18 July 1968
Supreme Court
Download

KONAPPA RUDRAPPA NADGOUDA Vs VISHWANATH REDDY & ANR.

Case number: Appeal (civil) 1705 of 1967


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9  

PETITIONER: KONAPPA RUDRAPPA NADGOUDA

       Vs.

RESPONDENT: VISHWANATH REDDY & ANR.

DATE OF JUDGMENT: 18/07/1968

BENCH: HIDAYATULLAH, M. (CJ) BENCH: HIDAYATULLAH, M. (CJ) MITTER, G.K.

CITATION:  1969 AIR  447            1969 SCR  (1) 395  CITATOR INFO :  AFR        1969 SC 604  (12,14)  D          1981 SC1177  (14,17)

ACT: Representation  of  the People Act, 1951,  s.  9A-Agreements between, respondent’s firm and State Government for building a  road  and  a  dispensary-work  at  first  certified   as- completed later certificates cancelled Agreements containing clauses  requiring  contractor  to  repair  faulty   work-if contracts  subsisting  on  date  of  nomination-Respondents’ partnership firm dissolved before nomination without  notice to Government  of.

HEADNOTE: The  appellant and the first respondent were candidates  for election  in February, 1967 from the  Yadagiri  constituency which  was  won  by the  first  respondent.   The  appellant challenged his election by a petition on the ground that  he was  a  partner in a firm which had two contracts  with  the State Government, one for the construction of a road and the other  for the construction of a dispensary building,  which were subsisting on, the day when nominations were filed;  he was  therefore disqualified from being a candidate under  s. 9A  of  the Representation of the People Act, 1951  and  his election  was void.  The appellant also claimed that he  was entitled to be declared elected as the votes cast in  favour of  the  first respondent must be regarded as  thrown  away. From  the  evidence led before the High Court it  was  clear that  the  first respondent had obtained  certificates  from officers  of  the State Government to the  effect  that  the contracts  were  complete but that these  certificates  were subsequently  cancelled as it was considered that  the  work was not completed.  After appraising the evidence, the  High Court came to the conclusion that although some of the items from  the two contracts might not have been  completed,  the contracts  as  a  whole were  substantially  performed  and, therefore, there was no bar to the candidature of the  first respondent.   It  also  held that  although  the  agreements contained clauses for maintenance and repairs over a  period of  time after the completion of the work  of  construction, the  did  not  have the effect  of  making  them  subsisting contracts.  The High Court therefore dismissed the  election

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9  

petition. HELD : On appeal to this Court, The  High Court was in error in holding that  the  contracts had  been  fully  performed and s. 9A did  not  apply.   The appeal  must  therefore be allowed and the election  of  the first respondent declared void.  Furthermore the votes caste in favour of the first respondent must be treated as  thrown away  and in the absence of any other contesting  candidate, the appellant declared elected [403 F, 404 B-C] (i)  Taking  the  fact  that some portion  of  the  original contracts remained  to be performed with the fact that under the contracts the con tractor was   required  not  only   to complete  the  original  work but to repair  defects  or  do something which he had not properly done, the matter must be regarded as falling within s. 9A of the Act.  In the context of  construction of buildings and roads, it is obvious  that if  some part is found defective and has to be  done  again, the  contract  of  execution as such is still  to  be  fully performed.  It is possible to describe the action, taken  as one  to repair the defect, but in essence it is a,  part  of the contract 396 of execution, because no execution can be said to be  proper or complete till it is properly executed. [403 B-D] (ii) There  was no force in the contention that  under  Art. 299  the  ,contract  in question had to  be  signed  by  the Secretary  to the Government whereas in the present case  it was signed by the Executive Engineer. [403 G] Chatturbhuj  Vithaldas  Jasani v.  Moreshwar  Parashran  and Others, [1954] S.C.R. 817, applied. (iii)     The law requires that a candidate should not  have any  interest in any contract with Government and  therefore even  a  partner  in a firm has an  interest  sufficient  to attract  the  provisions  of  s.  9A.   The  fact  that  the partnership  itself had been dissolved in the  present  case would  have no effect upon the relations between  the  first respondent and, the Government. [403 H] The  first respondent could not by a private dissolution  of the  partnership escape his liability under the contract  to the  Government,  and there was here  no  notation,  because notice  of the dissolution was not given to  Government  and the  Government  had  not accepted the person  to  whom  the business was transferred in place of the respondent’s  firm. [404 A]

JUDGMENT: CIVIL  APPELLATE  JURISDICTION : Civil Appeal  No.  1705  of 1967. Appeal under section 1 1 6 A of the Representation of People Act,  1951 from the judgment and order dated  September  15, 1967 of the Mysore High Court in Election Petition No. 8  of 1967. M.   C.  Chagla,  S.  S.  Javali  and  B.  Datta,  for   the appellant. D.   Narsaraju, B. S. Patil and R. V. Pillai, for respondent No. 1. The Judgment of the Court was delivered by Hidayatullah,  C.J. This is an appeal from the judgment  and order of the High Court of Mysore, September 15, 1967, in an election  matter  in  which the present  appellant  was  the election  petitioner.  The election concerned  the  Yadagiri constituency  and was held in February 1967 during the  last general   elections.   To  begin  with,  there  were   seven

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9  

candidates.   Of these five withdrew leaving the seat to  be contested  by the appellant and the first  respondent  here. The   first  respondent  was  returned  as  the   successful candidate  having obtained 4,000 and odd votes in excess  of his  rival.   On  March  30,  1967  the  defeated  candidate preferred  an election petition which has given rise to  the present appeal.  The election petition was dismissed by  the High  Court  and  in this appeal,  the  election  petitioner claims that the decision of the High Court was erroneous and that  the  election  of the first respondent  was  void  for reasons to be stated hereafter. The  first respondent was a partner in a firm known as  that Yadagiri Construction Company, Yadagiri.  This firm held 397 several  contracts  from  the Mysore  Government.   In  this appeal, we are concerned with two contracts only which  were the construction of (1) a road known as "Nalwar Sonthi Road" in Gulbarga Division for a distance of four miles and (2)  a dispensary  building  for  the  Primary  Health  Centre   at Wadagara.   The contention of the, election  petitioner  was that  these  contracts were subsisting on January  20,  1967 when  the nominations were filed and the subsistence of  the contracts  with the Government rendered the election of  the first respondent void.  The election petitioner claimed that he  was  entitled to be declared elected  after  considering that  the  votes  cast in favour of the  1st  respondent  as thrown  away.  The High Court in its judgment held that  the contracts  were  not subsisting and that  the  election  was therefore not affected. The  matter  is one of fact but it is necessary,  before  we enter  into an examination of the facts, to set out the  law relating  to disqualification of candidates on this  ground. Under  s. 9A of the ’Representation of the People Act,  1951 it is provided as follows               "A person shall be disqualified if, and for so               long as there subsists a contract entered into               by him in course of his trade or business with               the  appropriate Government for the supply  of               goods  to, or for the execution of  any  works               undertaken by, that Government.               Explanation : For the purpose of this  section               where  a contract has been fully performed  by               the  person by whom it has been  entered  into               with the appropriate Government, the  contract               shall be deemed not to subsist by reason  only               of  the  fact  that  the  Government  has  not               performed  its  part of  the  contract  either               wholly or in part." It may be mentioned here that previously the section did not contain the Explanation.  In Chatturbhuj Vithaldas Jasani v. Moreshwar  Parashram  and others(1), the  existence  of  the liability  on the part of the Government to pay for a  fully executed  contract  was held to be a  disqualification.   It appears that Parliament thought that since Government  moves slowly  and many bills remain outstanding for a  long  time, this part of the disability may be removed.  The  amendment, therefore,  takes  away  from the ban  of  the  section  the subsistence   of  one  side  of  the  contract,   viz.   the performance  thereof by Government by paying for  the  goods supplied  or the work executed.  In other respects, the  law remains  very  much  the  same as it  was  when  the  ruling referred  to  above was given.  We shall have  to  refer  to certain observations in the ruling which in our opinion must be taken into (1) (1954) S.C.R. 817.

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9  

LI 2S.CI/68-11 398 account before reaching the conclusion whether the  contract or  contracts continued to subsist on the date on which  the candidate  offered  himself  for  election.   We  shall  now continue our narration of the facts. As has been stated already, there were two contracts one for the construction of a road for a distance of four miles  and the  other  for the construction of a  dispensary  building. Two  separate  agreements  have  been  produced  which  were entered  into by the Yadagiri Construction Company with  the Government  for  the  execution  and  performance  of  these contracts.   It was urged in the High Court by the  election petitioner  that  both these contracts  remained  incomplete and,  therefore, they subsisted and that the  candidate  was under  a  disqualification  and  could  not  stand  for  the election.   The contract for the construction of  the  road, ,entered into by the Yadagiri Construction Company, included ’twelve  items  which the firm had to  complete.   They  are conveniently  described  as items 1 to 7 and 8 to  12.   The case of the election petitioner was that although item 1  to 7  had  been  completed,  items  8  to  12  remained  to  be completed.  In the Schedule to the contract for the building of  the dispensary, a number of items were included  in  the Schedule.   Of  these, 8 items were found to  be  incomplete and,  therefore, the same position ensued as in the case  of road.   The evidence led in the case consisted of  documents from the Public Works Department and oral testimony ,of  the engineers  who-  were in charge of these  constructions  and others.  After appraising the evidence, the High Court  came to the conclusion that although some of the items from these two  ,contracts  might not have been  completed,  still  the contracts  as  a  whole were  substantially  performed  and, therefore,  there was no bar to the candidature of  the  1st respondent.   The High Court also held that  although  these agreements  contained a clause for maintenance  and  repairs over  a period of time after the completion of the  work  of construction, that did not make the contracts to subsist and therefore, that too was not a disability. Mr.  Chagla  in arguing the appeal tries to  establish  that both  the conclusion of the High Court are  erroneous.   The evidence  in  the case, as is usual,  is  widely  discrepant between the parties.  They both held certificates issued  by the  Public Works Department, one set showing that the  work had  been  completed and a subsequently issued  set  showing that  something remained to be done and that  the  contracts were  still subsisting.  We shall refer to  these  documents now. The  contract  in relation to the road was entered  into  on December  17,  1962  and is evidenced  by  Ex.   P-10.   The Schedule to the contract showed that the construction had to be  completed  according  to it.  The contract  went  on  to provide by cl. 20 as follows 399               "........  The contractor is to  maintain  the               reconstructed portion of the road for a period               of  three months after the Executive  Engineer               has certified the same to be completed to  his               satisfaction". The Schedule to this contract provided for surfacing of  the road,  collection of Shahabad soling stones,  collection  of muram for earth work, spreading muram over soling and  metal etc.  In addition to the proper construction of the road, it was  the duty of the contractor to supply and fix  mile  and hectometer  stones  and  to  fix  the  road  boundaries  and

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9  

demarcation stones etc.  This work represents items 8 to 12. Those  relating  to the road proper are items 1-7  to  which also reference has been made earlier. Now  it  is agreed on both sides that items  1-7  were  duty completed.  The dispute is with regard to items 8-12.  Nomi- nation to the Assembly had to be filed on 20th January, 1967 at  the latest. 21st January was fixed for scrutiny  of  the nomination  papers  and the election was to  follow  in  the month  of  February.   On  18th  January,  1967,  the  first respondent  obtained  a  certificate  (Ex.   P-1)  that  his contracts  had  been  fully performed.   He  approached  the Executive Engineer on the 19th.  The Executive Engineer  was busy throughout the day.  The respondent therefore asked his Personal  Assistant (who incidentally is a gazetted  officer of  the  rank  of an Assistant Engineer)  to  give  him  the necessary certificate.  The Personal Assistant telephoned to the  Assistant  Engineers in charge and on  their  statement that the work had been physically completed, he granted  the certificates  to that effect.  It appears that the  election petitioner   was  also  busy  in  his  turn.   He   obtained cancellation  of  these  certificates  from  the   Executive Engineer on the following day.  The Executive Engineer asked the  Assistant Engineers to state whether the work had  been completed  and  the Assistant Engineer  thereupon  gave  the certificate  that items 8-12 of the first contract were  not complete.   We  have so far described the  contract  dealing with the road. The contract for the construction of the dispensary was exe- cuted  on February 23, 1966.  The schedule to that  contract contained  a  description  of  27  items  which  had  to  be completed.  In addition, there was the requirement that  the entire premises would be cleaned and put in habitable  state and then handed over.  Here also the dispute is whether  the entire  contract had been completed or not.  It is the  case of the election petitioner that 9 items were left incomplete including  the construction of a compound wall 30  ft.  long for  the quadrangular open yard, supplying welded  mesh  for the front waiting room and to the rear opening, whitewashing of  one room, paint work, floors etc.  This also was  certi- fied at first to be completed but later the certificate  was revised 400 and  it  was stated that the work was not complete.   It  is between  these  two  rival  certificates  and  the  evidence relating to them that the matter has to be decided. In respect of the road, the Assistant Engineer in charge  of the  work  gave a notice on December 20,  1966  saying  that certain  work was not complete.  Items 8-12  were,  however, not mentioned there.  The High Court was of the opinion that this  omission completely demonstrated that portion  of  the work  which  is now stated to be incomplete must  have  been completed.  In answer to this, Mr. Chagla has contended that he had asked for the issue of a Commission in the High Court for  the  inspection  of the spot  (which  petition  he  has repeated  here) and he stated that even today, this part  of the  work has not been completed.  However we do not  go  by such  petitions  nor are we inclined to issue  a  Commission which  has  been asked for in this Court.  We  consider  the evidence,  such as it is, and we find the correct  situation to be this.  P.W. 3, the Assistant Engineer no doubt  stated in his notice that the "balance items" were only three.  lie had really mentioned 4 items, but had struck out item No. 2. That,  however, did not show that no other work remained  to be done.  The certificates are there.  That in favour of the completion of the work were given by the Personal  Assistant

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9  

to the Executive Engineer on the day the Executive  Engineer was absent.  No doubt, the Personal Assistant worked as  the head of the office in the absence of the Executive Engineer, but it is on record and duly proved that he had no authority to  issue  the completion certificates which  he  did.   The Personal   Assistant  explained  that  he  had  issued   the certificates   because  they  were  urgently  required   for election  purposes and because the Assistant Engineer  under whose  supervision the construction of the road  was  taking place  had reported completion of the work.   The  Executive Engineer,  however, verified this again from  the  Assistant Engineer and found that items 8-12 remained to be completed. Mr.  Narasaraju  complains of the conduct of  the  Executive Engineer by saying that he did not visit the spot to see for himself  whether  the completion had been made or  not.   He states  that  in  Ex.   P-11 in  which  the  completion  was reported on 18-1-1967 there is no mention of items 8-12  and it is different in language from Ex.  C-1 in which items  8- 12  are shown not to have been completed.  We do  not  think that  anything  turns on that.  The Officers of  the  Public Works  Department  have  come to the witness  box  and  have maintained  that these items were in fact not completed  be- fore  the  election  took  place.   We  are  satisfied  that although  the  construction  of the road  was  complete  the additional  items which are described as "miscellaneous"  in the  contract still remained to be completed.  What  bearing this will have upon the election of the first respondent  is something which we shall consider after we have analysed the evidence with regard to the hospital. 401 In  respect  of  the hospital  also,  the  first  respondent obtained ,the certificate from the Personal Assistant to the Executive  Engineer that the work had been completed.   This is  Ex.   P-1.   Here  again,  the  Assistant  Engineer  was consulted  and  the  certificate  showed  that  there   were physical completion of the work.  Later this certificate was also contradicted by the issuance of another certificate  by the  Executive Engineer that the work  remained  incomplete. This information was given by the Executive Engineer to  the Returning Officer by Ex.  P. 13 because it was an  important matter  connected with the election.  Mr. Narasaraju  hinted that some outside influence was at work in the  cancellation of the earlier certificate inasmuch as the Minister for  the Public Works Department was present at Yadagiri and had also camped  at  Gulbarga on the following day.  He  pointed  out that the Chief Engineer and the Executive Engineer were also present.   The insinuation is that this was done  under  the pressure  of  the Minister, because the  Congress  had  been consistently losing the seat at Yadagiri and it was intended that  the first respondent should be knocked out  to  ensure Congress  victory.  We do not find any evidence which  shows that the Minister took any interest in this matter  although his presence may give rise to some suspicion.  We cannot  go on  suspicion  alone.  It is obvious that  both  sides  were straining  every nerve to get some documentary  evidence  in their  hands to prove, one that the work was incomplete  and the   other,  that  the  work  was  completed.   The   later certificates  clearly  show that certain parts of  the  work remained to be completed and they certainly were  overlooked when the first certificate was given.  That they were  minor items  is  not much to the purpose.  The contracts  as  such were  not  fully  performed.  Although  we  were  hesitating whether  to apply the de minimis rule to this case we  think that  there are other considerations why we  should  refrain from  applying that rule.  We make our position  clear.   If

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9  

the  work is completed, it would not mean that the  contract is  subsisting, if, say, a glass pane is found broken  or  a tower  bolt  or a drop bolt or a handle has not  been  fixed where it should have been.  The law is not so strict as  all that  and  a sensible view of the section will  have  to  be taken.  The right of a person to stand for an election is  a valuable right just as a right of a person to vote was  con- sidered  a valuable right in the leading case of.  Ashby  v. White(1).  But if the contract subsists in such manner  that it cannot be said to have been substantially completed,  the law must take ;Its own course.  It is of the essence of  the law  of  Elections that candidates must be free  to  perform their  duties without any personal motives being  attributed to them.  A contractor who is still holding a contract  with Government  is considered disqualified, because he is  in  a position  after  successful election to get  concession  for himself in the performance of his contract.  That he may not do so (1)  [1703] 2 Ld.  Raym, 938. 402 is  not  relevant.   The possibility being  there,  the  law regards  it  necessary  to keep him  out  of  the  elections altogether.   But as we stated, this will be only where  the contract has not been fully performed, although what is full performance  of  a contract or completion, is  a  matter  on which  we  do not wish to express a final  opinion  in  this case,  because it depends on the circumstances of each  case and   more  particularly  because  there  is  here   another condition to which we have referred. In  both  the contracts, there was a condition  that  for  a period  of three months in one and for a period of one  year in  the other, the contractor would make due repairs to  all the  defective parts in the execution of the contract.   The question  is  whether  the  contract  can  be  said  to   be subsisting  in view of this clause.  Both sides referred  us to  Hudson’s  Building and Engineering  Contracts.   In  one passage, Hudson regarded such a clause as in the nature of a ’repair clause.  But Hudson was not dealing with the law  of election when he was discussing a clause such as we have  in this case.  We have to interpret this clause in the  context of  election law.  Now the contract must be said to  subsist if a portion of it is required to be performed at any  time, because so long as the contract has not been discharged,  by full  performance,  it  must  be  taken  to,  subsist.   Mr. Narasaraju  contends  that  the phrase "  contract  for  the execution of the work" shows that it is the execution of the original work which is contemplated and not any condition of guarantee  for  repair.   In  our  opinion,  this  argument, however,  ingenious,  is not acceptable  because  a  similar point  arose in the case to which we referred  earlier.   In Chatturbhuj Vithaldas Jasani’s(1) case, Bose J. dealt with a similar point in the following words :               "It  was argued that assuming that to  be  the               case, then there were no longer any  contracts               for  the " supply of goods" in  existence  but               only an obligation arising under the guarantee               clause.  We are unable to accept such a narrow               construction.   This  term  of  the  contract,                             whatever  the parties may have chosen  to  call               it, was a term in a contract for the supply of               goods.   When a contract consists of a  number               of  terms and conditions each  condition  does               not form a separate contract but is an item in               the  one contract of which it is a part.   The

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9  

             consideration  for  each condition in  a  case               like   this  is  the  consideration  for   the               contract taken as a whole.  It is not split up               into   several   considerations    apportioned               between each term separately.  But quite apart               from  that,  the obligation, even  under  this               term,  was  to supply fresh stocks  for  these               three depots in exchange for the stocks  which               were returned and so eve               (1)   [1954] S.C.R. 817.               403               when regarded from that narrow angle it  would               be a contract for the supply of goods.  It  is               true  they are replacements but a contract  to               replace  goods is still one for the supply  of               the goods which are sent as replacements." Applying  these observations in the context of  construction of  buildings and roads, it is obvious that if some part  is found  defective and has to be done again, the  contract  of execution  as  such is still to be fully performed.   It  is possible  to describe the action taken as one to repair  the defect,  but  in essence, it -is a part of the  contract  of execution, because no execution can be said to be proper  or complete till it is properly executed.  Taking the fact that some  portion  of  the original  contracts  remained  to  be performed  with  the  fact  that  under  the  contracts  the contractor  was required not only to complete  the  original work  but to repair defects or re-do something which he  had not properly done, we think this matter must fall within  s. 9A  of the Representation of the People Act.  This is not  a case  like the supply of a refrigerator which  after  giving service for some time goes out of order and something has to be  done to replace a part which is defective.  The  analogy is not quite apposite.  Here the building was completed very recently  and  the flooring had to be  re-done  and  various other  things  were  left unfinished and  these  had  to  be completed  by the contractor.  Similarly in relation to  the road, although the surface was prepared and the road was  in actual  use, under the contract, mile and hectometer  stones had to be fixed and certain other stones fixed at curves and boundaries.  This was not done.  The two contracts therefore were not fully performed and under cl. 20 of the  agreement, it  was incumbent upon the contractor to complete this  part of  his obligation.  In our opinion, the High Court  was  in error in holding that the contracts had been fully performed and therefore s. 9A did not apply. Mr. Narasaraju raises three legal points.  The first is that under  Art.  299,  the  contract had to  be  signed  by  the Secretary to the Government whereas the contract was  signed by  the Executive Engineer.  This point was also  considered in  Jasani’s(1) case and it was held that it did not  go  to save  the bar of the election law to the candidature.   Next it  is  argued that the section is applicable  to  a  person whereas the contract was with a firm and therefore the first respondent  was not barred from standing for  the  election. In  our opinion, the High Court has taken the right view  of the  matter.  The law requires that a candidate  should  not have any interest in any contract with Government and even a partner has an interest sufficient to attract the provisions of s. 9A.  Lastly it is argued that the partnership (1)  (1954.) S C.R. 817. 404 itself  had been dissolved.  That would have no effect  upon the   relations  between  the  first  respondent   and   the Government.   The  first respondent could not by  a  private

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9  

dissolution  of the partnership escape his  liability  under the contract to the Government, and there was here notation, because   notice  of  the  dissolution  was  not  given   to Government  and the Government had not accepted Hampanna  to whom the ’business was transferred in place of the firm.  We view  the transfer of the entire contracts to Hampanna  with some suspicion.  It appears that on the eve of the election, the  first  respondent who wished to contest the  seat  from Yadagiri,  hurried through his contracts, managed to  get  a completion   certificate  which  was  not  quite   accurate, dissolved the partnership with a view to clear himself  from all  connections with the contracts so that he  could  stand for the election.  In this effort, he has distinctly failed. We  are  satisfied  that this appeal must  succeed  and  the appeal  is  therefore  allowed, the election  of  the  first respondent  is declared void.  In this view of  the  matter, the  votes  cast in favour of the first respondent  must  be treated  as thrown away.  As there was no  other  contesting candidate  we  declare the appellant  (election  petitioner) elected  to  the seat from the Yadagiri  constituency.   The first  respondent  shall  bear the costs  of  the  appellant throughout. R.K.P.S. Appeal allowed. 405