05 December 2006
Supreme Court
Download

RAMCHANDRA MURARILAL BHATTAD Vs STATE OF MAHARASHTRA .

Bench: S.B. SINHA,DALVEER BHANDARI
Case number: C.A. No.-005610-005610 / 2006
Diary number: 5607 / 2004
Advocates: P. N. GUPTA Vs A. S. BHASME


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 17  

CASE NO.: Appeal (civil)  5610 of 2006

PETITIONER: Ramchandra Murarilal Bhattad & Ors.

RESPONDENT: State of Maharashtra & Ors.

DATE OF JUDGMENT: 05/12/2006

BENCH: S.B. Sinha & Dalveer Bhandari

JUDGMENT: J U G D M E N T (Arising out of S.L.P. (C) No.5900 of 2004) WITH  

CIVIL APPEAL NO. 5611/2006 (Arising out of S.L.P. (C) No.23665 of 2004)

S.B. Sinha, J.

Leave granted.

The Mumbai Metropolitan Region Development Authority (for short,  ’the Authority’) was created under the Mumbai Metropolitan Region  Development Authority Act, 1974 (’the Act’).  It conceptualized the idea of  establishing a Convention and Exhibition Centre (’C&EC).  Pursuant thereto  and in furtherance thereof it called for "Expression of Interest for  development of C&EC" in Bandra Kurla Complex.  An advertisement was  issued inviting ’Expression of Interest for development of C&EC’.     Appellant No.1, pursuant whereto and in furtherance whereof, entered into a  Memorandum of Understanding (MoU) with M/s. Larsen & Toubro Ltd.  (L&T) for setting up such a complex.  It also conducted conference of  investors therefor.  It submitted its tender on 7.4.2003, highlighting :

a)      Entire ground of 75,000 sq.m. would be required for international  standard C&EC.    

b)      They have formed a consortium for bidding for the said project and  giving the names of the members of the consortium as including  L&T and IMAG (Germany).

c)      Letters of acceptance from L&T was also annexed to show its  participation.

d)      The Authority was offered equity participation to the extent of 5%  of the total equity base.

Several other companies also submitted their tenders.   

The tenders were to be considered at three stages and thus, three  different covers were to be submitted along with tenders.  The first cover  contained compliance with minimum eligibility criteria, the second cover  contained financial bid and the third one contained technical and business  proposals.  The technical bid was opened on 7.5.2003.  The financial bid was  thereafter opened which was contained in second cover, on 8.5.2003.   Appellant was the highest bidder having offered 91.514 crores.  M/s.  Reliance Capitals Ltd. was said to be the lowest bidder therein.  The offer of  the bidders thereof are as under :

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 17  

1.      M/s. Shapurji Pallonji & Co. Ltd.       Rs.50.005 Crores. 2.      M/s. Reliance Capitals Ltd.             Rs.13.032 Crores. 3.      M/s. R.M. Bhuther & Co. Ltd. and          its Associate companies in consor-         tium with L&T Ltd.                      Rs. 91.514 Crores.       

3rd Cover thereof was opened thereafter and the Authority, on  26.6.2003 informed Appellants that it had decided to arrange a presentation  on the business proposal by them on 3.7.2003.  Pursuant thereto they made a  presentation on 4.7.2003.   Appellants, by a letter dated 29.8.2003, informed the Authority that :

a)      reputed concerns like L&T and IMAG were associated in the  project.

b)      A presentation was made on 4th July, 2003, a copy whereof was  enclosed.

c)      Thereafter it did not receive any query from the Authority.

d)      List of business partners shown with details of Convention  projects of L&T and business of IMAG.

e)      Role of IMAG was also set out.

The Authority, however, took a decision to reject all the bids on  1.9.2003, which was said to have been communicated to Appellants by a fax  message on 22.10.2003.

Allegedly, the news item appeared in the ’Economic Times’ on  2.10.2003, wherein, inter alia, it was reported  that :

a)      The Authority is close to finalizing the much talked about  Convention centre in Bandra Kurla Complex. b)      An official of the Authority had stated that they were trying to  get private participation and three bidders had been finalized  and in a few days the plans for the Centre would be finalized in  an area of 5.5 hectares.

Appellant issued a letter to the Chairman of the Authority, in terms  whereof he was, inter alia, informed that the project would start getting  yield only after 12 years from the date of commencement thereof.  It was  furthermore informed that its consortium members included L&T and  IMAG.   

It was contended :

i)      The company has offered highest bid price for the land at BKC  for a reserved plot for C&EC since the company is interested in bringing up  an international standard Exhibition Centre, a long over-due infrastructure  asset for a city like Mumbai inspite of reserved plot (restricted utility) area  with high gestation period and longest break even which is almost about 7  years.  In all, the project starts getting yield only after 12 years from date of  commencement of construction.

(ii)    It has also been the contention of the company to relocate the  asset base of the company on account of core competency of the company in  the field for more than 50 years and intending to continue to command on  industry.

iii)    As per the press release for a commercial block bidding invited  by the Authority, it was awarded at Rs.25,000/- per square metre in spite of

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 17  

having a total flexibility to exploit the commercial aspect vis-‘-vis an offer  given by the company for the reserved plot for convention centre at the rate  of Rs.14,642/- per square metre.

iv)     Company also expressed that the projects of such type are  always being given land at very concessional rate.  Statistics indicates that  world over such exhibition centres are either funded by way of concessional  land price or absolute government contribution by way of land to make the  project to early break even.  

The expertise of L&T and IMAG in setting up Exhibition Centres was  again highlighted by a letter dated 20.10.2002, therein it was alleged :

a)      The Authority had informed in the presence of other bidders  that the consortium led by the appellants were the successful bidders. (b)     Some committee members informed that the matter had not  been decided on 1.9.2003 and the matter was deferred till the next meeting  to be held on 27.10.2003.

(c)     The detailed history was set out including the fact that Reliance  Capital had quoted Rs.13.032 crores against Rs.91.514 crores quoted by  Appellants.

d)      L&T and IMAG were the consortium members and the decision  would have an international impact.      

A writ petition was filed before the Bombay High Court by  Appellants, inter alia, questioning :

a)      the validity of clause 2.4 of the Request for Proposal in which  the Authority reserved the right to reject at any stage all or any of the bids  without assigning any reason. b)      the power of the Authority to cancel or reject the bids.

c)      the cancellation of the bid by the decision purported to have  been made on 1.9.2003.

The contentions of Respondents before the High Court were : a)      the decision to reject all bids is in pursuance of the power was  conferred by the terms of the contract.

b)      the authorities acted reasonably and fairly and have now  reached a decision to set up the convention centre on their own without any  private participation.

c)      By virtue of sections 12(1)(b)(d) and (h) and the power to issue  directions under S.14 of the Act, it could, at any stage, review any decision  including the decision of the executive committee and direct either rejection  of all bids or issuance of fresh bids.

The writ petition filed by Appellants was dismissed by the High Court  holding :

A.      the Executive Committee is not the sole judge in matters of  approval or rejection of tenders for projects and schemes of the authorities.

B.      In view of sections 12, 13, 14 and other provisions of the  Chapter, the power of the Authority cannot be whittled down or restricted.

C.      It being the authority entitled to acquire, hold and dispose of the  property it cannot be said that its power in such mattes will not include the  power to reject a tender or bid which is invited for projects and schemes  framed by it.

D.      In exercise of the powers under Article 226 it could not act as

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 17  

an Appellate Authority to review of supervise the functions of authorities  like the Mumbai Metropolitan Region Development Authority.

E.      Considering the material on record it cannot be held that the  Authority acted unreasonably unfairly or in an unjust manner.

F.      The Authority consisting of people possessing expertise and  skill in the field its decision to develop the property as a C&EC by itself  cannot be faulted with. G.      It is not a case where Article 14 can be said to have been  infringed.

H.      It cannot be said the facts which are pleaded   are not based on  evidence or materials which are not annexed to the counter affidavit.

I.      Reasons in such matters can be gathered from files/records  maintained by the authorities.

A review petition filed thereagainst was dismissed. Appellants filed the special leave petition on 29.10.2004 against the  order dated 20.1.2004 as also against the order dated 11.10.2004 dismissing  the review petition.   

In its counter affidavit filed before this Court the Authority, inter alia,  disclosed that the rate of premium for the commercial properties was  increased from Rs.25,000/- per square metre to Rs.42,500/- per square  metre.  It was further disclosed that the Authority called for fresh tenders for  development of 5.5 hectares as C&EC and 2.0 hectares for a commercial  complex, in terms whereof the bidders were required to quote separately for  C&EC and Real Estate Components.  Whereas the rate for C&EC was fixed  at 130 crores (Rs.20,000/- per square metre); for the Real Estate Component  the bidder was required to quote higher than 350 crores (i.e. higher than  Rs.70,000/- per square metre).  It was further stipulated that the successful  bidder was required to pay 50% of the compensation amount within one  month of acceptance thereof and the rest 50% within three months thereof.   The other terms and conditions and procedure for evaluating bids, however,  remained the same.  A supplementary affidavit was filed by Respondents on  20th February, 2006, wherein it was brought to this Court’s notice that in  response to the tender floated in 2005, Reliance Industries Ltd. had bid  Rs.974,00,00,111/- for the commercial portion and the fixed price of Rs.130  crores for the C&EC.  Reliance Industries Limited thereafter was directed to  be impleaded as a party by an order dated 24.4.2006, wherein this Court  recorded :

"These matters pertain to the construction of a  Convention-cum-Exhibition Centre and commercial  complex at Bandra Kurla, Mumbai.  The petitioner  before us is the unsuccessful bidder who has challenged  the action of the Mumbai Metropolitan Region  Development Authority (MMRDA) cancelling all the  bids at an earlier stage.  Despite the application made by  the petitioner, we declined to grant injunction in the  matter.  As a result, MMRDA re-tendered and we are  informed that the highest bid was by Reliance Industries  Limited, which is said to have been granted the contract  and paid a sum of Rs.552 crores. The petitioner desires to demonstrate to this Court  (a) that the bid was cancelled by the MMRDA, which  had no jurisdiction to do so under the Act; and (b) that  there was mala fides in cancelling all the bids as it was  intended to engineer the re-tendering process to favour  the party who has now succeeded.  To demonstrate his  bona fides, the petitioner’s counsel states that the  petitioner would not only match the bid of the presently  successful party only for the Convention Centre, but that

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 17  

he would also pay the amount at one go instead of paying  it over a period of time. We are informed that there is another party who is  involved.  Mr. R.F. Nariman, the learned senior counsel,  states that the petitioner would move an application to  implead that other party (Reliance Industries Limited)."           The Reliance Industries Limited was impleaded as a party to this  appeal thereafter.

Mr. R.F. Nariman, learned Senior Counsel appearing on behalf of  Appellant in support of this appeal would contend that \026

i)              the purported major shift in the policy by the Authority was  impermissible in law;

ii)             rejection of the bid offered by the Authority was wholly illegal  as the Executive Committee alone was the sole judge in relation thereto;

iii)            in accepting the bid of Reliance Industries Ltd., the offer of the  appellants that they would pay @2=% per year from the annual turnover  from the 21st year had not been considered;

iv)             in rejecting the tender of the appellant, the Executive  Committee/Mumbai Metropolitan Region Development Authority was  required to assign sufficient and valid reason; and the same having not been  done, the order impugned in the writ petition was vitiated in law.

Mr. Harish N. Salve, learned Senior Counsel appearing on behalf of  the Reliance Industries Ltd., on the other hand, would submit that \026

i)      the Executive Committee could not have taken a decision in  regard to the change of policy;

ii)     when the second tender was floated, Appellant did not take part  therein;

iii)    procedural lapses, if any, cannot be a ground for judicial  review.

Contentions of Mr. Shekhar Naphade, learned Senior Counsel  appearing on behalf of the Authority were \026

i)      judicial review is not maintainable as Appellant has not  disclosed infringement of any constitutional or statutory right;

ii)     the Authority was entitled to reject the tender on appreciation of  professional competence and capacity of Appellant to run the centre  profitably, as well as the fact that prices offered by them were competitively  low; and

iii)    the policy being in relation to a mega project and the judgment  of the authority being objective criterion, no interference is called for by this  Court.

The Act was enacted for forming Brihan Mumbai and certain areas  round about into a Mumbai Metropolitan Region.  Section 4 thereof deals  with the composition of the Authority.  Section 4A provides for powers and  functions, inter alia, of its Chairman and Metropolitan Commissioner.  Section 7 provides for constitution and powers of Executive Committee.   Clause (iii) of Sub-Section (3) of Section 7 reads as under :

"7. (3)(iii)    approval or rejection of tenders for  projects and schemes of the Authority;"

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 17  

Section 12 of the Act provides for powers and functions of the  Authority.  Clause (b) of Sub-Section (1) of Section 12 deals with the power  of reviewing any project or scheme for development which may be proposed  or may be in the course of execution or may be completed in the  Metropolitan Region.  Clause (d) thereof refers to execution of projects and  schemes and Clause (h) provides for co-ordination in execution of the  project or schemes for the development of the Metropolitan Region.   Pursuant to or in furtherance of its regulation making power contained in  Section 50 of the Act, regulations were framed by the Authority, known as  the Mumbai Metropolitan Region Development Authority (Disposal of  Land) Regulations, 1977 (Regulations).  Regulations 7 and 9 of the  Regulations are as under :

"7.     Disposal of land by offers to Government,  Local Authority or Public Sector Undertaking  

Where the Authority determines to dispose of land  by making offers to the Government, Local Authority or  Public Sector Undertaking, the offers shall be made by  the Metropolitan Commissioner in such form as he may  decide, incorporating the terms and conditions of offers  determined by the Authority which shall include the  condition that the offer shall remain open and valid for  acceptance for a period of 30 days and shall lapse if it  remains unaccepted by the expiry of this period; provided  that it shall be lawful for the Metropolitan Commissioner  to renew any lapsed offer on an additional condition that  the Government, Local Authority or Public Sector  Undertaking, as the case may be, shall pay interest at the  rate of 18% per annum over the premium specified in the  lapsed offer with effect from the date on which the lapsed  offer was made; provided further that nothing contained  herein shall authorize the Metropolitan Commissioner to  renew any lapsed offer after three months of its lapse."

Regulation 9 provides for the mode and manner of payment of  premium.

Sub-Regulation (ii) of Regulation 9 reads as under : "9(ii)  Notwithstanding anything contained in the  foregoing Clause to contrary, if there shall a scheme  formulated and sanctioned by the Authority to erect or to  finance erection of a building or buildings on land agreed  to be leased to the Government, a Local Authority or a  Public Sector Undertaking to subserve the development  of the Metropolitan Region or any part thereof and to  grant in lease such building or buildings to the concerned  government, Local Authority or Public Sector  Undertaking it shall be lawful to agree with the  concerned Government local authority or Public Sector  Undertaking to recover the premium agreed to be paid in  consideration of the lease of such building or buildings in  yearly installments, not exceeding ten in number."     

We may also notice some of the provisions of "Request for Proposal  for Grant of Lease of Land for developing and operating a Convention and  Exhibition Centre". Clause 3.15 defines "successful bidder" to mean the  bidder selected according to the evaluation criteria as detailed in Section 7  for grant of lease of land.  The concept of Convention and Exhibition Centre  is contained in Clause 4.3 thereof.  Clause 5 provides for specification of  C&EC.  Clause 5.1 reads as under :

"5.1    The C&EC facility for Phase I is estimated to  require approximately 35,750 sq.m. of built up area

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 17  

which will be reckoned as 44,525 sq.m. for computation  of FSI after allowing for height in excess of 4.20 m. for  exhibitions areas.  In Phase II there is a provision of a  further 10,650 sq.m. of built up area (which will be  reckoned as 15,975 sq.m. for computation of FSI for  Exhibition areas having height in excess of 4.20 m) that  is to be used for further expansion of exhibition areas  having at least 2 additional exhibition halls having an  area of 5000 sq.m. each."     

The total built-up area comes to about 60,500 sq.m.   

Provision of Convention Auditorium was made in Clause 5.3.  Clause  7 provides for submission and evaluation of bids stating that interested  parties shall submit their bids in three separate sealed covers : (1) Cover 1  should contain compliance in regard to minimum eligibility criteria.   Evaluation of minimum eligibility criteria is contained in clause 7.15 in the  following terms :

"7.15   The objective of the minimum eligibility criteria is  to short list Bidders who have :

?       The financial strengths necessary to contribute  and/or arrange the funds required to execute the  Project in the desired time frame.

?       The technical skills necessary to design,  construct, operate and maintain the Facility as  per the Principles of Good Industry Practice.

?       The commercial skills necessary to market the  Facility and successfully develop business.  

Clause 7.17 provides for the eligibility criteria being :

?       "Tangible Net worth not less than Rs. 750 Million  as per the latest audited financial statement.

?       Annual turnover not less than Rs.500 Million as  per the latest audited financial statement.

?       Net Profit not less than Rs. 50 Million as per the  latest audited financial statement or Average  annual net profit of the last three financial years  not less than Rs.50 Million."  

Category "I", related to field of activity defined as Convention &  Exhibition Centres, Hotels, Restaurants and Banquet Halls.   

Clause 7.22 provides for Category "II" to include an indirectly related  field of activity defined as shopping centers, commercial complexes,  housing or office complexes, retail stores, entertainment centres and  amusement parks.  Clause 7.23 provides for the eligibility criteria to show  that the bidding company must have developed during last five years at least  one Project having Capital Cost not less than Rs.1,000 Million.  Clauses  7.24 and 7.25 thereof read as under :  

"7.24   The turnover of the Bidding Company or the  combined turnover of the Financially Significant  Members of the Bidding Consortium from the  directly related field of activities shall not be less  than Rs.500 million.

7.25    Format for Cover I \026 compliance to minimum  eligibility criteria

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 17  

       Bidders are required to organize "Cover I \026  Companies with Minimum Eligibility Criteria"  according to the following checklist :

Cover 1 Compliance to Minimum Eligibility  Criteria Section 1 \005\005\005\005\005\005. Section 2 a)      \005\005\005\005 b)      \005\005\005\005 c)      Letters of Acceptance, as per the  format specified in Exhibit 4, from each  of the Consortium Members in case of a  Bidding Consortium. Section 3 a) \005\005\005\005.. b) Letters of Commitment as per the  format specified in Exhibit 3, from each of  the entities which are Financially  Significant Consortium Member, the  strengths of which is to be considered for  the purpose of evaluation.

Clause 7.26 reads as under :

"7.26 MMRDA on demand will return unopened  Financial Bids and Technical Bids (Covers 2 and  3) of the Bidders who do not comply with the  minimum eligibility criteria."

Step 2 (Cover 2) provides for financial bid.  Clause 7.30 provides for  methodology for evaluation of bids.

Clause 7.30 deals with the manner in which the bids would be dealt  with.

Clause 7.34 provides for technical and business proposal evaluation  criteria.  Clauses 7.38 and 7.39 are as under :

"7.38   In evaluating the Business Proposal, MMRDA  reserves the right to seek clarifications from the  Bidders.  The Bidders shall be required to furnish  such clarifications.

7.39    The Technical and       Business Proposal of only the  Rank 1 bidder will be opened.  He may also be  requested to make a presentation at his own cost,  for clarifications and additional information on  bidder’s capability, concept plan and the business  proposal in this regard to the evaluation committee  appointed by the Metropolitan Commissioner,  MMRDA.  The Committee may seek further  clarifications and make suggestions in respect of  the proposal, within the permitted built-up area,  which will not include any change in the premium  or the manner in which it is to be paid.  These  suggestions will have to be incorporated by the  bidder."

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 17  

The Bidding Companies/Bidding Consortium of Appellants included :

1.      M/s. R.M. Bhuther & Co. Ltd. 2.      M/s. Larsen & Toubro Ltd. 3.      M/s. R.M. Bhuther & Co. 4.      M/s. M.B. Development Corporation 5.      M/s. M.B. Constructions 6.      M/s. Bhattad Bros. 7.      M/s. Alusett System (India) Pvt. Ltd.

The principal question which arises for consideration is as to whether  the Authority had any jurisdiction to cancel the bid.

The Executive Committee is a statutory functionary.  The powers and  functions of the authority and the respective committees concededly are  governed by the provisions of the statute, but, then the jurisdiction of the  Executive Committee is limited.  It was confined to rejection or acceptance  of the tender.  The Authority exercises a larger power.  For the said purpose  we would assume that the Authority had no incidental or ancillary power,  but there cannot be any doubt or dispute that the Executive Committee could  not cancel the entire tender.  It could not have caused any change in the  entire scheme or policy.  It could not make alterations in the methodology of  tender.  It could not have gone into the working of the project.  It also could  not have gone into the question as to whether the project would be  financially viable if the method of calculation is changed.  

Strong reliance has been placed by Mr. Nariman on Marathwada  University v. Seshrao Balwant Rao Chavan [(1989) 3 SCC 132 : AIR  1989 SC 1582] to contend that as therein the power of the Vice Chancellor  and the Executive Council was different, the former’s power could not have  been exercised by the latter.   

We do not dispute the proposition of law laid down therein.   

We would assume that the power of the Executive Committee and the  Authority under the Act are different and the latter for all intent and purport  could not usurp the functions of the former.  But in this case, it has not been  so done.

Jurisdiction of the Authority being larger, and the power to cancel the  tender being not vested in the Executive Committee, the action on the part of  the former was neither illegal nor without jurisdiction.   This Court rejected the contention that the power of the Vice  Chancellor to regulate work also included the power to initiate disciplinary  action, stating :     

"This takes us to the second contention urged for  the appellants. The contention relates to the legal effect  of ratification done by the Executive Council in its  meeting held on December 26/27, 1985. The decision  taken by the Executive Council is in the form of a  resolution and it reads as follows : "Considering the issues, the Executive Council  resolved as follows : 1. The Executive Council at its meeting held on  22-3-1979, had by a resolution given full authority to  the Vice-Chancellor for taking further proceedings  and decision in both the cases of the defaulting  officers. 2. In exercise of above authority, the Vice- Chancellor appointed an Inquiry Officer and as  suggested by the Inquiry Officer issued show-cause

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 17  

notices, obtained replies from the officers and lastly  issued orders for terminating their services;                 *                       *                       * It was further resolved that\027 (i)     There has been no inadequacy in the  proceedings against both the officers; (ii)    The punishment ordered against both the  officers is commensurate with the defaults and  allegations proved against both the officers; and (iii)   The Executive Council, therefore, wholly,  endorses the actions taken by the then Vice-Chancellor  against both the officers." By this resolution, we are told that the Executive  Council has ratified the action taken by the Vice- Chancellor. Ratification is generally an act of principal  with regard to a contract or an act done by his agent. In  Friedman’s Law of Agency (5th edn.) Chapter 5 at p. 73,  the principle of ratification has been explained : "What the ’agent’ does on behalf of the  ’principal’ is done at a time when the relation of  principal and agent does not exist: (hence the use  in this sentence, but not in subsequent ones, of  inverted commas). The agent, in fact, has no  authority to do what he does at the time he does it.  Subsequently, however, the principal, on whose  behalf, though without whose authority, the agent  has acted, accepts the agent’s act, and adopts it,  just as if there had been a prior authorisation by the  principal to do exactly what the agent has done."

As noticed hereinbefore, we have proceeded on the basis that the  powers of the Executive Committee and the Authority are separate and  distinct and we have pointed out that the powers vested in the Executive  Committee being limited, the decision taken by the Authority cannot be said  to be illegal.

It was furthermore contended that the Executive Committee had a  special power which would prevail over general power vested in the  Authority.  In J.K. Cotton Spinning & Weaving Mills Co., Ltd. vs. The  State of Uttar Pradesh & Ors. [(1961) 3 SCR 185], this Court applied the  rule of construction that general provisions yield to special provisions, but,  the said rule has no application in the facts and circumstances of the present  case.  Executive Committee does not exercise any special power.  The  jurisdictions of both the authorities are separate and distinct.     

Dr. A.M. Singhvi, learned Senior Counsel appearing for Appellants in  the connected appeal relied upon Bhavnagar University vs. Palitana Sugar  Mill Pvt. Ltd. & Ors. [(2003) 2 SCC 111], wherein it was held :

"It is the basic principle of construction of statute  that the same should be read as a whole then chapter by  chapter, section by section and words by words.  Recourse to construction or interpretation of statute is  necessary when there is ambiguity, obscurity, or  inconsistency therein and not otherwise. An effort must  be made to give effect to all parts of statute and unless  absolutely necessary, no part thereof shall be rendered  surplusage or redundant."

We fail to understand as to how the principle laid down therein can be  said to have been violated.

Reliance has also been placed on State of Uttar Pradesh vs.  Singhara singh & Ors. [AIR 1964 SC 358 : (1964) 4 SCR 485], wherein

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 17  

this Court quoted with approval the decision in Taylor v. Taylor [([1875] 1  Ch. D. 426, 431] for the proposition that where a power is given to do a  certain thing in a certain way, the thing must be done in that way or not at all  and that other methods of performance are necessarily forbidden.  There is  again no quarrel over the aforementioned proposition of law.  Here the  Authority has not exercised any power forbidden by law.  The Authority has  also not exercised its power in the manner which is not in accordance with  law.

On merit of the matter, Mr. Nariman has pointed out, the distinction  between 2002 and 2005 tenders to show that such a policy decision as laid  down in the 2005 tender was not in pari materia with 2002 tender.  The  comparison of methodology for evaluation of bids is as under :

2005 TENDER 2002 TENDER METHODOLOGY FOR  EVALUATION OF BIDS 7.30  The bidder will have to quote  separately for the Convention &  Exhibition Centre and the  Commercial Complex.  The built-up  area (considered for FSI computa- tion) of the Convention & Exhibi-  tion Centre shall be considered as  65,000 sq.m. irrespective of the  reduction that may be possible on  finalization of detailed architectural  designs.  Similarly the floor space  considered for FSI computation for  the commercial Complex will be  50,000 sq.m.  The bidder will have  to quote a fixed rate of Rs.20,000  per sq.m. of built up area for total  built-up area 65,000 sq.m. for  Convention & Exhibition Centre.   The amount will be Rs.130 crores.   The bidder will also have to quote a  rate of premium higher than  Rs.70,000 per sq.m. of built-up area  for 50,000 sq.m. of total built-up  area for Commercial Complex.  The  premium amount will be higher than  Rs.350 crores.  The total minimum  amount of lease premium to be  quoted by the bidder will be higher  than Rs.480 crores of the total  amount of lease premium that will  be payable to MMRDA 50% will  have to be paid within one month  and the balance will have to be paid  within two months i.e. within three  months from the time the bid is  accepted.  The lease period is of 80  years as is indicated in the  MMRDA (Disposal of land)  Regulation 1977.   

METHODOLOGY FOR  EVALUATION OF BIDS 7.30   The bidder will have to quote  separately for the C&EC and the  Real Estate component.  The built- up area (considered for FSI  computation) of C&EC shall be

12

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 17  

considered as 60,500 sq.m. (Phase I  and II) irrespective of the reduction  that may be possible on finalization  of detailed architectural designs.   Similarly the floor space considered  in FSI computation for the Real  Estate component shall be 15,000  sq.m.  The bidder has the option of  bidding only for the C&EC without  the Real Estate component.  The  bidder has to quote a rate of  premium in terms of Rs. per sq.m.  of FSI and the total premium,  separately for the C&EC and the  Real Estate component subject to  the condition that the rate quoted for  the Real Estate component shall be  greater than that quoted for the  C&EC.  

The Authority is a statutory authority.  It consists of not only  politicians but also various other responsible officers.  It, while exercising its  power under the Act, must necessarily take policy decisions.  Whereas under  the 2002 tender the bidder had to quote the rate of premium in terms of  rupees per square meter of FSI and the total premium separately for C&EC  and the Real Estate component subject to the condition that the rate quoted  for the Real Estate component should be greater than that quoted for the  C&EC, upon having come to know that the value of the land would be much  more, the Authority in the 2005 tender decided that the bidders should be  required to quote a fixed rate of 20,000 per sq.m. of built-up area for total  built-up area 65,000 sq.m. for Convention & Exhibition Centre.  Economic  viability of the entire project component, taking into consideration two  different components for C&EC and the Commercial Complex, could have  been taken differently.  The premium amount was to be quoted higher than  Rs. 350 crores for the Commercial Complex.  While exercising its  jurisdiction of judicial review, the Court is required to decide the cases  before it, keeping the well known principles therefor in mind and having  regard to the fact situation obtaining therein.  No hard and fast rule can be  laid down therefor.  Recently, in Noble Resources Ltd. vs. State of Orissa  and Anr. [2006 (9) SCALE 181] this Court has noticed the power of  judicial review vis-‘-vis contractual disputes, opining : "Although terms of the invitation to tender may  not be open to judicial scrutiny, but the courts can  scrutinize the award of contract by the Government or its  agencies in exercise of their power of judicial review to  prevent arbitrariness or favouritism. [See Directorate of  Education and Ors. v. Educomp Datamatics Ltd. and Ors.  2004 (4) SCC 19]. However, the court may refuse to  exercise its jurisdiction, if it does not involve any public  interest. Although the scope of judicial review or the  development of law in this field has been noticed  hereinbefore particularly in the light of the decision of  this Court in ABL International Ltd. (supra), each case,  however, must be decided on its own facts. Public  interest as noticed hereinbefore, may be one of the  factors to exercise power of judicial review. In a case  where a public law element is involved, judicial review  may be permissible."   Noticing some of the areas where judicial review would be  permissible, this Court opined that ordinarily, this Court would not enforce  specific performance of contract where damages would be adequate remedy.   It was also held that conduct of the parties would also play an important role.   The expansive role of Courts in exercising its power of judicial review

13

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 17  

is not in dispute.  But as indicated hereinbefore, each case must be decided  on its own facts.   

Dr. Singhvi placed reliance upon Star Enterprises & Ors. vs. City  and Industrial Development Corporation of Maharashtra & Ors.  [(1990) 3 SCC 280], wherein Ranganath Misra, J., as His Lordship then was,  opined :

"In recent times, judicial review of administrative  action has become expansive and is becoming wider day  by day. The traditional limitations have been vanishing  and the sphere of judicial scrutiny is being expanded.  State activity too is becoming fast pervasive. As the State  has descended into the commercial field and giant public  sector undertakings have grown up, the stake of the  public exchequer is also large justifying larger social  audit, judicial control and review by opening of the  public gaze; these necessitate recording of reasons for  executive actions including cases of rejection of highest  offers. That very often involves long stakes and  availability of reasons for action on the record assures  credibility to the action; disciplines public conduct and  improves the culture of accountability. Looking for  reasons in support of such action provides an opportunity  for an objective review in appropriate cases both by the  administrative superior and by the judicial process. The  submission of Mr. Dwivedi, therefore, commends itself  to our acceptance, namely, that when highest offers of the  type in question are rejected reasons sufficient to indicate  the stand of the appropriate authority should be made  available and ordinarily the same should be  communicated to the concerned parties unless there be  any specific justification not to do so."  

In this case, highest offer has not been rejected.  A new policy  decision has been taken.  Question as noticed herein is not as to whether the  offer of the Appellants should have been rejected but is as to whether the  Authority in law could have altered its policy in regard to disposal of its  properties.  ’Public Trust Doctrine’ was also sought to be invoked by Mr.  Nariman against the Authority and in this behalf reliance has been placed on  Bangalore Medical Trust Vs. B.S. Muddappa & Ors. [(1991) 4 SCC 54].   This Court therein was dealing with a master plan in the light of justifiability  of exercise of discretionary jurisdiction under the Town Planning Act.   Having regard to the provisions contained in Sub-Section (4) of Section 19  of the Bangalore Development Authority Act, 1976 as also the fact that the  discretionary jurisdiction had been arbitrarily exercised, this Court invoked  the ’public trust doctrine’ saying that although the State is required to keep a  vigil on the local body, but, thereby the power thereunder cannot be  stretched so as to entitle the Government to alter any scheme and convert  any site or power specifically reserved in the statute in the Authority.   By floating a tender in furtherance of a public project, the Authority  was not truly concerned with the enforcement of its master plan.  No such  argument was advanced before the High Court.  Such an argument has been  advanced for the first time before us.  We would consider the efficacy of  said contention a little later.

 The next question which arises for consideration is as to whether any  reason was required to be assigned.  A power to deal with a contractual  matter and a power of a statutory authority to exercise its statutory power in  determining the rights and liabilities of the parties are distinct and different.   Whereas reasons are required to be assigned in a case where civil or evil  consequences may ensue, the same may not be necessary where it is  contractual in nature, save and except in some cases, e.g., Star Enterprises  (supra).

14

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 17  

Whether assignment of reasons forms third pillar of principle of  natural justice, is not free from doubt.  There is a diversity of opinion as has  been noticed by this Court in Rajesh Kumar & Ors. vs. D.C.I.T. & Ors.  [2006 (11) SCALE 409].

Reliance has also been placed by Mr. Nariman on Commissioner of  Police, Bombay vs. Gordhardas Bhanji [1952 (1) SCR 135] and Union of  India & Ors. vs. Dinesh Enginering Corporation & Anr. etc. [(2001) 8  SCC 491].  In Commissioner of Police (supra) the Court was concerned  with a situation where a statutory authority had acted on dictation of an  Appellate Authority, which was found to be illegal.  In Dinesh Enginering  (supra), this Court opined that the Railways have no arbitrary power to reject  the bid offered by a party merely because it has that power, particularly,  when the same can be exercised only on the existence of certain conditions  which in the opinion of the Railways are not in the interest of the Railways  to accept the offer.   

We have noticed hereinbefore that power has not been exercised by  the Executive Committee in rejecting the tender.  The power has been  exercised by the Authority in canceling the tenders so as to enable it to have  a re-look of the entire project.  

Some reasons may be required to be assigned for rejecting the bid, but  in the instant case, in our opinion, no reason was required to be assigned as  there has been a change in the policy decision.   The news item appearing in the Economic Times is not of much  significance.  No affidavit has been affirmed as regards the correctness or  otherwise of the said news item.   

It may be true that the Authorities at one point of time, as was  disclosed in the Counter Affidavit, had thought of setting up a Convention  Centre of their own and without any private participation, but only because  there has been a deviation from the said stand would not, in our considered  opinion, render the entire policy decision vitiated in law.   

It had set up its Evaluation Committee.  The decision presumably has  been reached by experts.   

The reasons as regards purported unsatisfactory performance of  Appellants, take a back seat once having a re-look to the entire situation was  thought of.   

It is not a case where the Court is called upon to exercise its equity  jurisdiction.  It is also not a case where ex facie the policy decision can be  held to be contrary to any statute or against a public policy.  A policy  decision may be subjected to change from time to time.  Only because a  change is effected, the same by itself does not render a policy decision to be  illegal or otherwise vitiated in law.   

       In Harminder Singh Arora vs. Union of India & Ors. [(1986) 3  SCC 247], whereupon Dr. Singhvi relied upon, the tender was arbitrarily  rejected.  Therein the writ petition was dismissed in limine only on the  premise that the question involved therein related to contractual obligations  and the policy decision could not be termed as unfair or arbitrary.  It was  opined that therein no question of policy decision arose and as such contract  was to be given to the lowest bidder in terms of the tender notice and the  contract should have been awarded to the appellant therein, especially when  he had been doing the job for many years.   As to how the said decision is  applicable to the facts of the present case, we fail to understand.  For the  self-same reasons we are unable to appreciate the contention that only  because a change has been effected in computation of total price under the  new tender, the same was invalid in law.

       In New Horizons Ltd. & Anr. vs. Union of India & Ors. [(1995) 1  SCC 478], this Court opined that in the matter of grant of tender the State

15

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 17  

cannot act as a private person having regard to Article 14 of the Constitution  of India.  It was categorically opined that departing from the narrow  legalistic view the Courts have taken note of the realities of the situation  which, by no stretch of imagination, would mean that the Court would  substitute itself in the place of a statutory authority.  The Court in a case of  this nature must exercise judicial restraint.  It may be one thing to say that  having regard to the public interest, the Court may itself invite bids so as to  verify the justification of accepting a palpably lower bid as was done in  Ram and Shyam Company vs. State of Haryana and Ors. [(1985) 3 SCC  267], but it is another thing to say the Court would under all circumstances  not allow a play in joint in favour of the employer.     

However, if the Court in a given situation is not in a position to allow  a bid to take place before, it may not still venture to strike down an Act in  the name of public interest, although, no such public interest exists.   

Appellant stated before us that he is ready and willing to take a part of  the contract, viz., construction of the C&EC and pay the same amount as has  been done by Reliance Industries Ltd. and in addition it would pay 2.5% of  its annual turnover from the Convention Centre from the 21st year, as was  initially offered.

Appellant did not participate in the second bid.  The tender process is  complete.  Before us only a higher bid has been given.  We do not intend to  enter into the intricacies of the question.  Appellants could have submitted  its bids pursuant to the new tender and new conditions, even without  prejudice to its rights and contentions in this appeal.  The stipulations made  in 2002 tender could have been repeated by it so as to demonstrate before  the experts comprising members of the Executive Committee that its bid was  the highest.  If, in view of the change in the policy decision, the Authority  does not intend to become a partner in the profit making and opt for having  the entire bid amount at one go instead of waiting for 20 years, we do not  find any fault therewith.   Before us comparative bids of the bidders have been placed on the  second tender, which are as follows :

SR.No. Name of the Bidder Bid Amount  Rs. Rate per sq.  m.  (approx.)  Rs. 1. Reliance Industries Ltd. 11,04,00,00,111 96000 2. DLF 1050 crores 91304 3. Reliance Communications &  Infrastructure Ltd. 1011.12 crores 87913 4. Gammon India 1011 crores 87913 5. EMAR 911.07 crores

16

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 17  

79217

The comparative statistics reads as under  :

1. Rate offered by the Petitioners Rs.          91.514 crores (divided by) 75,500 sq.mtrs.

Rs.12,121 per sq.  mtrs. 2. Rate expected by MMRDA Rs. 25,000 per  sq.mtrs. 3. Amount for 75,500 sq. mtrs @ Rs.25,000/-  per sq.mtrs. (This should have been the  minimum bid in 2003)

Rs.188.75 crores 4. Amount for 1,15,000 sq.mtrs @ Rs.25,000/-  per sq.mtrs. (This would have been the  reserve price at old rate in 2005) Rs.287.50 crores 5. Reserve Bid of MMRDA in 2005  (Minimum price revised as below)

Rs.480 crores 6. Rate per sq. mtrs in the Reserve bid  Rs.480 crores (divided by) 1,15,000 sq.mtrs.

Rs.41,739/- per sq.  mtrs. 7. Bid by Reliance Industries Ltd. Rs.1104,00,00,111/- 8. Rate per sq.mtrs of RIL Bid  Rs.11,04,00,00,111/- (divided by)      1,15,000 sq. mtrs.

Rs.96,000/- per sq.  mtrs.

Appellant complains that whereas the bid of Sister concern of  Reliance Industries Ltd. was very low, now it has offered a bid of  Rs.1104,00,00,111/-.  From the chart placed before us it would appear that  there had been a stiff computation.  The Reliance Industries Ltd. has become  the highest bidder.  Its competitors had taken part in the earlier contracts.   No mala fide in accepting the tender has been alleged nor do we find any.   

We, therefore, in the facts and circumstances of this case and having  regard to the subsequent events, are of the opinion that it is not a case where  we should interfere with the judgment of the High Court.   

It, however, would not mean that the Authority or the Executive  Committee would not be entitled to take note of the offer of Appellant.  It  may do so.  It would not further mean that if the terms of new tender are  violative of the provisions of the master plan, the same would not be suitably  dealt with.  We merely place on record that we have not gone into the said

17

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 17  

questions, although raised before us by the learned counsel for the appellant,  simply on the ground that no such plea had been taken before the High  Court.  In the absence of any plea that the policy decision adopted by the  Authority would be violative of the provisions of the Act or any master plan,  the same cannot be entertained.  The question, however, is left open.  For the reasons aforementioned, there is no merit in these appeals,  which are accordingly dismissed.  There shall, however, be no order as to  costs.