M.D., MAHARASHTRA STATE FINAN.CORP.&ORS. Vs SANJAY SHANKARSA MAMARDE
Bench: D.K. JAIN,H.L. DATTU, , ,
Case number: C.A. No.-007189-007189 / 2002
Diary number: 15527 / 2002
Advocates: M. J. PAUL Vs
SUNIL KUMAR VERMA
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 7189 OF 2002
Managing Director, Maharashtra State Financial Corporation & Ors.
— Appellants
VERSUS
Sanjay Shankarsa Mamarde — Respondent
J U D G M E N T
D.K. JAIN, J.:
1.Challenge in this appeal, filed under Section 23 of the
Consumer Protection Act, 1986 (for short “the Act”), by the
Maharashtra State Financial Corporation (hereinafter
referred to as “the Corporation”), is to the final order, dated 7th
January, 2002, passed by the National Consumer Disputes
Redressal Commission, New Delhi (for short “the
Commission”) in Original Petition No. 9 of 1995. By the
impugned order, the Commission has accepted the complaint
preferred by the respondent (hereinafter referred to as “the
complainant”) against the Corporation and has directed the
Corporation to pay to the complainant an amount of
Rs.4,84,457/- as compensation, within a period of two months
from the date of the order and in case of default, to pay
interest at the rate of 18% per annum from the date of order
till actual payment.
2.Succinctly put, the material facts giving rise to the present
appeal are as follows:
The complainant approached the Corporation for sanction
of loan for his hotel project at Amravati. As per the project
report, the capital outlay was of Rs.74.45 lakhs. The means of
finance envisaged in the project report were as follows:
i) Proprietor’s capital : Rs.16.80 lakhs ii) Term loan from
Corporation : Rs.30.00 lakhs
iii) Special Capital Incentive from SICOM
: Rs.21.30 lakhs
iv) Unsecured loans : Rs. 6.35 lakhs Total : Rs.74.45 lakhs
2
3.The Complainant’s loan proposal was approved by the
Executive Committee of the Corporation on 27th May, 1992,
sanctioning a term loan of Rs.30 lakhs to the complainant.
Accordingly, a sanction letter along with terms and conditions
of the loan was issued to the complainant on 2nd July, 1992.
The material conditions of loan were as follows:
“(a) The loan shall be utilised exclusively for the project
as per the scheme approved by MSFC and the
specific purposes for which the same is sanctioned.
(b) The loan shall be disbursed by MSFC in one lump
sum or in instalments as and when the said
purposes are fulfilled or at the entire discretion of
the Corporation or may be refused if in the opinion
of the Corporation, the purpose for which the full
loan has been sanctioned are not properly fulfilled.
(c) The loan will be disbursed either for acquisition of
fixed assets under the said scheme or for
reimbursement of funds utilised for acquisition of
fixed assets taken for security under the said
scheme.
3
(d) A minimum margin of 55% over all on fixed assets
shall be maintained during the currency of the loan.
(e) The loan shall be repaid within a period of 8 years
by 13 half yearly instalments commencing from the
end of 2nd year of disbursement of the first
instalment of the loan. The amount of each
instalment repayable being about 1/13 of the amount
sanctioned regardless of the amount disbursed.
(f) The interest shall be charged @ 22% p.a. and the
same shall be payable quarterly on the total loan
and the same shall be charged from the date of
disbursement of first instalment of the loan.”
Additionally, it was also agreed that the loan amount
would be disbursed depending on the progress of the work in
accordance with a set time schedule. The progress of the
construction work was required to be evaluated by the valuer
approved by the Corporation.
4.The said conditions were accepted by the complainant.
Pursuant to complainant’s request vide his letter dated 2nd
4
September, 1992, undertaking to bring entire 100% capital;
filing his banker’s confirmation for grant of bridge loan
against subsidy i.e. (SCI) and load sanction letter from MSEB,
before availing of the next disbursement, the first instalment
of the loan of Rs.2,90,000/- was released by the Corporation to
the complainant. On the same day, the complainant issued a
cheque in the sum of Rs.30,000/- towards up-front fees to the
Corporation. However, the said cheque of Rs.30,000/- was
dishonoured when presented for payment. By their letter
dated 15th December, 1992, the Corporation intimated the
complainant that despite the release of first instalment of
Rs.2.90 lakhs, he had neither submitted papers for further
disbursements nor reported progress of the project and had
also failed to submit Chartered Accountant’s certificate
showing his investment. Subsequently, a valuation report
dated 7th January 1993, showing that a total amount of
Rs.6,97,057/- (Rs.5,02,099/- as per previous valuation +
Rs.1,94,958/- as per present valuation) had been spent on the
construction of the hotel was filed by the complainant.
According to the Corporation, despite the fact that the
complainant had failed to submit complete documents, second
5
instalment of Rs.87,000/- was released to him on 19th January
1993, after adjusting therefrom the amount of interest due in
terms of the conditions of loan.
5.Vide their letter dated 5th March, 1993, the Corporation
requested the complainant to inform them about the progress
of the project and avail the balance loan limit by submitting
valuation report, Chartered Accountant’s certificate towards
further investment made by him for creation of fixed assets.
According to the Corporation, since they had learnt that there
was a proposal for laying a railway line between Amravati and
Narkhed which was likely to affect the hotel project and the
complainant had also defaulted in payment of interest despite
repeated requests by them vide their letters dated 10th
December 1993 and 24th February, 1994, they did not release
further instalments of the loan sanctioned to the complainant.
On the contrary, the stand of the complainant was that
although by June 1993, he had spent Rs.27,25,510/- but no
evaluation was done by the valuer of the Corporation and all
his request for release of further instalments fell on deaf ears.
All the time, the Corporation insisted on a written assurance
6
from the railway authorities that the proposed Amravati and
Narkhed railway line would not be passing through the hotel
project site, before releasing the balance loan amount.
6.Finally, vide their letter dated 5th September, 1994, the
Corporation informed the complainant that the entire balance
unavailed term loan of Rs.26.23 lakhs had been treated as
cancelled. The said intimation was followed by a legal notice
dated 18th October, 1994 by the Advocate of the Corporation,
wherein it was alleged that the complainant had failed to pay
the interest on the amount already disbursed to him; as on
31st March, 1994 he was in arrears by more than Rs.1 lakh as
interest and he had also failed to give any alternative
proposal for the hotel project as the project at the existing site
was likely to be affected by new railway track from Amravati
to Narkhed. The complainant was called upon to repay the
entire loan amounting to Rs.5,19,726/-, the outstanding
amount as on 23rd September,1994, within fifteen days from
the date of receipt of the said notice.
7.It appears from the impugned order that by his letter dated
15th September 1994, the complainant protested to the recall
7
of loan sanctioned to him. It is stated that the complainant
pointed out that though a number of instalments of the loan
had fallen due to be paid to the complainant, it was only as
late as on 29th July, 1994, that he was asked to submit a letter
from the competent authority regarding the status of the
railway line and that he promptly submitted a certificate
issued by the Commissioner, Amravati Division affirming that
there was no proposal of Amravati – Narkhed line.
8.Having failed to get any favourable response from the
Corporation, on 17th January 1995, the complainant filed a
complaint with the Commission. It seems that during the
pendency of the complaint before the Commission, the
Corporation retraced their steps and proposed to renew the
loan on certain conditions, which were not acceptable to the
complainant.
9.As already stated, the Commission has accepted the
complaint and has come to the conclusion that there was no
justifiable ground for the Corporation to deny disbursement of
loan to the complainant. According to the Commission,
having sanctioned the loan and then stopping its
8
disbursement without any cause amounted to deficiency in
service on the part of the Corporation. However, keeping in
mind the passage of time, the Commission did not find it
expedient to direct the Corporation to release further
instalments of the loan, sanctioned as far back as in July
1992.
10.Being aggrieved by the award of compensation, the
Corporation has preferred this appeal.
11.We have heard Mr. Santosh Paul, learned counsel appearing
for the Corporation and Mr. Manish Pitale, learned counsel
appearing for the complainant.
12.Learned counsel appearing for the Corporation submitted
that in the instant case there was no deficiency in service as
defined in Section 2(g) of the Act. The learned counsel argued
that the Commission has exceeded its jurisdiction in examining
the administrative decision of the Corporation to recall the loan
as it felt that having regard to the past conduct of the
complainant it was not in the interest of the Corporation to
disburse the balance amount of loan to him. Relying on the
decision of this Court in U.P. Financial Corporation & Ors. Vs.
9
Naini Oxygen & Acetylene Gas Ltd. & Anr.1, it was submitted
that unless the action of the Corporation was held to be mala
fide, even a wrong decision taken by it was not open to
challenge as it is not for the Courts or a third party to
substitute its decision, however more prudent, commercial or
businesslike it may be, for the decision of the Corporation.
Reliance was also placed on another decision of this Court in
Haryana Financial Corporation & Anr. Vs. Jagdamba Oil Mills
& Anr.2, to contend that in commercial matters the Court
should not risk their judgments for the judgments of the bodies
to whom that task is assigned. It was asserted that since the
Corporation was of a bona fide belief that the entire hotel
project of the complainant may get affected because of the
proposed railway line and further there were defaults on the
part of the complainant to discharge his liability towards
quarterly instalments of interest, the decision of the
Corporation not to disburse further instalments cannot be
termed as mala fide or unreasonable and, therefore, there was
no question of any deficiency in the service of the Corporation
towards the complainant. 1 (1995) 2 SCC 754 2 (2002) 3 SCC 496
10
13.Supporting the impugned judgment, learned counsel
appearing for the complainant, on the other hand, submitted
that in the absence of any stipulation in the conditions of loan
for stopping the disbursement on account of default in the
payment of interest on time, the action of the Corporation in
not releasing the remaining instalments on the stipulated dates
not only affected the hotel project, it also caused a huge loss to
the complainant as he was deprived of the special capital
incentive by SICOM. It was argued that the non release of the
instalments on the specious plea that there was a proposal for a
railway line was mala fide inasmuch as there was no such
proposal.
14.The short question arising for consideration is whether the
Commission was correct in holding that there has been
deficiency in service provided by the Corporation to the
complainant on account of their failure to release the balance
loan amount?
15. Clause (o) of Section 2 of the Act defines “service” to
mean:-
11
“service” means service of any description which is made available to potential users and includes, but not limited to, the provision of facilities in connection with banking, financing insurance, transport, processing, supply of electrical or other energy, board or lodging or both, housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service;”
The use of the words ‘any’ and ‘potential’ in the context these
have been used in clause (o) indicates that the width of the
clause is very wide and extends to any or all actual or potential
users. The legislature has expanded the meaning of the word
further by extending it to every such facilities as are available
to a consumer in connection with banking, financing etc.
Undoubtedly, when the bank or financial institutions advance
loans, they do render ‘service’ within the meaning of the clause.
In that behalf, there is no dispute.
16. “Deficiency” under clause (g) of Section 2 of the Act
means:-
“deficiency” means any fault, imperfection, shortcoming or inadequacy in the quality, nature and manner of performance which is required to be maintained by or under any law for the time being in force or has been
12
undertaken to be performed by a person in pursuance of a contract or otherwise in relation to any service;”
It is manifest from the language employed in the clause that
its scope is also very wide but no single test as decisive in the
determination of the extent of fault, imperfection, nature and
manner of performance etc. required to be maintained can be
laid down. It must depend on the facts of the particular case,
having regard to the nature of the ‘service’ to be provided.
17. Therefore, in so far as the present case is concerned, in
order to examine whether there was a deficiency in service by
the Corporation, it has to be seen if there was any inadequacy
in the quality, nature and manner of performance which was
required to be maintained by the Corporation in terms of their
letter dated 2nd July, 1992, conveying the sanction of loan to the
complainant. As noted above, the Corporation was obliged to
disburse to the complainant a loan of Rs.30 lakhs in
instalments on complainant’s furnishing the progress report of
the project. Although, no specific information with regard to
the actual dates for release of the instalments of the loan
amount are forthcoming, yet it can be gathered from the
13
correspondence on record that the loan amount was to be
disbursed periodically (perhaps half yearly), on the basis of the
report of the approved valuer on the progress of the project. It
is evident from Corporation’s letters dated 5th March, 1993, 10th
December, 1993, 24th February, 1994 and 29th July, 1994 that
the complainant not only failed to furnish the progress report,
he also did not discharge his liability towards interest, as
demanded from him from time to time. As already stated, even
the cheque in the sum of Rs.30,000/- issued by the
complainant to the Corporation on 2nd September, 1992
towards up-front fee was returned unpaid by his bankers. In
Corporation’s letter dated 24th February, 1994 it was alleged
that the complainant had not only failed to pay interest, it was
also found on inspection on couple of occasions by the Regional
Manager that during the last four months there was no further
progress in implementation of the project. It is significant that
these allegations and details of interest due from the
complainant had not been seriously disputed by the
complainant either before the Commission or in the counter
affidavit filed by him in this appeal. In the background of the
factual scenario as emerging from the material on record, we
14
are convinced that there was no shortcoming or inadequacy in
the service on the part of the Corporation in performing its
duty or discharging its obligations under the loan agreement.
The Corporation was constrained not to release the balance
instalments and recall the loan on account of stated defaults on
the part of the complainant himself. Non release of loan
amount was not because of any deficiency on the part of the
Corporation but due to complainant’s conduct and therefore,
the failure of the Corporation to render ‘service’ could not be
held to give rise to claim for recovery of any amount under the
Act.
18. We also find substance in the contention of learned
counsel for the Corporation that unless the action of a financial
institution is found to be mala fide, even a wrong decision
taken by it is not open to challenge, as the wisdom of a
particular decision is normally to be left to the body authorized
to decide. In U.P. Financial Corporation & Ors. Vs. Naini
Oxygen & Acetylene Gas Ltd. & Anr. (supra) this Court had
observed that a Corporation being an independent autonomous
statutory body having its own constitution and rules to abide
15
by, and functions and obligations to discharge, in the discharge
of its functions, it is free to act according to its own right. The
views it forms and the decisions it takes would be on the basis
of the information in its possession and the advice it receives
and according to its own perspective and calculation. In such a
situation, more so in commercial matters, the court should not
risk their judgments for the judgments of the bodies to which
that task is assigned. It was held that: (SCC p. 761, para 21)
“Unless its action is mala fide, even a wrong decision taken by it is not open to challenge. It is not for the courts or a third party to substitute its decision, however more prudent, commercial or businesslike it may be, for the decision of the Corporation. Hence, whatever the wisdom (or the lack of it) of the conduct of the Corporation, the same cannot be assailed for making the Corporation liable”.
19. Having considered the matter in the light of the
correspondence exchanged between the Corporation and the
complainant, we have no hesitation in holding that there has
not been any deficiency in the service the Corporation was
required to provide to the complainant. In our opinion, the
Commission was not correct in coming to the aforestated
conclusion. We are of the view that the complainant being
16
himself a defaulter right from inception of his dealing with the
Corporation, when his cheque in the sum of Rs. 30,000/- got
dishonoured, coupled with persistent defaults in discharging
his liability to the Corporation towards interest, despite
repeated demands, he cannot be permitted to plead at the later
stage that he suffered on account of deficiency in service by the
Corporation because of non-disbursement of balance
instalments of loan by them. As was observed by this Court in
Jagdamba Oil Mills (supra), while not insisting upon the
borrower to honour the commitments undertaken by him, the
Corporation alone cannot be shackled hand and foot in the
name of fairness. Fairness cannot be a one-way street. Where
the borrower has no genuine intention to repay and adopts
pretexts and ploys to avoid payment like in the present case, he
cannot make the grievance that the Corporation was not acting
fairly, even if requisite procedures have been followed.
20. For the foregoing reasons, we allow the appeal; set aside
the order passed by the Commission and dismiss the complaint
filed by the complainant. Amount deposited in terms of order
dated 19th July, 2004 shall be released to the Corporation on
17
maturity of the fixed deposit. There shall, however, be no order
as to costs.
……………………………. J.
(D.K. JAIN)
…………………………….J. (H.L. DATTU)
NEW DELHI; JULY 9, 2010.
18