NATIONAL ALUMINIUM CO. LTD. Vs G.C. KANUNGO
Case number: C.A. No.-000062-000062 / 2003
Diary number: 21139 / 2002
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No. 62 OF 2003
NATIONAL ALUMINIUM CO. LTD. & ANR. ... Appellant(s) Versus G.C.KANUNGO ... Respondent(s)
J U D G M E N T
Dr.ARIJIT PASAYAT,
Heard.
Challenge in this appeal is to the order of a learned Single Judge of the
Orissa High Court dismissing the miscellaneous appeal filed by the present
appellant. In the miscellaneous appeal which was filed under Section 39 of
Arbitration Act, 1940 (in short the 'Act') challenge was to the order passed by
learned Civil Judge, Senior Division, Angul making the award rule of the Court.
The primary stand before the High Court was that the claim made by the
respondent-contractor was barred in terms of Section 137 of the Limitation Act,
1963, (in short 'Limitation Act') The High Court did not accept the stand of the
appellant.
In the present appeal, Mr. A.Sharan, learned ASG appearing for the
appellant submitted that the claim was
-2-
barred and for substantiating this stand reference was made to certain dates which
are almost undisputed. The work order in this case was issued on 18.12.1985 and the
work was completed on 15.6.1987. On 20.05.1995, the respondent made a request for
appointment of an Arbitrator and on 29.6.1995 an Arbitrator was appointed. It is
the case of the appellant that sometime in 1989, final bill was paid and there was
nothing remaining to be paid and therefore the further correspondence, if any, are of
no consequence. In any event, the office notings on which reliance has been placed
by the Arbitrator as well as the courts below did not confer any legal right on the
respondent. It was also submitted that the award for the additional work done was
against the terms of the contract. It was, however, fairly accepted that the later
point was never argued before the High Court. It was also submitted that the rate at
which interest has been awarded is high.
In response, Mr. R.K.Rath, learned senior counsel appearing for the
respondent submitted that there are several documents on which the courts below
have placed reliance. This unmistakably show that the matter was alive and more
particularly the letter of the appellant dated 26.8.1992 to the respondent puts the
controversy beyond doubt.
-3-
“Dear Sir,
The case file for consideration of your different claims for the
above said work is processed.
The decision is awaited.
After the decision is known, the same shall be communicated to
you.
In other words, there was no finality in the matter and the matter was
alive for consideration. If this date i.e. 26.5.1992 is taken into account, the claim
made was within the period of three years. That being so, the claim as made was
within the period of limitation and the stand of the appellant that the claim was
barred by limitation is not tenable.
Another point which has been urged with some vehemence is that the rate
at which interest has been granted is 15%. It is stated that rate is quite high. In
response, learned counsel for the respondent stated that presently the applicable rate
is 18% and there is nothing infirm in the award of interest @ 15%.
Considering the peculiar facts of the case we direct that the interest
payable will be 12% p.a. in place of 15% as awarded. The appeal is allowed to the
aforesaid extent.
-4-
The documents submitted by way of furnishing security as filed in this
court shall be handed over to learned counsel for the respondent.
...................J. (Dr. ARIJIT PASAYAT)
....................J. ((ASOK KUMAR GANGULY)
New Delhi, April 29, 2009.