MAHINDRA & MAHINDRA LTD. Vs AVINASH DHANIRAMJI KAMBLE
Case number: C.A. No.-007993-007993 / 2009
Diary number: 13184 / 2008
Advocates: K. RAJEEV Vs
CHANDAN RAMAMURTHI
Non- Reportable
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 7993 OF 2009 (Arising out of S.L.P. (Civil) No. 12402/2008)
Mahindra & Mahindra Ltd. ..Appellant
Versus
Avinash Dhaniramji Kamble ..Respondent
WITH
Civil Appeal Nos. 7994/2009 to 8018/2009
(Arising out of SLP (Civil) Nos. 12534/08,19022/08, 17741/08, 17749/08, 17987/08, 17989/08, 17992/08, 18000/08, 18032/08, 18033/08, 18036/08, 18037/08, 18047/08, 18052/08, 18054/08, 18058/08, 18063/08, 18068/08, 18070/08, 18075/08, 18080/08, 18082/08, 18083/08, 18090/08 and 18092/08)
J U D G M E N T
R.M. LODHA, J.
Leave granted.
2. In this group of 26 appeals, the common judgment
dated March 3, 2008 passed by the Division Bench of the High
Court of Bombay, Nagpur Bench, Nagpur is under challenge at
the instance of the employer.
3. In light of the order that we intend to pass, it is not
necessary to set out the facts in detail. Suffice it to say that in
the complaints by the present respondents seeking declaration of
unfair labour practices on the part of the employer under Items
5, 6, 9 and 10 of Schedule IV of Maharashtra Recognition of
Trade Unions and Prevention of Unfair Labour Practices, Act,
1971 (for short MRTU & PULP Act”), the Industrial Court,
Maharashtra (Nagpur Bench) Nagpur, in its order dated March
19, 2003 held that complaints were not maintainable under
Item 6 of Schedule IV to the MRTU & PULP Act. The Industrial
Court also held that the complaints were liable to be rejected in
so far as it related to Items 5 & 10 of Schedule IV but as
regards the unfair labour practice under Item No.9 of Schedule
IV, although relief was granted by the Industrial Court to 149
temporary workmen who had completed 240 days of continuous
service, no relief was granted to the present respondents as
2
they have not completed 240 days of continuous service as
required under the Model Standing Orders. The Industrial Court,
in its order, in respect of the present respondents held as
follows:
“From the evidence adduced by the complainants in all other complaints it appears that in all 58 complainants have not at all completed 240 days working during the entire period they were in the employment of the respondent. The list of these complainants is at Ex.101. Hence, their confirmation in service as per clause 4-C of the Model Standing Orders does not arise.”
4. Dealing with the writ petitions challenging the order
of the Industrial Court at the instance of the employees as well as
employer, the single Judge in his judgment dated April 29, 2005,
inter alia, did notice that there was dispute between parties
about putting of uninterrupted service of 240 days by the
employees but while dealing with this aspect of the controversy,
he held that the period during which the employer engaged
other batch or other persons in place of the employees (like the
present respondents) will have to be treated as period of
‘involuntary unemployment’. The single Judge held thus:
“………The case of the present nature where employer resorts to rotation and grants employment only in batches,
3
considering the scheme of Model Standing Orders, it is apparent that the period during which employer engaged other batch or other person in place of employee like present complainants, will have to be treated as period of “involuntary unemployment”. It is not the case where no work is available for an employee with employer but the case is where employer gives that work to another temporary employee”……….
5. The aforesaid judgment of the single Judge was
assailed by the employer in a group of Letters Patent Appeals.
The Division Bench heard these Letters Patent Appeals
together and disposed of them by a common judgment dated
March 3, 2008. The Division Bench, inter alia, held as follows:
“……..Though the workman had not been able to establish that the employer had engaged two sets of temporaries employed alternatively, they have demonstrated that though the work was still available a temporary workman appointed for a fixed term was not re-employed or continued, but was given a break. Another temporary was appointed likewise for a fixed period and then again given a break. ………………………………………………………………………
………In any case, it would not be open to the employer to now contend that the work was not available after having entered into agreement with the employees’ representative on 12.1.2008, whereby it has undertaken to grant permanency to 105 workmen.” .
6. Pertinently, the present respondents in the
complaints set up a specific case that they had completed 240
days uninterrupted service as required under the Model Standing
4
Orders. Having pleaded that, they also pleaded that they were
employed for six months in rotation with other temporaries and
upon expiry of each terms of six months they were replaced by
another set of temporaries and that this practice was followed
with a view to prevent them to complete 240 days uninterrupted
service. That these employees (present respondents) have not
actually completed 240 days of uninterrupted service is not in
dispute. As regards rotational employment to temporaries, the
Division Bench held that the concerned workmen had not
been able to establish that the employer had engaged two sets
of temporaries employed alternatively. Despite having held
that, the Division Bench concluded that although work was
available, temporary workmen appointed for a fixed term were
not re-employed or continued but were given break. It is here
that we find that findings of the Division Bench are inconsistent.
The Industrial Court recorded a categorical finding of fact in
respect of the present respondents that they had never
completed 240 days of continuous service. But the single
Judge as well as the Division Bench, however, treated the gaps
between diverse spells of employment as part of continuous
5
service on the ground that these were due to involuntary
unemployment. This approach of the High Court suffers from
legal flaw for more than one reason. For one, this was not
even the case set up by the complainants in the complaints.
Secondly, and more importantly, the termination and fresh
employment in respect of some temporaries had been several
times and none of the complainants (present respondents)
challenged their termination being illegal as and when their
services were brought to an end on expiry of the period for
which they were engaged under the contract of service.
7. Although the judgment of the Division Bench runs
into more than 50 foolscap typed pages and reflects good
amount of industry put therein but as noticed above crucial
aspects have been mixed up necessitating reconsideration of
letters patent appeals by the Division Bench of the High Court.
In view thereof, we deem it unnecessary to deal with the
diverse contentions raised by the learned senior counsel and
counsel for the parties and leave all these contentions to be
raised before the Division Bench.
6
8. By way of footnote, we may observe that during
course of hearing, Mr. C.U. Singh, learned senior counsel for
the employer made a proposal for amicable settlement that
benefit of permanency to the present respondents as per
agreement dated January 12, 2008 could be given from 2005 or
so but even such fair and reasonable proposal was not
acceptable to Mr. S.D. Thakur learned counsel for the
respondents.
9. In what we have discussed above, the impugned
judgment dated March 3, 2008 is set aside. Letters Patent
Appeals are restored to the file of the High Court for fresh
hearing and disposal in accordance with law. All contentions of
the parties are kept open to be agitated before the Division
Bench of the High Court. No order as to costs. Pending
applications, if any, stand disposed of.
…………………………..J (Tarun Chatterjee)
…………………………..J (R.M. Lodha)
7
…………………………..J (Dr. B.S. Chauhan)
New Delhi, December 3, 2009
8