LUDHIANA IMPROVEMENT TRUST Vs M/S TODAY HOMES & INFRASTRUCTURE P.LD.
Bench: ALTAMAS KABIR,MARKANDEY KATJU, , ,
Case number: C.A. No.-006104-006104 / 2008
Diary number: 11392 / 2008
Advocates: AJAY PAL Vs
J S WAD AND CO
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.6104 OF 2008 (@Special Leave Petition (Civil) No.10550 of 2008)
Ludhiana Improvement Trust & Another ...Appellants
Vs. M/s Today Homes and Infrastructure (Pvt) Limited ... Respondent
J U D G M E N T
ALTAMAS KABIR,J.
1. Leave granted.
2. This appeal has been filed by the Ludhiana
Improvement Trust, through its
Administrator, and the State of Punjab,
against the order passed by the Chief
Justice of Punjab and Haryana High Court in
a petition filed by the respondent herein
under Section 11 of the Arbitration and
1
Conciliation Act, 1996 (hereinafter referred
to as ‘the 1996 Act’) for the appointment of
an Arbitrator. In the said application,
which was numbered as Arbitration Case No.76
of 2007, the appellants herein were made
respondents.
3. The Ludhiana Improvement Trust (hereinafter
referred to as “the Trust”) was constituted
under the Punjab Town Improvement Act, 1922
(hereinafter referred to as “the 1922 Act”)
for the planned development of the city of
Ludhiana. For the purpose of construction of
the City Centre in Ludhiana, the Trust, with
the intention of entering into a joint-
venture with developers in the private
sector, invited bids by a Request of
Proposal document dated 15.3.2005. Bids
were filed by interested parties by
10.5.2005 and evaluation of the Technical
bids was completed by 16.5.2005. In the
final evaluation the respondent was found to
2
be the highest bidder and a Letter of Intent
was thereupon issued to him on 18.5.2005 for
development of the City Centre, Ludhiana.
The said Letter of Intent was alleged to
have been approved by the Trust in its
meeting held on 18.5.2005, which was
attended by 7 out of its 10 members.
4. The records indicate that on being issued
the Letter of Intent the respondent
deposited an amount of Rs.3.72 crores with
the Trust towards security for the purposes
of the contract. According to the Agreement,
the respondent would ultimately be required
to pay to the Trust an amount of (Rs.371.12
crores). The records also reveal that
possession of an area measuring 25.59 acres
was handed over to the said respondent by
the Trust on 24.5.2005. The Trust also
appears to have entered into a part-time
agreement with the respondent and the HDFC
Bank limited whereby it was agreed that the
3
entire proceeds received from bookings of
the area to be sold would be deposited in an
Escrow Account with the HDFC Bank, out of
which 30% of the amount so deposited would
be credited automatically to the account of
the Trust and the balance 70% would be
available to the respondent No.1 for the
purpose of development of the City Centre. A
Power of Attorney was also executed by the
Trust in favour of the respondent No.1
empowering the said respondent to act as its
lawful attorney for the development work and
marketing of the City Centre.
5. During the continuance of the agreement
certain disputes arose and certain
allegations surfaced that under-hand
dealings were being resorted to and up to
70% of the total amounts payable, by those
who had booked space in the City Centre,
were being received in cash and only 30%
being received by means of cheques was being
4
deposited in the Escrow account, resulting
in huge losses to the Government of Punjab
towards its share of revenue.
6. Accordingly, the Trust issued a letter to
the respondent No.1 on 12.9.2006 seeking an
explanation regarding the allegations to
which a reply was sent by the respondent
No.1 on the very next day denying the
allegations and indicating that its accounts
could be scrutinized, and, if the
explanation was not found to be
satisfactory, the dispute could be referred
to arbitration.
7. The suggestion made by the respondent No.1
was rejected by the Trust by its letter
dated 14th September, 2006, and in the said
letter it was mentioned that an Arbitrator
for auditing the accounts, would be
appointed within the next two days.
According to the respondent No.1, the said
action of the petitioner was not in keeping
5
with the terms and conditions of the
Agreement and clause 17 of the Concession
Agreement dated 24th May, 2005, and the
petitioner ought to have invoked clause 17.1
(a) and (b) of the said Agreement which
provides for conciliation and settlement of
disputes in an amicable manner. The
respondent No.1 accordingly filed
Arbitration Petition No. 263 of 2006 under
Section 11(6) of the 1996 Act for
appointment of an Arbitrator in accordance
with clause 17 of the Concession Agreement.
The said petition was contested by the
petitioner on the ground that no cause of
action had accrued to the respondent No.1
for making such application.
8. Subsequently, however, an application was
moved on behalf of the respondent No.1 on 9th
August, 2007, for withdrawal of the
arbitration case. The same was allowed and
the said case was dismissed as withdrawn on
6
22nd August, 2007, with liberty as was prayed
for. Thereafter, various circumstances
intervened. The Trust was dissolved by the
Government on 14th September, 2006 and one of
the major decisions taken was to revoke the
Power of the Attorney granted in favour of
the respondent No.1 from 5th October, 2006,
upon the agreement that the sales and/or
leases of the Ludhiana City Centre property,
which had been effected till then, which was
approximately 22% of the total saleable
area, would go to the share of the
petitioner herein which would have the
effect of validating the sales and leases
which had already taken place.
9. It also appears that since the terms of the
Memorandum of Settlement dated 6th October,
2006, provided for the execution of a
supplementary agreement, and nothing further
was done in that regard, the respondent No.1
wrote a letter to the Trust on 29th December,
7
2006, requesting such supplementary
agreement to be executed. When nothing
more was heard from the petitioners, the
respondent No.1 again addressed a letter to
the Trust on 8th June, 2007, that in the
absence of the procedure under clause 17.1
(a) and (b) the dispute should be settled by
way of an amicable settlement. Again on 30th
June, 2007, another letter was written by
the respondent No. 1 indicating the name of
the Arbitrator from its side. The proposal
was, however, rejected on the ground that in
the absence of any dispute, merely on vague,
false or motivated averments, arbitration
could not be resorted to. It was in such
circumstances, that the application under
Section 11(6) of the Arbitration Act for
appointment of an Arbitrator by the Court
came to be filed.
10. In the proceedings under Section 11(6) of
the 1996 Act, it was contended that the
8
Trust had awarded the contract to the
respondent No.1 herein in keeping with all
the norms and procedures and after bids had
been invited by way of public advertisement.
It was submitted that after the Technical
and Financial bids submitted by the bidders
were opened, the contract was awarded to the
respondent No.1 herein, as the highest
bidder. Subsequently, disputes arose
between the parties with regard to the
working of the Agreement, which prompted
the respondent No.1 to invoke the
arbitration clause in the Agreement and on
the failure of the appellant herein to
appoint an Arbitrator, the respondent No.1
had applied to the Chief Justice of Punjab
and Haryana under Section 11(6) of the
Arbitration and Conciliation Act, 1996, for
the appointment of an Arbitrator.
11. On behalf of the appellant herein, it has
been contended that the said Agreement
9
itself was void having been entered into in
suspicious circumstances and by perpetrating
fraud by altering the terms of the
advertisement inviting bids thereby
enlarging the eligibility criteria for
participation in the bid, so that persons,
who were otherwise ineligible, were given an
entry into the bidding process and
ultimately the contract was awarded to one
of such persons. Various irregularities
were also pointed out by which it was
claimed that the main Agreement which
contained the Arbitration Agreement was
itself void and hence the Arbitration
Agreement could not also survive.
12. After considering the submissions made on
behalf of the respective parties, by placing
reliance upon the decision of this Court in
the Case of Konkan Railway Corporation
Limited and Anr. Vs. Rani Construction
Private Limited, [2002 (2) SCC 388], which
10
was followed in Hindustan Petroleum
Corporation Ltd. vs. Pinkcity Midway
Petroleum [2003 (6) SCC 503], the Hon’ble
the Chief Justice took the view that having
regard to Section 16 of the Arbitration and
Conciliation Act, 1996, it was for the
Arbitrator and not the Chief Justice to
decide the question of jurisdiction.
13. Incidentally, no reference has been made in
the order of the Hon’ble Chief Justice to
the later decision of the Bench of Seven
Judges in S.B.P. and Company vs. Patel
Engineering Ltd. and Anr. [2005 (8) SCC
618], wherein the views expressed by the
Constitution Bench in the Konkan Railway
case (supra) were overruled and it was
asserted that an order passed by the Chief
Justice or his delegatee Judge, on an
application under Section 11(6) of the
aforesaid Act, would be a judicial order and
11
not an administrative order as had been held
in the Konkan Railway case(supra).
14. On the basis of his aforesaid finding, the
Chief Justice appointed a former Chief
Justice of India as Sole Arbitrator to
adjudicate upon all the disputes between the
parties, including the disputes which had
been indicated in the order which has now
been made before us in the instant appeal.
15. On behalf of the appellant various
submissions were made regarding the manner
in which the contract had been awarded to
the respondent company in violation of the
provisions of Rule 94 of the Punjab Town
Improvement Trust Rules, 1939. It was
contended that since the main Agreement had
been fraudulently obtained, even the
Arbitration Agreement contained therein was
void and unenforceable. The said contention
was opposed by Mr. Shanti Bhushan, learned
Senior Counsel appearing for the respondent-
12
company, and it was urged that the High
Court had quite correctly allowed the
application filed by the Company under
Section 11(6) of the Arbitration and
Conciliation Act, 1996. Mr. Shanti Bhushan
contended that the main Agreement and the
Arbitration Agreement contained therein
could not be equated as they were for
different purposes. According to Mr. Shanti
Bhushan, even if the main Agreement was held
to be void, it did not affect the
Arbitration Agreement which had been
included in the main Agreement for the
purpose of deciding such issue.
16. Mr. Shanti Bhushan, submitted that even if
it is accepted that the High Court ought to
have taken into consideration the later
decision of the seven-Judge Bench in the
Patel Engineering case (supra), such an
omission could be rectified by this Court
itself in these proceedings on the basis of
13
the detailed submissions advanced on behalf
of the parties.
17. We have considered the submissions of both
the parties and have also considered Mr.
Shanti Bhushan’s submissions that the issues
which had been left undecided by the High
Court could be decided in these proceedings
itself. However, in our view, such a course
of action would have been justified if after
considering the submissions of the
respective parties the High Court had
arrived at a finding regarding the dispute
between the parties. Unfortunately, relying
on the earlier Constitution Bench decision
of this Court in the Konkan Railway case
(supra), the High Court left it to the
learned Arbitrator appointed by it to decide
the said issues under Section 16 of the 1996
Act, which was contrary to the directions
given by the seven-Judge Bench of this Court
in the Patel Engineering case (supra), which
14
categorically overruled the decision of the
Constitution Bench in the Konkan Railway
case. In fact, in sub-paragraphs (10) and
(12) of Paragraph 47 of the said judgment,
the seven-Judge Bench specifically indicated
that the orders which had already been
passed in applications under Section 11(6)
of the 1996 Act, prior to the decision in
the Patel Engineering case (supra), would be
treated as valid, leaving all objections to
be decided under Section 16 of the Act. It
was also indicated that from the date of the
judgment, however, the decision rendered in
the Patel Engineering case (supra), would
govern all applications and even pending
applications under Section 11(6) of the 1996
Act.
18. We have, therefore, no option but to set
aside the order of the Chief Justice and
remit the matter for a fresh decision in
keeping with the decision of the seven-Judge
15
Bench in S.B.P. & Company vs. Patel
Engineering Limited and Another [2005 (8)
SCC 618].
19. The appeal is disposed of accordingly.
20. There will be no order as to costs.
_________________J. (ALTAMAS KABIR)
_________________J. (MARKANDEY KATJU)
New Delhi
Dated:October 14, 2008
16