MAHADEVAPPA LACHAPPA KINAGI Vs STATE OF KARNATAKA .
Bench: TARUN CHATTERJEE,AFTAB ALAM, , ,
Case number: C.A. No.-004728-004728 / 2008
Diary number: 33603 / 2007
Advocates: Vs
HETU ARORA SETHI
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
NON-REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
Interlocutory Application Nos. 1 and 2 of 2008 IN
CIVIL APPEAL NO.4728 OF 2008 (Arising out of SLP(C) No. 22346 of 2007) Mahadevappa Lachappa Kinagi and Ors. …Appellants
VERSUS State of Karnataka and Ors. …Respondents
O R D E R
1. Leave granted.
2. This appeal is filed against the
judgment and order dated 3rd of October,
2007 passed in Writ Appeal No. 834 of
2007 whereby the High Court had
dismissed the appeal of the appellants
holding that in the facts and
circumstances of the case, the power
under Section 17 of the Land Acquisition
1
Act (in short the “Act”) was validly
invoked.
3. Before we proceed further, we may note
that at the time of issuing notice on
the respondents, this Court on 14th of
December, 2007 passed the following
order :- “Issue notice. Status quo as on today shall be maintained.”
4. An application for vacating the interim
order was listed for hearing on 16th of July,
2008 and the learned counsel appearing for
the parties submitted before us, on
instructions, that instead of hearing out
the application for vacating the interim
order, it would be fit and proper if the
Special Leave Petition itself was decided.
Accordingly, with the consent of the learned
counsel for the parties, the SLP itself was
taken up for hearing which was heard on
2
grant of leave in presence of learned
counsel for the parties.
5. The appellants are owners of Sy Nos.
172/1A, 2A, 2B and 173/2 totaling 18.5 Acres
situated at Almel Village Sindagi Taluk in
the State of Karnataka. During the year
1962, due to over flow of Bhima river,
Tharapura village was submerged. The State
Government acquired about 14 Acres of land
in Sy No. 188, 189 and 190/2 of Almel
Village in order to rehabilitate the
families of Tharapura village which was
submerged by the over flow of Bhima river.
On the said acquired lands, the State
Government had rehabilitated 85 families of
Tharapura village whereas 145 families of
the said village were still not
rehabilitated. It is not in dispute that
after rehabilitating 85 families as stated
hereinabove on the aforesaid acquired lands,
another 145 families still were residing in
3
the Tharapura village including the
appellants. In the year 1994, technical
sanction was given for the Bhima Lift
Irrigation Project. Accordingly, sanction
was accorded to construct a barrage on the
Bhima river, for which final sanction was
given in the financial year 2003-2004.
Thereafter, construction work began and this
project was aimed to extend irrigation
facilities to 24,200 hectares of land. As a
result of the detailed technical status, it
was found that the project, i.e., Bhima
Irrigation Project, would result in the
complete submergence of Tharapura village
owing to water spread when the barrage is
commissioned. For this reason, it was found
imperative and absolutely necessary to
evacuate the villagers still staying in
Tharapura village. Accordingly, before
commissioning the barrage, decision was
taken to rehabilitate another 145 families
of Tharapura village in some other area.
4
6. It is not in dispute that construction
work of the barrage is ready for operation.
At this stage, it was thought proper to
rehabilitate 145 families, for which lands
were sought to be acquired. Under these
circumstances, the commissioning of the
barrage on the Bhima river could not be
started although it was completed because
the 145 families in the said village could
not be shifted. To meet this problem, the
notification under Section 4(1) of the Act
was issued on 10th of August, 2006 for
acquiring the lands of the appellants
namely, Sy Nos. 172/1A, 2A, 2B and 173/2
totaling 18.5 Acres.
7. This notification was under challenge
before the High Court by way of a writ
application, which was dismissed by a
learned Single Judge of the High Court and
the said order was affirmed by a Division
Bench of the High Court. The orders of the
5
High court are now under challenge before us
in appeal. The learned senior counsel
appearing on behalf of the appellants, Mr.
Vasudev substantially raised the submission
before us that since the rehabilitation
project was pending since 1962, the
emergency power under Section 17 of the Act,
could not have been exercised by the State
Government in the year 2006. Accordingly, it
was contended by Mr.Vasudev, learned senior
counsel appearing on behalf of the
appellants, that since there was no urgency
in the matter to invoke emergency provision
for acquisition under Section 17 of the Act
and normal procedure ought to have been
followed, the notification under Section 4
of the Act should be quashed. In support of
this contention whether emergency power
under Section 17 of the Act could be invoked
in the facts and circumstances of the
present case particularly after such a long
delay, Mr. Vasudev strongly relied on a
6
decision of this Court in the case of Union of India and Ors. vs. Mukesh Hans etc.(2004) 8 SCC 14, particularly on paragraphs 31 and 32 of the said Judgment.
9. Mr. Vasudev contended that since Section
17 provides that in cases where an
appropriate Government has come to a
conclusion that there exists an urgency or
unforeseen emergency as required under Sub-
Sections (1) and (2) of Section 17, it may
direct that the provisions of Section 5A
shall not apply and if such direction is
given, then Section 5-A inquiry can be
dispensed with and a declaration may be made
under Section 6 on publication of Section 4
(1) notification and possession can be
taken. Relying on these two paragraphs,
namely paragraphs 31 and 32 of the aforesaid
decision of this Court, Mr. Vasudev sought
to argue that in this case, the High Court
7
had failed to consider that it was the duty
of the authorities to come to a conclusion
that there exists an urgency or unforeseen
emergency as required by Sub-section (1) and
(2) of Section 17 before such emergency
provision could be invoked. Mr.Vasudev
learned counsel for the appellants further
contended that the notification under
Section 4(1) read with Section 17 of the Act
must be quashed as there was nothing on the
record to show that the State Government had
made out any case to invoke such emergency
provision. There is no quarrel on this
proposition at all. It is true that if the
Court comes to a conclusion whether there
exists any unforeseen emergency to invoke
power under Section 17 of the Act, it was
the duty of the authorities to proceed with
the normal procedure under Section 5A of the
Act. We are, however, on the facts and
circumstances of this case, unable to rely
on this observation of this Court in the
8
aforesaid paragraphs of this decision cited
by Mr. Vasudev. In this case, we find that
emergency power under Section 17 was
required to be invoked, as the admitted
facts of the present case, that on the lands
initially acquired, only 85 families were
reallocated or rehabilitated. The Tharapura
village was going to be sub-merged after the
construction of the barrage and 145 families
would be immediately shifted to somewhere
else. In view of this emergency and in view
of the fact that the barrage has already
been completed and it is going to be
commissioned, it was thought fit and proper
that the land, as noted hereinabove, should
be acquired.
11. It cannot be forgotten that the
commissioning of the entire project has been
held-up on account of the present appellants
only. In fact, the appellants challenged
the resolution of the concerned Panchayat
9
before the High Court of Karnataka, which
was rejected by the learned Single Judge,
who found that the acquisition process was
proper.
12. This fact of moving the writ petition
practically challenging the proposal to
acquire the land was suppressed when the
present writ application was moved. The
rehabilitation of 145 families could be
immediately required because of the
commissioning of the barrage on the Bhima
river. Not only this, pursuant to the
acquisition of the lands in question, the
respondents have awarded contract for
construction for Tharapura Rehabilitation
Centre for providing civic amenities as part
of the Lift Irrigation Scheme, which is
valued at Rs. 3,34,17,747/-. If this
contract is not permitted to be executed and
works are not completed, the 145 families of
Tharapura village cannot be shifted and the
10
entire contract amount will be wasted. This
being the admitted position, we are unable
to agree with Mr. Vasudev that in the facts
and circumstances of the present case, the
invocation of emergency power under Section
17 of the Act without following the normal
procedure was not proper.
13. It is no doubt true that Section 17 of
the Act confers extraordinary powers on
the authorities under which it can
dispense with the Normal procedure laid
down under Section 5-A of the Act in
cases of exceptional urgency. It is also
true that such powers cannot be lightly
resorted to except in case of real
urgency enabling the Government to take
immediate possession of the land
proposed to be acquired for public
purpose. In Union of India vs. & Ors.
vs. Krishan Lal Arneja & Ors. {(2004) 8
SCC 453], this Court has clearly laid
11
down that Section 17 confers
extraordinary powers on the authorities
to dispense with the normal procedure
under Section 5-A of the Act if the
authorities are of the opinion that it
was a case of exceptional urgency. In
view of our discussions made herein
above to the extent that the barrage
itself over the Bhima River could not be
commissioned and if such commissioning
is done before rehabilitating the 145
families of Tharapura Village which will
be submerged on such commissioning is
shifted, the project would then also
result in total submergence of Tharapura
Village. It is not possible to hold that
this was not an exceptional case where
emergency power under Section 17 could
not be invoked.
For the reasons aforesaid, we do not
find any merit in this appeal and the appeal
12
is, therefore, dismissed. There will be no
order as to costs.
The interim order granted on 14th
December, 2007 stands vacated. In view of
this judgment by which the appeal itself has
been disposed of, no order need be passed on
the application for vacating the interim
order, it is also disposed of as
infructuous.
……………………………………………J. [TARUN CHATTERJEE]
New Delhi. ………………………………………….J. July 30, 2008. [AFTAB ALAM]
13
14