SST SOFTWARE INTERNATIONAL PVT.LTD. Vs NEOS INTERACTIVE LIMITED
Bench: J.M. PANCHAL, , , ,
Case number: ARBIT.CASE(C) No.-000022-000022 / 2007
Diary number: 25939 / 2007
Advocates: Vs
RAVI PRAKASH MEHROTRA
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
Arbitration Application No. 22 of 2007
Speech & Software Technologies (India) Pvt. Ltd. … Applicant
Versus
Neos Interactive Ltd. … Respondent
J U D G M E N T
J.M. Panchal, J.
1. By filing the instant application under Section 11
(6) of the Arbitration and Conciliation Act, 1996 (“the
Act” for short), the applicant, i.e., Speech & Software
Technologies (India) Pvt. Ltd. has prayed to appoint
Mr. Justice Arvind Sawant (Retd.), former Chief
Justice, High Court of Kerala, as sole arbitrator and to
refer the disputes to him, which have arisen between
the applicant and the respondent during the course of
execution of Services Agreement dated July 15, 2006.
2. The relevant facts, which emerge from the record
of the case, are as under: -
The applicant is a company registered under the
Companies Act, 1956. Its registered office is situated
at Chennai. The respondent is a company having its
registered office at London. The applicant and the
respondent entered into a Services Agreement dated
July 15, 2006. Under the said agreement, the
applicant was to provide services to the respondent as
set out in schedule 2 to the said agreement. The
respondent had agreed to make payment of ₤15,500
per month to the applicant and also to compensate the
Director of the applicant for coordination activities. A
copy of the agreement dated July 15, 2006 is produced
by the applicant at Annexure ‘1’ to the application. It
is the case of the applicant that since December, 2006
the respondent refused to make any payment to the
applicant and insisted for execution of another
2
agreement as suggested by the principal shareholder
of the respondent. The applicant has averred that the
applicant was not inclined to enter into new agreement
as suggested by the respondent and as the respondent
had failed to comply with the terms of the Services
Agreement dated July 15, 2006, it terminated the said
agreement by sending notice dated February 15, 2007
in terms of Clause 19 of the agreement. By the said
letter the applicant also appointed Mr. Justice Arvind
Sawant (Retd.), former Chief Justice of Kerala High
Court, as the sole arbitrator and called upon the
respondent to appoint its arbitrator in the event the
respondent did not agree to the appointment of Mr.
Justice Arvind Sawant (Retd.) as the sole arbitrator. A
copy of the notice dated February 15, 2007 is
produced by the applicant at Annexure ‘3’ to the
application.
3. On receipt of the notice the advocate of the
respondent addressed a letter dated March 15,
2007 urging the applicant not to take any
unilateral action for a period of two weeks so as
3
to enable him to obtain comprehensive
instructions in the matter in order to effectively
study and evaluate the issues involved in the
matter. The case of the applicant is that the
respondent did not give reply to the notice dated
February 15, 2007, nor concurred in the
appointment of Mr. Justice Arvind Sawant (Retd.)
as sole arbitrator nor appointed its arbitrator.
The applicant has claimed that it is entitled to
recover a sum of ₤252,911-76 from the
respondent for the services rendered. Under the
circumstances the applicant has filed the instant
application and claimed relief to which reference
is made earlier.
4. On receipt of notice from this Court, the
respondent has filed reply affidavit. In the reply
affidavit it is mentioned by the respondent that
the Services Agreement dated July 15, 2006 was
signed on July 31, 2006 and August 1, 2006 by
the applicant and the respondent respectively,
after which Tripartite Share Purchase Agreement
4
was executed on August 1, 2006, of which
Services Agreement dated July 15, 2006 formed
part as schedule ‘A’ to the agreement. It is
averred in the reply that Share Purchase
Agreement, inter-alia provided that on certain
events not taking place by July 31, 2006, the
Tripartite Share Purchase Agreement would
stand terminated. According to the respondent
the said Tripartite Share Purchase Agreement
stood automatically terminated as the various
events mentioned therein did not take place by
July 31, 2006 and as Services Agreement relied
upon by the applicant was part of the said
agreement the same also stood automatically
terminated and, therefore, the applicant is not
entitled to invoke arbitration clause incorporated
in the agreement dated July 15, 2006. It is
claimed by the respondent that the Tripartite
Share Purchase Agreement stood novated,
rescinded and revoked on account of Letter of
Intent dated August 1, 2006, executed by the
5
parties, which totally replaced the Tripartite
Share Purchase Agreement and, therefore, also
the present application was not maintainable. By
filing the reply, the respondent demanded
dismissal of the application filed by the applicant.
5. The applicant has filed rejoinder affidavit to the
affidavit in reply filed by the respondent. In the
rejoinder affidavit, the applicant has, by and
large, reiterated what is stated in the application
and, therefore, this Court is of the opinion that it
is not necessary to make a detailed reference to
the rejoinder filed by the applicant.
6. This Court has heard the learned counsel for the
parties at length and in great detail. This Court
has also considered the documents forming part
of the application.
7. By now it is well settled that exercise of power
under Section 11(6) of the Act is judicial power.
After the decision of this Court in SBP and
Company vs. Patel Engineering Ltd. (2005) 8 SCC
6
618, the Designated Judge has to consider the
claim of both the parties to the matter and pass a
reasoned order. It is also well settled that
existence of arbitration agreement is a condition
precedent before exercise of powers under
Section 11(6) of the Act. The preliminary matters
to be considered by the court are (1) existence of
arbitration agreement, (2) territorial jurisdiction,
(3) whether there are live issues to be referred to
the arbitrator, and (4) whether application is filed
within the period of limitation prescribed by the
law. If the court finds that the arbitration
agreement does not exist or is rescinded then the
prayer for referring the dispute to the arbitrator
will have to be rejected.
8. The contention raised by the learned counsel for
the respondent that the Tripartite Share
Purchase Agreement stood automatically
terminated because various events mentioned
therein did not take place and, therefore, the
Services Agreement dated July 15, 2006, which
7
was part of the Tripartite Share Purchase
Agreement, ceased to exist, cannot be accepted.
9. In order to ascertain whether the Services
Agreement dated July 15, 2006 exists or not, it
will be relevant to notice salient features of two
agreements, namely, (1) Services Agreement
dated July 15, 2006 and (2) Tripartite Share
Purchase Agreement executed on August 1,
2006. Clause (2) of the Services Agreement dated
July 15, 2006 requires the applicant to supply
services to the respondent on payment of
consideration by the respondent. The services to
be supplied have been detailed in Schedule 2 to
the agreement. The consideration to be paid by
the respondent is mentioned in Schedule 1 to the
agreement. Clause 4 of the said agreement
provides that invoicing shall be done at the
beginning of each calendar month and the
amount due would be payable monthly. Clause 9
of the Services Agreement dated July 15, 2006
confers right upon the applicant to terminate the
8
agreement if payment for services rendered is not
received by the applicant within a period of fifteen
days from the expiry of the previous month.
Clause 10 of the said agreement provides for
consequences which would ensue on termination
of the agreement, whereas clause 19 enables the
aggrieved party to approach arbitrator for
resolution of the disputes. It is relevant to note
that by letter dated February 15, 2007 the
applicant had terminated the Services Agreement
and appointed its sole arbitrator as well as called
upon the respondent to concur with the said
appointment or to appoint its arbitrator. It is an
admitted fact that no reply was given by the
respondent to the said notice. It is also relevant
to notice that the execution of the Services
Agreement dated July 15, 2006 is not denied by
the respondent. What is claimed by the
respondent is that the Services Agreement ceased
to exist in view of termination of Tripartite Share
Purchase Agreement.
9
10. From the record of the case it becomes at once
evident that the Services Agreement dated July
15, 2006 was never a schedule to the Tripartite
Share Purchase Agreement. This becomes clear
from the contents of clauses 5.2 and 5.2.5 of the
Tripartite Share Purchase Agreement dated
August 1, 2006. Clause 5 of the Tripartite Share
Purchase Agreement, which is to be found on
running page 99 of the short counter affidavit
filed on behalf of the respondent, provides the
venue where completion of the said agreement
would take place and also mentions post
completion obligations. According to clause 5.1
of the said agreement, completion was to take
place at a venue to be agreed between the
applicant and Abela on the second business day
after the day on which the conditions stipulated
were satisfied. The consequences which were to
follow on the completion of the Tripartite Share
Purchase Agreement are mentioned in clause 5.2.
Clause 5.2.5 of the agreement reads as under: -
10
“SST and the Company shall enter into the Services Agreement and Shareholders Agreement (SHA) as per drafts given in Schedule A and B.”
It is the specific case of the respondent that the
Tripartite Share Purchase Agreement dated July 15,
2006, of which Schedules A and B were intrinsic and
inseparable parts, stood automatically terminated on
July 31, 2006 owing to non-completion of the
material conditions as postulated in clause 3.4 of the
agreement, without any further obligations, liability or
claim between the parties under the agreement. As
the Tripartite Share Purchase Agreement
automatically stood terminated due to non-
completion of the conditions mentioned in clause 3.4
of the agreement, there was no obligation on the
applicant to enter into the Services Agreement, draft
of which was annexed to the Tripartite Share
Purchase Agreement as Schedule A or Shareholders
Agreement, draft of which was produced as Schedule
B to the agreement. It is not the case of the
respondent at all that the draft of the Services
11
Agreement was signed by the applicant at any point of
time. Hence, automatic termination of Tripartite
Share Purchase Agreement has nothing to do with the
existence of the Services Agreement dated July 15,
2006, which was already separately executed between
the parties. The record would indicate that the
Services Agreement was executed before the Tripartite
Share Purchase Agreement was executed. The
existence of the said agreement was not dependent
upon the completion of events as contemplated by the
Tripartite Share Purchase Agreement and, therefore,
it is wrong to contend that the Services Agreement
ceased to exist on termination of the Tripartite Share
Purchase Agreement.
11. Similarly, the plea that the Tripartite Share
Purchase Agreement was novated, rescinded and
revoked on account of Letter of Intent dated
August 1, 2006 and, therefore, the instant
application should be rejected, has no force. The
Letter of Intent dated August 1, 2006 under no
circumstances can be treated as novating,
12
rescinding or revoking the Tripartite Share
Purchase Agreement. The said Letter of Intent on
a bare reading is nothing but an agreement to
enter into another agreement because it is
provided in the said letter that “both parties agree
to have set a deadline to sign this agreement by
15th September, 2006”. It is well settled legal
position that an agreement to enter into an
agreement is not enforceable nor does it confer
any right upon the parties. The agreement in
terms of the said Letter of Intent was to be signed
on or before September 15, 2006. It is not the
case of the respondent that any agreement was
executed between the parties on or before
September 15, 2006. The respondent has not
stated in its counter reply that the agreement,
which was to be executed by September 15,
2006, was in fact executed. During the course of
hearing of the instant application it was fairly
conceded by the learned counsel for the
respondent that no such agreement was executed
13
between the parties at all. Hence, as the
agreement contemplated by the Letter of Intent
was never executed, it cannot be said that the
agreement contemplated by the said Letter of
Intent had novated, rescinded or superseded the
Tripartite Share Purchase Agreement. Further,
the scope/terms of the Tripartite Share Purchase
Agreement as well as those of the Services
Agreement and the terms contemplated by Letter
of Intent dated August 1, 2006 are not consistent
at all and, therefore, it is difficult to hold that
novation of the Tripartite Share Purchase
Agreement read with the Services Agreement had
taken place, as contended by the respondent.
12. The net result of the above discussion is that the
Services Agreement dated July 15, 2006 has not
ceased to exist and the applicant is entitled to
invoke the arbitration clause contained in that
agreement. The application filed by the applicant
is within the time prescribed by law. There is no
manner of doubt that disputes are existing
14
between the parties relating to the execution of
the Services Agreement dated July 15, 2006,
which are arbitrable. Under the circumstances,
the instant application will have to be accepted.
13. For the foregoing reasons the application
succeeds. Mr. Justice Arvind Sawant (Retd.),
former Chief Justice, High Court of Kerala, is
appointed as the sole arbitrator. The learned
arbitrator is requested to enter on the reference
and do the needful in the matter as early as
possible in accordance with law.
14. There shall be no order as to costs.
……………………….J. [J.M. Panchal]
New Delhi; December 05, 2008.
15