M/S ELECTRICAL MANUFACTURING CO.LTD. Vs M/S POWER GRID CORP.OF INDIA LD.
Bench: ALTAMAS KABIR,MARKANDEY KATJU, , ,
Case number: C.A. No.-000801-000801 / 2009
Diary number: 15732 / 2008
Advocates: RABINDRA SINGH Vs
SHARMILA UPADHYAY
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 801 OF 2009 [Arising out of Special Leave Petition (Civil) No.14858 of 2008]
M/s. Electrical Manufacturing Company Ltd. .. Appellant
-versus-
M/s. Power Grid Corporation of India Ltd. & Anr. .. Respondents
J U D G M E N T
MARKANDEY KATJU, J.
1. Leave granted.
2. This appeal has been filed against the impugned judgment dated
26.5.2008 of the Delhi High Court in Writ Petition (Civil) No.3668 of 2008.
1
3. Heard Shri Sudhir Chandra, learned senior counsel for the appellant,
and Shri K.K. Venugopal, learned senior counsel for the respondent and
perused the record.
4. The appellant Electrical Manufacturing Company Ltd.,
(hereinafter as `EMC’) has alleged that it is a leading modern power system
company in India and is the first ISO 9001 certified company in India in
Transmission Line Projects. It was established in 1951 and carries out such
projects in India as well as overseas. It filed a writ petition in the Delhi
High Court with the following prayer :-
“To quash the decision taken by the Board of Directors in its meeting held on 06.5.2008 with respect to not awarding of contract to the petitioner with respect to Package A1, A2 & A7 in spite of the fact that it is L1, technically qualified as per the requirement and more so its bid is Rs.16.34 crores less than L2 bidders.”
5. The respondent no.1, the Power Grid Corporation of India Ltd.
((hereinafter as `PGCIL’) is a Public Sector Undertaking of the Government
of India working under the Ministry of Power. The petitioner has been
carrying out the contract of respondent no.1 for a long time.
2
6. On 5.11.2007, a Notice inviting tender with respect to Package A1
and A2 was made by respondent no.1 PGCIL. On 8.11.2007, Notice
inviting tender with respect to Package A7 was made by respondent no.1.
These tenders were for setting up electrical transmission lines.
7. On 8.1.2008 and 9.1.2008, bids were opened for the above mentioned
packages, respectively. In both the petitioner was declared the Lowest
Quoted Bidder (L1).
8. On 16.4.2008 the petitioner made representations to the respondent
no.1 with respect to Package A1, A2 and A7, explaining as to how the
petitioner was fully qualified and met the requirements of technical
experience stipulated in Clause 1.1 of Annexure `A’ of Special Condition of
Contract.
9. On 6.5.2008, the respondent no.1, decided not to award the contract
for the above mentioned packages to the petitioner as it was of the opinion
that the appellant did not have the requisite technical experience as set out
in Clause 1.1 of Annexure `A’ of the Special Condition of Contract.
3
10. The appellant has alleged that the above refusal by respondent no.1 to
award the contract for the above mentioned packages was arbitrary and
illegal since the appellant’s bid was the lowest among all the bidders.
11. Shri Sudhir Chandra, learned senior counsel for the appellant has
submitted that the appellant has been denied the contract in question on an
erroneous interpretation of Clause 1.1 of Annexure `A’ of the Special
Conditions of Contract. The aforesaid Clause 1.1 states :
“1.1 Technical Experience
The bidder shall have satisfactorily completed as a prime contractor or as a sub-contractor or as a member in a Joint Venture, 345/400 KV Double Circuit or higher voltage class transmission line(s) within the last seven (7) years as on date of bid opening. The bidder’s experience should include the following :
(i) The bidder should have surveyed, optimized tower locations, erected and strung with tension stringing equipment, not less than following cumulative route length of transmission lines of 345/400 KV Double Circuit or higher voltage class involving bundle conductor.
Package – A7 : 100 Kms
Package – A8 : 100 Kms”
4
12. Learned counsel for the appellant submitted that the appellant fully
satisfied the requirements mentioned in Clause 1.1 namely that the
petitioner has surveyed, optimized tower locations, erected and strung with
tension stringing equipment, not less than following cumulative route length
of transmission lines of 345/400 KV Double Circuit or higher voltage class
involving bundle conductor, which in so far as the petitioner is concerned is
100 Kms. for package A1 and A7 and 200 Kms. for package A8. Hence
learned counsel submits that the appellant should have been given the
contract in question.
13. On the other hand Shri K.K. Venugopal, learned senior counsel for
respondent submitted that sub-clause (i) of Clause 1.1 has to be read along
with the main clause 1.1 which stipulates that the bidder should have
satisfactorily completed the requisite length of 100 Kms. He submitted that
the petitioner has only satisfactorily completed 83 Kms. of transmission line
as on 9.1.2008 and therefore, did not fulfill the technical experience
required by Clause 1.1.
14. The dispute thus in this case is whether the appellant has the requisite
technical experience mentioned in Clause 1.1 of the Special Conditions of
Contract.
5
15. Shri K.K. Venugopal, learned senior counsel for respondent
submitted that the appellant has satisfactorily completed only 83 Kms. of
transmission lines as on the date of the opening i.e. 8/9.1.2008 instead of the
requisite 100 Kms. He submitted that the appellant had in addition laid
various incomplete transmissions lines, but these cannot be added to
the lines
satisfactorily completed because they are incomplete. The chart showing
the work done by the appellant is as follows:
Transmission Line
Extent completed by petitioner as on 8/9.1.2008
Total extent of the line in question
Lines Satisfactorily Completed by petitioner
Meerut- Mandola
60 km (on 29.9.03) 60 km 60 km
Bhadrawati- Chandrapur
23 km (on 13.4.06) 23 km 23 km
Trivenveli- Udmalpet
134 km (on 8/9.1.08; 2 km incomplete)
136 km
TAPP- Kankaroli
87 km (on 8/9.1.08; 10.3 km incomplete)
97.3 km
Total 304 km 83 km
6
16. A perusal of the above chart shows that the appellant has only
satisfactorily completed 83 Kms. of transmissions lines. The line
Trivenveli-Udmalet in Tamil Nadu was incomplete because only 134 Kms.
out of the total extent of the line of 136 Kms. had been completed by the
appellant. Hence this transmission line could not be treated to be
satisfactorily completed. Similarly the line Tapp-Kankaroli was also
incomplete as it was only laid for 87 Kms. but the entire line had to be 97.3
Kms.
17. Shri Sudhir Chandra, learned senior counsel for the appellant has
submitted that the view taken by the High Court that satisfactorily
completing the line means commissioning the line is not correct. We are of
the opinion that even if satisfactory completion may not necessary mean
commissioning of the line but it certainly means completion of the entire
length of the line and thereafter testing the line to find out whether it is
functioning satisfactorily. Without testing it how can one be sure that it has
been completed satisfactorily.
18. For instance, if an electrical line is laid inside a person’s house, the
only way to find out whether the electrical line has been laid satisfactorily is
to find out by pressing the switch and seeing whether the bulb in the house
7
is lighted or the fan starts running. Merely putting wires dangling inside the
house but which do not light the bulb or turn the fan cannot be said to be
satisfactory completion of the electrical line.
19. In the present case, as can be seen from the chart set out above the
appellant has not completed the lines from Trivenveli to Udmalet nor from
Tapp to Kankaroli. Unless the entire line is laid and is found to be
functioning satisfactorily, it cannot be said that there was satisfactory
completion of the line.
20. As regards the interpretation of Clause 1.1 we cannot agree with Shri
Sudhir Chandra that the words `Satisfactorily Completed’ would not govern
sub clause (i) of Clause 1.1. A fair reading of the entire Clause 1.1 along
with sub clause (i) clearly indicates that the requisite technical experience
requires satisfactorily completion of the requisite length of the line. Sub
clause (i) is a part of Clause 1.1 and hence mere surveyance, optimizing
tower locations, erecting and stringing with tension stringing equipment,
etc. is not sufficient to give the requisite technical experience to the bidder
unless such work was satisfactorily completed, which means that it was
tested and found to be functioning satisfactorily.
8
21. If the bidder has surveyed, optimized tower locations, erected and
strung with tension stringing equipment, the requisite length of transmission
lines, but these transmission lines do not function, surely it cannot be said
there was satisfactory completion of these transmission lines. In our
opinion the expression `Satisfactory Completion’ govern sub clause (i) of
Clause 1.1 also. Hence mere surveying, optimizing tower locations,
erecting and stringing with tension stringing equipment the requisite length
of transmission lines will not be enough to give the necessary technical
experience because it is possible that even after doing the above work the
transmission lines may not function. Unless after doing the above works the
line is tested and found to be successfully functioning it surely cannot be
said that there was satisfactory completion of the transmission lines.
22. Apart from the above, completion of a part of the line will be of no
avail and the entire line from one location to another has to be completed
before there can be said to be satisfactory completion of the line.
Completion of part of the line has to be totally ignored as a line is one
integral whole and cannot be divided into sections.
23. Thus there is no force in this appeal and it is dismissed. No costs.
9
…………………………J. (Altamas Kabir)
……………………… …J.
(Markandey Katju)
New Delhi; February 09, 2009
10