KISHORSINH RATANSINH JADEJA Vs MARUTI CORP..
Case number: C.A. No.-002186-002187 / 2009
Diary number: 13988 / 2008
Advocates: T. MAHIPAL Vs
EJAZ MAQBOOL
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.2186-2187 OF 2009 (Arising out of S.L.P.(C)Nos.12854-12855 of 2008)
Kishorsinh Ratansinh Jadeja ... Appellant Vs.
Maruti Corp. & Ors. ... Respondents
J U D G M E N T
ALTAMAS KABIR, J.
1. Leave granted.
2. The appellant and the Respondent Nos.2 to 7 are
owners of agricultural land in Survey No.36
measuring 32 acres and 38 gunthas situated in
Village Nanamauva, Taluka & District Rajkot
(hereinafter referred to as the ‘suit land’). On
1
19th March, 1980, the appellant and the other joint
owners of the suit land entered into an Agreement
with Tirupati Cooperative Housing Society – a
proposed Cooperative Housing society – for
development of the said land upon obtaining
necessary permission under Section 20 of the Urban
Land (Ceiling & Regulation) Act, 1976 (hereinafter
referred to as the ‘Land Ceiling Act, 1976’) for
exemption and for construction of houses for the
weaker sections. The application made by the
proposed Society on 29th April, 1988, under Section
20 of the Land Ceiling Act, 1976, was rejected and
according to the appellant and other joint owners,
on the failure of the proposed Society to get such
permission, the Agreement could not be performed
and, therefore, by Public Notice dated 24th April,
1988, the Agreement was declared to have been
cancelled.
3. A legal notice was received from one Sharad N.
Acharya, Advocate, denying that the Agreement had
been cancelled, as indicated in the Public Notice.
2
Despite cancellation of the Agreement, the
Respondent No.1 called upon the appellant to give
effect to the Agreement dated 19th March, 1980,
executed with the said respondent for development
of the said land. The Respondent No.1 thereupon
filed Special Civil Suit No.299 of 1999 on 29th
November, 1999, before the Civil Court at Rajkot
against the appellant, inter alia, praying for a
declaration that the Respondent No.1 was in
possession of the suit land and for a decree for
specific performance of the said Agreement. In the
alternative, for a decree for refund of the earnest
money of Rs.1,81,000/- and for damages amounting to
Rs.16,30,670/- with interest @12% per annum. The
Respondent No.1 also filed an application for
interim injunction to restrain the appellant from
entering into the said land and disturbing the
possession of the Respondent No.1 and to further
restrain the appellant from alienating the land to
any third party. The Civil Court at Rajkot
dismissed the said application by its order dated
29th April, 2002, against which the Respondent No.1
3
filed appeal from Order No.372/2000 before the
Gujarat High Court, which was ultimately withdrawn
with a direction for expeditious disposal of the
suit within a period of 10 months. The suit was
thereafter taken up for trial by the Civil Court at
Rajkot, and by judgment and order dated 23rd
November, 2007, while rejecting the prayer for
specific performance, the Trial Court directed
refund of the earnest money.
4. The Respondent No.1, thereafter, filed an
appeal on 15th February, 2008, being First Appeal
No.853/2008, along with an application, being Civil
Application No.2405/2008, inter alia, to restrain
the respondents therein from transferring or
alienating the land in question to any third party
till the disposal of the appeal. Since the
appellant was on caveat before the High Court,
after hearing the parties, the Division Bench of
the Gujarat High Court admitted the appeal but did
not grant any stay, as prayed for, and only
directed that if the property in question was dealt
4
with in any way, that would be subject to the
decision of the appeal.
5. Although, the Respondent No.1 failed to obtain
any order of injunction in the appeal, he issued a
Public Notice through his learned Advocate on 7th
March, 2008, asking the public not to deal with the
property. In response thereto, the appellant also
caused a Public Notice to be published on 10th
March, 2008, clarifying that no injunction order
had been passed by the Gujarat High Court. The
said fact was brought to the notice of the Gujarat
High Court by the Respondent No.1 by way of an
additional affidavit on the basis whereof, the High
Court passed an order on 22nd April, 2008, directing
that the property in question should not be sold.
Thereafter, on 6th May, 2008, a further application
for injunction No.5618/2008 was filed in the
pending First appeal by the Respondent No.1 herein
indicating that constructions were being raised on
the land in question. On the basis of the above,
the Division Bench of the Gujarat High Court, on 7th
5
May, 2008, passed the following order impugned in
these appeals :
“By this application, learned counsel for the applicant submits that inspite of the directions of this court issued vide orders dated 29.02.2008 and 22.04.2008, the constructions are being raised in the disputed land.
Learned counsel Mr. Pahwa, the respondent No.2 submits that the constructions were raised about 6 months back, and part of the property was already sold.
To avoid further complications and multiplicity of litigations, we order that no construction be raised on the disputed land. In spite of our direction, if further construction is raised, the applicant will be at liberty to approach the concerned police authority, and the concerned police authority is also directed to take immediate steps to stop the construction on the disputed land.
Civil application stands disposed of.”
6. Appearing for the appellants, Mr. Mukul
Rohtagi, submitted that the Respondent No.1, Maruti
Corporation (plaintiff in the suit), came to be
registered as a partnership firm on 21st June, 1989,
but has sought specific performance of an agreement
alleged to have been entered into with the
6
appellant on 19th March, 1980, executed on a Non-
judicial stamp paper dated 17th March, 1990. Mr.
Rohtagi urged that it was obvious that the claim of
the Respondent No.1 in the plaint had no valid,
legal and/or factual foundation, on the basis of
which the interim orders could have been passed by
the High Court. He submitted that none of the
three orders impugned in the appeal were speaking
or reasoned orders. As the orders would themselves
reveal, they were simply reactions to new facts
brought to the notice of the Court from time to
time and orders were passed on the basis thereof
without even giving the appellant herein or other
interested parties a proper opportunity of meeting
the allegations or questioning the same. Mr.
Rohtagi submitted that the several interim orders
passed by the Division Bench were devoid of any
reason and were liable to be set aside.
7. Mr. Ranjit Kumar, learned senior counsel, who
appeared for the Respondent Nos.2 to 7, who were
the joint owners of the property with the
7
appellant, while adopting Mr. Rohtagi’s
submissions, supplemented the same by contending
that the original agreement with Tirupati
Cooperative Housing Society stipulated that the
said proposed Housing Society would have to apply
to the authorities of the Land Ceiling Act, 1976,
under Section 20 thereof, for exemption and leave
to construct on the vacant land. Learned counsel
submitted that such application had been made by
Tirupati Cooperative Housing Society, but the same
was rejected and on such rejection, a public
announcement was made discontinuing the agreement
between the owners of the land and the proposed
Tirupati Cooperative Housing Society.
8. Mr. Ranjit Kumar urged that the owners of the
property had never entered into any agreement with
Maruti Corporation-Respondent No.1 herein, which
filed a suit identical to that filed by Tirupati
Cooperative Housing Society, relying on the same
cheques by which Tirupati had advanced certain sums
to the owners of the property. Mr. Ranjit Kumar
8
also urged that, in any event, even if the case of
the Respondent No.1 is accepted as correct, for 19
years it had not applied for exemption to develop
the land under Section 20 of the Land Ceiling Act,
1976, without which it was not possible to develop
the property. It is only after the repeal of the
Land Ceiling Act, 1976, on 19th March, 1999, that
the Respondent No.1 filed the aforesaid suit
seeking enforcement of an agreement alleged to have
been entered into between the parties on 19th May,
1980, when exemption under Section 20 of the said
Act was no longer required.
9. Mr. Ranjit Kumar submitted that initially when
the First Appeal of the Respondent No.1 was
admitted in the Gujarat High Court, an order was
also passed in Civil Application No.2405 of 2008 to
the effect that if the property in question was
dealt with in any way the same would be subject to
the decision in the appeal. Learned counsel urged
that since in its order the High Court had embodied
the principles of Section 52 of the Transfer of
9
Property Act, 1882 and there was no bar to the
alienation of the property, as many as 280 plots
had been sold to different purchasers by way of
registered sale deeds and they had started
construction on the plots which they had acquired
presumably after obtaining necessary development
permission sanctioned by the Rajkot Municipal
Corporation. It was submitted that up to such point
there could be no objection with regard to the
orders passed in the First Appeal. Thereafter,
when the interim order was modified on 22nd April,
2008, on the same application and the owners of the
property were restrained from selling the same, the
said modification, though not called for, was still
capable of being defended.
10. The real problem was created when on 7th May,
2008, on a fresh Civil Application for Injunction
No.5618 of 2008 filed on 6th May, 2008, an order was
passed by the Division Bench which not only had
serious consequences for the transferees but also
for the owners of the land who were parties to the
10
suit. The order which has been extracted
hereinabove directed that no construction be raised
on the disputed land and if any further
construction was raised, the Respondent No.1 herein
would be at liberty to approach the concerned
police authorities who were directed to take
immediate steps to stop the construction on the
disputed land. Mr. Ranjit Kumar emphasised that
the cryptic manner in which the said application
was disposed of by such a mandatory order, was
contrary to all legal principles and even
procedural law. He submitted that no liberty to
deal with the fresh application filed on 16.5.2008
was even given by the Division Bench to the
respondents in the appeal and on the very next day
on 7th May, 2008, without even giving any reasons
for passing such an order, it disposed of the same
finally to the severe prejudice of the appellant
and the Respondent Nos. 2-7 herein and the 280
transferees to whom plots had been conveyed and
that too when they were not parties to the appeal.
11
11. It was also submitted that no thought was even
given to the principles embodied in Order XXXIX
Rules 1 and 2 of the Code of Civil Procedure before
such a drastic order of injunction was passed by
the High Court in the First Appeal. Mr. Ranjit
Kumar submitted that the basic principles for
granting injunction involving the making out of a
prima facie case, the balance of convenience and
inconvenience, and irreparable loss and injury,
were not even taken into consideration when the
orders of injunction were passed.
12. In addition to the above, Mr. Ranjit Kumar also
referred to the decision of this Court in Mandali
Ranganna & others vs. T. Ramachandra [(2008) 11 SCC
1] wherein an additional principle was sought to be
enunciated relating to grant of injunction by way
of an equitable relief. This Court held that in
addition to the three basic principles, a Court
while granting injunction must also take into
consideration the conduct of the parties. It was
observed that a person who had kept quiet for a
12
long time and allowed others to deal with the
property exclusively would not be entitled to an
order of injunction. The Court should not
interfere only because the property is a very
valuable one. Grant or refusal of injunction has
serious consequences depending upon the nature
thereof and in dealing with such matters the Court
must make all endeavours to protect the interest of
the parties.
13. Mr. Ranjit Kumar submitted that having filed
the suit for enforcement of its purported rights
under the Agreement of 1980 in the year 1999 and
having allowed the owners of the property to deal
with the same and certain rights having been
created in favour of third parties when there was
no restraint orders of the Courts, the High Court
erred in granting such an interim order with such
drastic consequences without even giving the
persons, who were to be adversely affected by the
order, an opportunity of being heard.
13
14. Opposing the submissions made on behalf of the
appellant and the Respondent Nos.2 to 7, Mr. Soli
J. Sorabjee, learned senior counsel, submitted that
it was necessary to clear the impression that had
been given that the Respondent No.1-Maruti
Corporation came into existence only on 21st June,
1989. He submitted that, on the other hand, the
Respondent No.1 was in existence even in 1980, but
as an unregistered partnership, and that it became
a registered partnership on 21st June, 1989. Mr.
Sorabjee submitted that the question of the
existence of Maruti Corporation or the validity of
the agreement executed between Maruti Corporation
and the owners of the property would have to be
considered on evidence and till a decision was
arrived at in the matter, it was only appropriate
that the status-quo of the property be maintained,
particularly when a large number of transfers are
alleged to have been made, which could make the
relief sought for by the Respondent No.1 a mere
paper relief, if it ultimately succeeded.
14
15. Mr. Sorabjee also contended that when the
application for a restraint order against
construction was sought to be filed on 6th May,
2008, neither the appellant nor the other
respondents had disclosed the fact that such
transactions had already taken place and that the
transferees had started raising their construction
on the basis of such conveyances.
16. Mr. Sorabjee took pains to point out that while
in the suit all the issues had been decided against
the plaintiff, the issue relating to limitation
had, however, been decided in favour of the
plaintiff and it was held that the suit for
specific relief was not barred by limitation. Mr.
Sorabjee submitted that since the injunction order
was in force since 7th May, 2008 and more than 10
months had passed since then, without disturbing
the interim order of stay, the High Court could be
requested to dispose of the First Appeal which is
pending before it expeditiously.
15
17. Mr. Huzefa Ahmadi, who appeared for the
Respondent No.1 - Maruti Corporation in Special
Leave Petition (Civil) No. 12855 of 2008, while
adopting Mr. Sorabjee’s submissions, urged that the
Tirupati Cooperative Housing Society had been
created by Maruti Corporation with a definite
object in mind. He submitted that the lands in
question were agricultural in nature and could not,
therefore, be acquired by any other body other than
a cooperative society. It was on account of such
bar that the Tirupati Cooperative Housing Society
was proposed to be created on grounds of expediency
and was yet to be registered. He also submitted
that the payments made to the owners by Tirupati
Cooperative Housing Society had been made from the
account of Maruti Corporation and consequently when
exemption under Section 20 of the Land Ceiling Act,
1976, was not granted to the proposed Cooperative
Society, the Respondent No.1 filed a separate suit
for specific performance of the agreement which had
been entered into with the Maruti Corporation and
the payments made by Tirupati Cooperative Housing
16
Society were shown to be the payments which had
been made by Maruti Corporation. Mr. Ahmadi also
submitted that Maruti Corporation could not apply
for exemption under Section 20 of the Land Ceiling
Act, 1976, and as a consequence it filed the suit
for specific performance only after the said Act
was repealed, thereby doing away with the necessity
of obtaining exemption under Section 20 thereof.
Mr. Ahmadi also contended that unless the appellant
and the other joint owners of the property and
their transferees were suitably restrained from
dealing with the properties during the pendency of
the two appeals before the first Appellate Court,
the appeals would be rendered infructuous as it
would become impossible once the constructions had
come up, to revert back to the position when the
plots were still undeveloped.
18. On a careful consideration of the submissions
made on the behalf of the respective parties, the
scenario which emerges is that while on the one
hand the Respondent No.1 is strongly in favour of
17
the status quo of the suit lands being maintained
during the pendency of the suit for specific
performance filed by it, the appellant and the
other joint owners have projected a case of both
balance of convenience and inconvenience and
irreparable loss on being restrained from
developing their own property by the Respondent
No.1, purportedly on the basis of a spurious
document. Mixed with the aforesaid issues is the
issue of the 280 transferees to whom plots have
been conveyed by the owners and who were enjoying
the same by raising structures which were at
different stages of construction. We are faced
with a situation where inspite of having obtained
the said plots at a point of time when the
injunction against the owners was not in force, the
transferees, who were not even parties before the
Court, have been restrained by an interim order of
injunction of a mandatory nature which seriously
affects them, but without giving them any
opportunity of hearing.
18
19. We have to consider the effect of the third
order passed on 7th May, 2008, on Civil Application
for Injunction No.5618 of 2008 filed of the
previous day on 6th May, 2008, ordering that no
construction be raised on the disputed lands on the
280 transferees who were in the process of raising
their constructions. As will be apparent from the
order itself, the same was passed in great haste
without even giving the owners of the lands an
opportunity of contesting the application. In
fact, the application was disposed of by a cryptic
order which does not even contain any reason for
passing the same. The Division Bench has merely
indicated that to avoid further complications and
multiplicity of litigation, the order was being
passed not to raise constructions on the disputed
land, without even taking into consideration the
several transferees who were to be adversely
affected by such an order. Even the appellant
herein and the Respondents No.2 to 7 were not given
an opportunity of filing any affidavit to counter
19
the statements and allegations made in the
application for injunction.
20. It is quite obvious that the High Court was
completely oblivious to the facts of the case and
passed different orders at different times on the
applications filed at regular intervals by the
Respondent No.1 Corporation.
21. The reasoning provided in the interim order
dated 22nd April, 2008, is, to say the least,
legally untenable. Having passed an order earlier
on 29th February, 2008, based on the principle of
lis pendens, the Division Bench of the High Court
in its second order dated 22nd April, 2008, observed
that when the First Appeal was admitted and the
matter in dispute as regards the property in
question was sub-judice, the properties in question
should not be sold and passed an order which was
contrary to the initial order which was made in
keeping with Section 52 of the Transfer of Property
Act.
20
22. It is well established, that while passing an
interim order of injunction under Order XXXIX Rules
1 and 2 CPC, the Court is required to consider
three basic principles, namely,
(i) prima facie case;
(ii) balance of convenience and inconvenience;
and
(iii) irreparable loss and injury.
None of the said principles have been
considered by the High Court while passing the
second and third interim orders dated 22nd April,
2008 and 7th May, 2008, nor has the High Court taken
into account the long silence on the part of the
Respondent No.1 Corporation in filing a suit after
19 years.
23. In our view, while passing the interim order
dated 7th May, 2008, the High Court ought to have
considered the effect which its order would have on
the 280 transferees to whom some portions of the
21
land had already been sold and who had commenced
construction thereupon, particularly when they were
not even parties in the appeal, nor were they heard
before they were injuncted from continuing with the
construction work. Such an order affecting third
party rights in their absence, as they were not
parties to the proceedings, cannot be sustained
having further regard to the manner in which the
said order was passed. An application for an order
which would have far and wide reaching consequences
was sought to be disposed of by the Division Bench
on the very next day without giving an opportunity
of controverting the allegations made therein even
to those who were parties in the suit, though it
had been brought to the notice of the Court that
conveyances had been executed in favour of 280
purchasers. This is not a case where the appellant
and the other co-owners had violated any restraint
order passed by the Court in transferring the plots
in question to the said 280 transferees. The said
transfers were effected at a point of time when
there was no injunction or restraint order against
22
the appellant and the other owners of the property
and as far as the said transfers are concerned, the
only order that could have been passed on the said
application is the order which was passed at the
first instance on 29th January, 2008, based on the
principles of Section 52 of the Transfer of
Property Act, 1882. The restraint order on the
transferees must, therefore, be held to be bad and
liable to be set aside.
24. As far as the lands which the appellant and the
other joint owners have been restrained from
alienating by the second order dated 22nd April,
2008, are concerned, we are of the view that in the
event the order of 22nd April, 2008, is set aside,
the Respondent No.1 can be compensated in terms of
money and no irreparable loss and injury will be
caused to it on account thereof. On the other
hand, if the owners of the property remain
restrained from developing the same, it is they,
who will suffer severe prejudice, as they will be
deprived of the benefit of the user of their land
23
during the said period. The balance of convenience
and inconvenience is against grant of such
injunction. The success of the suit for specific
performance filed by the Respondent No.1 depends to
a large extent on tenuous proof of genuineness of
the agreement sought to be enforced after 19 years,
despite the finding of the Trial Court that the
suit was not barred by limitation.
25. The question of conduct of the Respondent No.1
also becomes relevant, inasmuch as, having slept
over its rights for more than 19 years, it will be
inequitable on its prayer to restrain the owners of
the property from dealing with the same, having
particular regard to the fact that a large portion
of the land has already been conveyed to as many as
280 purchasers who are in the process of erecting
constructions thereupon.
26. We are, therefore, unable to sustain the
interim orders passed by the Division Bench of the
24
Gujarat High Court on 22nd April, 2008 and 7th May,
2008 in the appeals pending before it.
27. We, accordingly, set aside the orders dated
22nd April, 2008 and 7th May, 2008, passed by the
Division Bench of the Gujarat High Court in
F.A.No.853 of 2008 and C.A. Nos.2405 and 5618 of
2008 and maintain the initial order dated 29th
February, 2008. The appeals and the connected
Interlocutory Applications are, accordingly,
disposed of.
28. The High Court is requested to dispose of the
appeals pending before it at an early date without
being influenced by any observations made in this
judgment.
29. There will be no order as to costs.
______________J. (ALTAMAS KABIR)
25
New Delhi ______________J. Dated:06.04.2009 (CYRIAC JOSEPH)
26