M/S. MADNANI CONSTRUCTION CORPN.(P)LTD. Vs UNION OF INDIA .
Case number: C.A. No.-008385-008385 / 2004
Diary number: 15885 / 2003
Advocates: SHIBASHISH MISRA Vs
B. KRISHNA PRASAD
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
Page 30
Page 31
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.8385 OF 2004
M/s. Madnani Construction Corporation (P) Ltd. ...Appellant(s)
Vs.
Union of India & Others ...Respondent(s)
J U D G M E N T
GANGULY, J.
1. The subject matter of challenge in this appeal is
the judgment and order dated 29.04.2003 passed by
the High Court of judicature at Allahabad in
F.A.F.O. No. 40 of 1993, in a matter arising from
the order dated 1.12.1992 of the learned Senior
Civil Judge, making the Award a Rule of the Court,
and whereby the High Court had partly allowed the
Appeal filed by the respondent.
1
2. The appellant, a private limited company, is
carrying on, inter alia, various construction
works for both the State and Central Government
and their undertakings. The appellant’s case is
that an agreement dated 03.11.1981 was entered
between the appellant and the North Eastern
Railway for the construction of bridge island nos.
13 and 14 over the Kosi river. There were certain
special conditions of the contract (hereinafter,
SCC) and they stipulate that the General
Conditions of Contract (hereinafter, GCC) and
standard specifications of the North Eastern
Railways shall form part of the aforesaid
contract. In terms of the contract, the
construction was to be completed by 15.02.1982.
Certain payments were made to the appellant after
completion of the contract but they were received
by them “under protest”. Thus, disputes cropped-up
between the parties. The appellant is said to
have served a notice dated 16.11.1983 for the
appointment of an arbitrator to settle the
2
disputes. The General Manager of the respondent-
Railways by an order dated 24.03.1986 rejected the
appellant’s prayer for appointment of an
arbitrator on the ground that the disputes were
not arbitrable, as they fell under ‘expected
matter’ in the contract.
3. On or about 18.08.1987, the appellant filed an
application under Section 20 of the Arbitration
Act, 1940 (hereinafter, the Act) before the Court
of Addl. Civil Judge, Gorakhpur for appointment of
an arbitrator which was transferred on 21st
February, 1990, to the Court of Judge of Small
Causes /Additional Civil Judge (hereinafter, the
Court below). The Court below passed an order on
2.3.1990 that ‘file received, put up on the date
fixed’. Then by an order dated 31.05.1991 the
learned Civil Judge appointed one Mr. B. N.
Shukla, the Sole Arbitrator, to adjudicate the
disputes arising out of the agreement dated
03.11.1981. Against the order of appointment of
arbitrator the responder approached the High Court
3
by filing F.A.F.O. No. 534 of 1991 (the earlier
F.A.F.O.), but the same was dismissed vide order
dated 27.08.1991.
4. The learned Arbitrator gave his award on 13.4.1992
holding that the Railways should pay an amount of
Rs.4,48,873.22 along with compoundable bank
interest prevalent at that time from 16.11.1983 to
21.3.1992. In passing the award the Arbitrator
relied on the Level book No. I, the Graph Sheets,
the Log Book No. IA and the Log Book No. 4. The
Arbitrator found that there were subsequent
alterations and over writing in the entries made
in the Log Book No.IA and the same were without
any initials by the concerned authority on behalf
of the respondent Railways. From such materials
the Arbitrator held that all the
manipulations/alterations/overwritings had
resulted in reducing the quantities of the work
done by the appellant. It was further observed
that clause 21 (iv) of the special conditions was
not followed by the respondent Railways at all.
4
Moreover in utter violation of the Railway rules
and orders on the subject, the measurements were
hardly entered in the measurement book directly
and mostly entries in the measurement books were
copied down from subsidiary records or note books.
After recording such findings, the Arbitrator gave
the aforesaid award.
5. Thereafter on 08.05.1992 the appellant filed an
application under Section 17 of the Act for
pronouncing judgment and making decree according
to the award.
6. On 20.5.1992 the respondent Railways filed
application under Section 30 read with Section 33
(Section 30/33) of the Act before the Civil Judge
for setting aside the award. Then on 24.08.1992
they also filed their objections against the
application filed by the contractor under Section
17 of the Act. The following facts were recorded
in the judgment of the High Court.
5
“The Railways filed an application before the District Judge for transfer of the application filed by the contractor under Section 20 of the Act and under Section 24 of the Civil Procedure Code. It was dismissed on 13th November, 1992. The Railways filed an application on 23rd November, 1992, before the court below for summoning their application and under Section 30/33 of the Act from the Court where it was filed. This was objected to by the Contractor on the same date. However, the Court below summoned it and not only rejected it but also rejected their objections against the application under Section 17 of the Act. The Court below by its order dated 1.12.1992 also pronounced judgment according to the award and decreed interest at the rate given by the Bank from the date of the award till actual payment".
7. On 1st December 1992, the Senior Civil Judge,
Gorakhpur of the Court of Judge, Small Causes
Gorakhpur made the award a Rule of Court and
directed that a decree be prepared accordingly and
directed that from the date of the award to the
date of payment the rate of interest on the Bank
loan is to be paid.
8. Challenging the aforesaid order of the Civil
Judge, the Railways filed an appeal before the
High Court. 6
9. Before the High Court, 7 issues were framed. The
appeal was partly allowed by the High Court and in
doing so the High Court came to the conclusion
that the court below had the jurisdiction to
entertain the application under Section 17 of the
Act.
10. On the application of the Railways under Section
30/33 of the Act, the High Court held that the
case is not required to be remanded as the court
below decided the case correctly on merits.
11. Referring to the decision of the General Manager
dated 24.03.1986 rejecting request for appointment
of Arbitrator on the ground that dispute fell
under excepted matters, the High Court concluded
that there is difference of opinion between the
parties whether the dispute falls under excepted
matters or not and the decision of the General
Manager regarding excepted matters is not final
between the parties. The General Manager by
7
wrongly deciding this question could not exclude
the jurisdiction of the Court.
12. On the issue as to whether the respondent Railways
are entitled to raise objections regarding the
excepted matters at the stage of Section 20, the
High Court concluded that the trial Court did not
say a word about it and the High Court merely
affirmed the order passed by the trial court. As
such the issue was left to be decided by the
Arbitrator who has held that none of the claims of
the contractor were excepted matters. It was held
that as the question was not decided in the
earlier litigation, it cannot be said that the
Railways are precluded from raising this question
in these proceedings.
13. On the issue of excepted matters the High Court
held that Item Nos. 1 to 3 and 5 to 8 were
excepted matters and were non-arbitrable and the
Arbitrator committed an illegality in allowing
them. For the remaining items viz. item No. 9 (a)&
8
(d) relating to supply of boats, 11 (b) relating
to cost of wastage of labour, it was held that
these were not covered by Clause 22 (5) or 45 (a)
of the GCC, as such they do not fall in the
category of non-arbitrable matters and are
arbitrable.
14. On the award of interest it was contended that
clause 16 (1) read with 16 (2) of GCC prohibits
payment of interest on amounts payable to the
appellant under the contract except the Government
securities mentioned therein. In this regard, the
High Court considered Clause 30 of SCC and Clause
52 of GCC and found them to be similar and these
clauses, according to High Court, bar interest and
damages in respect of withholding or retention
under the lien. Further by placing reliance on the
case of Executive Engineer, D.M.I. Division v. N.
C. Budhraj, AIR 2001 SC 628 High Court held that
interest could not be awarded since there was
specific prohibition in the contract regarding
awarding of interest.
9
15. On the award of interest High Court’s specific
conclusions are:
“(f) The contract prohibited payment of interest. Item 10 is award for interest; it could not be awarded. Similarly no interest could be awarded under clause 3 of the Award.
(g) There is no illegality in awarding interest payable at the bank rate, but it could only be awarded from the date of decree and not from the date of award.”
16. Appellant also filed a review petition before the
High Court but the same was dismissed vide order
dated 15.05.2003.
17. This Court finds that the High Court’s conclusion
that Item Nos. 1 to 3 and 5 to 8 of the award are
‘excepted matters’ and non-arbitrable is not
correct for the reasons discussed below.
18. In coming to the aforesaid finding, the High Court
relied on Clause 45 (a) of GCC. Clause 45(a) of
the GCC is set out below:
10
"45(a): It shall be open to the Contractor to take specific objection to any recorded measurement or classification on any ground within seven days of the date of such measurements. Any re-measurements taken by the Engineer or the Engineer’s Representative in the presence of the Contractor or in his absence after due notice has been given to him in consequence of objection made by the Contractor shall be final and binding on the Contractor and no claim whatsoever shall thereafter be entertained regarding the accuracy and classification of the measurements.”
19. A plain reading of Clause 45(a) of the GCC makes
it clear that re-measurement are to be made by the
Engineer or the Engineer’s representative in the
presence of the Contractor. It may be done in the
absence of the contractor but that has to be done
only after due notice. On a proper construction
of Clause 45(a) it appears that it gives the
contractor, (a) an opportunity to take a specific
objection to any recorded measurement within seven
days of such measurements; (b) Then any re-
measurements is to be taken by the Engineer or the
Engineer’s representative in the presence of the
contractor or in his absence after due notice; if
11
the steps under (a) and (b) are strictly followed,
(c) no claim whatsoever by the contractor shall be
entertained about the classification or the
accuracy of the measurement.
20. Under Clause 62 of the GCC it is provided that
matters for which provisions have been made in
Clause 45(a) shall be excepted matters.
21. The arbitrator in his award after perusal of the
level Book No.1, Graph-Sheets, Logbook No. 1A and
Logbook No.4 came to a clear finding that there
were manipulations/alterations/over writings by
the railways and as a result of which the volume
of work done by the contactor has been reduced.
22. It is well settled that the arbitrator is the
master of facts. When the arbitrator on the basis
of record and materials which are placed before
him by the railways came to such specific findings
and which have not been stigmatized as perverse by
the High Court, the High Court in reaching its
conclusions cannot ignore those findings.
12
23. But it appears that in the instant case, the High
Court has come to the aforesaid finding that the
items mentioned above are excepted matters and
non-arbitrable by completely ignoring the factual
finding by the arbitrator and without holding that
those findings are perverse.
24. It goes without saying that in order to deny the
claims of the contractor as covered under excepted
matters, the procedure prescribed for bringing
those claims under excepted matters must be
scrupulously followed. The clear finding of the
arbitrator is that it has not been followed and
the High Court has not expressed any dis-agreement
on that. Therefore, the finding of the High Court
that those items are non-arbitrable cannot be
sustained.
25. On the question of grant of interest by the
arbitrator, the High Court held that Clause 16(2)
13
of the GCC contains a provision against grant of
interest. Clause 16(2)of the GCC is set out below:
“16(2): No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract but government securities deposited in terms of such clause (1) of this clause will be repayable with interest accrued thereto.”
26. The High Court has also relied on Clause 30 of the
SCC and Clause 52 of the GCC to hold that payment
of interest has been barred. The relevant portion
of Clause 30 of the SCC relating to interest is
set out below:
“…That the contractor will have no claim for interest and damage whatsoever on any account in respect of such with-holding or retention under the lien referred to supra and duly notified as such to the Contractor.”
27. The High Court has held that Clause 30 of the SCC
is similar to Clause 52 of the GCC.
28. Before discussing the implication of these
clauses, it may be noted that the Arbitration Act,
14
1940 does not contain any provision enabling the
arbitrator to give interest.
29. Section 29 of the Arbitration Act enables the
Court to award interest from the date of the
decree and at such rate as the Court deems
reasonable.
30. The present Act of 1996 (the Arbitration and
Conciliation Act, 1996), however, empowers the
Arbitrator under Section 31(7)(a) and (b) to grant
interest. Admittedly, in this case the 1996 Act is
not attracted. Therefore, the provisions of 1940
Act will govern. The arbitrator’s power to grant
interest is governed by the various judicial
pronouncements and the provisions of Interest Act
of 1978.
31. It goes without saying that in the instant case,
the provision of the Interest Act, 1978 is
attracted. Under the Interest Act, 1978, Section
15
2(a) defines “Court” to include both a tribunal
and an arbitrator.
32. Under the Interest Act, Section 3 empowers the
Court to allow interest. But sub-Section (3) of
Section 3 contains a proviso, namely, Section 3,
sub-Section (3), Clause (a) (ii), to the following
effect:-
“3. (3) Nothing in this section, -
(a) shall apply in relation to -
(i) xxx xxx
(ii) any debt or damages upon which payment of interest is barred, by virtue of an express agreement’”
33. In the context of the aforesaid provision in the
Interest Act, the Clauses in the agreement quoted
hereinabove assume importance.
34. Normally there are three periods for which
interests are awarded - (a) pre-reference period
i.e. from the date of the cause of action for
going to arbitration and to the date of reference; 16
(b) the pendente lite period i.e. from the date of
reference to the date of award; and (c) the post-
reference period i.e. from the date of the award
to the date of realization.
35. Initially there was a judgment of this Court in
the case of Executive Engineer (Irrigation), Balimela and Others Vs. Abhaduta Jena and Others [1988 (1) SCC 418] which held, the arbitrator has
no power to award interests in the absence of
contract or any substantive law.
36. Construing the provision of the 1940 Act, the
Court held:-
“..in cases arising after the commencement of Interest Act of 1978 an arbitrator has the same power as the court to award interest up to the date of institution of the proceedings, in cases which arose prior to the commencement of the 1978 Act the arbitrator has no such power under the Interest Act of 1839.” (Para 4)
37. The decision in Abhaduta Jena (supra), however, was overruled by the Constitution Bench of this
Court in Secretary, Irrigation Department, 17
Government of Orissa and Others Vs. G.C. Roy, [1992 (1) SCC 508].
38. The Constitution Bench in G.C. Roy (supra) discussed several aspects of the Act of 1940 and
also the provisions of Section 34 of the Civil
Procedure Code and also those of the Interest Act.
After discussing those provisions, the
Constitution Bench formulated the question which
arose in that case as follows:-
“……In the context of these provisions the question arises whether an arbitrator to whom reference is made by the parties has jurisdiction or authority to award interest pendente lite. If the arbitration agreement or the contract itself provides for award of interest on the amount found due from one party to the other, no question regarding the absence of arbitrator’s jurisdiction to award the interest could arise as in that case the arbitrator has power to award interest pendente lite as well. Similarly, where the agreement expressly provides that no interest pendente lite shall be payable on the amount due, the arbitrator has no power to award pendente lite interest. But where the agreement does not provide either for grant or denial of interest on the amount found due, the question arises whether in such an event the arbitrator has power and authority to grant pendente lite interest.
18
39. After formulating the above question and
discussing various decisions and legal issues, the
Constitution Bench in paragraph 43 at page 532
further held:
“The question still remains whether arbitrator has the power to award interest pendente lite, and if so on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest….”
40. After posing the question as above, the
Constitution Bench laid down the following
principles in paragraph 43 at page 532 to 533:
“(i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34, Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.
(ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he
19
must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has no power to award interest pendente lite, the party claiming it would have to approach the court for that purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator. This would lead to multiplicity of proceedings.
(iii) An arbitrator is the creature of an agreement. It is open to the parties to confer upon him such powers and prescribe such procedure for him to follow, as they think fit, so long as they are not opposed to law. (The proviso to Section 41 and Section 3 of Arbitration Act illustrate this point). All the same, the agreement must be in conformity with law. The arbitrator must also act and make his award in accordance with the general law of the land and the agreement.
(iv) Over the years, the English and Indian courts have acted on the assumption that where the agreement does not prohibit and a party to the reference makes a claim for interest, the arbitrator must have the power to award interest pendente lite. Thawardas has not been followed in the later decisions of this Court. It has been explained and distinguished on the basis that in that case there was no claim for interest but only a claim for unliquidated damages. It has been said repeatedly that observations in the said judgment were not intended to lay down any such absolute or universal rule as they appear to, on first impression. Until Jena case almost all the courts in the country had upheld the power of the arbitrator to award interest pendente lite. Continuity and certainty is a highly desirable feature of law.
(v) Interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference (pre- reference period). For doing complete
20
justice between the parties, such power has always been inferred.”
41. Ultimately in paragraphs 44 and 45 at page 533 to
534 of the report the Constitution Bench held as
follows:
“Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes — or refer the dispute as to interest as such — to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.
45. For the reasons aforesaid we must hold that the decision in Jena, insofar as it runs counter to the above proposition, did not lay down correct law.”
42. Following the Constitution Bench ratio in G.C. Roy (supra), another three-Judge Bench in the case of
Hindustan Construction Company Limited vs. State 21
of Jammu and Kashmir – (1992) 4 SCC 217, while referring to the ratio in G.C. Roy (supra), held in paragraph 5 at page 220:
“……Though the said decision deals with the power of the arbitrator to award interest pendente lite, the principle of the decision makes it clear that the arbitrator is competent to award interest for the period commencing with the date of award to the date of decree or date of realisation, whichever is earlier. This is also quite logical for, while award of interest for the period prior to an arbitrator entering upon the reference is a matter of substantive law, the grant of interest for the post-award period is a matter of procedure. Section 34 of Code of Civil Procedure provides both for awarding of interest pendente lite as well as for the post-decree period and the principle of Section 34 has been held applicable to proceedings before the arbitrator, though the section as such may not apply…….”
43. Subsequently, in the case of State of Orissa v. B.N. Agarwalla – (1997) 2 SCC 469, before another three-Judge Bench a similar question came up for
consideration and this Bench following the ratio
in G.C. Roy (supra) and Hindustan Construction (supra) considered the question of payment of
interest. After discussing the ratio in Abhaduta Jena (supra) and G.C. Roy (supra) and various other cases, the learned Judges in paragraph 18 at
22
page 477 of the report came to the conclusion
that; (a) it is well settled that the arbitrator
has a jurisdiction to award pre-reference interest
in cases which arose after the Interest Act, 1978
had become applicable. It is no doubt that in this
case arbitration proceedings were initiated after
the 1978 Act became applicable; (b) for the period
in which the arbitration proceedings are pending
the arbitrator has the power to award interest;
(c) the Court also held that the power of the
arbitrator to award interest for the post-award
period also exists.
44. In G.C. Roy (supra) this Court made it clear that the arbitration clause was silent on the payment
of interest but in B.N. Agarwalla (supra) the Court considered Clause (4) which had the
following stipulation on interest:
“……No interest is payable on amounts withheld under the item of the agreement……. ”
23
45. Considering the said Clause (4), the learned
Judges held that the claim which was made before
the arbitrator was for non-payment of the full
amount as per the final bill submitted by the
claimant and the arbitrator awarded interest on
that. The interest so awarded, according to the
learned Judges, is not prohibited under Clause (4)
of the Contract. Therefore, the three Judge Bench
clearly held that just a stipulation in the
contract purporting to indicate non-payment of
interest cannot denude the arbitrator of his right
to pay interest.
46. In a subsequent decision of three-Judge Bench in
the case of State of U.P. v. Harish Chandra and Company – (1999) 1 SCC 63, there was stipulation in the arbitration agreement against grant of
interest. The relevant clause namely Clause 1.9
to the aforesaid effect is set out below:
“1.9 No claim for delayed payment due to dispute etc.—No claim for interest or damages will be entertained by the Government with respect to any moneys or balances which may be lying with the Government owing to any dispute,
24
difference; or misunderstanding between the Engineer-in-Charge in marking periodical or final payments or in any other respect whatsoever.”
47. Considering the said clause, the Court held that
the prohibition in the said clause does not
prevent the contractor from raising the claim of
interest by way of damages before the arbitrator
on the relevant items placed for adjudication.
(see paragraph 10 page 67). In saying so, the
learned Judges relied on the ratio in the case of
B.N. Agarwalla (supra) and G.C. Roy (supra).
48. In Board of Trustees for the Port of Calcutta v. Engineers-De-Space-Age, (1996) 1 SCC 516, a two- judge Bench of this Court considered the same
question. That was a case under the 1940 Act. In
Engineers (supra), the so-called prohibition in the contract relating to payment of interest was
in Clause 13(g), which is set out below:-
“13(g) No claim for interest will be entertained by the Commissioners with respect to any money or balance which may be in their hands owing to any dispute between themselves and the Contractor or with respect to any delay
25
on the part of the Commissioners in making interim or final payment or otherwise.”
49. Relying on the said clause, the appellant in
Engineers (supra) argued that there was absolute prohibition against payment of interest. The
learned Judges however, relying on the ratio in
G.C. Roy (supra) held that Clause 13(g) merely prohibits the Commissioner from entertaining any
claim for interest but it does not prohibit the
arbitrator from awarding interest. The learned
Judges held that such clauses must be strictly
construed in view of the ratio of the Constitution
Bench in G.C. Roy (supra). The reasoning given by the learned Judges in favour of strict
construction runs as follows:-
“...Clause has to be strictly construed for the simple reason that as pointed out by the Constitution Bench, ordinarily, a person who has a legitimate claim is entitled to payment within a reasonable time and if the payment has been delayed beyond reasonable time he can legitimately claim to be compensated for that delay whatever nomenclature one may give to his claim in that behalf. If that be so, we would be justified in placing a strict construction on the term of the contract on which reliance has been placed. Strictly construed the term of the contract merely prohibits the Commissioner from paying interest to the contractor for delayed payment but once the matter goes to
26
arbitration the discretion of the arbitrator is not, in any manner, stifled by this term of the contract and the arbitrator would be entitled to consider the question of grant of interest pendente lite and award interest if he finds the claim to be justified.” (Para 4, page 520)
50. It was argued before us by the learned counsel
for the respondent that a subsequent Division
Bench of this Court in the case of Union of India v. Saraswat Trading Agency & others, JT 2009 (9) SC 648, has taken a view different from the ratio
in Engineers (supra). We do not think so.
51. In Saraswat Trading (supra) the Clause which was construed by the Court as clamping a prohibition
on the grant of interest was Clause 31 and which
is quoted in paragraph 15 of the judgment at page
656 of the report and runs as follows:-
“31. No interest or damage for delay in payment – No interest or damage shall be paid to the Contractor for delay in payment of the bill or any other amount due to the contractor for any reason whatsoever. The Railway Administration will, however, make every endeavour for payment of the bills or other amount due to the contractor within a reasonable time.”
27
52. The learned Judges in Saraswat Trading (supra) in paragraph 16 held that Clause 31 is different from
Clause 13(g) which was considered in Engineers (supra). The ratio in Engineers (supra) was not questioned.
53. In the instant case also the relevant clauses,
which have been quoted above, namely, Clause 16(2)
of GCC and Clause 30 of the SCC do not contain any
prohibition on the arbitrator to grant interest.
Therefore, the High Court was not right in
interfering with the arbitrator’s award on the
matter of interest on the basis of the aforesaid
clauses. We therefore, on a strict construction
of those clauses and relying on the ratio in
Engineers (supra), find that the said clauses do not impose any bar on the arbitrator in granting
interest.
54. Reference in this connection may be made to
another Constitution Bench judgment of this Court
in the case of Executive Engineer, Dhenkanal Minor
28
Irrigation Division, Orissa and others v. N.C. Budharaj (deceased) by Lrs. and others, (2001) 2 SCC 721.
55. In N.C. Budharaj (supra), Justice Raju, speaking for the majority, considered the question of the
arbitrator’s jurisdiction and authority to grant
interest in great detail and also considered both
Indian and English cases and the ratio of the
Constitution Bench of this Court in G.C. Roy (supra).
56. In paragraph 25 of the judgment the learned Judge
summed up the position as follows:-
“...By agreeing to settle all the disputes and claims arising out of or relating to the contract between the parties through arbitration instead of having recourse to civil court to vindicate their rights the party concerned cannot be considered to have frittered away and given up any claim which otherwise it could have successfully asserted before courts and obtained relief. By agreeing to have settlement of disputes through arbitration, the party concerned must be understood to have only opted for a different forum of adjudication with less cumbersome procedure, delay and expense and not to abandon all or any of its substantive rights under the various laws in force, according to which only even the arbitrator is obliged to adjudicate the claims referred to him. As long as there is
29
nothing in the arbitration agreement to exclude the jurisdiction of the arbitrator to entertain a claim for interest on the amounts due under the contract, or any prohibition to claim interest on the amounts due and become payable under the contract, the jurisdiction of the arbitrator to consider and award interest in respect of all periods subject only to Section 29 of the Arbitration Act, 1940 and that too the powers of the court thereunder, has to be upheld.” (Emphasis supplied)
57. We are constrained to note that Hon’ble High Court
unfortunately erred in appreciating the ratio of
N.C. Budharaj (supra) in passing the impugned judgment and order.
58. In view of such consistent views taken by both the
Constitution Bench judgments, in G.C. Roy (supra) and N.C. Budharaj (supra), we are of the view that in the facts of this case, no interference is
called for with the award passed by the
arbitrator. The judgment of the High Court is,
therefore, set aside and the award is upheld. The
appeal is allowed.
59. There will be no order as to costs.
30
.......................J. (MARKANDEY KATJU)
.......................J. New Delhi (ASOK KUMAR GANGULY) December 07, 2009
31