22 September 1998
Supreme Court
Download

STATE OF ANNDHRA PRADESH Vs CHANDRASEKHARA REDDY & ORS.


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7  

PETITIONER: STATE OF ANNDHRA PRADESH

       Vs.

RESPONDENT: CHANDRASEKHARA REDDY & ORS.

DATE OF JUDGMENT:       22/09/1998

BENCH: S.B.  MAJUMDAR, M.  JAGANNADHA RAO.

ACT:

HEADNOTE:

JUDGMENT: J U D G M E N T S.B.  Majumdar.  J : Leave granted. These  appeals by special leave are preferred by the State of Andhra Pradesh being aggrieved by a common judgment and order dated 08.04.1996  of  the  High  Court  of  Andhra Pradesh  in  appeal against order of the Trial Court as well as in companion civil revision petition arising out  of  the very same  judgment  of  the  Trial  Court.  The question in controversy between the parties in these appeals which  were finally  heard by consent of learned counsel for the parties is to the following effect :- Whether  the  award of the arbitrator to the tune of Rs.  38,32,697/- with 18% interest per annum from  the  date of reference  i.e.    27.06.1985  till  payment  in favor of Respondent No.1 which  was  made  rule  of  the  court,  was legally justified or not. A  few  relevant  facts  leading  to  these  appeals deserve to   be  noted  at  the  outset.    Respondent  No.1 contractor had executed a works contract assigned to him for laying distribution pipe to 32 fluoride affected villages in Prakasam District  of  Andra  Preadesh.    A  per  the  said agreement   dated   30.07.1980  executed  by  the  executive Engineer on behalf of the appellant-State granting the  said contract  to  Respondent No.1, the initial value of the work was Rs.  8,52,335.66.  The site in question was handed  over to Respondent  No.1 contractor on 01.08.1980.  The period of work was twelve months.   Some  dispute  arose  between  the appellant-State  on  the one hand and Respondent No.1 on the other.  As there was an arbitration clause in  the  contract for  referring  the dispute to arbitration for resolving the same, the said clause got invoked between the parties.   The contention  of  Respondent No.1 Contractor was that the sole arbitrator, as provided in the articles of agreement,  being the  Superintending  Engineer  of  Panchayat Raj, Hyderabad, N.A.P.  Guntur, could  not  act  as  arbitrator  as  he  was directly  concerned  with the contract work, he was required to be substituted by some other  arbitrator.    Accordingly, Respondent No.1 moved  an application being C.P.  No.  56 of 1984  under  Section  8  of  the   Arbitration   Act,   1940

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7  

(hereinafter  referred  to  a  ’the  Act) in the Court of II Additional  Judge,   City   Civil   Court,   Hyderabad   for substituting.   The said petition was decided by the learned Judge  after  hearing  the  parties  by  his   order   dated 25.02.1985.   In  place  of sole arbitrator mentioned in the contract one Shri T.  Nabi Saheb,  Superintending  Engineer, Retired.    Ramchandranagar,  Ananthapur,  (Respondent  No.2 herein) was appointed as soil arbitrator for adjudication of disputes that had arisen between Respondent No.1 (Petitioner before the court) and the appellant-State (first  respondent before  the  court) in respect of agreement dated 30.07.1980 relating to the work i.e.  providing distribution pipe lines to 32 fluoride affected villages in Prakasam District.   The arbitrator was directed to sign a copy of the minutes of the order  and  enter  upon  reference  in  accordance  with the agreement and to make the award within four months from  the date  of  entering  upon  the reference pursuant to the said agreement between the parties.  It is not in dispute between the parties that the said decision has become final. Pursuant to the aforesaid order of the Trial  Court, the arbitrator entered upon the reference, heard the parties and adjudicated upon the dispute by a non-speaking award and on various heads submitted before him by Respondent No.1 for adjudication, the  aforesaid  award of Rs.  38,32,697/- with interest was passed by him on 25.10.1985.   The  said  award was submitted by Respondent No.1 for making it a rule of the court by filing O.S.No.1420 of 1985.  A notice was issued to the appellant State authorities about the said filing of the award by  the  Trial  Court.  The appellant-State filed O.P. No.34 of 1988 on 26.02.1980 for  setting  award  on  various grounds raised therein.   That O.P.  was moved under Section 30 of the Act raising diverse objections to the award.   The Trial  Court  took  the view that the said application under Section 30 of the Act raising objections was time-barred and as there was no application for condonation  of  delay,  the objections could  not  be  entertained  on merits.  However, they were gone into on merits by treating them as a  counter of application  of Respondent No.  1 which was registered as O.S.  No.35 of 1985 under which the award was sought  to  be made the  rule of the court.  The Trail Court considered the objections on merits and took the view that  they  were  not sustainable in  law.   Resultantly, the Trial Court made the award rule of the  court  by  its  order  dated  27.02.1989. Against the said order of the Trail Court, as noted earlier, the  appellant-State  filed  an appeal from order as well as civil revision application  challenging  the  order  of  the Trial  Court  making  the  ward  rule  of the court and also rejecting the objections filed by the  State  as  barred  by limitation.    As   both   the  appeal  from  order  and  by limitation.   As  both  the  appeal  from  order  and  civil revision petition raised common contentions, they were heard together by  a  Division  Bench of the High Court.  The High Court came to the conclusion that there was no substance  in either  of  them  and consequently dismissed both of them by its  impugned  common  order  dated  08.04.1996   and   thus confirmed the order of the Trail Court making the award rule of the  court.  As noted earlier, it is the aforesaid common order of the High Court that has resulted in these appeals. RIVAL CONTENTION Shri A.   Raghuvir, learned Senior Counsel appearing for the appellant-State raised two contentions in support of these appeals.  He submitted that the learned Trial Judge as well as the High Court patently erred  in  taking  the  view that  the objections under Section 30 of the Act were barred by 62 days.  That in fact, the delay was  only  of  8  days,

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7  

which  deserved to be condoned in the interest of justice as the advocate to  whom  the  papers  were  entrusted  by  the State-authorities  for  filing  objections  before the Trial Court under Section 30 of the Act had suffered from a family bereavement which required him to go out for one week.   The moment he came back, the objectors were filed.  The delay in filing   the  objections  was,  therefore,  required  to  be condoned in the interest of justice  and  that  it  was  not necessary  that a petition to condone the delay was required to be filed, as wrongly assumed by the  Trial  Court.    He, therefore,  submitted  may  be  remanded  to Trail Court for considering objections  under  Section  30  of  the  Act  on merits.   He next contended that in any case the award was a nullity being without jurisdiction as the procedure required by preliminary specification no.73 which was binding on  the parties was  not  followed  in the present case.  That after the order of the Trial Court  substituting  the  arbicrator, Respondent  No.1  was  required  to  move the Superintending Engineer of the area who  was  in  charge  of  the  work  in question  for  referring  the dispute to the newly appointed arbitrator and till that was come the new  arbitrator  could not assume jurisdiction to adjudicate upon the reference and hence  the  arbitration proceedings before him and the final award passed by him were nullities. Shri P.P.  Rao, learned Senior Counsel appearing for the contesting respondent, on the other hand, submitted that the question of condonation of delay  in  filing  objections under  Section  30 of the Act does not survive at this stage as the Trial Court had considered the objections  on  merits by  treating  them as written statement to the suit files by the respondent contractor for making the award rule  of  the court.All  these  objections  were  found  unsustainable  on merits both by the Trial Court as well as by the High Court. So far as  the  second  contention  of  the  learned  Senior Counsel   for  the  appellant-State  is  concerned,  it  was submitted by Shri Rao  for  Respondent  No.1  that  no  such contention  was ever canvassed before the arbitrator or even raised in any objections filed under Section 30 of the  Act, not  was  such a contention placed before the Trail Court or even before the High Court.  That this contention  raised  a highly  disputed question of fact whether the Superintending Engineer, Panchayat Raj, Ongile, could ever be approached by Respondent   No.1   -   Contractor   as   per    preliminary specification no.    73  as  according  to him the concerned Superintending Engineer was functioning at Guntur  and  that the   said   Supterintending   Engineer  who  was  the  sole arbitrator as per the terms of the contract was  supersended and  substituted  by  Shri Nabi Saheb as per the order dated 27.02.1989 passed by the Trail Court which had become  final between the  parties.   In any case the said decision of the court itself directed  the  arbitrator  to  enter  upon  the reference  and, therefore, such a technical contention could not be entertained for the first time in these appeals. In  view  of  the  aforesaid  rival contentions, the following points arise for our consideration :- (1)Whether the delay in filing objections under Section 30 of the Act is required  to  be  condoned  in  the interest  of  justice and the proceedings are required to be remanded to the Trail Court for fresh decision; (2)Whether the arbitration  award  was  without jurisdiction  and nullity in the absence of any reference by the Superintending  Engineer,  Ongole,  to  the  substituted arbitrator Shri Nabi Saheb. We  shall proceed to deal with these points seriatim :-

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7  

POINT NO. 1 It  is  true  that the learned Trial Judge held that objections under Section 30 of the Act as moved on behalf of the appellant-State were  barred  by  62  days.    The  said finding was arrived at by the Trail Court on the ground that the  notice  under  Section  14(2)  of the Act served on the appellant-State  on  18.12.1985  while  the  petition  being O.P.No.34 of 1988  was.  However, Shri A.  Raghuvir, learned Senior Counsel for the appellant-State, vehemently contended that there is a patent error in the aforesaid finding of the learned Trial Judge.  That in fact, the notice of the  court was  served  on  18.01.1986  on the Superintending Engineer, Panchayat Raj, N.A.P Circle Ongole,  Prakasam  District,  as stated  by  him  in  his affidavit before the High Court and accordingly the limitation for filling the objections  would expire on  17.02.1986.  That the papers for filing Srinivasa Rao s/o Shri Ranga Rao by the deponent within  time.    That objections  raised  in  O.P were within time but because the learned advocate had to leave immediately from Hyderabad  to Bangalore as his close relative had expired, the O.P.  could be  filed  only  on 25.02.1986 when the advocate returned to Hyderabad on 24.02.1986.  That is mentioned in the affidavit of Shri L.K.  Srinivasa Rao which  was  filed  in  the  High Court.   Consequently,  there was eight day’ delay in filing objections which should have been condoned in  the  interest of justice.   We would have been required to closely examine this contention to find out as to whether the delay  was  of 62 days  or  eight days.  In either case, we would have been inclined to condone the delay in the interest of justice  as a huge  amount  of  public  money is involved.  It has to be kept in view that though originally the claim of  Respondent No.1  was  confined  at  that stage only to certain heads of dispute which totally amounted to Rs.7,55,760/-, as per  the two  letters  written  by  the  claimant  to  the  Executive Engineer dated 22.10.1983 and 24.10.1983, the  claim  before the  arbitrator  got  highly  inflated to Rs.46,93,858/- and towards  the  said  claim  ultimately  Rs.38,34,097/-   were awarded by the arbitrator. However,  on  the peculiar facts of this case, it is not necessary for us to consider this question any  further. The reason  is  obvious.    The  learned  Trial Judge in his judgment while making  the  award  rule  of  the  court  has clearly held that through the objections under Section 30 of the  Act  were barred by time, he thought it fir to consider the question whether the award was to be set aside on any of the grounds under Section  30  of  the  Act  and  having  so observed   the  learned  judge  proceeded  to  consider  the objections to the award on merits in details.  Reasoning  of the  Trail  Court  Judge  is  found  in  paragraph  6 of his judgement   wherein   the   objections   were   meticulously considered  and  ultimately  it  was  held  that no doubt it appeared that the contractor had made excessive claim before the arbitrator but there was no material on record to  point out  that  the  petitioner (present appellant) had taken the same plea before the arbitrator.  There was also  no  record to  show that they had brought the matter into consideration of the learned arbitrator.  The learned Judge also  observed that  the award was a non-sperned one and on merits it could not be interferred with by the court by  sitting  in  appeal over the   findings   of  the  arbitrator.    The  aforesaid reasoning adopted by the learned Judge is well sustained  in the present  case.   When we turn to objections filed by the appellant-State before the arbitrator,  it  become  at  once clear  that the appellant-State through it fit to join issue on merits of the claim before the arbitrator.   No  argument

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7  

was  placed  before  the  arbitrator  to the effect that the claim put forward before the arbitrator  by  the  contractor was  in  excess  of the original claim before the arbitrator and, therefore, could not  be  adjudicated  upon.    On  the contrary,   in   the   counter   filed   on  behalf  of  the appellant-State before the arbitrator  it  was  stated  that such claims that were required to be adjudicated upon by the arbitrator  were  according  to the appellant not justified. The arbitrator considered those  claims  with  reference  to their  various  sub  heads and out of the total claim of Rs. 46,93,858/- as found  in  the  claim  statement  before  the arbitrator and also the total claim at the time of rejoinder amounting to  Rs.    80,03,950/-,  the arbitrator ultimately reduced the grantable claim to Rs.38,34,097/-.  In our  view Therefore,  it  cannot  be  said that the arbitrator had not applied his mind to the relevant heads of the claim  as  put forward  by  Respondent  No.1 nor the State authorities ever contended before the arbitrator that the excess claim  could not be adjudicated upon.  Having chosen to join the issue on merits  of  the claim, the award of the arbitrator had to be treated as binding on the State-authorities.    It  is  also pertinent   to   note   that  the  amounts  claimed  by  the respondent-claimant in  his  letters  dated  22.10.1983  and 24.10.1983 did  not  amount  to  total final claims.  On the contrary, we find on the  scrutiny  of  these  letters  that Respondent  No.1  Contractor  had  reserved  liberty  to put forward further claim on topics  of  disputed  items.    The matter  would  have  stood differently, if these letters had confined the total claim of Respondent No.1 to  the  amounts mentioned therein.    Then  a  further  question  would have survived for consideration  as  to  whether  there  was  any further  material available to enhance the said claim before the arbitrator but such was not the situation on  the  facts of the present case.  Consequently, the decision rendered by the  learned  Trail  Judge  on  merits  of  these objections overruling them  cannot  be  found  fault  with.    In  this connection,   learned  Senior  Counsel  for  the  respondent rightly invited our  attention  to  a  decision  of  learned single  Judge  of  Orissa High Court in the case of State of Orissa & Anr.  vs.  M/s Civien Construction Co.  & Anr  (Air 1983 Orissa 48).  wherein  Hon’ble  R.N.  Misra.  J.  (as he then was) in a similar situation held that as per the  terms of  the  notice  when  the  amount  of  claim was subject to further variations, if found necessary, addition claim could be submitted by the claimant before the  arbitrator.    Once this conclusion is reached, the result becomes obvious.  The question  whether  the  delay in filing the objections under Section 30 of the Act  should  have  been  condoned  in  the interest  of  justice or not would have been condoned in the interest of justice or not would  pale  into  insignificance and  would be academic as the very same objections have been considered on merits and rejected by the Trial Court and the said rejection in our view is well sustained on the facts of the present case.  The first  point  for  consideration  is, therefore,  answered  against  the appellant and in favor of the respondent by holding that there is no need  to  condone the  delay  even  in  absence  of  a written application and remand the  proceedings  for  fresh  decision  as  the  said question has become of academic nature. POINT No.2 So far as  this  point  is  concerned,  Shri Raghuvir,   learned   Senior   Counsel  for  the  appellant, vehemently contended placing reliance on a decision of  this Court in the  case of Banwari Lal Kotiva vs.  P.C.  Aggarwal [(1985) 3 SCC 255] that a reference to the  newly  appointed

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7  

arbitrator had to be made after following the procedure laid down by preliminary  specification  no.    73.    It  is not necessary for us to closely examine this contention for  the simple  reason  that  this  contention  immediately raises a disputed question of fact as to whether Shri Nabi Saheb  who was   appointed   as   a  substituted  arbitrator  vice  the Superintending Engineer, Guntur, the sole  arbitrator  could have  been  required  to  be issued a fresh reference by the Superintending Engineer,  Ongole.    If  the  Superintending Engineer,  Ongole,  was not in charge of the work and if the contract  work  was  done  by  Respondent  No.1  under   the supervision and jurisdiction of the Superintending Engineer, Guntur  was  substituted  by  Shri  Nabi  Saheb  as the sole arbitrator, there would remain  no  occasion  for  requiring very  same  Nabi  Saheb  to  refer the matter to himself for adjudication.  Realising  this  difficulty,  Shri  Raghuvir, learned  Senior  Counsel  for  appellant, submitted that the reference of dispute was required to  be  made  not  by  the Superintending  Engineer,  Guntur  but by the Superintending Engineer, Ongole under whose jurisdiction the work had to be carried out.  This contention was never raised either before the arbitrator or before the Trail  Court  or  in  any  case before the High Court and it is too late now for the learned Senior  Counsel  for  the appellant to raise this contention for the first time before us in these proceedings.  But even that apart, the order of the Trail Court  substituting  Shri Nabi   Saheb   as  the  sole  arbitrator  in  place  of  the Superintending Engineer,  Guntur,  as  early  as  1985,  has become final.    As we have noted earlier, the said decision dated 25.02.1985 has clearly directed the arbitrator to sign the copy of the minutes of the  order  and  enter  upon  the reference in  accordance  with  the  agreement.    Thus, the arbitrator got jurisdiction  to  enter  upon  the  reference pursuant  to  the  order of the court which has become final between the parties.  Even on this ground,  this  contention about   the   requirement   of   further  reference  by  the Superintending  Engineer  concerned  does  not  survive  for consideration.  Point No.2 also fails and is rejected. These were the only contentions canvassed in support of  the  appeals  and  as there is no substance in either of them, the net result is that  these  appeals  fail  and  are liable   to  be  dismissed  and  the  award  passed  by  the arbitrator as made the rule of the court and as confirmed by the High Court would stand untouched.  However,  as  a  huge amount of  public  money was involved.  through his counsel. It was recorded by an order of this Court  dated  05.09.1997 which reads as under :-               " Learned counsel  appearing  for               the    respondents    states   on               instructions that he is  prepared               to  put an end to this litigation               by accepting 20% less out of  the               total  awarded  amounts  which by               now       work       up        to               Rs.81,00,000/(Rupees  Eighty  one               lakh only) inclusive of  interest               till date.    Thus  as  a package               deal a lump  sum  amount  of  Rs.               61,00,000/-   (Rupees  Sixty  one               lakh only) will be acceptable  to               the respondents in full and final               satisfaction  of  their  claim in               these cases.  Learned counsel for               the  respondents  further  states               that  out of Rs.15,00,000/(Rupees

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7  

             Fifteen  lakh  only)  which   the               respondents have already received               form  the  petitioner towards the               award decree.  According  to  him               now   his   dues   will  be  only               Rs.46,00,000/(Rupees  Forty   six               lakh    only)    towards    which               Rs.5,00,000/(Rupees   Five   Lakh               only)   lying  deposited  in  the               Lower Court will be adjusted  and               the petitioner-State will have to               pay   the   balance   amount   of               Rs.41,00,000/- (Rupees Forty  one               lakh  only)  towards  the awarded               dues of the respondents  if  this               proposal is accepted by them.               At the request of learned               senior  counsel appearing for the               petitioner, adjourned for a weeks               to   get    response    of    the               patitioner-State      to     this               proposal."               proposal." As   per   the  said  fair  stand  and  proposal  for compromise submitted on behalf of Respondent No.1 Contractor, he had agreed to reduce the  amount  of  the  claim  by  20%. Unfortunately,   that   proposal  was  not  accepted  by  the State-authorities.  However, Shri Rao, learned Senior Counsel fairly  stated  that  whatever  may  be  the  view   of   the State-authorities  regarding  settlement  of this dispute and through it is ultimately found by this Court that the appeals are liable to fail, he  would  leave  it  ti  the  Court  for reducing  the  amount of the award decree as earlier proposed by Respondent No.1 before this Court.  We appreciate the fair stand taken by learned counsel  for  Respondent  No.1.,  even through  the respondent had emerged successful in the present proceedings.   Consequently,   while   rejecting   both   the contentions  of  learned counsel for the appellant in support of the appeals, we deem it fit by consent of Respondent No.1, as recorded in the order dated 05.09.1997 to direct that  the appeals  will  stand  allowed  to the limited extent that the award  decree  amount  as  passed  by  the  Trail  Court  and confirmed  by  the  High  Court  will stand reduced by 20% as fairly agreed  to  by  Respondent  No.1  through  his  senior counsel.   After  adjusting  the amount withdrawn towards the decretal dues and also after permitting  Respondent  No.1  to withdraw Rs.5,00,000/- which are deposited in the Trail Court towards the decretal dues, the net amount of Rs41,00,000/will now remain  payable  by  the appellant to Respondent No1.  in full and final satisfaction  of  his  claim  in  the  present proceedings.   The said balance amount of Rs.41,00,000/- will have to be paid by the appellant to Respondent No.1  with  9% interest  thereon  from 05.09.1997 till the actual payment to Respondent No1.  The award decree passed by the  court  below and as confirmed by the High Court will stand modified to the aforesaid extent by consent of the respondent-decree holder. The appeals are partially allowed accordingly with no order as to costs.