the terms of the contract between the parties. In the guise of doing  justice he cannot award contrary to the terms of the contract. If he  does so he will have misconducted himself. Of course if an  interpretation of a term of the contract is involved than the  interpretation of the arbitrator must be accepted unless it is one which  could not be reasonably possible. However where the term of the  contract is clear and unambiguous the arbitrator cannot ignore it.  Mr. Luhadia submitted that the respondents had made claims  totaling Rs. 4556155.56p. He submitted that claims for damages were  to the tune of Rs. 27.50 lacs. He submitted that the claim for final bill  was for Rs. 2 lacs. He submitted that the claims for extra items were  for Rs. 1598495.  He  submitted  that the Umpire had only awarded  Rs. 2996060. He submitted that as the award is a non speaking award,  even presuming without admitting that some claims were covered by  the terms of the contract, it still could not  be said that the Umpire has  awarded towards claims covered by the contract. He submitted that  thus the award could not be set aside. In support of this submission he  relied upon the case of Paradip Port Trust & Ors. vs. Unique  Builders, reported in AIR (2001) SC 846. In this case the claim had  been for Rs. 1293260. The arbitrator awarded as follows: "M/s Unique Builders Ltd. the claimant is entitled to receive  from Paradeep Port Trust a sum of Rs. 851315  with  interest\005\005\005\005.." It was contended in that case that claims 2 and 7 (therein) could not  have been awarded. This Court held that as the award was a lump  sum award and as only Rs. 851315 had been awarded against a claim  of Rs. 1293260 it was not possible to say whether any amounts had  been awarded against claims 2 and/or 7. relying on this Mr. Lohadia  submitted that even in this case it cannot be said whether any  amounts have been awarded against claims alleged to be  covered by  the contract.  We are unable to accept this submission.  In this case  the award itself states that the award of Rs. 29,96,060/- is against  claims 1 to 39, except claim no. 30. Therefore this award is in respect  of claims covered by the contract and to that extent the Umpire has  misconducted himself. Even otherwise the claim for damages is not in  a sum of Rs. 27.50 lacs as claimed. Claims 27 and 28 which deal with  damages are for Rs. 3,07,038/- and Rs. 1,58,904.85. The other  claims, included in the figure of Rs. 27.50 given to this Court appear to  be claims at enhanced rates for the contracted work done during the  extended period. Mr. Lohadia denied that Respondents had agreed to  do work during the extended period at the contracted rate.  Thus at  this stage, unlike in Paradip Port Trust’s case (supra), it does appear  on the face of the record that higher rates for items covered by the  contract have been awarded.  As regards claim No. 2 Mr. Luhadia fairly admitted that Clause  5.11(iii) of the Contract requires chiseling of stones on all sides.  He  however submitted that the rates given in Schedule G were only for

16

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 17  

chiseling of stones on one side.  He submitted that this was clear from  Note 1 under Schedule G which stated that Schedule G was based on  B.S.R. 1975.  He submitted that B.S.R. 1975 showed that such rates  were only for chiseling stones on one side.  He submitted that  when  the stone has to be chiseled on all sides the rates given in B.S.R. 1975  were to be applied. He submitted that  claim No. 2 was based on those  rates.  We are unable to accept this submission of Mr. Luhadia.  The  Contract is very specific.   The work specified in the Contract has to be  done at the rates specified in Schedule ‘G‘.  Even though Schedule G  may be based on B.S.R. 1975 it is not exactly as B.S.R. 1975. Where  in respect of a work specified in the contract the  rate has been given  in Schedule G that work could only be done at that rate.  Works  specified in the Contract does not become extra work.  It is only in  respect of  extra work that rates specified in B.S.R. 1975 can be  applied.  To us it is clear that the claim No. 2 is contrary to the terms  of the Contract.  It is barred by Clauses 57, 60 and 61 of the Contract.   As regards claim No. 26, Mr. Luhadia relied upon the case of   Tarapore & Co. vs. State of M.P. reported in (1994) 3 SCC 521.  In  this case, the question was whether the contractor was entitled to  claim extra amounts because he had to pay increased wages to his  workers.  This Court has held that the contractor would have tendered  on the basis of the then prevailing wages and as the contract required  the contractor to pay the minimum wages if the minimum wages  increased it was an implied term of the contract that he would not be  entitled to claim the additional amount.  However, it must be noted  that, in this case, there was no term in the contract which prohibited  any extra claims being made because of the increase in wages.    Clause 31 of the Special Conditions of the Contract, which has been  reproduced hereinabove, specifically bars the contractor from claiming  any compensation or an increase in rate under such circumstances.    Not only that but the Respondents had with their initial tender  put in a  term  which provided that if there was any increase in the minimum  wages by the  Government the rates quoted by him would be  increased by the same percentage.   At the time of negotiation this  clause was dropped.   Thus, the Respondents had themselves  specifically agreed not to claim any compensation or increase by  reason of increase in wages.  This claim could therefore not have been  granted.          It prima-facie appears that the majority of the claims are against  the terms of the Contract.  However, there are also other claims which  are not against the terms of the Contract.  To merely set aside the  Award on ground of misconduct would work hardship on the  Respondent as they would then be deprived of  claims which may be  maintainable. In our view the correct course would be to set aside the  award and refer the matter back to an independent Umpire appointed  by this Court. The Umpire will fix his own terms and conditions. We  however clarify that only those claims covered by the two applications  will be considered. Of course the Umpire will decide how many of the  39 claims formed part of the claims made in the two applications.  Needless to state that the terms of the contract will be kept in mind  and claims contrary to terms of the contract will undoubtedly not be  allowed. The Umpire will also decide whether the Respondent had  agreed to do the contracted work done during the extended period at  the same rates and/or whether the Respondent is entitled to increased  rates and if so at what rate. The Umpire shall decide only on the basis  of the materials already placed before the earlier Arbitrators and the  earlier Umpire.           Under the circumstances and for reasons set out hereinabove,  we set aside the Award and appoint Justice N. Santosh Hegde, a  retired Judge of this Court, as the Umpire.  The Umpire, Mr. V. K.  Gupta, shall forthwith forward all papers and documents to Justice N.  Santosh Hegde at his residence, i.e., 9, Krishna Menon Marg, New  Delhi.  The parties shall appear before Justice N. Santosh Hegde on  6.10.2005 at 5.00 P.M. at 9, Krishna Menon Marg, New Delhi.   Justice  N. Santosh Hegde shall fix his fees which shall be borne by both the

17

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 17  

parties equally.  Justice N. Santosh Hegde is requested to fix the  schedule and give his award within a period of 4 months from the date  of receipt of all the papers and documents from the outgoing Umpire  Mr. V. K. Gupta.  The award to be filed in this Court.  We leave the  question of grant of interest open to be decided by the Umpire in  accordance with law.         Lastly, it is clarified that this is not a new reference but a  continuation of the earlier proceedings and thus the Arbitration Act  1940 shall continue to apply.

       The Appeals stand disposed off accordingly.  There will be no  order as to costs.