M/S JAYABHERI PROPERTIES PVT.LTD. Vs STATE OF ANDHRA PRADESH .
Case number: C.A. No.-000052-000052 / 2008
Diary number: 29432 / 2007
Advocates: GUNTUR PRABHAKAR Vs
LAWYER S KNIT & CO
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 52 OF 2008
M/s. Jayabheri Properties Pvt. Ltd. & Ors. .. Appellants
Vs. State of Andhra Pradesh & Ors. .. Respondents
WITH CIVIL APPEAL NOS.74 OF 2008 AND 215 OF 2008
J U D G M E N T
ALTAMAS KABIR, J.
1. Civil Appeal No.52 of 2008 arising out of
SLP(C)No.19592 of 2007 filed by M/s. Jayabheri
Properties Pvt. Ltd. and others, was taken up for
1
hearing and final disposal along with Civil Appeal
Nos.74 and 215 of 2008 arising out of SLP(C)No.
19633/07 and SLP(C)D.No.29751/07 respectively.
Since all the three appeals arise out of the same
set of facts and give rise to the same set of
issues, they have been taken up together for
hearing and final disposal.
2. Two writ petitions being Writ Petition
Nos.22809 and 22810 of 2006, were filed by the
appellants herein, whereas Writ Petition No.26996
of 2006 was filed by T. Chittaiah and three others
against the State of Andhra Pradesh and, in
particular, against the Hyderabad Urban Development
Authority (hereinafter referred to as the ‘HUDA’).
The three writ petitions relate to the challenge
thrown to the acquisition of land comprised in
Survey Nos.176, 189, 190, 191, 197, 198, 199, 200,
201 and 202 of Narsingi Village and Survey Nos.292,
293 and 294 of Poppalguda Village of Rajendranagar
2
Mandal, Ranga Reddy District for the Outer Ring
Road (ORR) Project for the twin cities of Hyderabad
and Secunderabad.
3. The said project was for the purpose of
providing an Inner and Intermediate Ring Road and
an Outer Ring Road as part of the main circulation
system for traffic. In 1984, HUDA undertook a
detailed study for the development of the
Intermediate Ring Road, but there was little or no
progress in view of the growth of the city and
advent of the Information Technology industry and
various other educational and industrial projects.
In 2001, the Government of Andhra Pradesh initiated
a project known as the “ORR Project” and HUDA
engaged M/s. MECON for feasibility study.
4. The report submitted by M/s. MECON contemplated
the laying of a 109 km. 4-lane connectivity around
the city. In July, 2004, the project was re-
examined and on the recommendations made by senior
3
officers of the Government and HUDA, the project
was revised so that ORR could pass through open
areas avoiding major settlements and habitations.
The revised project was notified vide G.O.Ms.No.442
dated 19th October, 2004. The ORR alignment was
finalised in April, 2005, providing for a 159 km.
road around the twin cities and Ranga Reddy
District.
5. The final alignment comprised of Western,
Northern, Eastern and Southern sectors.
Thereafter, notifications dated 13th April, 2005 and
21st April, 2005, were issued under Section 4(1) of
the Land Acquisition Act, 1894, for acquisition of
various lands in different sectors. Since the
alignment of the Western Sector was through
Poppalguda and other villages which comprised
hillocks, tanks and lakes, representations were
made for change of the said alignment which led to
the inspection of the same by officers of the
4
technical wing of the ORR Project. It was found
that the alignment involving huge rock-cutting,
would be highly uneconomical. The proposed Trumpet
Interchange at the T-Junction point which was
incorporated at Poppalguda Junction, was found to
be affecting a water body and school building.
Accordingly, an alternative alignment was
considered by a Committee comprising senior
officials of the Government and HUDA which
inspected the alternative alignments and made
certain observations. Among the observations which
affected the parties to the present proceedings,
was observation (e), which, on the basis of a quick
survey, inter alia, provided as follows :
(i) The alignment should not affect any
water body, as it was
environmentally sensitive zone.
5
(ii) The alignment should involve minimal
rock cutting and filling, as the
terrain was uneven.
(iii) The alignment should involve minimal
bends and curves keeping the design
standards of the Outer Ring Road in
mind.
6. On the basis of the aforesaid suggestions, the
matter was assigned to NSS Associates, which
submitted its report on 15th November, 2005, with
the recommendation that the notified Western
Alignment joining Phase I at Poppalguda Village was
not advisable and an alignment passing through
Narsingi village should be worked out to lessen the
expenses for cutting through rock forming part of
the proposed alignment. After considering the
report submitted by NSS Associates, the Alignment
Committee, once again studied the entire matter and
recommended that the alignment suggested by NSS
6
Associates be accepted. One of the observations
made by the Alignment Committee with regard to the
Western Sector alignment, as suggested by NSS
Associates, is that the new alignment avoids all
water bodies in the area, which was an
environmentally sensitive area with a need to
protect all water bodies. Upon approval of the
State Government of the Report of the Alignment
Committee, a G.O.M. No.8 dated 12.12.2005 was
issued, whereby the Project Director and the
Special Collector, Land Acquisition, Outer Ring
Road Project, were permitted to notify the final
alignment of the ORR.
7. Subsequent thereto, on 13th December, 2005, a
notification was issued under Section 4(1) of the
Land Acquisition Act for the purpose of acquiring
the land belonging to the appellants situated at
Narsingi Village. Another notice of even date was
also issued seeking to acquire the lands belonging
7
to the appellants situated at Poppalguda Village.
On 12th January, 2006, objections were filed by the
appellants under Section 5-A of the Land
Acquisition Act, inter alia, contending as follows:
(a) there is a water body in the impugned
alignment in Survey No.291 of
Poppalguda Village.
(b) the change of alignment is illegal,
since the earlier alignment was
straight in shape and the impugned
alignment is taking several twists and
turns.
(c) earlier alignment was finalized upon
scientific survey and consequently
notifications were earlier issued on
21-4-2005, which was a straight
alignment.
(d) impugned alignment was finalized
without any proper survey and
verification.
8
Reference was also made to a Land Use
Certificate issued by HUDA on 16th January, 2006,
indicating that as per the approved Zonal
Development Plan, there was a notified water body
in the land comprising Survey No.291 of Poppalguda.
The objections filed under Section 5-A were fixed
for consideration on 17th July, 2006, before the
Special Deputy Collector and on 21st July, 2006, the
same were rejected and on 29th July, 2006, a Draft
Declaration was published under Section 6 of the
Land Acquisition Act, 1894.
8. In the meantime, on the complaints made on
behalf of the appellants, a CBI inquiry was
directed by the Central Government in respect of 5
projects undertaken by the Government, including
the ORR Project and the HUDA Township at Kokapet.
9. After considering the objections filed on
behalf of some of the land owners, a draft
9
declaration dated 29.7.2006 was issued under
Section 6 of the aforesaid Act and the same was
published in the Andhra Pradesh Gazette Extra-
ordinary of the same date. By virtue of the said
draft declaration under Section 6 of the Land
Acquisition Act, the Government of Andhra Pradesh
declared that the land specified in the schedule to
the draft declaration situated at Narsingi village
of Rajendranagar Mandal, Ranga Reddy District,
measuring 23 acres and 23 guntas was needed for a
public purpose, namely, for formation of the Outer
Ring Road. The same was challenged by the
Appellants herein by way of a Writ Petition on 24th
October, 2006, on several grounds. One of the
grounds taken was that the earlier notifications
under Sections 4 and 6 of the Land Acquisition Act
had been issued keeping in view the scientific
alignment of the road and suitability of the land
proposed to be acquired and more importantly that
the proposed acquisition did not cover the land of
10
Narsingi village. Perhaps, the most important
ground was that the land covered by Survey No.291
was shown to be a water body and Survey No.292 was
a green belt touching a water body.
10. It was also urged on behalf of the Appellants
that the alignment of the road had been altered
with mala fide intent to benefit certain people
belonging to the ruling party in power. It was also
claimed that the revised alignment would convert
the straight road into a serpentine road with the
sole object of ensuring that the Outer Ring Road
passed in a manner which boosted the value of the
land held by ruling party leaders, their well-
wishers and kith and kin.
11. Appearing for the appellants, Mr. Bhaskar
Gupta, learned Senior Advocate, submitted that
although one of the reasons given for alteration of
the alignment was that water bodies on the said
alignment would be disturbed, in fact, the
11
alternative alignment would affect a larger number
of existing water bodies and destroy particularly
Survey Nos.291, 298, 299 and 300. It was urged
that the objections filed by the appellants under
Section 5-A of the Land Acquisition Act, 1894,
which gives a very valuable right to the appellants
and had been given almost the same status as a
fundamental right by this Court, had been dealt
with perfunctorily revealing non-application of
mind as the above-mentioned survey numbers had, in
fact, been identified by the local authorities,
including HUDA, to be water bodies. Mr. Gupta
pointed out from the Land Use Information given by
HUDA on 16th January, 2006, that Survey No.291 was a
water body, Survey No.292 was used for wet and dry
agriculture and was touching a water body and
Survey Nos.293 and 294 were also used for wet and
dry agriculture.
12
12. He contended that apart from the above, even in
GOM No.647 dated 3rd October, 2001, prescribing
registration of water bodies, Survey No.291 under
the entries relating to Poppalguda Village was
shown to be “Kunta”, meaning a tank.
13. Mr. Gupta submitted that in a letter dated 23rd
December, 2006, the Executive Engineer, Irrigation
Department, informed the appellants herein
regarding the existence of water bodies in Survey
Nos.291, 298, 299 and 300 of Poppalguda Village.
Mr. Gupta submitted that the concerned Executive
Engineer was suspended from service for giving a
true picture of the terrain to the appellants. It
was submitted that the report of the Central Water
Commission dated 27th November, 2007, which had been
submitted to this Court after inspection of Survey
Nos.291, 298, 299 and 300 on 24th November, 2007,
did not give a correct picture of the plots in
question, since the inspection was conducted during
13
the month of November which is a dry season in the
area when most of the tanks and water bodies tend
to dry up. Mr. Gupta submitted that although a
great deal of reliance has been placed by the
respondents on a letter written by another
Executive Engineer also dated 23rd December, 2006,
saying that there were no water bodies at all, such
a statement had to be incorrect in view of the
report of the Central Water Commission which also
indicated that there were water bodies, of which
some were dry. Mr. Gupta submitted that, in any
event, water bodies were required to be preserved
and could not be converted to other use, even if it
was for the public good.
14. In support of his aforesaid submissions, Mr.
Gupta referred to and relied upon the decision of
this Court in Intellectuals Forum, Tirupathi vs.
State of A.P. & Ors. [(2006) 3 SCC 549], wherein
the need for balancing water and land resources for
14
urban developmental needs was considered and it was
observed that the responsibility of the State to
protect the environment is now a well accepted
notion in all countries. Reference was also made
to a decision of this Court in Hinch Lal Tiwari vs.
Kamala Devi & Ors. [(2001) 6 SCC 496] and on a
decision of the Calcutta High Court in PUBLIC vs.
State of West Bengal [AIR 1993 Cal. 215], wherein
similar views have been expressed. Various other
decisions were also cited in this regard, which
will only have a multiplying effect to the views
already expressed in the earlier judgments.
15. On the question of the importance of Section
5-A, Mr. Gupta referred to several decisions of
this Court, such as : (i) Munshi Singh & Ors. vs.
Union of India [(1973) 2 SCC 337]; (ii) Union of
India & Ors. vs. Mukesh Hans [(2004) 8 SCC 14];
(iii) Hindustan Petroleum Corpn. Ltd. vs. Darius
Shapur Chenai & Ors. [(2005) 7 SCC 627]; and (iv)
15
Ram Krishan Mahajan vs. Union Territory of
Chandigarh & Ors. [(2007) 6 SCC 634], wherein the
importance of Section 5-A and the very valuable
right given to an individual, whose land is being
sought to be taken away, to raise an objection, has
been emphatically demonstrated.
16. Mr. Gupta submitted that since a very valuable
right to object to the acquisition of land has been
given to a person whose land was being sought to be
taken away, it was the statutory duty of the
Collector to consider the suitability of the land,
hear objections, if any, filed by any of the
persons affected, and, thereafter, to make his
recommendations on the objections so raised and
forward the same to the Government for further
action. Instead, the Collector appeared to be
helpless since a decision had already been taken by
the Government even before the publication of the
Section 4 notification. The report of the Collector
16
dated 23rd December, 1996, was nothing but an empty
formality.
17. Mr. Gupta also urged that the High Court, while
considering the two contradictory letters dated 23rd
December, 2006, written by two Executive Engineers,
erroneously chose to reject the letter which had
been relied upon by the Appellants merely on the
ground that according to the Gazette Notification
Survey No.291 falls in Narsingi Village, although,
the letters say that the same falls in Poppalguda
Village. Mr. Gupta submitted that the error
committed by the High Court would be evident from
the project description submitted by M/s NSS
Associates along with its communication dated 15th
November, 2005.
18. Mr. Gupta urged that the entire approach of the
High Court was erroneous and failed to take into
consideration the facts relating to the topography
17
of the land involving the changed alignment of the
ring road.
19. Mr. Altaf Ahmed, Senior Advocate, who appeared
for the Appellants in Civil Appeal Nos.74 of 2008
and 215 of 2008, reiterated Mr. Gupta’s submissions
relating to denial of a proper opportunity to the
Appellants (land owners) under Section 5-A of the
Land Acquisition Act, 1894. Mr. Ahmed submitted
that while the public purpose of the project could
not be denied, what we are called upon to consider
is regarding the viability of the land included in
the second alignment since it passed through and
affected some of the water bodies in the area. Mr.
Ahmed referred to the report submitted by the
Committee comprised of the Principal Secretary,
Infrastructure and Investment Department (IIT),
Managing Director, INCAP and Vice-Chairman,
Hyderabad Urban Development Authority (HUDA) and
other officers of HUDA, the Chief Engineer and
18
Special Collector, ORR, wherein in paragraph (e)
the Committee was of the view that the data
available was insufficient and a quick survey
should be made, inter alia, to ascertain that the
alignment did not affect any water body since the
area was an environmentally sensitive zone.
20. Reference was also made to the final decision
of the Committee which was based on the
recommendations of the Pollution Control Board in
which it was stated that the alignment avoids all
water bodies in the area, which statement was
incorrect. Having regard to the admission
subsequently made by HUDA in the Land Use
Certificate issued on 16.1.2006 indicating that
plot No.300, which falls squarely on the new
alignment, was a water body together with plot
No.291.
21. Mr. Ahmed urged that based on an incorrect
appreciation of the topography relating to the
19
second alignment, a decision had been taken to act
on the basis of the new alignment, which, in fact,
could not have been proceeded with for the same
reason as was given for abandoning the first
alignment. Mr. Ahmed repeated Mr. Gupta’s
submission regarding the two certificates dated 12th
August, 2009, which showed the existence of water
bodies in plot Nos.298, 299 and 300. He contended
that the creation of the second alignment was made
only to suit certain individuals who had an
interest in the lands which fell within the first
alignment.
22. Mr. Ahmed submitted that the decision taken to
approve the second alignment was motivated and was
contrary to the stand taken while disapproving the
first alignment.
23. Appearing for the Hyderabad Urban Development
Authority (HUDA), Mr. K.K. Venugopal, Senior
Advocate, referred to the report of the Alignment
20
Committee, on which strong reliance was placed by
him. Mr. Venugopal submitted that only after
examining the reports submitted by M/s NSS
Associates and M/s. Aarvee Associates that the
Alignment Committee set up by the Government
recommended change in the alignment of the Outer
Ring Road in the Poppalguda and Narsingi villages
in the Western Sector. Mr. Venugopal submitted
that proper care had been taken to avoid all major
structures, water bodies and habitations. Learned
counsel submitted that the change from the first
alignment to the second alignment was necessitated
by the fact that a large portion of the alignment
was comprised of hilly terrain which would involve
a considerable amount of rock cutting and that in
order to avoid the said hillocks at Poppalguda the
second alignment was proposed through Narsingi
village.
21
24. Mr. Venugopal submitted that a major portion of
the construction work in respect of the Western
Sector of the Outer Ring Road had been completed
and only the portion comprising about a two-
kilometer stretch, which is the subject matter of
the present appeals, was yet to be completed.
25. In this connection, Mr. Venugopal also referred
to the report of the visit of the Expert Central
Team of the Central Water Commission for an on the
spot study and to verify as to whether Survey
Nos.291, 298, 299 and 300 of Poppalguda Village
were, in fact, water bodies. The report of the
Central Water Commission indicated that none of the
three survey numbers, apart from Survey No.300,
disclosed the existence of a water body. On the
other hand, it was categorically indicated that
there was no water body existing as on the date of
inspection in plot Nos.291, 298 and 299.
22
26. Apart from the above, Mr. Venugopal submitted
that the possession of the land had already been
taken under Section 16 of the Land Acquisition Act,
1894, and as indicated hereinbefore, the major
portion of the construction work of the Outer Ring
Road had been completed and only the two ends of
the construction work had to be brought together in
order to complete the project. Mr. Venugopal
submitted that in respect of projects of national
importance, the balance of convenience and
inconvenience of the majority of the citizens would
have to be considered as opposed to private
interests. He referred to the decision of this
Court in Delhi Admn. vs. Gurdip Singh Uban [(2000)
7 SCC 296], wherein it was held that when several
plots of land are involved in an acquisition, the
objection of several individual plot owners could
not be entertained even under Section 5-A of the
1894 Act, particularly, because when several LA
Collectors were dealing with different segments of
23
the acquired lands, it would not be possible for
one of such Collectors to take a decision with
regard to the operation of the integrated project.
27. Mr. Venugopal ended on the note that since the
inconvenience that may be caused to a few
individual plot owners could not outweigh the
interest of the public, the appeal filed by M/s
Jayabheri Properties Pvt. Ltd. & others was liable
to be dismissed.
28. Mr. Anoop G. Chaudhari, Senior Advocate, who
appeared for the State of Andhra Pradesh, endorsed
the submissions made by Mr. Venugopal and added
that the Appellants could not be considered to be
“a person interested” within the meaning of Section
3(b) of the 1894 Act. He urged that the Collector
had duly applied his mind to the fact situation and
the decision ultimately taken did not merit any
interference.
24
29. Mr. A.K. Ganguli, Senior Advocate, appeared on
behalf of Mr. Purshottam Reddy, who had made an
application for intervention in the proceedings and
submitted that the intervenor who was the Director
of the Centre for Environmental Studies, Osmania
University, had challenged the change of alignment
on account of the fact that the integrated
hydrological system which was prevailing in the
area would be destroyed if the Western Sector of
the project was allowed to be completed.
30. We have taken pains to set out the fact
situation in some detail since a decision in this
matter depends on the fact situation leading to the
change of alignment of the Western Sector of the
Outer Ring Road Project in the twin cities of
Hyderabad and Secunderabad in Andhra Pradesh. From
the site plans of the area submitted by the
parties, it is clear that both the two alignments
touch and disturb existing water bodies, which was
25
the main ground for the change of alignment in the
first place. From the reports submitted by the
various local authorities, it is, however, clear
that in order to proceed according to the first
alignment, the respondents would have to cut
through a great deal of rock, which is not so as
far as the second alignment is concerned. It is no
doubt true that in terms of the environmental
policies of the State Government, the Western
Sector of the project has been shown to be a highly
ecologically sensitive zone, but we have no choice
but to consider the viability of either of the two
alignments for the purpose of the connectivity of
the Outer Ring Road and while doing so we have to
balance the aforesaid factor and also the interest
of the private land owners as against the interest
of the public. Apart from the above, we have also
to take into consideration the factors that the
major stretch of the Outer Ring Road is said to
have been completed, even in the Western Sector,
26
and only a small stretch involving the plots of the
appellants, is yet to be completed.
31. There is no doubt that in the facts of this
case the public interest will out-weigh the
interest of the individual plot holders. The only
consideration is with regard to the preservation of
the water bodies which are yet untouched, such as,
plot No. 300 mentioned in the report of the Central
Water Commission and also in the letter written by
the Executive Engineer on 23rd December, 2006. The
arguments advanced on behalf of the appellants have
their positive value but looking at the problem
holistically, we are of the view that their
objections to the use of the lands for the purpose
of the Outer Ring Road have to give way to the
construction of the said road. However, while
constructing the portion of the road affecting the
plots in question, maximum care has to be taken by
the concerned authorities to preserve as far as
27
possible the water bodies over which the road is to
be constructed.
32. The submissions advanced on behalf of the
appellants alleging that adequate opportunity had
not been given to them under Section 5A of the Land
Acquisition Act, 1894, to voice their objections,
is without substance as the objections filed
were duly considered by the Special Deputy
Collector and rejected by his order dated 21st July,
2006.
33. Although, we are not inclined to interfere
with the orders impugned in the three appeals or to
entertain the two writ petitions, we dispose of the
same with a direction to the authorities to take
all possible steps to ensure that the water bodies
in the area are not unduly affected and are
preserved to the maximum extent possible during the
construction of the remaining portion of the Outer
Ring Road on the Western Sector.
28
34. The Interlocutory Applications filed for
intervention are also disposed of by this order.
…………………………………………J. (ALTAMAS KABIR)
…………………………………………J. (CYRIAC JOSEPH)
New Delhi Dated:05.04.2010
29