18 May 2007
Supreme Court
Download

M/S. DELTA MECHCONS (INDIA) LTD. Vs M/S. MARUBENI CORPN.

Bench: P.K. BALASUBRAMANYAN
Case number: ARBIT.CASE(C) No.-000011-000011 / 2006
Diary number: 6184 / 2006


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4  

CASE NO.: Arbitration Petition  11 of 2006

PETITIONER: M/s Delta Mechcons (India) Ltd

RESPONDENT: M/s Marubeni Corporation

DATE OF JUDGMENT: 18/05/2007

BENCH: P.K. BALASUBRAMANYAN

JUDGMENT: JUDGMENT

O R D E R ARBITRATION PETITION NO.11 OF 2006           The respondent took up the project of construction of a thermal  power plant at Ramagundam in Karimnagar District of the State of Andhra  Pradesh.  It entered into four sub-contracts with the petitioner relating to that  work.   The general conditions of sub-contracts were to be part of the four  separate contracts.  The sub-contracts were terminated on 25.7.2001 with  effect from 7.8.2001.  It appears that there were subsequent discussions  between the parties and on the basis of ascertainment of the sums due to the  petitioner the same were paid  by the respondent and the petitioner in return  gave in writing that it had received full and final payment from the  respondent in terms of the settlement between the two and also a certificate  that all payments against the said four sub-contracts  have been made by the  respondent to the petitioner and received by the petitioner and that no bills  are pending with the respondent for settlement.   After the matters rested on  this basis, the petitioner made a claim in respect of the four sub-contracts.   The petitioner also named an arbitrator and called upon the respondent to  name an arbitrator in terms of the arbitration agreement.  The respondent  disputed the claims of the petitioner and pleaded that there was no subsisting  claim for the petitioner based on any of the four sub-contracts.  Even then  without prejudice to its contentions the respondent also named an arbitrator.   In terms of the arbitration agreement, the two nominated arbitrators had  together to name the Chairman of the Arbitral Tribunal or the presiding  arbitrator.  The nominated arbitrators failed to do so.

2.              Meanwhile the petitioner had also moved the concerned District  Court under Section 9 of the Arbitration and Conciliation Act seeking what  it called interim protection pending an arbitration.  Four separate  applications were filed.  The applications were dismissed by the District  Court.  The petitioner filed appeals in the High Court of Gujarat.  The High  Court disposed of the appeals recording the following: "After having argued at some length, learned counsel on both  sides agreed and submitted that the main dispute between the  parties is the subject-matter of separate arbitration proceedings  and at this stage it may not be necessary or advisable to invite  observations of this Court as regards the legality and validity of  any of the claims or liability of any of the parties to satisfy such  claims.  It was, therefore, jointly submitted that all the appeals  may be disposed as withdrawn with the observation that the  parties may put forward their case before the arbitral tribunal,  which may decide the dispute referred to it without being  influenced by any observation made in the impugned judgment  as also the fact that these appeals were not pressed for any  orders on merits."

3.              The relevant clauses relating to arbitration, as contained in the

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4  

agreement between the parties are as under: "21.    SETTLEMENT OF DISPUTES If at any time any question, dispute, or difference arise between  the Contractor and the Subcontractor in connection with or  arising out of the Subcontract or the Subcontract Works, either  party shall give to the other notice in writing specifying the  nature of such question, dispute or difference and the point at  issue, and the parties shall discuss the matter and shall  endeavour to reach an amicable settlement.  In case parties fail  to reach an amicable solution within sixty (60) days after the  date of the said notice, the matter shall be referred to an  arbitration in accordance with Clause 22 hereof.

22.     ARBITRATION 22.1    Any dispute which could not be resolved between the  parties in accordance with clause 21 hereof shall be settled  exclusively by arbitration conducted in accordance with the  Rules of Concilation and Arbitration of the International  Chamber of Commerce.  Each arbitral tribunal shall consist of  three arbitrators.  The Contractor and the sub-contractor shall  each appoint one arbitrator and the two arbitrators thus  appointed shall jointly agree upon the third arbitrator to act as  chairman.  If such agreement cannot be reached within thirty  (30) days from the date of appointment of the later member, the  third arbitrator shall be appointed by the International Chamber  of Commerce.  The said Chairman shall not be the same  nationality of either party to the sub-contract.

22.2    The arbitration shall be conducted in India 22.3    The language to be used on all written documents  provided in each arbitration shall be English.

22.4            The decision of the arbitral tribunal shall be  considered final and binding upon both parties and shall not be  subject to any appeal whatsoever.

22.5    The cost and expenses of arbitration shall be borne by the  party based on the award of the arbitral tribunal.

22.6    Performance of the sub-contract work shall continue  during the arbitration proceedings notwithstanding the  existence of any dispute, controversy or question."

4.              When the named arbitrators failed to nominate a presiding  arbitrator, the petitioner approached the International Chamber of Commerce  (for short ICC) with a request that the presiding arbitrator may be nominated  by the ICC.   There was some correspondence between the ICC and the  parties and ultimately the ICC informed the petitioner that the ICC had  decided not to appoint a Chairman of the arbitral tribunal pursuant to the  rules of ICC as appointing authority.  It was in that context that the petitioner  approached this Court with this application under Section 11 of the  Arbitration and Conciliation Act. 5.              Learned counsel for the petitioner submitted that going by the  arbitration agreement the petitioner and the respondent have nominated their  arbitrators but the nominee arbitrators had failed to appoint a presiding  arbitrator in terms thereof and in that context, as per the agreement, the  petitioner had approached the ICC for nominating a presiding arbitrator but  the ICC had refused the request without assigning any reason.   In that  context it was submitted that the jurisdiction of the Chief Justice of India ---  being an international arbitration --- under the Act was attracted and it was  just and necessary to appoint a presiding arbitrator in terms of Section 11 of  the Act.  This argument is controverted by the respondent, in addition to  pleading on the merits that there was no subsisting claim for the petitioner  and that the arbitration is barred by limitation, by contending that the  petitioner had not complied with the procedure set down by the ICC before

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4  

calling upon ICC to name the presiding arbitrator and in that context the  jurisdiction of the Chief Justice of India under Section 11 of the Act is not  attracted.  It was also contended that there were four sub-contracts and a  single application for the appointment of a presiding arbitrator in respect of  the disputes relating to four different contracts was not maintainable.    It  was for the petitioner to have agreed to follow the ICC Rules and to comply  with those rules so as to get an arbitrator appointed by the ICC in terms of  their Rules and the petitioner having failed to do so, the application filed by  the petitioner had only to be rejected.  The arbitration agreement clearly  provides that disputes between the parties are to be settled exclusively by an  arbitration conducted in accordance with the Rules of Conciliation and  Arbitration of the International Chamber of Commerce.  It is hence  submitted that the petitioner not having adhered to the said Rules, ICC was  not justified in refusing to act.   

6.              It is true that there is a clause that the arbitration is to be  conducted in terms of the Conciliation and Arbitration Rules of ICC.  But it  also provides that the arbitral tribunal shall consist of three arbitrators.  The  contractor and the sub-contractor had to each appoint one arbitrator and the  two arbitrators thus appointed, should jointly agree upon the third arbitrator  as Chairman.  If such agreement be not reached within the time provided, the  third arbitrator shall be appointed by the ICC.  The Chairman was not to be  of the same nationality of either party to the sub-contract.  The arbitration  agreement has to be read as a whole to know its purport.

7.              It is open to the parties while entering into an arbitration  agreement to provide as to how the arbitral tribunal should be constituted.  It  is also open to them to provide for the rules to be followed.  As I read the  arbitration agreement, I find that the parties had reserved unto themselves  the right to nominate an arbitrator each stipulating that the two arbitrators so  nominated, should agree upon the third arbitrator to act as the Chairman.  In  other words, the parties by their agreement have left it to the two arbitrators  to appoint a third arbitrator to act as the Chairman.  They have also agreed  that in case of failure of the two arbitrators to appoint the third arbitrator, the  third arbitrator was to be appointed by ICC.  The parties had also provided  that the arbitration should be conducted in accordance with the Rules of  Conciliation and Arbitration of the International Chamber of Commerce.

8.              It was the contention of learned senior counsel for the  respondent that once the machinery contemplated by the parties failed, the  petitioner could only go by way of the Rules of Conciliation and Arbitration  of the International Chamber of Commerce and the petitioner not having  proceeded in terms of the said Rules, the ICC was justified in not appointing  a presiding arbitrator and in that context no cause of action has arisen for the  petitioner for approaching this Court.  As I read the arbitration agreement it  consists of two parts.  Firstly, the parties have agreed that the arbitration  should be conducted in accordance with the Rules of Conciliation and  Arbitration of the International Chamber of Commerce.  Having agreed to  that, the parties also have agreed on the mode of creating the arbitral  tribunal.  This is by the parties nominating one arbitrator each and the  nominated arbitrators appointing the Chairman of the tribunal or the  presiding arbitrator.  They have contemplated the failure of the nominee  arbitrators to name the Chairman or the presiding arbitrator and they have  provided the means for supplying that omission.  They have agreed that in  that case, the presiding arbitrator should be got appointed by the ICC.    According to me, the agreement to follow the Rules of ICC in the conduct of  arbitration proceedings is different from the agreement regarding  appointment of the arbitral tribunal.  There is no obligation on the parties to  undertake before the ICC, to have the arbitration in accordance with its  procedure and Rules including even the constitution of the arbitral tribunal,  for the ICC to act to appoint the Chairman of the arbitral tribunal.  In fact,  except stating that it refuses to appoint a presiding arbitrator, the ICC has not  given any specific reason for refusing to do so.  Nor am I in agreement with  the submission of learned senior counsel for the respondent that unless the  parties surrender their rights of creating the arbitral tribunal to the ICC in

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4  

toto the ICC would be justified in refusing to name the presiding arbitrator.   After all, the process of settlement of disputes through arbitration is a  process of settlement extra cursum curiae and the parties are at liberty to  choose their judge and in the case on hand, the parties have provided the  manner of constituting the tribunal.  Therefore, no invalidity is attached to  their agreement.  They had agreed to approach ICC in case the nominated  arbitrators failed to name the Chairman.  One of the parties had moved ICC  to supply the omission in terms of the arbitration agreement.  The ICC for its  own reasons has filed to act.  I have, therefore, come to the conclusion that  the named arbitrators have failed to nominate a presiding arbitrator in terms  of the agreement and in that respect the ICC has not supplied the vacancy  approached in terms of the agreement.  In that context the procedure agreed  upon by the parties to constitute the arbitration tribunal has broken down  justifying the approach of the petitioner to the Chief Justice of India for the  appointment of a Chairman for the arbitral tribunal or the presiding  arbitrator.

9.              I do not see much merit in the contention of learned senior  counsel for the respondent that there should have been four separate  applications for appointment of the presiding arbitrators since four sub- contracts were involved.  Even assuming that the contention has merit, I  reject it as being too technical.

10.             There was not much argument before me on the merits  concerning non-subsistence of any further claim for the petitioner and the  request being barred by limitation.  The parties proceeded on the basis that  those were questions for the arbitral tribunal to decide.  This might have  been so particularly in the context of the stand adopted by them in the High  Court of Gujarat in the appeals arising from the orders of the District Court  in the applications under Section 9 of the Act.  These questions have tobe  decided by the arbitral tribunal, in the circumstances of this case.

11.             As per the arbitration agreement the Chairman of the arbitral  tribunal has to be of a nationality different from the nationality of the  contracting parties.  Learned counsel for the petitioner contended that since  the arbitrator was being appointed by the Chief Justice of India or his  nominee in terms of Section 11 of the Act, this restriction would not apply  and I was free to appoint anyone as Chairman or the presiding arbitrator.  I  am not in a position to agree.  In the light of my reasoning above, it is  obvious that this part of the agreement between the parties must also be  given effect to.  Therefore, this is a case where I have to appoint a Chairman  of the arbitral tribunal who is of a nationality different from the nationality  of either of the parties.  Suffice it to say that for the moment I hold that my  jurisdiction to name a Chairman of the arbitral tribunal has rightly been  invoked and that a Chairman of the arbitral tribunal has to be appointed by  me.

12.             To enable me to name the Chairman, I direct, the parties either  to submit an agreed name with the consent of that person or in case they are  not able to agree, submit two names each with the consent of the nominees,  for being considered for appointment as the Chairman of the arbitral  tribunal.  The parties are, therefore, directed to file either a joint statement or  separate statements in writing indicating the names as directed above on or  before the 10th of July, 2007 and the matter will be posted for further orders  on 13th July, 2007.