M/S.ANGEL BABY PRODUCTS PVT.LTD. Vs NEW OKHLA INDUST.DEV.AUTH. .
Bench: ALTAMAS KABIR,A.K. PATNAIK, , ,
Case number: SLP(C) No.-010940-010940 / 2008
Diary number: 11941 / 2008
Advocates: Vs
RAVINDRA KUMAR
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITION (CIVIL) NO.10940 OF 2008
M/S. ANGEL BABY PRODUCTS PVT. LTD. … PETITIONER VERSUS
NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY & ORS. … RESPONDENT
J U D G M E N T
ALTAMAS KABIR, J.
1. In this Special Leave Petition, the Petitioner
has challenged the decision of the Allahabad High
Court dismissing Writ Petition No.16819 of 2003,
filed by one Hira Lal Gupta and another praying for
quashing of the notices dated 1.5.2002, 25.7.2002,
6.9.2002 and 22.3.2003 sent by the authorities of
The New Okhla Industrial Development Authority,
hereinafter referred to as ‘NOIDA’, imposing
penalty against the writ petitioners for failing to
get the lease deed for commercial plot no.1/1-A,
Sector 27, NOIDA, executed within the stipulated
period of 120 days from the date of allotment of
the plot. The said plot measuring 2970 sq. meters
was initially allotted to the Writ Petitioner No.1,
Hira Lal Gupta, at the rate of Rs.15,552/- per sq.
meter. Later on, a revised allotment order was
issued to Shri Gupta reducing the area of the plot
from 2970 sq. meters to 2590 sq. meters and the
consideration for allotment of the plot was
proportionately reduced. Subsequently, disputes
arose in regard to an irrigation drain which
existed on a portion of the said plot, although,
the existence thereof was not indicated in the
brochure published by NOIDA. According to the Writ
Petitioners, since the said problem was not
2
attended to, the lease deed could not be submitted
for execution within the prescribed period of 120
days which attracted imposition of penalty.
2. On 24th March, 2002, the Petitioners made a
representation to the Chief Executive Officer,
NOIDA, for waiver of penalty on the ground that
since the exact area and location of the plot was
different from that specified in the brochure, the
delay in execution of the lease deed could not be
attributed to the Writ Petitioners and,
accordingly, penalty could not be imposed against
them. It appears that the Chief Executive Officer,
NOIDA, waived the penalty imposed on the Writ
Petitioners and granted them further two months’
time to complete the execution of the lease deed.
However, before the expiry of the said period of
two months, the NOIDA authorities had written to
the Writ Petitioners on 1st May, 2002, indicating
that penalty would be charged with effect from 22nd
November, 2001. The Writ Petitioners responded to
3
the said letter by submitting a representation
dated 15th May, 2002, praying for waiving the
penalty on account of the drain passing through
plot and also for providing any alternative plot in
lieu of the plot already allotted.
3. The Writ Petitioners were informed on 22nd
March, 2003, that the Board of NOIDA had rejected
their proposal for waiver of the penalty and that
the same would have to be paid within 30 days,
otherwise their allotment would be cancelled. At
the initial stage when the Writ Petition was filed,
the High Court had passed an interim order on 18th
April, 2003, staying the operation of imposition of
penalty against the Writ Petitioners. Ultimately,
after considering the submissions made on behalf of
the respective parties, the High Court took note of
Clause 25 of the Scheme indicating that the plots
were to be sold on “as is where is” basis, leading
to the presumption that the Writ Petitioners had
knowledge of the existing irrigation drain on the
4
plot. The High Court also took note of the power
reserved to the NOIDA authorities to vary the area
of the plot, which the allottee was bound to accept
as final. The High Court also took into
consideration the submissions made on behalf of the
Board of NOIDA that in its 113th meeting held on 10th
February, 2003, the Petitioners’ representation was
finally rejected but despite the same they did not
deposit the penalty and insisted upon the waiver of
penalty and interest.
4. Having arrived at the conclusion that the Writ
Petitioners had knowledge of all the terms and
conditions, status, location and other details
about the plot, which was advertised for allotment,
the High Court felt that there was no merit in the
Writ Petition and dismissed the same. The interim
order passed in the matter was also vacated.
5. Mr. Jayant Bhushan, learned Senior Advocate,
who appeared for the Petitioner Company, submitted
5
that having auctioned the plot in question without
proper specifications and contrary to the
description in its brochure, it was not within the
competence of the NOIDA authorities to impose
penalty on the Petitioner Company for not
completing the execution of the lease deed within
the stipulated period of 120 days from the date of
allotment. In fact, in the aforesaid background, a
representation was made by Shri Hira Lal Gupta to
the Chief Executive Officer, NOIDA, indicating that
he wanted to transfer the plot in question to the
Petitioner Company, wherein he and his son are
Directors. Since the said formalities were likely
to take some time, a prayer was made to the
aforesaid Authority to extend the time for
depositing the instalments and for making the
application in Form 37-I. In the same
communication, a further prayer was made to waive
the penalty due to the delay in execution of the
lease deed. It is on that basis that Shri Hira Lal
6
Gupta was granted two months' time, without
penalty, for completion of formalities.
6. The said extension came to be considered by the
Officer on Special Duty (G), who interpreted the
same to mean that the Petitioner Company had been
given two months' time without penalty only for
change of constitution, but that the interest on
the outstanding instalments, penal interest and
penalty, whatever was outstanding, would have to be
recovered, as it was. On 1st May, 2002, the Deputy
Manager (C), NOIDA, wrote to Shri Hira Lal Gupta in
regard to his request for effecting the change
relating to the transfer of the plot to the
Petitioner Company. In his said letter, the said
Authority requested Shri Gupta to submit the
documents indicated in the said letter in order to
effect the change of constitution in regard to the
allottee of the plot in question. In addition,
Shri Gupta was informed that on his failure to
complete execution of the lease deed, a sum of
7
Rs.62,18,088.00 had become payable by way of late
fee for the period between 22nd November, 2001 to
30th April, 2002. Furthermore, after the said
period, penalty of Rs.38,863.05 per day would also
be payable. The Petitioner was requested to deposit
the penalty amount for completion of Form 37-I for
change of constitution and execution of the lease
deed.
7. As indicated hereinabove, the imposition of
penalty is the bone of contention in this Special
Leave Petition.
8. Mr. Bhushan reiterated the submissions made
before the High Court that on 24th March, 2002,
when two months' time had been granted to the
Petitioner Company by the Chief Executive Officer,
NOIDA, for completion of the formalities for change
of constitution, the Officer on Special Duty had
acted illegally by passing an order on 11th April,
2002, which was within three weeks from the date of
8
the order of the Chief Executive Officer, demanding
payment of penal interest and penalty. Mr. Bhushan
contended that during the extended period of two
months, the Officer on Special Duty was not
entitled to demand payment of penalty when, in
fact, payment of such penalty had been specifically
waived by the Chief Executive Officer.
9. On the other hand, learned counsel for the
Respondent Authority, supported the order of the
Officer on Special Duty on the ground that the
period for execution of the lease had been extended
by a period of two months by the Chief Executive
Officer in view of the prayer made by Shri Hira Lal
Gupta to transfer the allotment in the name of the
Petitioner Company, wherein both he and his son
were Directors. Learned counsel reiterated the
submissions made before the High Court that the
order of the Chief Executive Officer, NOIDA,
extending the time for completion of the execution
of the lease deed would have to be considered in
9
that context only. He urged that notwithstanding
the time extended for completion of constitutional
changes, the liability for payment of penalty did
not stop on account of the order of the Chief
Executive Officer which continued to remain
operative after the expiry of 120 days from the
date of allotment and the Petitioner Company was,
therefore, liable to pay both the penalty charges
as also the lease rent at the rate of Rs.38,863.05
per day. Mr. Ravindra Kumar specifically referred
to the subsequent order of the Chief Executive
Officer dated 22nd July, 2002, by which he directed
that the land (2590.86 sq. meters) shown in the
brochure be given to Shri Hira Lal Gupta and
penalty be recovered as per rules. He urged that
the effect of the earlier order passed by the Chief
Executive Officer on 24th March, 2002, stood
superseded by the subsequent order, whereby penalty
was directed to be recovered from the Writ
Petitioners, according to the rules.
10
10. It was also reiterated that since the
Petitioner Company had decided to invest a huge sum
of money in the allotted land, it is difficult to
accept that the Petitioner Company or its Directors
would not have made enquiries as to the nature of
the land which was being allotted to them. In
other words, it has to be held that the Writ
Petitioners were fully aware of the existence of
the municipal drain on the land and absence of
knowledge thereof was nothing but a ploy on the
part of the Petitioner Company to avoid its
responsibility regarding payment of penalty for
non-compliance of the conditions to complete
execution of the lease deed within 120 days from
the date of allotment of the plot. Learned counsel
submitted that the position stood further
compounded by the fact that under Clause 25 of the
general terms and conditions spelt out in the
brochure, it was clearly indicated that the
allotment of the land was subject to variations in
11
the area of the plot and that the same would have
to be accepted by the allottees on “as is where is”
basis.
11. Mr. Ravindra Kumar submitted that no case had
at all been made out for interference with the
orders passed by the High Court dismissing the Writ
Petition.
12. For the reasons hereinafter following, we are
unable to accept Mr. Jayant Bhushan’s submissions
questioning the order passed by the Officer on
Special Duty dated 11th April, 2002, and the various
notices subsequently issued on the basis thereof,
demanding payment of penalty despite the order of
the Chief Executive Officer waiving imposition of
such penalty for the delay in execution of the
lease deed.
13. The materials on record indicate that there
had been correspondence exchanged between the
parties with regard to the land allotted and the
12
area thereof on account of the existence of the
municipal drain either on the plot or in its
vicinity. Shri Hira Lal Gupta had also made a
request for the plot allotted in his name to be
transferred in the name of the Petitioner Company
in which he and his son were Directors. Since the
same was likely to take some time for completion of
the formalities, a specific prayer was made to
serve the penalty due to delay in the execution of
the lease deed. In such background, the Chief
Executive Officer, NOIDA, extended the period for
completion of the formalities relating to the
constitutional change by a period of two months
without penalty from 24th March, 2002. Before the
said period could expire, the Officer on Special
Duty, on a misunderstanding of the order passed by
the Chief Executive Officer, NOIDA, indicated by
his order dated 11th April, 2002, that since the
Chief Executive Officer had given two months’ time
without penalty only for change of constitution,
13
interest on the outstanding instalments, penal
interest and penalty, were liable to be recovered
from the Writ Petitioners. To add to the confusion,
a further order was passed by the Officer on
Special Duty (G) on 26th April, 2002, directing that
steps be taken in terms of his earlier order dated
11th April, 2002, and indicating that two months’
time given to the Writ Petitioners was for
completion of formalities for change of the name of
the allottee.
14. Up to this stage, the case of the Petitioner
Company for waiver of penalty can be accepted, but
the subsequent correspondence which followed
between the parties and the failure of the
Petitioner Company and Shri Hira Lal Gupta to
complete the execution of the lease deed even
within the extended time of two months, indicate
that neither Shri Gupta nor the Petitioner Company
had any inclination to complete the formalities for
execution of the lease deed pursuant to the change
14
in the name of the allottee from Shri Hira Lal
Gupta to the Petitioner Company.
15. From the materials on record and the subsequent
correspondence beginning with the letter dated 1st
May, 2002, written by the Deputy Manager (C),
NOIDA, it is apparent that the Petitioner Company
and Shri Hira Lal Gupta were given a great degree
of latitude to complete the transaction. In fact,
meetings of the Committee had been convened on 23rd
October, 2002 and 26th November, 2002, in which Shri
Hira Lal Gupta appeared and made submissions for
waiver of the penalty but on the basis of the
record, the Committee rejected Shri Gupta’s
submissions and Shri Gupta was subsequently
informed of the decision of the Committee which was
approved at a meeting of the Authority convened on
15th February, 2003, under the Chairmanship of the
Additional Chief Executive Officer, NOIDA. Even if
initially a case may have been made out on behalf
of the Petitioner Company that the execution of the
15
lease deed could not be completed on account of the
mis-description of the plot and in view of the
prayer for change in the name of the allottee, on
account of the subsequent conduct of the Petitioner
Company and Shri Gupta, we are not inclined to
interfere with the order of the High Court or the
decision of the NOIDA relating to imposition of
penalty and interest. However, we are also not
inclined to accept the interpretation given by the
Officer on Special Duty to the order passed by the
Chief Executive Officer on 24th March, 2002, and,
accordingly, we direct that in calculating the
penalty and interest as payable under the agreement
entered into between the parties, the said period
of two months from the date of the order dated 24th
March, 2002, shall be excluded.
16. With the aforesaid modification of the order
passed by the Chief Executive Officer on 22nd July,
2002 and the subsequent resolution of the NOIDA
16
taken at the meeting convened on 15th February,
2003, the Special Leave Petition stands dismissed.
17. There will, however, be no order as to costs.
…………………………………………J. (ALTAMAS KABIR)
…………………………………………J. (A.K. PATNAIK)
New Delhi Dated: 27.10.2010
17