N.B.C.C.LTD. Vs J.G.ENGINEERING PVT.LTD.
Case number: C.A. No.-000008-000008 / 2010
Diary number: 26455 / 2007
Advocates: Vs
PRANAB KUMAR MULLICK
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO .8 OF 2010 (Arising Out of SLP© No. 19471 of 2007)
N.B.C.C. Ltd. …. Appellant
Versus
J.G. Engineering Pvt. Ltd. …. Respondent
WITH
CIVIL APPEAL NO.9 OF 2010 (Arising out of SLP©No.22243 of 2008)
J U D G M E N T
TARUN CHATTERJEE, J.
1. Leave granted.
2. These appeals are directed against the final Judgments and
orders dated 23rd of March, 2006, and 21st of September,
2007 passed by the High Court at Calcutta in G.A. No.235 of
2006 arising out of A.P. No. 361 of 2005, whereby the High
Court had allowed the petition of the respondent and thereby
terminated the mandate of the arbitrator and thus appointed a
new Arbitrator for deciding the dispute between the parties.
1
3. In order to appreciate the controversy existing between the
parties, it may be important to narrate the facts as emerging
from the case made by the appellant, which are as follows :-
In the month of December 1992, the appellant had issued
notice inviting tender for construction of terminal buildings and
various ancillary jobs at the Bhubaneshwar Airport at Bhubaneshwar,
Orissa. The respondent submitted its offer, which was accepted by
the appellant.
On 30th of March, 1993, the appellant entered into a contract
with the respondent for construction of the aforesaid work at the
Bhubaneshwar Airport for a total consideration of Rs.
5,71,13,541.33/-. The date of commencement of the work was fixed
on 1st of March, 1993 and the stipulated date of completion was 31st
of October, 1994. However, on 20th of March, 1996, the appellant
terminated the contract of the respondent alleging that the
respondent had failed to fulfill its part of the obligations required
under the contract. On 20th of May, 1996, the respondent invoked the
arbitration clause and sought for an appointment of an arbitrator for
adjudication of the disputes between the parties. On 9th of August,
1996, the Chairman-cum-Managing Director of the appellant
2
appointed a sole arbitrator to adjudicate upon the claims and counter
claims of the parties. The appellant filed its counter claim on 30th of
April, 1997 before the sole arbitrator. The respondent submitted its
rejoinder and objections to the counter claims on 12th of May, 2001,
after about 4 years from the date of reply by the appellant. During this
period, the appellant had virtually closed its regional office in Calcutta
as most of the work done in its office was completed. This, according
to the appellant, caused in several transfers of the arbitrators
appointed by the appointing authority. Meanwhile, the appointing
authority had appointed three arbitrators due to the above-mentioned
reason and the arbitration process had come to a stand still due to
the inaction of the respondent and its failure to participate.
Thereafter, on 20th of May, 2004, the respondent filed an
application before the Calcutta High Court seeking removal of the
then incumbent arbitrator and the arbitral proceedings were stayed by
the Court. On 20th of September, 2004, the High Court directed the
Chairman-cum-Managing Director of the appellant company to
appoint a new arbitrator in terms of the arbitration clause within a
period of four weeks from the date of communication of its order. The
High Court further directed the arbitrator so appointed to conclude the
3
arbitration proceedings within a period of six months from the date of
his appointment. Pursuant to the order of the High Court, the
Chairman-cum-Managing Director of the appellant company
appointed Shri A.K. Gupta, Deputy General Manager of the appellant
as the sole arbitrator. The said arbitrator finally concluded the
proceedings after hearing on 18th of June, 2005. It is an admitted
position that the time to conclude the arbitration proceeding in terms
of the order of the High Court before Shri A. K. Gupta, who was
appointed as the sole arbitrator by the Chairman-cum-Managing
Director of the company had by then already expired.
However, both the parties extended the time to conclude the
arbitration proceeding and to pass an award accordingly, the time
was enlarged for conclusion of the arbitration to 30 th of September,
2005.
It is also an admitted position that the time limit so fixed i.e.
arbitration must be concluded and award must be passed within 30th
of September, 2005, could not be adhered to by the arbitrator and he
failed to publish the award within this period. About three months
after the expiry of the period of concluding the proceeding and
passing of the award, it was the respondent who moved an
4
application before the High Court for a declaration that the mandate
of the arbitrator had already stood terminated. We may keep it on
record that the appellant had not filed any application for enlargement
of time for the conclusion of the arbitration proceeding or to pass the
award after the expiry of the period.
On 22nd of December, 2005, the High Court, vide an interim
order, restrained the arbitrator from making an award and at the
same time, had refused to accept the award produced by the
arbitrator before it which were well beyond the period fixed by the
High Court. On 23rd of March, 2006, the High Court, by its impugned
order, terminated the mandate of the arbitrator on the ground of delay
in making the award. The appellant then challenged the above
mentioned order of the Calcutta High Court before this Court vide
SLP No.19471 of 2007 on 12th of September, 2007. At the same
time, the High Court by the impugned order dated 21st of September,
2007 passed in AP No. 361/2005 appointed Mr. Justice Chittatosh
Mookherji (As His Lordship then was) as the sole arbitrator to
adjudicate the disputes between the parties. The appellant, feeling
aggrieved by this order as well has filed a special leave petition which
came to be registered as SLP No. 22243 of 2008, which after hearing
5
the learned counsel for the parties and on grant of leave, was heard
in presence of the learned counsel for the parties.
4. We have heard the learned counsel appearing on behalf of
the parties and examined the impugned orders of the High
Court and also other materials on record in depth and in
detail. As noted herein earlier, the respondent had made an
application before the Calcutta High Court under Section 14
of the Arbitration and Conciliation Act, 1996 (in short the
“Act”) for a declaration that the mandate of the arbitrator Shri
A.K. Gupta had already stood terminated. As had already
been mentioned above, the appointing authority had
appointed three arbitrators prior to the appointment of Shri
Gupta who were all unable to conduct the arbitral
proceedings for some reason or the other. It may be kept on
record that the respondent filed an application before the
High Court for a declaration that the appointment of the
arbitrator namely, Shri Amitava Basu, who was appointed as
the sole arbitrator prior to the appointment of Shri A. K. Gupta
had stood terminated by an order dated 20th of September,
2004, by which the High Court had terminated the
6
appointment and ordered the appointing authority of the
appellant to appoint a new arbitrator who will conclude the
proceeding and pass an award within six months from the
date of his appointment. Subsequent to this order of the High
Court, the appellant appointed Mr. AK Gupta as the new
arbitrator who was to complete his proceedings by 27th of
March, 2005 i.e. six months from the date of his appointment.
It is pertinent to mention that the appellant did not file any
appeal against the above-mentioned order of the High Court.
Therefore, it may be taken that the appellant had accepted
the aforesaid order of the High Court and thereby accepted
its decision to fix the time of the arbitration proceedings to be
mandatorily concluded within six months from the date of
appointment of the arbitrator. The order, thus having
assumed finality, a time limit was imposed for the conclusion
of the arbitration proceedings. Thus, the appellant is
estopped from raising any objection against the imposition of
the time limit as had been done by the Court in this respect.
From the records before us, we have noticed that inspite of
conducting a number of proceedings, the arbitrator was
7
unable to conclude the proceedings within the time fixed by
the High Court. The arbitration clause in the contract enables
the arbitrator to extend the time for making and publishing the
award by mutual consent of the parties. From a perusal of
the documents before us, we notice that the parties mutually
agreed to extend the time till 31st August, 2005 for making
and publishing the award, which were further extended by the
parties till 30th of September, 2005 on account of the
arbitrator having failed to conclude the proceedings within the
previous date fixed by the parties. But the arbitrator having
failed to do so by 30th of September, 2005, the respondent
moved the High Court to terminate the mandate of the
arbitrator as he had failed to conclude the proceedings within
the time limit fixed by the parties. The High Court accordingly
terminated the mandate of the arbitrator on account of his
failure to publish the award within the time fixed by the
parties. We are of the opinion that the High Court was
perfectly justified in doing so on an application filed by the
respondent before it. Quite interestingly, it has come to our
notice that the arbitrator in question had appeared before the
8
High Court and submitted that the award was ready but the
same could not be published on account of the interim order
passed by the same restraining him from publishing it. There
was, however, no order of the Court restraining the arbitrator
from publishing the award till almost three months after the
expiry of the time fixed by the mutual consent of the parties to
make and publish the award prior to the interim order passed
by the High Court.
5. A perusal of the arbitration agreement quite clearly reveals
that the arbitrator has the power to enlarge the time to make
and publish the award by mutual consent of the parties.
Therefore, it is obvious that the arbitrator has no power to
further extend the time beyond that which is fixed without the
consent of both the parties to the dispute. It is an admitted
position that the respondent did not give any consent for
extension of time of the arbitrator. Thus given the situation,
the arbitrator had no power to further enlarge the time to
make and publish the award and therefore his mandate had
automatically terminated after the expiry of the time fixed by
the parties to conclude the proceedings. The learned counsel
9
contended that the arbitration proceedings involved questions
of highly technical and complex issues which would require
sufficient amount of time to be decided in a just and proper
way. However the records clearly illustrate that even after a
passage of over nine years, the matter which was to be
decided between the parties by way of arbitration, could not
be resolved and the process lingered on. Arbitration is an
efficacious and alternative way of dispute resolution between
the parties. There is no denying the fact that the method of
arbitration has evolved over the period of time to help the
parties to speedily resolve their disputes through this process
and in fact the Act recognizes this aspect and has elaborate
provisions to cater to the needs of speedy disposal of
disputes. The present case illustrates that inspite of adopting
this efficacious way of resolving the disputes between the
parties through the arbitration process, there was no outcome
and the arbitration process had lingered on for a considerable
length of time which defeats the notion of the whole process
of resolving the disputes through arbitration. The contention
of the appellant therefore cannot be justified that since the
10
dispute was highly technical in nature, it had to be dealt with
elaborately by the arbitrator and thus, he was justified in
being late. The High Court had thus correctly fixed the time
for the arbitration to be concluded within a period of six
months from the appointment of the fourth arbitrator Shri A.K.
Gupta considering the time that had been spent for the
arbitration process prior to Mr. Gupta’s appointment. That
apart, even assuming that the arbitration process involved
highly technical and complex issues, which was time
consuming, even then, it was open for the arbitrator or for the
parties to approach the Court for extension of time to
conclude the arbitration proceeding which was not done by
either by the arbitrator or by any of the parties. As had been
correctly noted by the High Court in its impugned judgment,
there was no cogent reason for the delay in making and
publishing the award by the arbitrator. He already had the
relevant materials at his disposal and could base his findings
on the observations made by the three arbitrators who were
appointed prior to him. The Arbitrator was bound to make
and publish his award, within the time mutually agreed to by
11
the parties, unless the parties consented to further
enlargement of time. Therefore, the condition precedent for
enlargement of time would depend only on the consent of the
parties, that is to say, that if the parties agree for enlargement
of time. If consent is not given by the parties, then the
authority of the arbitrator would automatically cease to exist
after the expiry of the time limit fixed. In the present case, the
arbitrator had failed to publish the award within the time limit
fixed by the parties, and hence, the High Court was justified
in terminating the mandate of the arbitrator. We therefore do
not find any fault with the impugned order of the High Court in
this regard. From a perusal of the records, we can see that
the respondent had filed an application to terminate the
mandate of the arbitrator before the High Court almost after
three months from the date of expiry of the time to publish the
award although the appellant did not choose to file any
application for enlargement of time for conclusion of the
arbitration proceeding. It is obvious that the respondent
could not have possibly known about the outcome of the
award. Even after the expiry of the time as mentioned above,
12
the arbitrator did not make any effort to publish the award nor
was anything conveyed on behalf of the appellant to the
respondent for extending the time of the arbitrator to publish
his award. It was a clear lapse on the part of both the
arbitrators and the appellant who was well aware that the
mandate of the arbitrator had already expired and it could
only be extended by a mutual consent of the parties
according to the arbitration agreement.
It has been correctly observed by the High Court that the arbitrator
had become functus officio in the absence of extension of time
beyond 30th of September, 2005 to make and publish the award. After
the said date, the arbitrator had no authority to continue with the
arbitration proceedings. The learned counsel appearing on behalf of
the appellant argued that in the absence of any statutory period
prescribed under the Act for rendering an award, the direction of the
Court to conclude the arbitration proceedings within the time
prescribed by it, would not make an award passed beyond the time
so prescribed, null and void. He further argued that the High Court
was wrong in not extending the time fixed by it in the order dated 20th
of September, 2004, for early conclusion of the arbitration
13
proceedings and terminating the mandate of the arbitrator when
neither the Act nor the arbitration agreement prescribed any time for
making and publishing the award.
6. The learned counsel appearing on behalf of the appellant had
drawn our attention to a decision of this Court in Jatinder Nath Vs.
M/s Chopra Land Developers Pvt. Ltd. & Anr. [AIR 2007 SC 1401]
to satisfy us that the award which was passed after four months of
entering upon reference does not ipso facto become nonest and the
Court has power to extend time and give life to the vitiated award. So
far as this decision is concerned, we may keep it on record that this
decision was rendered under the Arbitration Act of 1940 and not
under the present act with which we are only concerned. In view of
our reasonings given hereinafter and in view of the facts involved in
this case, we do not find any ground to rely on this decision of this
Court for the purpose of this case. The other decision cited by the
learned counsel for the appellant is the decision reported in General
Manager, Department of Telecommunications,
Thiruvananthapuram Vs. Jacob S/o Kochuvarkey Kalliath (Dead)
by LRs. And Others [2003 (9) SCC 662]. The learned counsel
14
particularly relied on para 8 of the said decision. We have carefully
gone through para 8 of the decision relied on by the learned counsel
for the appellants. We may not forget that we are concerned in this
case with the Arbitration and Conciliation Act, 1996 and not under the
Land Acquisition Act, 1894. Without going into the details of this
decision, we may simply say that this decision cannot have any
manner of application and the principles laid down to the facts and
circumstances of the present case. The last decision, which was
cited by the learned counsel for the appellant is the decision reported
in National Aluminum Co. Ltd. Vs. Pressteel & Fabrications (P)
Ltd. and Another [2004 (1) SCC 540]. In our view, this decision also
is of no help to the appellant. The principles laid down in the said
decision cannot have any application in the present case although the
decision rendered in this case is the decision under the Arbitration
and Conciliation Act, 1996.
7. Taking into consideration the arguments of the appellant, it is
necessary to mention here that the Court does not have any power to
extend the time under the Act unlike Section 28 of the 1940 Act which
had such a provision. The Court has therefore been denuded of the
power to enlarge time for making and publishing an award. It is true
15
that apparently there is no provision under the Act for the Court to fix
a time limit for the conclusion of an arbitration proceeding, but the
Court can opt to do so in the exercise of its inherent power on the
application of either party. Where however the Arbitration agreement
itself provides the procedure for enlargement of time and the parties
have taken recourse to it, and consented to the enlargement of time
by the arbitrator, the Court cannot exercise its inherent power in
extending the time fixed by the parties in the absence of the consent
of either of them.
8. The counsel for the appellant further contended that the High
Court could not have terminated the mandate of the arbitrator on the
ground that the award was passed beyond the time limit fixed by it. It
is clear from an apparent perusal of the judgment of the High Court
and the records before us that the High Court had not terminated the
mandate of the arbitrator on the ground that the arbitrator could not
pass the award within the time fixed by it vide its order dated 20th of
September, 2004. In fact, the arbitrator had continued to proceed
with the arbitration procedure after the time fixed by the Court had
expired on account of the mutual consent of the parties to extend the
time limit. Such an action was clearly warranted under the arbitration
16
agreement in force between the parties. On the contrary, the
arbitrator had ceased to have any authority only after the time limit
fixed by the parties had expired and the respondent did not give
consent to the extension of the time for publishing the award. Thus,
such a contention of the appellant cannot be accepted. The High
Court had merely asserted this fact that the mandate of the arbitrator
had automatically expired after the time fixed by the parties to the
effect that it had lapsed.
9. The Appellant further argued that the High Court had failed to
appreciate that the parties had undergone the process of arbitration
for a long time and it was not wise to terminate the mandate of the
arbitrator when the award was ready and fit to be published,
considering the fact that a huge sum of money had been spent during
the proceedings. Therefore, the High Court should not have ordered
the appointment of a new arbitrator. It is to be noted that the High
Court in its impugned judgment had ordered Shri A.K. Gupta to hand
over the relevant materials relating to the proceedings to the newly
appointed arbitrator. Thus, such an action would inherently make it
clear for the newly appointed arbitrator to conduct the proceedings
17
and it is not required from him to start the proceedings from scratch
all over again. Further, if the award was ready as had been
contended by the appellant, it is baffling that even after three months
from the expiry of the period fixed by the parties for publication of the
award, the arbitrator had not come out with the award or had notified
the respondent that the award was ready. It was only when the High
Court restrained the arbitrator from coming out with any award in the
dispute that the arbitrator submitted before the Court that the award
was ready to be published. At the risk of repetition, we may once
again note, that the Court has no inherent power to enlarge the time
for publication of the award once it has not been extended by the
parties to that effect.
10. The appellant further argued that the arbitrator having
concluded the proceedings couldn’t be said to have failed to act so as
to attract the provisions of Section 14 of the Act and call for
termination of the mandate of the arbitration. He had also contended
that under Section 15 (2) of the Act, substitute arbitrator should be
appointed according to the rules that were applicable to the
appointment of the arbitrator. Accordingly, his contention was that the
High Court had erred in holding that the appointing authority had not
18
appointed an arbitrator while terminating the mandate of the arbitrator
in the same proceedings.
It is necessary to mention here Section 14 and Section 15 of the Act
for the sake of convenience.
“Section 14: Failure or impossibility to act –
(1) The mandate of an arbitrator shall terminate if-
(a) He becomes de jure or de facto unable to perform his
functions or for other reasons fails to act without undue delay;
and
(b) He withdraws from his office or the parties agree to the
termination of his mandate.
(2) If a controversy remains concerning any of the grounds
referred to in clause (a) of subsection (1), a party may, unless
otherwise agreed by the parties, apply to the court to decide on
the termination of the mandate.
(3)If, under this section or sub-section (3) of section 13, an
arbitrator withdraws from his office or a party agrees to the
termination of the mandate of an arbitrator, it shall not imply
19
acceptance of the validity of any ground referred to in this
section or sub-section (3) of section 12.”
“Section 15: Termination of mandate and substitution of
arbitrator-
(1) In addition to the circumstances referred to in section 13 or
section 14, the mandate of an arbitrator shall terminate-
(a) Where he withdraws from office for any reason; or
(b) By or pursuant to agreement of the parties
(2) Where the mandate of an arbitrator terminates, a substitute
arbitrator shall be appointed according to the rules that were
applicable to the appointment of the arbitrator being replaced.
(3)Unless otherwise agreed by the parties, where an arbitrator
is replaced under subsection (2), any hearings previously held
may be repeated at the discretion of the arbitral tribunal.
(4)Unless otherwise agreed by the parties, an order or ruling of
the arbitral tribunal made prior to the replacement of an
arbitrator under this section shall not be invalid solely because
there has been a change in the composition of the arbitral
tribunal.”
20
11. With reference to the contention made by the appellant that the
arbitrator having concluded the proceedings couldn’t be said to have
failed to act so as to attract the provisions of Section 14 of the Act,
which will call for termination of the arbitration proceeding. It is
pertinent to mention here that the arbitrator had not concluded the
proceedings as had been agreed to by the parties within the time
fixed for doing so. The mandate of the arbitrator was terminated only
because of the fact that the arbitrator having failed to conclude his
proceedings within time did not warrant to be continued as an
arbitrator in the absence of the consent of both the parties. It is clear
from a bare reading of sub section 1 (a) of section 14 of the Act, the
mandate of an arbitrator shall terminate if he fails to act without
undue delay. In the present case, it is clear that the arbitrator had
extended the time provided to it without any concrete reasons
whatsoever and thus his mandate was liable to be terminated. Sub
section 1(b) further states that the mandate of an arbitrator shall also
stand to be terminated if he withdraws from his office or the parties
agree to the termination of his mandate. From the perusal of the
records and the submissions of the parties, we observe that the
mandate of the arbitrator was extended by an agreement between
21
the parties, which was not extended beyond 30th September, 2005.
Thus it can be construed that the parties had not agreed to the
extension of the mandate of the arbitrator failing which, the mandate
was automatically terminated.
12. Further, Subsection (2) of Section 14 of the Act stipulates that if
a controversy remains concerning any of the grounds referred to
under clause (a) of subsection 1, a party may, unless otherwise
agreed to by the parties, apply to the Court to decide on the
termination of the mandate. Thus the respondent rightly applied to the
Court for the termination of the mandate of the arbitrator pursuant to
the provisions of this section, and the Court was within its jurisdiction
to decide accordingly.
13. However, the contention of the Appellant that the High Court
had erred in not allowing the appellant to decide upon the
appointment of an arbitrator pursuant to sub-section (2) of Section 15
of the Act must be accepted. Section 15 (2) of the Act provides that
where the mandate of an arbitrator terminates, a substitute arbitrator
shall be appointed according to the rules that were applicable to the
appointment of the arbitrator replaced. In this connection, it would be
appropriate to refer to the relevant portion of the impugned judgment
22
of the High Court, which gives an elaborate observation on the
above-mentioned issue raised by the appellant:
“The question therefore is, whether in view of section 15 (2) of the 1996 Act, an independent arbitrator can be appointed by this Court as prayed for by the appellant or whether the appellant should once again invoke the Arbitration Clause, call upon the Chairman-cum- Managing Director of the respondent to appoint an arbitrator, wait for a further period of 30 days, to see whether the Chairman-cum-Managing Director acts or not and then make a request to the Hon’ble Chief Justice or his designate under Section 11(6) of the 1996 Act to appoint an arbitrator. Arbitration is an informal, quick and easy alternative mode of adjudication of disputes by agreement of the parties. This Court cannot but take judicial notice of the fact that the Arbitration Clause was invoked way back in May 1996 and almost 10 years have expired since then. The appointment of successive Arbitrator by the Chairman-cum-Managing Director of the respondent has only resulted in delay.
When the mandate of an arbitrator is terminated on the ground of delay, the rules applicable to the appointment of the arbitrator are to apply to the appointment of a new arbitrator. It would, however, be a mockery of justice, if every time the mandate of an arbitrator was terminated or the arbitrator resigned or otherwise became unable to proceed, the parties were to start from scratch, by invoking the Arbitration Clause.
Once the mandate of the arbitrator terminates, the person required to appoint arbitrator is required to fill up the vacancy with utmost expedition, failing which the provisions of section 11 (6) of the 1996 Act would be attracted. In the instant case, as per the Arbitration agreement the Chairman-cum-Managing Director was
23
required to appoint a new arbitrator in case the arbitrator became unable to continue, whatever be the reason. Even thought the time limit for conclusion of arbitration expired on 30th September, 2005, the Chairman-cum- Managing Director of the respondent did not appoint another arbitrator.”
14. We have carefully examined the aforesaid observations of the
impugned judgment of the High Court. We are of the view that in view
of a three-Judge Bench decision of this Court in the case of Northern
Railway Administration, Ministry of Railway vs. Patel
Engineering Company Ltd. [2008 (10) SCC 240] in which a decision
of this Court in Ace Pipeline Contracts Private Limited vs. Bharat
Petroleum Corporation Limited [(2007) 5 SCC 304] was also
referred to, the application for appointment of an Arbitrator under
Section 11 of the Act should be referred back to the High Court for
fresh decision. Arijit Pasayat, (as His Lordship then was), heading a
three-Judge Bench of this Court after considering the scope and
object of the Act particularly Section 11 of the Act concluded the
following :-
“A bare reading of the scheme of Section 11 shows that the emphasis is on the terms of the agreement being adhered to and/or given effect as closely as possible. In other words, the Court may ask to do what has not been
24
done. The court must first ensure that the remedies provided for are exhausted. It is true as contended by Mr. Desai, that it is not mandatory for the Chief Justice or any person or institution designated by him to appoint the named arbitrator or arbitrators. But at the same time, due regard has to be given to the qualifications required by the agreement and other considerations. xxxxxxxxxxxxxx
In all these cases at hand the High Court does not appear to have focused on the requirement to have due regard to the qualifications required by the agreement or other considerations necessary to secure the appointment of an independent and impartial arbitrator. It needs no reiteration that appointment of the arbitrator or arbitrators named in the arbitration agreement is not a must, but while making the appointment the twin requirements of Sub-section (8) of Section 11 have to be kept in view, considered and taken into account. If it is not done, the appointment becomes vulnerable. In the circumstances, we set aside the appointment made in each case, remit the matters to the High Court to make fresh appointments keeping in view the parameters indicated above.”
In the aforesaid decision in the case of Northern Railway
Administration (Supra), Arijit Pasayat, J. (as His Lordship then was),
held that the High Court in the said case did not appear to have
focused on the requirement to have due regard to the qualifications
required by the agreement or other conditions necessary to secure
the appointment of an independent and impartial arbitrator. In the
aforesaid decision, this Court also concluded that since the
25
requirement of sub-section (8) of Section 11 was not at all dealt with
by the High Court in its order, the appointment of an arbitrator without
dealing with Sub-Section 8 of Section 11 of the Act became
vulnerable and accordingly, such appointment must be set aside.
Similar is the position in this case. In this case also, before
appointing an arbitrator under Section 11(6) of the Act, the High Court
had failed to take into consideration the effect of Section 11(8) of the
Act as was done in Northern Railway Administration (supra).
15. In view of the discussions made hereinabove and particularly,
in view of the principles laid down by this Court in Northern Railway
Administration (supra), we set aside the impugned order and
remand the case back to the High Court for fresh decision of the
application under Section 11(6) of the Act and while considering the
application afresh, the High Court is directed to take into
consideration the aforesaid decision of this Court.
16. The appeals are thus allowed to the extent indicate above.
There will be no order as to costs.
…………………...J. [Tarun Chatterjee]
New Delhi; …………………….J. January 05, 2010. [Aftab Alam]
26
27