KANPUR ELECT.SUPPLY CO.LTD. Vs M/S L.M.L.LIMITED .
Case number: SLP(C) No.-033984-033984 / 2009
Diary number: 37359 / 2009
Advocates: Vs
E. C. AGRAWALA
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
Page 21
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
Page 30
Page 31
Page 32
Page 33
Page 34
Page 35
Page 36
Page 37
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITION (CIVIL) NO. 33984 OF 2009
Kanpur Elect. Supply Co. Ltd. & Anr. … Petitioners
Vs.
M/s. L.M.L. Limited & Ors. … Respondents
J U D G M E N T
ALTAMAS KABIR, J.
1. The Respondent No.1 is a Public Limited Company
engaged in the manufacture and sale of two-
wheelers, scooters and motorcycles, having its
registered office at Panaki Industrial Area in
Kanpur, U.P. The Company obtained power load from
the Kanpur Electricity Supply Administration,
hereinafter referred to as “KESA”, which was
extended from time to time. In the year 2006, the
sanctioned load of the Company was 8 MVA from 132
KV line.
2. On account of a decreasing market the Company
apprehended that its work force would be directly
affected and, accordingly, made a representation to
the State Government for declaring the Respondent-
Company as a “Relief Undertaking” under Section
3(1) of the U.P. Industrial Undertaking (Special
Provisions for Prevention of Unemployment) Act,
1966. A Notification was issued by the State
Government on 24th June, 2004, suspending all
contracts, agreements and other instruments in
force under any law, for a period of one year which
resulted in a strike disrupting the operations of
the company. Consequently, all manufacturing
activities of the Respondent-Company came to a
halt, ultimately leading to the declaration of a
lockout on 7th March, 2006. As a result, on 31st
2
March, 2006, the Respondent-Company applied to the
Kanpur Electricity Supply Company, hereinafter
referred to as “KESCO”, for reduction of the
contract load from 8 MVA to 1.25 MVA with effect
from 1st April, 2006. On 19th April, 2006, a meeting
took place between the officers of KESCO and the
Respondent-Company in which a decision was taken
for reduction of the load with certain conditions.
On the said date itself KESCO conveyed its
agreement for reduction of load to the U.P.
Electricity Regulatory Commission and sought its
formal approval.
3. The Commission did not raise any objection
regarding the decision to reduce the load but it
observed that the agreement which had been reached
between the parties was internal to the parties and
the same had to be implemented strictly in
accordance with the Electricity Supply Code, 2005.
Thereafter, the Respondent wrote to KESCO on 17th
3
May, 2006, to reduce the load with effect from 1st
April, 2006. However, the electricity bill for the
month of May, 2006 based on 8 MVA load was
presented to the Respondent on 7th June, 2006. The
Respondent immediately sent a letter of protest
indicating that the bill amount ought to have been
raised on the basis of the agreed load of 1.25 MVA.
The respondent paid the bill on the basis of 1.25
MVA load and also invoked the provisions of the
Sick Industrial Companies (Special Provisions) Act,
1985, hereinafter referred to as the “SICA”. The
said reference was registered as Case No.80 of 2006
on 15th September, 2006 and, thereafter, on 8th May,
2007, the Respondent-Company was declared as a sick
industrial company under section 6(3)(o) of the
1985 Act and the IDBI Bank was appointed as the
Operating Agency. On 4th October, 2006, KESCO wrote
to the Respondent-Company for submitting a Bank
Guarantee for the arrears of the amount as per
Clause 4.49 of the U.P. Supply Code, 2005 so that
4
action could be taken to reduce the load from 8 MVA
to 1.25 MVA. In response, the Respondent No.1-
Company wrote to KESCO indicating that once the
normal work of the factory was restored, the
payment of arrears of electricity dues would be
finalized.
4. On 11th March, 2007, the Respondent-Company
restarted its manufacturing activities and
requested KESCO to increase the load from 1.25 MVA
to 2.25 MVA. KESCO, however, responded on 20th
March, 2007, informing the Petitioners that the
load reduction could not be considered owing to
non-submission of the Bank Guarantee by the
Respondent-Company for the balance amount of the
bill raised for the month of May, 2006. On 3rd
August, 2007, a settlement was arrived at with
regard to the payment of arrears. As the
respondent was registered as a Sick Unit with the
Board for Industrial and Financial Reconstruction,
5
hereinafter referred as the “BIFR”, the said Board
by its order dated 22nd October, 2007 directed KESCO
to continue to accept Rs.5 lakhs per month against
their arrears, besides payment of current
electricity bills on actual consumption basis, and
not to adopt coercive measures to disconnect the
supply of electricity. However, on 6th April, 2009,
a disconnection notice was issued by KESCO against
which the Respondent-Company filed Writ Petition
No.20499 of 2009 in which an interim order was
passed by the Allahabad High Court on 22nd April,
2009, directing that in case the Respondent-Company
continued to pay the amount as directed by the
BIFR, its electricity supply would not be
disconnected. The said writ petition is still
pending disposal. However, since, in the meantime,
the claim of the Respondent-Company for reduction
of the load from 8 MVA to 1.25 MVA with effect from
1st April, 2006, was not decided or implemented, the
Respondent-Company filed Writ Petition No.20499 of
6
2009, inter alia, for an appropriate writ or
direction to the effect that the load of the
Respondent-Company stood reduced from 8 MVA to 1.25
MVA pursuant to the then prevalent provisions of
Clause 4.41(b) of the 2005 Code, with effect from
1st April, 2006, 2.25 MVA with effect from April,
2007 and 2.50 MVA with effect from August, 2007.
5. Interpreting the provisions of Clauses 4.41 and
4.49 of the U.P. Electricity Code, 2005, the High
Court came to the conclusion that the decision with
regard to the reduction of the load of the
Respondent-Company stood approved on 19th April,
2006, and, accordingly, the effective date of such
reduction would have to be reckoned from the first
day of the following month, namely, from 1.5.2006,
in terms of Clause 4.41(e) of the Code. The writ
petition was, accordingly, allowed and it is
against such order of the writ court, that the
present Special Leave Petition has been filed.
7
6. From what has been indicated hereinabove, it
will be clear that the question required to be
answered in the present Petition involves the
interpretation of Clause 4.41 read with Clause 4.49
of the U.P. Electricity Supply Code, 2005, framed
under Section 50 of the Electricity Act, 2003. In
order to appreciate the issue raised, the
provisions of Clause 4.41 are reproduced
hereinbelow :
“4.41 Reduction in Contracted load.
(a) Every application for reduction of contracted load shall be made in duplicate to the concerned officer on prescribed form (Annex-4.10) along with the prescribed processing fee and charges for reduction of load alongwith the following documents:
(i) Work completion certificate and test report from the licensed electrical contractor where alteration of the installation is involved.
(ii) Maximum demand recorded in the last two billing cycles if the meter has the facility to record
8
maximum demand and the electricity bill of the previous two billing cycles.
(iii) Letter of approval from the Electric-Inspector, wherever applicable (or as per rules when framed under Section 53).
(iv) Copy of the latest paid electricity bill. If matter related to dues is pending in court, the procedure as per Clause 4.49 may be followed.
(b) The designated authority of the Licensee shall communicate to the consumer the decision on his application within thirty days of receipt of the duly completed application.
(c) A fresh agreement for reduced load shall be executed for 2 years but the period of compulsory agreement 2 years for the purpose of payment of MCG shall be counted from the date of original agreement for the purpose of P.D.
(d) No refund shall be allowed for the deposited cost of the line and substation. However, if the security deposited earlier is in excess of the requirement for the reduced load, the excess of the requirement for the reduced load, the excess shall be adjusted in future bills.
(e) The effective date of such reduction shall be reckoned from the first day of the following month in which the
9
application has been sanctioned by the licensee.
(f) ………………”
7. Clause 4.49 was amended with effect from 14th
September, 2006. Accordingly, both the unamended
provisions of Clause 4.49 and the amended
provisions are set out hereinbelow :
Unamended version :
“4.49. Release of Connection/Load where arrears disputed are stayed by Court/other forums :
Where there is stay order by any Court, Forum, Tribunal, or by Commission, staying the recovery of any dues by licensee, and during the operating period of any such order:
(i) If a consumer sells a premises and an application for release of new connection is made by the purchaser.
Or
(ii) If any application for enhancement or reduction of load is made by a consumer.
10
the licensee shall release the new connection to such consumer and also permit reduction or enhancement of loads,
Subject to
• Submission either of Bank Guarantee, or Bonds, or any instruments to the satisfaction of licensee of equivalent amount of pending dues, by the applicant, and,
• Agreement with licensee on terms of extension/invoking of guarantee, and,
• Levy of surcharge amount on pending dues,
And the application of such consumers shall not be kept pending by the licensee.”
Amended version :
“4.49. Permanent disconnection/ release of Connection/Enhancement and Reduction of Load where arrears disputed are stayed by Court/other forums :-
Where there is a stay order by any Court, Forum, Tribunal, or by Commission, staying the recovery of any dues by licensee, and during the operating period of any such order –
(i) If a consumer sells a premises and an application for release
11
of new connection is made by the purchaser; or
(ii) If any application for new connection, reconnection, en- hancement or reduction of load is made by a consumer; or
(iii) If any application for permanent disconnection is made by a consumer the licensee shall release the new connection to such consumer and also permit reconnection reduction or enhancement of Loads, as well as allow permanent disconnection.
Subject to
• Submission of Bank Guarantee to the satisfaction of licensee, of equivalent amount of pending dues, by the applicant or owner, and,
• Agreement with licensee on terms of extension/invoking of guarantee, and
• Levy of surcharge amount on pending dues,
and the application of such consumers shall not be kept pending by the licensee.”
12
8. As will be seen from the above, if any
application for reduction of load is made by a
consumer, such reduction could be permitted subject
to :
“Submission either of Bank Guarantee, or Bonds, or any instruments to the satisfaction of the licensee of equivalent amount of pending dues by the applicant.”
9. The said condition was replaced in the amended
provisions by the following condition :
“Subject to submission of Bank Guarantee to the satisfaction of the licensee, of equivalent amount of pending dues, by the applicant or owner.”
10. It is the difference between the said two
provisions, whereby the submission of a Bond had
been excluded from the amended provisions, which
has given rise to the disputes in the present case.
11. It appears that the outstanding dues of the
Respondent-Company were 8.42 crores as on 31st
13
March, 2006 and hence the load was not reduced. In
the meantime, after the amendment of Clause 4.49 of
the Code, a letter was sent to the Respondent-
Company on 4th October, 2006, asking it to submit a
Bank Guarantee/Bond securing the amount of Rs.10.24
crores outstanding as arrears on that date. The
Respondent-Company, accordingly, by its letter
dated 17th June, 2007, submitted a Bond stating
therein that the Company was agreeable to make
payment of the arrears, if any, to KESCO upon the
directions of the Court and the amount as was
decided by the Courts. However, since the two
affidavits and the Bond did not secure the
outstanding dues of the Petitioners and were also
not to its satisfaction, the load was not reduced.
As indicated hereinabove, the Respondent-Company,
thereafter, filed Civil Misc. Writ Petition
No.24900 of 2009 before the Allahabad High Court.
14
12. Learned ASG, Mr. Parag Tripathy, appearing for
the Petitioners, submitted that since neither the
two affidavits nor the Bond filed by the
Respondent-Company were acceptable to the
Petitioners, the load was not reduced from 8 MVA to
1.25 MVA, as requested, since securing the
outstanding balance was one of the pre-conditions
for such reduction. The learned ASG urged that
since securing the amount payable was involved,
neither the affidavits nor the Bond could guarantee
recovery of the arrear dues in case of breach. It
was further urged that even the unamended version
of clause 4.49, on which the Respondent-Company
relies, makes it very clear that either release of
a new connection or the reduction or enhancement of
loads would be subject to submission of either a
Bank guarantee or Bond or any instrument to the satisfaction of the licensee (emphasis added). The learned Additional Solicitor General submitted that
the High Court appears to have lost sight of the
15
said condition and that the Petitioner-Company
could not be compelled to accept the affidavits or
Bond as security/guarantee for the arrears due.
13. The learned ASG then submitted that while the
Respondent-Company had relied upon Annexure 6.5 to
the U.P. Electricity Supply Code, 2005, the same
only provides relief to Sick Industrial Companies
and Relief Undertakings falling under Clause 6.16
of the said Code, which provides as follows :-
“6.16. Disconnected Industrial Units seeking revival : For industries lying disconnected over six months and seeking to revive, the Commission order dated 12th July, 2005 given in Annexure 6.5, shall apply to the extent specified in the order, and if not contrary to any G.O., or any court order.”
Mr. Tripathy urged that the said clause would not
apply to the case of the Respondent-Company since
it was not the case of a disconnected industrial
unit seeking revival and hence no reliance could be
placed on Annexure 6.5 to the above Code. It was
16
also pointed out that although the load had not
been reduced, as requested by the Respondent-
Company, on 13th July, 2007, another request was
made for increase of the load from 1.25 MVA to 2.25
MVA, which action was not permissible.
14. The learned ASG submitted that till such time
the provisions of Clause 4.49 were not complied
with by the Respondent-Company, the question of
reduction of the contracted load from 8 MVA to 1.25
MVA did not arise and the further request to
increase the same to 2.25 MVA was also not
maintainable. The learned ASG submitted that the
approach of the High Court to the problem was
completely wrong and cannot, therefore, be
sustained.
15. On the other hand, appearing for the
Respondent-Company, Mr. M.L. Lahoty, Advocate,
reiterated the submissions made before the High
Court that on account of the deteriorating
17
financial health of the Company and apprehending a
further adverse effect on its work force, the State
Government on 24th June, 2004, upon exercise of its
power under Section 3 of the U.P. Industrial
Undertakings (Special Provisions for Prevention of
Unemployment) Act, 1966, issued a notification
granting the Respondent-Company the status of a
“Relief Undertaking”. The notification, which was
initially issued for a period of one year, was
subsequently extended for two consecutive periods
of one year each on 14th June, 2005 and 23rd June,
2006, respectively. The consequence of the same
was that all contracts, agreements, etc. stood
suspended for a period of one year and all
proceedings pending before any Court, Tribunal,
Authority, etc. stood stayed.
16. On account of the deteriorating market
conditions and suspension of most of its
manufacturing activities, the Respondent-Company
applied for reduction of load from 8 MVA to 1.25
18
MVA and made a formal application to KESCO to
reduce its load in the manner indicated above with
effect from 1st April, 2006. The said application
was in the prescribed proforma under Clause 4.41 of
the U.P. Supply Code, 2005.
17. In order to prevent a stalemate, the
Respondent-Company sought the intervention of the
Member Secretary (Energy), U.P., regarding
reduction of the contracted load from 8 MVA to 1.25
MVA on account of the market conditions.
According to Mr. Lahoty, this led to a meeting
between the Managing Director of KESCO and the
Executive Director of LML on 19th April, 2006, in
which a decision was taken to reduce the load from
8 MVA to 1.25 MVA, as requested by the Respondent-
Company, with effect from 1st April, 2006. The said
decision of load reduction was, of course, subject
to the condition that (i) LML would pay its monthly
electricity dues, (ii) both LML and KESCO would
19
accept the decision on dues pending in the Courts
and (iii) the decision on load reduction would be
sent for approval to the Regulatory Commission
(UPERC), which would be acceptable to both the
parties. Mr. Lahoty contended that once a decision
had been arrived at between the Managing Director
of KESCO and the Executive Director of the
Respondent-Company, KESCO ought not to have raised
inflated bills based on 8 MVA load thereafter.
18. Mr. Lahoty urged that while the aforesaid
controversy was continuing, on 8th May, 2007, the
Respondent-Company was declared to be a “Sick
Industrial Company” under Section 3(1)(o) of SICA.
In addition to the above, the BIFR also invoked its
jurisdiction under Section 22(3) of SICA on
22.10.2007 directing that (i) against arrears,
KESCO would continue to accept Rs.5 lakhs per
month, (ii) current bills would be paid on actual
consumption basis and (iii) KESCO would not resort
20
to any coercive measures such as disconnection of
supply. According to Mr. Lahoty, the Respondent-
Company has been strictly adhering to the said
order of the BIFR and has in the process already
liquidated about Rs.3.09 crores of the outstanding
dues. Mr. Lahoty reiterated that although the
Respondent-Company had complied with the provisions
of the Supply Code and also complied with the
payment schedule as per the agreement dated 3rd
August, 2007, and the order dated 22nd October,
2007, passed by the BIFR in the light of Annexure
6.5 to the Supply Code, KESCO went on raising
monthly electricity bills on the basis of 8 MVA
which compelled the Respondent-Company to file Writ
Petition (C) No.24900 of 2009 before the Allahabad
High Court, inter alia, for a direction upon the
Petitioner-Company that the load stood reduced from
1st April, 2006. It was submitted that all the
submissions made on behalf of KESCO relating to the
application for load reduction, were not in
21
accordance with the provisions of the Code and in
the absence of any stay order by any Court or Forum
in respect of arrears, the provisions of Clause
4.49 was not fulfilled. However, all the issues
raised by KESCO were negated by the Division Bench
of the High Court in its impugned judgment. Mr.
Lahoty submitted that having regard to the decision
of the Rajasthan High Court in Modern Syntax (I)
Ltd. Vs. Debts Recovery Tribunal, Jaipur [AIR
(2001) Raj. 170) which in its turn is based on the
judgment of this Court in Doburg Lager Breweries
Pvt. Ltd. Vs. Dhariwal Bottle Trading Co. [(1986) 2
SCC 382], wherein it was held by this Court that
the object of a Relief Undertaking Act is to sub-
serve the public interest and to prevent
unemployment in particular, the relevant provisions
are to be given a liberal interpretation.
19. Mr. Lahoty also submitted that in clause 4.49
of the Code prior to its amendment, there was an
22
option of furnishing a Bond and filing an
instrument in the nature of a Bond, apart from
furnishing a Bank Guarantee and no fault could,
therefore, be found with the affidavits and the
Bond submitted on behalf of the Respondent-Company.
It was submitted that since no shortcoming or
illegality was mentioned in the decision taken by
the Managing Director of KESCO and the Executive
Director of LML and since the load reduction
application was to be considered as per the
unamended Code, nothing further was required to be
done by the Respondent-Company after the said
decision was taken on 19th April, 2006. It was
urged that it was in the said context that the
Division Bench observed that KESCO’s stand in
raising the monthly bills on the basis of 8 MVA
contracted load was wholly unjust and unfair, more
particularly when the Respondent No.1 Company was
on its part complying with the conditions of
payment of the monthly bills based on actual
23
consumption and instalments towards the arrears.
20. Referring to the exercise of power by the UPERC
under Section 23 of the Electricity Supply Act,
2003 and Clause 9.5 of the Supply Code, it was
submitted that the same was a separate regime in
the larger public interest with the sole object of
preventing unemployment and loss of production in
order to serve a social cause. It is in that
context that it was recorded that only current dues
were to be realized from a “Relief Undertaking” or
a “Sick Industry” from whom only current dues would
be realized and as far as the past dues are
concerned, the same would be recovered in equal
monthly instalments. As far as late payment sur-
charge are concerned, the same would be subject to
the orders of the BIFR under the SICA or the State
Government under the 1966 Act. It was submitted
that the said provisions of paragraph 8(c) and (d)
of Annexure 6.5 to the Code squarely applied to the
24
case of the Respondent No.1 Company after it was
declared as a “Relief Undertaking” on 24th June,
2004, and as a “Sick Industry” by BIFR on 8th May,
2007, but with effect from 31st August, 2006.
21. It was then submitted that even though KESCO
was fully aware of the pendency of arrears, it
decided to enter into an arrangement for load
reduction as it was satisfied that the said
decision was in the interest of both KESCO and LML
and was warranted by the circumstances then
existing. Since the arrangement was to the full
satisfaction of KESCO it itself recommended to the
Regulatory Body that KESCO’s decision to reduce the
load from 8 MVA to 1.25 MVA may be approved,
notwithstanding the pendency of arrears. Mr.
Lahoty submitted that being a public undertaking it
did not lie in the mouth of KESCO to try to wriggle
out of a conclusive decision which had been acted
upon for at least four years.
25
22. A further submission was made by Mr. Lahoty to
the extent that Respondent No.1 Company had secured
KESCO by an amount of Rs.64 lakhs approx. which was
deposited by the Respondent No.1 Company as per
Clause 4.20 of the Supply Code, and the same could
be utilized by KESCO in any eventuality. When
against the excess security deposit an amount of
Rs.65 lakhs approximately was found to be surplus,
the Respondent-Company permitted KESCO to adjust
the total amount of Rs.84 lakhs as late as in
October, 2009, which would show the bonafides of
the Respondent No.1 Company.
23. Mr. Lahoty concluded his submissions by
submitting that because of the financial hardship
under which the Respondent No.1 Company was
functioning, both the State Government as well as
the BIFR had shown a great deal of concern and that
the Respondent-Company is continuing to pay Rs.5
lakhs in monthly instalments towards arrears, along
26
with the current dues, and that it was in no
position to provide any Bank Guarantee as demanded
by the Petitioners. Mr. Lahoty submitted that a
public authority should not be allowed to exert
pressure when the Respondent-Company was complying
with its commitments and the order passed under
Section 22(3) of SICA by BIFR. Mr. Lahoty
submitted that the Special Leave Petition was
without any merit and was liable to be dismissed.
24. The facts of this case are relatively simple
and straightforward. What is difficult to
comprehend is the inscrutable manner in which
decisions arrived at in common are sought to be
negated on account of bureaucratic lethargy. The
case of the Respondent-Company, which is not denied
on behalf of the Petitioners, is that owing to
market fluctuations the Respondent-Company had to
put a halt to its manufacturing activities and to
make a representation to the State Government for
27
declaring it to be a “Relief Undertaking” under the
relevant provisions of the U.P. Industrial
Undertaking (Special Provisions for Prevention of
Unemployment) Act, 1966. Responding to the said
representation, the State Government issued a
notification on 24th June, 2004, suspending all
contracts, agreements and other instruments in
force for a period of one year leading to strikes
and complete disruption of the work of the
Respondent No.1-Company, impelling the Respondent-
Company to apply to the Petitioners for reduction
of the contracted load from 8 MVA to 1.25 MVA from
1st April, 2006. The materials on record indicate
that as a result of such representation a meeting
took place between the Managing Director of KESCO
and the Executive Director of the Respondent-
Company on 19th April, 2006, wherein a decision was
taken to reduce the load as requested by the
Respondent-Company with effect from 1st April, 2006,
on certain terms and conditions, which have been
28
set out hereinabove in paragraph 18. Apart from
the above, the Respondent-Company was also declared
as a “Sick Company” under SICA on 8th May, 2007, and
an order was passed by BIFR under Section 22(3) of
SICA on 22nd October, 2007, inter alia, directing
that KESCO would continue to accept Rs.5 lakhs per
month against the arrear dues together with the
current dues on the basis of the actual
consumption. What is of significance is that
despite compliance by the Respondent No.1-Company
with the said order the Petitioners continued to
raise bills on the Respondent-Company on the basis
of 8 MVA load, although, it had agreed to reduce
the same from 8 MVA to 1.25 MVA with effect from 1st
April, 2006.
25. This case is an example of how a positive
decision taken to help a struggling industry to
find its feet can be scuttled by legalese,
although, an agreement had been reached between the
29
parties regarding payment of the arrears in
instalments along with the dues, and despite the
same being duly followed by one of the parties to
the agreement. The threat to yet again disrupt its
manufacturing operations looms large on the horizon
on account of the inability of the Respondent No.1-
Company to comply with the provisions of Clause
4.41 read with Clause 4.49 of the U.P. Electricity
Code, 2005. On 31st March, 2006, the outstanding
dues of the Respondent-Company was Rs.8.42 crores
and when Clause 4.49 was amended, the Respondent-
Company was asked to submit a Bank Guarantee/Bond
to secure the amount of Rs.10.24 crores outstanding
as arrears on that date. In compliance thereof,
the Respondent-Company duly furnished a Bond on 17th
June, 2007, which was not accepted by the
Petitioners on the ground that it did not secure
the outstanding dues of the Petitioner No.1 and
were not to its satisfaction. As a result of the
above, although, the Petitioners were fully aware
30
of the precarious financial condition of the
Respondent-Company and having agreed to reduce the
contract load from 8 MVA to 1.25 MVA, it refused to
do so on the ground that the Bond provided did not
secure the outstanding dues, resulting in a vicious
circle of events. On the one hand, the high MVA
load continued to contribute to the raising of high
electricity bills, which the Respondent-Company was
not able to pay, and, on the other hand, the
Respondent-Company continued to suffer further
financial losses on account thereof.
26. An argument had been advanced on behalf of the
Petitioners that in the unamended provisions of
Clause 4.49, provision had been made for the
defaulting Company to furnish a Bond and as an
alternative, to furnish a Bank Guarantee,
apparently to assuage the aggravated economic
conditions. In the amended provisions of Clause
4.49 the furnishing of a Bond by way of security
31
was excluded. However, the discretion not to
accept such Bond always lay with the Petitioners,
giving them the discretion not to accept the Bond
furnished by the Respondent-Company. That is
exactly what has happened in the instant case.
While agreeing to give the Respondent-Company the
benefit of a reduced MVA, the Petitioners had
prevented the Respondent-Company from accessing
such privilege by continuing to raise bills on the
basis of the high MVA which the Respondent-Company
apparently was unable to bear on account of its
financial conditions. As a result, instead of
helping the Respondent-Company to come out of its
financial crisis, the Petitioners have prevented
the Company from doing so by refusing to lower the
load from 8 MVA to 1.25 MVA, as agreed upon. It is
not the case of the Petitioners that the agreement
which had been arrived at between the Managing
Director of the Petitioners and the Executive
Director of the Respondent-Company, had been
32
breached by the Respondent-Company. On the other
hand, it has been categorically contended by the
Company that it had scrupulously given effect to
the said agreement as also the order of the BIFR
dated 22nd October, 2007 upon the Respondent No.1-
Company being declared a Sick Industrial Company
under Section 3(1)(o) of SICA on 8th May, 2007.
27. It is apparent that while passing the impugned
order, the High Court lost sight of the said order
of the BIFR and confined itself to the provisions
of Clauses 4.41 and 4.49 of the U.P. Electricity
Supply Code, 2005 framed under Section 50 of the
Electricity Code, 2003. If the Respondent No.1-
Company is to revive, and, thereafter, survive, a
certain amount of consideration has to be shown,
which was fully realized by the Petitioners
themselves, but they allowed themselves to be tied
up in knots over compliance with the provisions of
Clauses 4.41 and 4.49 which are Rules framed for
33
application in special cases in order to help
industries which had fallen on difficult days, to
recoup its losses and to bring its finances on an
even keel.
28. There is no dispute that pursuant to an
application made on 31st March, 2006 by the
Respondent No.1-Company, praying for the reduction
of the contract load from 8 MVA to 1.25 MVA with
effect from 1st April, 2006, a Meeting had been held
between the Managing Director of KESCO and the
representatives of the Respondent-Company in which
a decision was taken for reduction of the load with
certain conditions. There is also no dispute that
on the said date itself KESCO conveyed its
agreement for reduction of load to the U.P.
Electricity Regulatory Commission and sought its
formal approval and that no objection was raised by
the Commission with regard to the said decision
except to indicate that the said decision would
34
have to be implemented strictly in accordance with
the Electricity Supply Code, 2005. There is also
no dispute that when the decision was taken on 19th
April, 2006 to reduce the contract load, the
unamended version of Clause 4.49 of the Code was in
existence and that the same provided for submission
of either a Bank Guarantee or a Bond or any other
instrument to the satisfaction of the licensee of
the equal amount of pending dues. The only problem
which has arisen is KESCO’s decision not to accept
the Bond given by the Respondent-Company on the
ground that it did not provide sufficient security
for the outstanding dues. In the totality of the
existing circumstances, of which KESCO was fully
aware, the decision not to accept the Bond was not
in accordance with the decision arrived at on
19th April, 2006 to reduce the contract load from 8
MVA to 1.25 MVA. In fact, the Respondent-Company
had been declared to be a Relief Undertaking by the
State Government on an application dated 24th June,
35
2004. Furthermore, soon after the decision was
arrived at to lower the contract load, the
Respondent-Company was also declared as a Sick
Company on 8th May, 2007 and the BIFR, while
considering the revival of the Respondent-Company
by its order dated 22nd April, 2007, directed KESCO
to continue to accept Rs.5 lakhs per month against
the arrears apart from payment of the current
electricity bills on actual consumption basis and
also not to adopt coercive measures to disconnect
the supply of electricity of the Respondent-
Company. As indicated hereinabove, the result of
the continued insistence of KESCO that a Bank
Guarantee should be provided by the Respondent
No.1-Company in respect of its outstanding dues,
had the effect of negating the decisions to revive
the Company.
29. We are, therefore, of the view that no
interference is called for in this petition in
36
regard to the impugned order of the High Court.
The Special Leave Petition is, accordingly,
dismissed, but this will not prevent the
Petitioner-Company from taking appropriate steps
against the Respondent-Company in the event the
latter Company commits default in paying the
instalments as directed by the BIFR towards the
arrears or in respect of the current electricity
bills.
30. There will be no order as to costs.
………………………………………….J. (ALTAMAS KABIR)
………………………………………….J. (CYRIAC JOSEPH)
………………………………………….J. (C.K. PRASAD)
New Delhi Dated: 07.05.2010
37