SHYAM TELELINK LTD. Vs UNION OF INDIA
Bench: MARKANDEY KATJU,T.S. THAKUR, , ,
Case number: C.A. No.-007236-007236 / 2003
Diary number: 13905 / 2003
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICITION
CIVIL APPEAL NO.7236 OF 2003
Shyam Telelink Ltd. now Sistema Shyam Teleservices Ltd. …Appellant
Versus
Union of India …Respondent
J U D G M E N T
T.S. THAKUR, J.
1. This appeal under Section 18(1) of the Telecom
Regulatory Authority of India Act, 1997 is directed against
an order dated 9th April, 2003 passed by the Telecom
Dispute Settlement and Appellate Tribunal whereby Petition
No.24/2001 filed under Section 14(a)(i) read with Section
14A(1) of the Telecom Regulatory Authority of India Act,
1997 has been dismissed. The factual matrix giving rise to
the appeal may be summarised at the outset.
2. The appellant-Shyam Telelink Ltd. was granted a
licence under the Indian Telecom Act, 1885 on 4th March,
1998 for providing basic telecom services in Rajasthan
Circle. A licence agreement was executed between the
parties that, inter alia, required the appellant to start
commercial operations within twelve months from the date
on which the agreement was executed. The appellant’s case
before the Tribunal so also before us is that, it was ready to
commence commercial operations in the last week of
February 1999 and had sought permission of the
respondents to do so. Permission was, however, denied on
the ground that certain technical deficiencies remained to be
removed and certain conditions for the grant of permission
remained to be fulfilled. In the meantime the Union of India
appears to have offered a Migration Package to all the
Telecom Operators in July 1999. Under this package which
was offered to the appellant-Shyam Telelink Ltd. on 22nd
July, 1999 the fixed licence fee was to stand replaced by a
revenue-sharing arrangement w.e.f. 1st August, 1999
2
subject to the stipulation that atleast 35% of all outstanding
dues including interest payable as on 31st July, 1999 and
liquidated damages in full is paid by the appellant on or
before 15th August, 1999. Migration Package further
provided that the company shall have to accept all the
conditions stipulated in the package and that all proceedings
instituted by the licensee or their associations against the
Union of India shall have to be withdrawn.
3. It is not in dispute that the appellant gave an
unconditional acceptance to the Migration Package on 22nd
July, 1999 nor is it disputed that on 10th August, 1999 the
respondent advised the appellant that a sum of
Rs.6,74,90,481/- was payable towards outstanding licence
fee and interest due thereon apart from a sum of Rs.7.30
crores payable towards liquidated damages that were
provisionally determined. The appellant-company was
informed that in terms of the Migration Package at least
35% of the total licence fee along with interest amounting to
Rs.6,74,90,481/- had to be paid by it before 16th August,
3
1999 and the balance dues covered by a Financial Bank
Guarantee by the 30th November, 1999. The liquidated
damages payable by the appellant-company were demanded
in full and had to be paid on or before 16th August, 1999.
4. On receipt of the intimation demanding payment of the
amounts mentioned above the appellant-company appears
to have prayed for waiver of the liquidated damages on the
ground that it could not commence commercial operations
by the stipulated date on account of certain procedural
delay. That prayer was upon consideration turned down with
the result that the appellant paid 35% of the outstanding
licence fee and interest amounting to Rs.2.36 crores on 16th
August, 1999. It also paid the full amount of Rs.7.30 crores
towards liquidated damages as demanded by the
Government.
5. Commercial operations in Rajasthan were finally started
by the appellant-company on 5th June 2000. In March 2001
a demand was raised by the respondent for payment of a
4
further amount of Rs.70 lakhs as liquidated damages for the
delay in the commissioning of the service. Aggrieved by the
demand of Rs.8 crores towards liquidated damages out of
which the appellant had already paid Rs.7.30 crores on 16th
August, 1999 the appellant approached the Tribunal for
redress. As mentioned earlier the appellant’s case before the
Tribunal was that it was ready to commence commercial
operations in the last week of February 1999 and had sought
permission to do so from the respondent which permission
was in an arbitrary, illegal and discriminatory manner
refused by the respondent. Recovery of the liquidated
damages was, therefore bad, argued the appellant who
demanded refund of the entire amount of Rs.8 crores
recovered towards liquidated damages from it.
6. The respondent contested the petition before the
Tribunal, inter alia, on the ground that the petitioner-
appellant was not entitled to question any demand arising
out of the agreement executed between the parties after it
had unconditionally accepted the Migration Package under
5
which it agreed to deposit without demur the outstanding
licence fee as also the liquidated damages payable under the
licence agreement. The respondent also asserted that the
appellant was not ready with the commissioning of the
service as was evident from the admissions made in several
communications sent by it to the respondent. It was further
pointed out by the respondent that the computation of
actual liquidated damages could be undertaken only after
the appellant had commenced commercial operations. The
actual charges after such computation were according to the
respondent determined at Rs.29.86 crores but the demand
was restricted to Rs.8 crores in terms of the explicit
limitation prescribed under the licence. An amount of Rs.7.3
crores having already been paid under the Migration
Package, a demand for payment of Rs.70 lakhs only was
raised by the respondent. It was also asserted by the
respondent that the appellant had not disputed calculation of
the amount of Rs.7.3 crores as liquidated damages for non-
commissioning of the service at the time of Migration
6
Package and paid the same with other dues. Having done
so, the Migration Package which contained a specific
stipulation that the acceptance of the package “will be
deemed as a full and final settlement of all existing disputes
whatsoever irrespective of whether they are related to the
present package or not“ could not be questioned by the
petitioner-appellant. The respondent also raised the question
of limitation and assailed the maintainability of the petition
on that ground. By its order dated 9th April, 2003 impugned
in this appeal the Tribunal dismissed the petition filed by the
appellant aggrieved whereof the appellant has filed C.A.
No.7236 of 2003 before this Court.
7. We have heard learned counsel for the parties and
perused the record. A two-fold contention was urged in
support of the appeal by counsel appearing for the
appellant. Firstly, it was contended that the appellant was
ready to commence commercial operations in February 1999
i.e. within one year of the date on which the agreement was
signed between the parties. The fact that the petitioner had
7
applied for the grant of permission to commence commercial
operations in Jaipur from 3rd February, 1999 was according
to the appellant sufficient to show its readiness to
commence such operations. There is, in our opinion, no
force in that contention. It is not disputed that the actual
operations started only on 5th June, 2000. The material
placed before the Tribunal clearly established that during the
intervening period the appellant had been informed by the
respondent that clearance for commencing commercial
operations could be considered only after the following
requirements of the licence agreement were complied with:
(a) Payment of next instalment of licence fee due
on 3.3.1999;
(b) Provision of Performance Bank Guarantee
(PBG) and enhanced Financial Bank
Guarantee (FBG) for requisite amount and
validity before commencement of succeeding
year on 3.3.1999;
8
(c) Rectification of deficiencies pointed out by
TEC before the commencement of
commercial operations;
(d) Submission of plan in respect of providing
Direct Exchange Lines (DEL-s) and Village
Public Telephones (VPT-s) as per committed
targets failing which Liquidated Damages
(LD-s) are payable; and
(e) Establishment of a separate bank account (an
escrow account as stipulated under condition
18.6 of the Licence Agreement).
8. Material further established that the deficiencies
pointed out by the TEC could not be rectified by M/s
Qualcomm manufacturer of the equipment purchased by the
appellant forcing the latter to go for a new set of equipment
from a new vendor in December 1999 which equipment was
finally delivered and installed in April 2000. It was only after
the installation of the said equipment that fresh test
9
certificates were issued by TEC on 1st June, 2000 leading to
the start of the commercial operations on 5th June, 2000.
The fact that the appellant was not ready to commence
commercial operations in February 1999 is evident from its
own letter dated 19th July, 1999 in which the appellant had
clearly admitted that the system was not yet ready for such
operations and that the appellant was engaged only in
monitoring and testing the credential of the new technology
and the related software/hardware. It is also evident from
the letter of the appellant dated 25th August, 1999 that the
appellant was not in a position to indicate any firm date for a
formal launch of the service as the system was not yet in a
position to do so. The relevant part of the letter reads as
under:
“………… at this stage we are unable to indicate any date for formal commissioning of the commercial launch of the service since still there are bugs in the system provided by our supplier. In any case the testing has to continue for monitoring the behaviour of the equipment even after 75% loading of the system which is also being followed by DoT/MTNL, while acceptance testing of the
10
systems. However, we hope to commercialize the services by middle of December 1999, as supplier is continuously working to resolve the bugs in the software.”
9. In the light of the above admission which is the best
evidence against the appellant, it is not open to the
appellant to argue that it was ready to start commercial
operations in February 1999. The Tribunal was, therefore,
perfectly justified in holding that the commercial operations
were started only on 5th June, 2000 and that for the
intervening period such operations could not be commenced
on account of deficiencies that were attributed entirely to
the defects in the system which the appellant had installed.
The Tribunal was also justified in our opinion in holding that
the denial of permission to the appellant was neither
arbitrary nor mala fide especially when the conditions in the
licence agreement requiring the appellant to arrange and
install suitable equipment to meet the prevailing technical
specifications by Telecommunication Engineering Centre
were not complied with nor were all performance tests
11
required for successful commissioning of the services carried
out by the Licensor before the services are commissioned for
public use.
10. The argument that the respondent has acted arbitrarily
and in a discriminatory manner by overlooking similar
deficiencies in the case of other service providers has also
been correctly repelled by the Tribunal on the ground that
the nature of the deficiencies found in the case of the
appellant have not been found similar to those found in
other cases where permission was granted. As a matter of
fact, the appellant was given an opportunity to implead the
other service providers so that the allegation could be
examined in detail but the appellant failed to do so nor was
any material placed on record to show that any
discriminatory treatment was meted out to it. At any rate so
long as the conditions of the agreement entitled the
respondents to decline permission to commence commercial
operations on account of failure on the part of the appellant
to comply with the conditions stipulated in the said
12
agreement, which condition included a defect-free efficient
system, the fact that some other service providers were
given permission in the peculiar facts of their cases and
deficiencies allegedly noticed in their system could not make
out a case for the appellant to question the demand raised
on the basis of a package which the appellant had accepted
unconditionally and pursuant to which acceptance a
substantial part of the liquidated damages amounting to
Rs.7.3 crores had been deposited by it without any demur.
11. The Tribunal has also held and in our view correctly so
that the computation of the liquidated damages for non-
commencing of the services as well as limiting the same to a
total amount of Rs.8 crores was in conformity with the
licence conditions executed between the parties. There is
nothing before us to suggest that any error has crept in the
computation of liquidated damages nor was any such error
pointed out before the Tribunal. As a matter of fact,
according to the respondents the amount of damages works
13
out to Rs.29.86 crores was limited to Rs.8 crores in explicit
terms of the limitation laid down in the licence agreement.
12. The factual aspects apart we need to remember that
the payment of liquidated damages was an essential
condition of the Migration Package which was offered to the
service providers. Unconditional acceptance of the package
including the payment of outstanding licence fee with
interest due thereon and liquidated damages was a specific
requirement of the Migration Package which was
unequivocally accepted by the appellant in terms of the
declaration made in the following words:
“.. With reference to the letter No.842- 153/99-VAS (Vol.V) (Pt.) dated 22nd July, 1999 on the subject noted above, I hereby covey unconditional acceptance on behalf of the Licensee with regard to the package proposed for migration of the existing licenses to NTP 1999 Regime on the terms and conditions in the letter under reference…. ”
13. The unconditional acceptance of the terms of the
package and the benefit which the appellant derived under
14
the same will estop the appellant from challenging the
recovery of the dues under the package or the process of its
determination. No dispute has been raised by the appellant
and rightly so in regard to the payment of outstanding
licence fee or the interest due thereon. The controversy is
limited to the computation of liquidated damages of Rs.8
crores out of which Rs.7.3 crores was paid by the appellant
in the beginning without any objection followed by a
payment of Rs.70 lakhs made on 29th May, 2001. Although
the appellant had sought waiver of the liquidated damages
yet upon rejection of that request it had made the payment
of the amount demanded which signified a clear acceptance
on its part of the obligation to pay. If the appellant proposed
to continue with its challenge to demand, nothing prevented
it from taking recourse to appropriate proceedings and
taking the adjudication process to its logical conclusion
before exercising its option. Far from doing so, the appellant
gave up the plea of waiver and deposited the amount which
clearly indicates acceptance on its part of its liability to pay
15
especially when it was only upon such payment that it could
be permitted to avail of the Migration Package. Allowing the
appellant at this stage to question the demand raised under
the Migration Package would amount to permitting the
appellant to accept what was favourable to it and reject
what was not. The appellant cannot approbate and
reprobate. The maxim qui approbat non reprobat (one who
approbates cannot reprobate) is firmly embodied in English
Common Law and often applied by Courts in this country. It
is akin to the doctrine of benefits and burdens which at its
most basic level provides that a person taking advantage
under an instrument which both grants a benefit and
imposes a burden cannot take the former without complying
with the latter. A person cannot approbate and reprobate or
accept and reject the same instrument. In Ambu Nair v.
Kelu Nair AIR 1933 PC 167 the doctrine was explained
thus:
“Having thus, almost in terms, offered to be redeemed under the usufructuary mortgage in order to get payment of the other
16
mortgage debt, the appellant, Their Lordships think, cannot now turn round and say that redemption under the usufructuary mortgage had been barred nearly seventeen years before he so obtained payment. It is a well- accepted principle that a party cannot both approbate and reprobate. He cannot, to use the words of Honyman, J. in Smith v. Baker (1878) LR 8 CP 350 at p. 357 ‘at the same time blow hot and cold. He cannot say at one time that the transaction is valid and thereby obtain some advantage to which he could only be entitled on the footing that it is valid, and at another time say it is void for the purpose of securing some further advantage’.”
14. View taken in the above decision has been reiterated
by this Court in City Montessori School v. State of Uttar
Pradesh and Ors. (2009) 14 SCC 253. To the same effect
is the decision of this Court in New Bihar Biri Leaves Co.
v. State of Bihar 1981 (1) SCC 537 where this Court said :
“It is a fundamental principle of general application that if a person of his own accord, accepts a contract on certain terms and works out the contract, he cannot be allowed to adhere to and abide by some of the terms of the contract which proved advantageous to him and repudiate the other terms of the same contract which might be
17
disadvantageous to him. The maxim is qui approbat non reprobat (one who approbates cannot reprobate). This principle, though originally borrowed from Scots Law, is now firmly embodied in English Common Law. According to it, a party to an instrument or transaction cannot take advantage of one part of a document or transaction and reject the rest. That is to say, no party can accept and reject the same instrument or transaction (Per Scrutton, L.J., Verschures Creameries Ltd. v. Hull & Netherlands Steamship Co.)”
15. The decision of this Court in R.N. Goswain v. Yashpal
Dhir AIR 1993 SC 352, brings in the doctrine of election in
support of the very same conclusion in the following words :
“10. Law does not permit a person to both approbate and reprobate. This principle is based on the doctrine of election which postulates that no party can accept and reject the same instrument and that “a person cannot say at one time that a transaction is valid and thereby obtain some advantage, to which he could only be entitled on the footing that it is valid, and then turn round and say it is void for the purpose of securing some other advantage”. [See: Verschures Creameries Ltd. v. Hull and Netherlands Steamship Co. Ltd. (1921) 2 KB 608, at p.612, Scrutton, L.J.] According to Halsbury’s Laws of England, 4th Edn., Vol. 16, “after taking an advantage under an order (for example for the payment of costs) a party may be precluded from saying that it
18
is invalid and asking to set it aside”. (para 1508)”
16. In America Estoppel by acceptance of benefits is one of
the recognized situations that would prevent a party from
taking up inconsistent positions qua a contract or transaction
under which it has benefited.
17. American Jurisprudence, 2nd Edition, Volume 28, pages
677-680 discusses ‘Estoppel by acceptance of benefits’ in
the following passage:
“Estoppel by the acceptance of benefits: Estoppel is frequently based upon the acceptance and retention, by one having knowledge or notice of the facts, of benefits from a transaction, contract, instrument, regulation which he might have rejected or contested. This doctrine is obviously a branch of the rule against assuming inconsistent positions.
As a general principle, one who knowingly accepts the benefits of a contract or conveyance is estopped to deny the validity or binding effect on him of such contract or conveyance.
This rule has to be applied to do equity and must not be applied in such a manner as to
19
violate the principles of right and good conscience.”
18. For the reasons set out by us hereinabove, we have no
hesitation in holding that the appellant was not entitled to
question the terms of the Migration Package after
unconditionally accepting and acting upon the same.
19. In the result this appeal fails and is hereby dismissed
but in the circumstances without any order as to costs.
……………………………J. (MARKANDEY KATJU)
……………………………J. New Delhi (T.S. THAKUR) October 5, 2010
20