ROYAL EDUCATION SOCIETY Vs LIS(INDIA)CONSTRUCTION CO. PVT.LTD.
Bench: LOKESHWAR SINGH PANTA,AFTAB ALAM, , ,
Case number: C.A. No.-007012-007012 / 2008
Diary number: 16426 / 2006
Advocates: Vs
ANIL KUMAR JHA
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No. 7012 OF 2008 [Arising out of S.L.P. (C) No.12194 of 2006]
Royal Education Society ..... Appellant
Versus
LIS (India) Construction Co. Pvt. Ltd. ..... Respondent
J U D G M E N T
Lokeshwar Singh Panta, J.
1. Leave granted.
2. This appeal is directed against the judgment and order
dated 19.04.2006 passed by the Division Bench of the High
Court of Judicature at Bombay in Appeal No. 198 of 2006.
The appellant-Society has filed the above-said appeal
challenging the order dated 14.11.2005 of the learned Single
Judge whereby the appellant’s Arbitration Petition No.423 of
2004 filed under Section 34 of the Arbitration and Conciliation
Act, 1996 against the award of the Arbitral Tribunal was
dismissed.
3. Briefly stated, the relevant facts are as follows:
The appellant is an educational society duly registered
with the Charity Commissioner, Bombay under Bombay
Public Trust Act, 1956. The appellant-Society is running an
educational institution at Borli Panchatan, Taluk
Shriwardhan, District Raigad, Maharashtra. The President of
the appellant-Society is stated to be a renowned Surgeon and
a gold medalist of University of Bombay, in Surgery and is
affiliated to various well-known Hospitals in Bombay. The
President of the appellant-Society hails from village
Barli/Konkan and out of his emotional love to his native
village and in order to educate his own village children; he
took upon the responsibility to establish the school and
institution at his ancestral land at Barli in Konkan area of
2
Maharashtra. The appellant-Society is running English
Medium School for the last about 20 years.
4. The appellant-Society desired to establish a women’s
college at Borli and, therefore, it invited tenders for
construction of a building at Borli, Panchatan. The Society
was depending upon magnanimous donors, who have agreed
to donate the entire amounts for the Project.
5. The respondent-company is incorporated under the
Companies Act. The Director of the respondent-company
visited the site and in the presence of the donor, they agreed
to construct the building at the proposed site. The
respondent-company offered tender for constructing the
building at a total cost of Rs.1,55,37,981.20 [Rupees one crore
fifty five lacs thirty seven thousand nine hundred eighty one
and twenty paise]. The college was named after the donor as
‘Kalsekar Institute of Science’. It is the case of the appellant-
Society that the tender of the respondent-company was
accepted with the condition that the time was essence of the
contract and the respondent-company by its letter dated
29.04.2000 assured to the appellant-Society that the company
3
will complete the Project within the stipulated time. The
standard agreement drafted by the Council of Architect was
executed on 20.04.2000 and the entire Project was to be
completed within 18 months on or before 01.11.2001. It was
also agreed that the final measurement and valuation shall be
done in the 17th month. The date of the commencement was
agreed upon 01.05.2000. The procedure for payment was that
the respondent-company would submit the bills to the
appellant’s Architect and the same would be forwarded to the
donor (President of the appellant-Society) and thereafter the
cheque issued by the donor in the name of the appellant-
Society and, in turn, the appellant-Society would pay the
amount to the respondent-company.
6. The respondent-company allegedly failed to complete the
Project as on 01.11.2001 and the appellant-Society did not
give any extension of time to the respondent-company. The
respondent-company paid a total sum of Rs.1,41,59,956/- as
on 19.10.2001 for the cost of work done. The respondent-
company abandoned the work in the midstream. The donor
refused to give any amount beyond the agreed amount of
4
Rs.1,55,37,981.20 when he found that the building was still
incomplete and the contractors were demanding astronomical
amount for completion of the entire building. The respondent-
company removed their entire labour and machinery from the
site and it left the building incomplete as an orphan without
any care or maintenance to face the wrath of seasons. The
building has no windows and doors on the upper floors.
Subsequently, correspondence was exchanged between the
appellant-Society and the respondent-company. The
respondent-company also failed to pay the electricity bill of
Rs.1,29,000/-.
7. On these premises, the respondent-company filed
Arbitration Application bearing No. 61 of 203 before the High
Court of Judicature at Bombay. The President of the
appellant-Society appeared in-person. The said Arbitration
Application came up before the learned Single Judge on
02.05.2003, on which date following order was passed:-
“… The Petitioners have already appointed Mr. Devbhakta as their arbitrator. Mr. Roshan Nanavati is appointed as second arbitrator. These two arbitrators will appoint third
5
arbitrator who will act as Presiding Arbitrator. The arbitral tribunal so constituted will decide all issues between the parties including claims and counter claims, if any, and also existence of arbitral clause and/or that the claims as raised by the Petitioners are arbitrable or not. Application stands disposed of accordingly.”
8. The respondent-company filed its alleged claim on
31.07.2003, whereas the appellant-Society filed reply thereto
and counter claim also on 21.1.2003 accompanied by report
dated 21.01.2002 of the Architect Khalil R. Shaikh and
Associates. The arbitration proceedings were heard on
various dates and finally the Arbitral Tribunal passed an
Award on 23.02.2004, but since the respondent-company did
not pay the fees of the Arbitral Tribunal, therefore the Award
was not declared. Subsequently, it appears that the
respondent-company paid the fees of the Arbitral Tribunal and
thereafter on 20.04.2004 the said Award was communicated
and declared to the appellant-Society by the Arbitral Tribunal
by its letter dated 20.04.2004. The following Award was
passed by the Arbitral Tribunal:-
6
1. We do hereby award that the Respondents namely M/s. Royal Education Society do pay to the Claimants namely M/s LIS (India) Construction Co. (P) Ltd., the sum of Rs.35,50,762.03 [Rupees thirty five lakhs fifty thousand seven hundred sixty two point zero three only] in full and final payment of the claim No.1 upheld by us in this arbitration proceedings.
2. We do hereby award that the Respondent do bear and pay interest at 7% per annum on the amount of Rs.35,50,762.03 [Rupees thirty five lakhs fifty thousand seven hundred sixty two point zero three only] from 13.06.2003 till the date of award as also interest at 7% p.a. from the date of award till the date of payment excluding two months needed to make arrangement for payment.
3. We do hereby award that the Respondents namely M/s. Royal Education Society do pay to the Claimants namely M/s LIS (India) Construction Co. (P) Ltd., the sum of Rs.5,00,000/- [Rupees five lakhs only] towards claim No.2.
4. We do hereby award that the Respondent do bear and pay interest at 7% p.a. on the above amount of Rs.5,00,000/- from the date of award to the date of payment excluding one month needed to make arrangement for payment.
5. We do hereby award that each party do bear and pay its own legal cost as well as cost of this arbitration proceedings.
7
6. We do hereby award that each party do bear and pay three Arbitrators’ fees in equal parts.”
9. Being aggrieved by the Award of the Arbitral Tribunal,
the appellant-Society filed Arbitration Petition 423 of 2004
before the High Court of Judicature at Bombay. The learned
Single Judge dismissed the said arbitration petition on
14.11.2005.
10. Feeling aggrieved thereby, the appellant-Society filed
appeal challenging the correctness and validity of the order
dated 14.11.2005 of the learned Single Judge and the Award
passed by the Arbitral Tribunal. The Division Bench of the
High Court, as noticed above, dismissed the appeal on
19.04.2006. Now, the appellant-Society has filed this appeal
by special leave.
11. We have heard the learned counsel for the parties and
meticulously examined the judgment and order of the Division
Bench confirming the order of the learned Single Judge
dismissing the Arbitration Petition of the appellant-Society.
12. It is not in dispute that Dr. Abdur Rahim Undre is the
8
President of the appellant-Society. He registered the
appellant-Society with the Charity Commissioner, Bombay.
The appellant-Society is running schools and college for
women at a small village Borli Panchatan in Taluka
Shrivardhan, District Raigad. Dr. Abdur Rahim Undre, as a
President of the appellant-Society, donated all his immovable
property and established English medium school in his native
place. The appellant-Society through its Architects, M/s
Salim Dawawala, had invited tenders for construction of Girls
College at Borli Panchatan. The respondent-company had
submitted its tender for the said work. It is not in dispute
that the tender of the respondent-company was accepted on
behalf of the appellant-Society. The work was awarded to the
respondent-company by the appellant-Society. Thereafter, a
formal contract agreement dated 20.04.2000 was entered into
by and between the parties. As per the terms of the contract,
the work under the contract was stipulated to be completed by
01.11.2001, i.e. within 18 months period from 01.05.2000.
The total estimated cost of Project was Rs.1,55,37,981.20
based on item-rate contract. Undisputedly, as the
9
respondent-company could not complete the work within the
stipulated period, therefore a dispute arose between the
parties, which was referred by the learned Single Judge to
three members of Arbitral Tribunal, namely, Shri Russi R.
Mistry, Shri Madhav Deobakhta and Dr. Roshan N. Nanavati.
Both the parties filed their statements of claim and counter-
claim before the Arbitral Tribunal. The respondent-company
under Claim No.1 had claimed a sum of Rs.38,06,576.75 for
outstanding R.A. Bills. Against R.A. Bill No.17, an amount of
Rs.21,33,423.18 was claimed, whereas against R.A. Bill No.18
a sum of Rs.15,35,356.97 was claimed out of which a sum of
Rs.1,37,796.60 was claimed beyond prolonged period of work,
i.e. 01.11.2001 to 21.01.2002. The Arbitral Tribunal had
allowed the following claims:-
1. In regard to R.A Bill No.17, a sum of Rs.22,45,708.61 was awarded.
2. For R.A. Bill No.18, a sum of Rs.13,05,053.42 was awarded.
3. Bill beyond R.A. Bill No.18 was rejected.
10
The total amount awarded under Claim No.1 was
Rs.35,50,762.03.
13. It was the claim of the respondent-company before the
Arbitral Tribunal that gross value of the work executed by it
within the stipulated period was to the tune of
Rs.1,45,59,956/-, but the total work executed was to the
extent of Rs.1,80,78,908/-. Thus, the difference between the
gross value of the work and the amount of total work got
executed in the prolonged period was Rs.35,18,952 and the
said amount was claimed on escalation rate at 10%. The
Arbitral Tribunal awarded a sum of Rs.35,50,762.03 under
Claim No.1 and a sum of Rs.5,00,000/- under Claim No.2 to
the respondent-company along with interest at the rate of 7%
p.a. from the date of award till the date of payment, excluding
two months needed to make arrangement for payment. Claim
Nos.3, 4, 5, 6, 7 and 8 were rejected. The counter claim of the
appellant-Society was rejected.
14. As stated above, the Award of the Arbitral Tribunal was
upheld by the learned Single Judge as well as by the Division
Bench of the High Court.
11
15. We have gone through the general conditions of contract
executed between the appellant-Society and the respondent-
company. The Type of Contract in terms of clause (3) of the
Contract was item-rate contract and the Contractor was to be
paid for the actual quantity of work done, as measured at site,
at the rates quoted by him in the Contract Bills. In terms of
clause 16 (1) the Architect shall be the Owner’s representative
during the construction period, who shall periodically visit the
site to familiarise himself generally with the progress and the
quality of the work and to determine in general if the work was
proceeding in accordance with the contract document. As per
clause 32, when any instruction or decision given at site
involves an extra or whereby the Contractor may plan to claim
an extra, it shall be the responsibility of the Contractor to
inform the Architect of the extra amount and get written
authorization from the Architect before proceeding with the
work involved. Clause 40 of the Arbitration Agreement
stipulates that upon it becoming reasonably apparent that the
progress of the works is delayed, the Contractor shall
forthwith give written notice of the cause of the delay to the
12
Architect and if in the opinion of the Architect, the completion
of the work to be or has been delayed beyond that date for
completion stated in the appendix to these conditions or
beyond any extended time previously fixed under this clause.
The record shows that the Architect of the appellant-Society
issued letter dated 20.4.2000 to the Managing Director of the
respondent-company whereby the tender quotations of the
respondent-company was accepted by the appellant-Society
on certain conditions contained in the said letter. One of the
conditions was that total cost of the Project will be within
Rs.1.55 crores. Further condition was that the Project of the
construction of the Girls College at Borli, Panchatan for the
appellant-Society shall be completed within stipulated time
frame of 18 months from 01.05.2000 and if the Project was
not completed within stipulated time, a penalty of Rs.1,000/-
per day will be charged and if completed before time, same
amount will be paid as bonus. It was also stipulated that the
respondent-company could mobilize the work from
21.04.2000. The MOU will be read in conjunction with tender
document and other prevailing laws of the State Government.
13
16. In response to the said work order, the Director of the
respondent-company vide reference : LIS/RES/00/06 dated
29.04.2000 acknowledged and accepted the work order dated
20.04.2000 and stated that the respondent-company had
started mobilization for the commencement of the said Project
and assured the appellant-Society to complete the same
within the stipulated time limit. In terms of the Agreement,
the Director of the respondent-company informed the
Architect of the appellant-Society vide letter dated 16.05.2000
that in terms of the Agreement the respondent-company had
already mobilized the site and executed the work at the site.
The parties thereafter have exchanged various
communications with each other. The respondent-company
could not complete the work within the stipulated period, the
appellant-Society vide letter dated 04.09.2001 refused to give
further extension of time beyond stipulated period as
contemplated in the Terms of the Agreement. It is not
disputed that the appellant-Society has paid a sum of
Rs.1,41,000/- to the respondent-company before 01.11.2001,
i.e. the stipulated period for execution of the work. The
14
respondent-company submitted R.A. Bill Nos. 17 for
Rs.22,45,708.61 and R.A. Bill No. 18 for Rs.13,05,053.42 after
the stipulated period of the execution of the work. The
appellant-Society has not extended the stipulated time beyond
01.11.2001. The respondent-company claimed a sum of
Rs.1,80,78,908/- for the work done by it till 21.01.2002.
17. Undisputedly, the appellant-Society is an educational
society duly registered by the Charity Commissioner under
Bombay Public Trust Act, 1956. Dr. Syed Akhtar, a renowned
Surgeon, is the President of the appellant-Society. He has
established a women’s college at his native village Borli
Panchatan with a sole purpose of giving education to the
children of his native village. He has donated his entire land
for the construction of the women’s college and received
substantial amounts by donations from magnanimous donors
for the Project. The work of construction of the college was
entrusted to the respondent-company for a total cost of
Rs.1,55 crores. Looking to the charitable cause for which the
President-Donor of the appellant-Society has donated his land
and raised money from the donors, we do not wish to embark
15
upon the merits of the claims and counter claims raised by
the parties before the Arbitral Tribunal. In the interest of both
the parties and in order to settle their dispute finally, we think
it proper and reasonable that in addition to Rs.1,41,51,956/-
already paid by the appellant-Society to the respondent-
company for the work executed by it, an extra sum of Rs.21
lakhs shall be paid by the appellant-Society to the
respondent-company on account of the work claimed in R.A.
Bill No.17. The respondent-company is not entitled to the
payment of the amount claimed for prolonged period of work
done after 01.11.2001 to 21.01.2002. The claim beyond
01.11.2001 made by the respondent-company and awarded
by the Arbitral Tribunal, therefore, is wholly untenable and
unsustainable.
18. In the facts and circumstances of the case, the
respondent-company cannot be held entitled to the retention
money and interest as awarded by the Arbitral Tribunal in its
Award, which has been affirmed by the High Court. The
balance amount of Rs.21 lakhs, as ordered by us, shall be
16
paid by the appellant-Society to the respondent-company
within eight weeks from the date of this order.
19. In the result, for the above-said reasons, the appeal is
partly allowed and the judgment and order dated 19.04.2006
of the Division Bench of the High Court affirming the order of
the learned Single Judge in Arbitration Petition No. 423 of
2004 whereby the Award of the Arbitral Tribunal was upheld,
shall stand modified in the aforesaid terms and to the extent
indicated above. The parties are left to bear their own costs.
........................................J. (Lokeshwar Singh Panta)
........................................J. (Aftab Alam)
New Delhi, December 02, 2008.
17