P.K. SINGH Vs M/S. S.N. KANUNGO .
Case number: C.A. No.-006551-006551 / 2002
Diary number: 63228 / 2002
Advocates: FOX MANDAL & CO. Vs
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6551 OF 2002
P.K. Singh … Appellant
Versus
M/s. S.N. Kanungo and others …Respondents
O R D E R
The instant appeal is directed against the judgment
dated April 9, 2001 rendered by the High Court at
Calcutta in Contempt Application No. 010 of 2001 by
which the appellant is held guilty of contempt of court
and is directed to pay the cost of the application to the
respondent which is assessed at 200 GMS.
2. From the record of the case it is evident that a
contract was entered into between the respondent-
contractor and the Andaman and Nicobar
Administration through Union of India for execution
of the work of extension of runway by 1542 meters
(5000 ft.) at Port Blair Airport on 29.12.1995.
During the course of the execution of the said
contract, dispute arose between the parties
regarding payments of bills. The dispute was
referred to sole arbitration of Mr. O.P. Goel. The
arbitrator made his Award on March 22, 1999 and
directed the Andaman and Nicobar Administration
to pay to the respondent a sum of Rs.2,81,83,305/-
(Rupees two crores eighty one lacs, eighty three
thousand, three hundred and five only) with 12%
interest per annum from the date of withholding of
the amount of Rs.41,42,000/- (Rupees forty one
lacs forty two thousand only) till the date of
payment.
3. Feeling aggrieved, the Union of India, through the
Executive Engineer, Andaman and Nicobar Public
2
Works Department, filed an application under
Section 34 of the Arbitration and Conciliation Act,
1996 on 17th June, 1999 for setting aside the
Award. By judgment dated 29.9.2000 the learned
District Judge, Andaman and Nicobar Island, Port
Blair, dismissed the application with cost of
Rs.500/-. Thereupon, Union of India, through the
Executive Engineer, preferred an appeal, i.e., FAT
No. 4220 of 2001, before the High Court at
Calcutta. The Division Bench of the High Court
dismissed the appeal by judgment dated 26.2.2001.
However, the High Court clarified that the claim No.
4 of the Award dated 22.3.1999 would stand
modified and the respondent-contractor would be
entitled to interest @ 12% per annum from the date
of reference of the dispute to arbitration till the date
of payment of the said amount.
4. Thereafter, the appellant, who is Executive
Engineer, Construction Division II, APWD, South
3
Andaman, addressed a letter to the Superintending
Engineer, Construction Circle No. 1, Andaman
Public Works Department, on 5.3.2001 giving
details of the financial implication of the Award
dated 22.3.1999. The appellant received a letter
dated March 30, 2001 from the Executive Engineer
(PLG), CE’s Office, APWD, Port Blair stating that the
principal component of the Award might be released
to the agency, i.e., the respondent herein,
immediately. The appellant thereupon wrote a letter
dated 30.3.2001 to the Chief Engineer, APWD
requesting that the acceptance of the Award should
be communicated with details regarding
amount/principal component to be paid. It was
also mentioned in the said letter that for delay, if
any, in payment of the amount, he would not be
responsible. The appellant thereafter addressed
another letter on the same day to the respondent
requesting it to intimate its acceptance of the Award
amount to Rs.2,81,83,305/- in full and final
4
settlement of its claim. The respondent thereupon
replied by a letter dated 30.3.2001 to the appellant
that it was not willing to accept the amount stated
in the aforesaid letter. The appellant, therefore,
wrote another letter on 30.3.2001 to the respondent
informing that the principal component of the
Award of Rs.2,81,83,305/- would be released on the
same day and requested the respondent to reconcile
with the appellant for mutual understanding about
payment of interest. The respondent wrote a letter
to the appellant on March 31, 2001 mentioning that
it was willing to accept the principal amount of the
Award “at present” but the remaining amount of the
interest etc. should be released within a fortnight.
Thereupon, the appellant addressed a letter dated
2.4.2001 to the Chief Engineer, APWD, Port Blair,
forwarding a copy of the letter received by him from
the respondent and pointed out that the respondent
was unwilling to accept the amount of the Award
without interest. The appellant addressed another
5
letter dated 2.4.2001 to the Chief Engineer
informing him about the changed stand of the
respondent regarding its willingness to accept the
principal component of the Award and requested
him to communicate the decision regarding
payment of interest without further delay.
5. The respondent filed Contempt Application No. 010
of 2001 in the month of April, 2001 under Section
14 of the Contempt of Courts Act, 1971 complaining
about willful and deliberate violation of the
judgment and decree dated February 26, 2001
passed in First Appeal T. No. 4220 of 2001. The
High Court issued notice to the respondent. On
notice being served, the appellant filed a reply
denying that there was willful and deliberate breach
of the decree passed by the court. By impugned
judgment the Division Bench of the High Court at
Calcutta, Circuit Bench at Port Blair, found the
respondent guilty of contempt of court and while
6
accepting the unconditional apology of the
appellant, imposed cost of Rs.200 GSM upon him to
be paid within a week. This judgment has given rise
to the instant appeal.
6. This Court has heard the learned counsel for the
appellant and considered the documents forming
part of the instant appeal.
7. From the facts mentioned above, it is evident that,
after Award of the arbitrator was confirmed by
Division Bench of the Calcutta High Court, the
appellant had made an attempt to adjust the decree
in terms of Order XXI Rule 2 of Code of Civil
Procedure by requesting the respondent to accept
the principal amount and waive the interest
awarded thereon. The contents of the two letters
written by the appellant to the respondent do not
show that any attempt was made by the appellant
to sit in appeal over the judgment of the High Court.
7
Those two letters do not indicate that the appellant
had criticized the High Court for awarding interest
in favour of the respondent. The record would
indicate that within the framework of law, the
appellant had made an attempt to persuade the
respondent to forego claim relating to interest.
Order XXI Rule 2 of Code of Civil Procedure relates
to the payment of amount to a decree holder out of
court and inter alia provides that when any wrong
payment under a decree of any other kind is paid
out of court to the decree holder, the decree holder
has to certify payment made as required by the said
Rule. An agreement, which extinguishes the decree
as such in whole or in part and results in the
satisfaction of the decree in respect of the particular
relief or reliefs granted by the decree, is an
‘adjustment’ within the meaning of this Rule. It is
open to the parties to enter into a contract or
compromise with reference to their rights under the
decree. If the contract or the compromise amounts
8
to an ‘adjustment’ of the decree, it must be recorded
under this Rule and unless so recorded cannot be
recognized by the executing court. Adjustment is
not the same as satisfaction of the decree but is
some method of settling decree which is not
provided for in the decree itself. The right of the
judgment debtor to make an attempt to adjust the
decree is independent and cannot be treated as
contempt of court. Having regard to the interest of
the department concerned, the appellant had
addressed letters to the respondent to adjust the
Award. The letters for adjustment of Award could
not have been treated as contempt of court within
the meaning of the provisions of the Contempt of
Courts Act, 1971. The tenor of letters do not
indicate that there was any willful disobedience on
the part of the appellant in not complying with the
judgment of the High Court.
9
8. Even if it is assumed for the sake of argument that
writing of the letter dated 30.3.2001 amounts to
contempt, this Court finds that the two letters dated
30.3.2001 and 2.4.2001 addressed by the appellant
to the Chief Engineer, APWD, Port Blair, indicate
that the appellant had taken all possible steps to
comply with the Award confirmed by the High
Court. According to the High Court, asking the
respondent to accept only the principal amount vide
letter dated 30.3.2001 amounts to violation of the
judgment of the High Court. Having held so, the
High Court proceeded to examine the question
whether the violation of judgment of the High Court
would amount to the contempt of court. The High
Court also considered the question whether
violation of judgment by the appellant was willful
and deliberate. The High Court noticed that after
addressing letter dated 30.3.2001, another letter on
the same day was addressed by the appellant
inviting the respondent for negotiation with
10
reference to the rate of interest payable to the
respondent and concluded that even if previous
letter amounted to violation of the judgment of the
court, the appellant did not do so willfully and
deliberately. Though the High Court ostensibly
proceeded to examine the question whether
violation of the judgment of the High Court would
amount to contempt of court, the said question is
neither determined nor answered one way or the
other. The error of law committed by the High
Court is that without answering the question
whether the violation of the judgment amounts to
the contempt of court, the High Court presumed
that the violation of the judgment amounts to
contempt of court and proceeded to examine the
question whether the violation of judgment was
willful or deliberate. After reaching the conclusion
that the violation is neither willful nor deliberate,
the High Court should have at once dropped the
contempt proceedings and could not have accepted
11
the unconditional apology tendered by the appellant
nor could have imposed cost on the appellant. In
any view of the matter, the High Court, after
accepting the unconditional apology tendered by the
appellant, should not have imposed cost on the
appellant for negligence and reckless manner in
which it had allegedly acted in the instant case.
9. Further, the High Court itself came to the
conclusion that a letter being written by the
Executive Engineer would not amount to willful and
deliberate disobedience of the decree of the court.
10. On the facts and in the circumstances of the case,
this Court is of the opinion that the judgment
impugned cannot be sustained and is liable to be
set aside.
11. For the foregoing reasons, the appeal succeeds. The
impugned judgment is set aside. The cost, if any,
recovered from the appellant be refunded to him.
The appeal stands, accordingly, disposed of.
12
12. There shall be no order as to costs.
………………………………J. [J.M. Panchal]
………………………………J. [Dr. B.S. Chauhan]
New Delhi; February 18, 2010.
13