05 October 1989
Supreme Court
Download

K.V. GEORGE Vs SECRETARY TO GOVT., WATER AND POWERDEPARTMENT, TRIVANDRUM &

Bench: RAY,B.C. (J)
Case number: Appeal Civil 4209 of 1989


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9  

PETITIONER: K.V. GEORGE

       Vs.

RESPONDENT: SECRETARY TO GOVT., WATER AND POWERDEPARTMENT, TRIVANDRUM &

DATE OF JUDGMENT05/10/1989

BENCH: RAY, B.C. (J) BENCH: RAY, B.C. (J) MUKHARJI, SABYASACHI (J)

CITATION:  1990 AIR   53            1989 SCR  Supl. (1) 398  1989 SCC  (4) 595        JT 1989 (4)   166  1989 SCALE  (2)822

ACT:     Arbitration Act 1940---Sections 30, 33 and  41--Arbitra- tor  to  make  award after considering  claims  and  counter claims of the parties-Failure to do so is  misconduct--Prin- ciples  of res-judicata applicable to  arbitration  proceed- ings.

HEADNOTE:     The appellant, a contractor had entered into a  contract with the Respondent on 22nd April 1978 for the  construction of  an  embankment across Musaliyar Podom  between  chainage 2573.5 M to 2827 M of E.B. Main conal of Kallada  Irrigation Project.  Under the contract-agreement, the work was to  the completed by March 30, 1980 i.e. two years From the date  of selection notice which was dated March 30, 1978. The  appel- lant having failed to complete the work as per the terms  of the  contract,  the  Respondent by a  notice  dated  26.4.80 cancelled  the  contract at his risk  and  cost.  Consequent there-to the appellant filed a claim before the named  Arbi- trator (Case No. 132 of 1980), claiming enhancement of rates in  respect of the earth work involved in the  contract.  He also  claimed  interest on delayed payment  and  costs.  The respondent  resisted the claim and urged that the  appellant was not entitled to any enhancement, as the appellant should have  visualised and assessed the position  before  entering into work contract which was to be completed within 2 years. According to respondent the appellant had not even completed 35%  of  the  work. Respondent, No. 2,  therefore,  filed  a counter-claim for Rs.28,84,000. The  Arbitrator  made the award on 22.1.1981 in  respect  of claim No. 1 thereby directing the Respondents to pay 35  per cent increase in the agreed rate for the item of earth work. However  claim  regarding interest on  delayed  payment  was disallowed.  As  regards the counterclaim filed by  the  Re- spondent,  the Arbitrator ordered that those issues will  be considered  separately and thus no award in respect  thereof was made. The appellant thereupon filed O.P. (Arbitrator) 81 of 1981 before the Sub-Judge Trivandrum for making the award a rule of the Court. 399     The Respondents having raised objection to the making of

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9  

the  award a Rule of the Court, the Sub-Judge  remitted  the reference  to the arbitrator by his order dated 18.8.81  for fresh consideration, as the arbitrator had failed to consid- er  the counter-claim made by the respondent. The  appellant applied  for review of the said order passed  by  Sub-Judge. Contemporaneously,  the appellant filed another claim  peti- tion before the arbitrator (case No. 276 of 1980) in respect of  the wrongful termination of the contract and made  claim in respect of 13 items. On 29th October 1981, the arbitrator made an award whereby he ordered that the re-arrangement  of the  work should not be at the risk and cost of  the  appel- lants.  He also ordered 30% increase in rates for all  items of  work carried out by the appellant, except however  those items, which stood covered by his earlier award. Some of the other  claims  were also allowed. The appellant  filed  O.P. (Arbitrator) 296 of 1981 for making the second award a  Rule of the Court to which the Respondents raised objections. The Sub-Judge by his order dated March 18, 1982 made the award a rule of the Court dismissing the plea of res-judicata raised by the Respondents. The Respondents being dissatisfied  with the  order passed by Sub-Judge preferred two appeals  before the  Kerala  High  Court. The High Court  allowed  both  the appeals  holding  that the Sub-Judge could  not  review  his order of the facts of the present case. The High Court  also held that principle of constructive res-judicata would apply to  the  arbitration case. Accordingly the  High  Court  set aside  the  orders of the Sub-Judge as also  the  award  and directed that the arbitrator shah dispose of the Arbitration case No. 132 of 1980 afresh in the light of the Judgment  of Sub-Judge in O.P. (Arbitrator) No. 81 of 1981 and in accord- ance  with law after taking into consideration the claim  of the  appellant  and the counter claim  of  the  Respondents. Hence these appeals by the appellant by Special Leave. Dismissing the appeals, this Court,     HELD: It is the duty of the Arbitrator while considering the  claims of the appellants to consider also  the  counter claims  made  on behalf of the Respondents and to  make  the award after considering both the claims and counter  claims. This  has  not been done and the Arbitrator did not  at  all consider the counter-claims of the respondents in making the award.  As  such the first award dated 22.1.81 made  by  the Arbitrator  in  Arbitration Case No. 132 of 1980  is  wholly illegal  and  unwarranted and the High Court  was  right  in holding that the Arbitrator misconducted himself and in  the proceedings  by making such an award, and in setting,  aside the  same  and directing the Arbitrator to  dispose  of  the reference in accordance with law con- 400 sidering  the claim of the contractor and the counter  claim of the respondent. [406F-G]      The  order allowing the application for review  by  the Trial Court is also had inasmuch as there was no mistake  or error  apparent  on the face of the order dated  August  18, 1981  made O.P. (Arbitrator) No. 81 of 1981 nor  any  suffi- cient reason has been made out for review of the said order. [406H; 407A]     In the instant case, the contract was terminated by  the Respondents  on  April 26, 1980 and as such all  the  issues arose out of the termination of the contract and they  could have  been raised in the first claim petition  fried  before the arbitrator by the appellant. This having not been  done, the second claim petition before the arbitrator raising  the remaining disputes is clearly barred. [407H; 408A]     Section  41  of the Arbitration Act  provides  that  the provisions of the Code of Civil Procedure will apply to  the

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9  

Arbitration proceedings. The provisions of res-judicate  are based  on the principle that there shall be no  multiplicity of  proceedings and there shall be finality of  proceedings. [408B]     Muhammad Hafiz & Anr. v. Mirza Muhammad Zakaria &  Ors., AIR  1922  (PC) 23; Darvao & Ors. v. The State of  U.  P.  & Ors.,  [1962]  1 SCR 574 at 582-83; Satish Kumar &  Ors.  V. Surinder Kumar & Ors., AIR 1970 SC 833, referred to.

JUDGMENT:     CIVIL APPELLATE JURISDICTION: Civil Appeal Nos.  4209-10 of 1989.     From  the  Judgment  and Order dated  10.4.1987  of  the Kerala High Court in M.F.A. No. 291 and 304 of 1982. K.N. Bhat and Mukul Mudgal for the Appellant.     M.M.  Abdul Khader and T.T. Kunhikanan for the  Respond- ents. The Judgment of the Court was delivered by RAY, J. Special leave granted. These  appeals on special leave have been filed by the  con- tractor, 401 K.V.  George against the judgment and order passed  on  10th April,  1987 by the Kerala High Court in M.F.A. No. 291  and 304 of 1982 whereby the High Court set aside the judgment of the Sub-Court, Trivandrum in O.P. (Arb.) No. 296 of 1981  as also the award of the Arbitrator in A.C. No. 276 of 1980 and directed that the Arbitrator will dispose of the Arbitration case  No.  132 of 1980 in the light of the judgment  of  the Sub-Court  in O.P. (Arb.) No. 81 of 1981 in accordance  with law  considering the claim of the  contractor-appellant  and the counter-claim of the respondents.     The  appellant who is a contractor entered into  a  con- tract  with the respondents on April 22, 1978 in  connection with  the  construction of an  embankment  across  Musaliyar Padom between Chaniage 2573.5 M to 2827 M of E.B. Main canal of  Kallada Irrigation Project. The work was required to  be completed  by 30th March, 1980 i.e. two years from the  date of selection notice which was dated 30th March, 1978. As the appellant  failed to complete the work as per the  terms  of the contract, the respondents sent a notice dated April  26, 1980  to the appellant cancelling the contract at  his  risk and cost. On July 2, 1980 the appellant filed a claim  being arbitration case No. 132 of 1980 before the named Arbitrator i.e.  the Chief Engineer (Arbitration), Vellayambalam,  Tri- vandrum  claiming  enhancement of rates in  respect  of  the earth  work  involved in the contract, interest  on  delayed payments and costs. The second respondent, the  Superintend- ing  Engineer,  K.I.P.  Circle, Karnataka  filed  a  defence statement  stating inter alia in para 2(1) that the time  of completion of the work was fixed as 24 months from the  date of  handing  over site to the contractor and he  could  have anticipated all such variations before quoting rates. As per agreement  the rates once agreed will not be  enhanced.  The department  is not bound to pay the claimant a  revision  of schedule. In para 2(m) it has also been pleaded that as  per agreement  the contractor is bound to carry  out  additional and  extra items of works that arise during  execution.  The additional  and extra items of works done by the  contractor are  quite meagre when compared to the total volume  of  the work. The extra and excess items were covered by  supplemen- tal agreement. The contractor was not able to complete  even 35%  of the total work within the time of completion of  the

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9  

work and as such the claimant is not entitled to  attributed delay  on  this  account. A counterclaim was  filed  by  the Superintending  Engineer, K.I.P. Circle,  Kottarakkara,  the respondent  No. 2 wherein a claim of a sum  of  Rs.28,84,000 was made. The Arbitrator by his order dated January 22, 1981 made the 402 award in regard to claim No. 1 directing the respondents  to pay  35% increase in the agreed rate for the item  of  Earth work  excavating and filling for forming the  compacted  em- bankment  with earth from barrow area. Claim No. 1 was  thus allowed.  Claim Nos. 2 and 3 regarding interest were  disal- lowed. As regards counter-claim Nos. 1 and 2, it was ordered that  those issues will be considered separately and  so  no award was made.     The  appellant  thereafter filed O.P. (Arb.) No.  81  of 1981 in the court of Sub-Judge, Trivandrum under section  14 of  the Arbitration Act for making the award a rule  of  the court.  On objections being raised by the  respondents,  the Court  of the Sub-Judge after hearing the parties  by  order dated August 18, 1981 remitted the reference to the Arbitra- tor for fresh consideration on the ground that the  Arbitra- tor did not consider the counter claims made by the respond- ents. The appellant thereafter filed I.A. No. 3780/81 in the court  of Sub-Judge praying that the order dated August  18, 1981 may be reviewed. In the, meantime, the appellant  filed another  arbitration case No. 276 of 1980 before.  the  same Arbitrator  in  respect of the wrongful termination  of  the contract  and  also raised 13 items of claims  therein.  The Arbitrator  after  going through the objections of  the  re- spondent  made an award on October 29, 1981 whereby  he  or- dered  that the re-arrangement of the work should not be  at the risk and cost of the appellant. As regards claim No.  2, he  ordered 30% increase in rates (as per original and  sup- plemental  agreement) for all items of work carried  out  by the  appellant except on items covered by Award No.  132  of 1980  dated 22.1.1981. Claim Nos. 3 and 5 were rejected.  As regards claim No. 4 an increase of 20 per cent in the agreed rates  for these items was allowed. Claim No.  11  regarding interest  was  disallowed. It was also stated in  the  award inter alia that the claimant shall be entitled to the refund of  the security amount as well as refund of  the  retention amounts, the claimant shall be entitled to his final bill in terms of the Award, the counter claim for recovery of  costs of  rearrangement of work and also the counter claims  filed by  the  respondent dated April 8, 1981 were  declined.  The appellant  filed O.P. (Arb) No. 296 of 1981 for  making  the second award a rule of the court. A statement of defence was filed  by the respondents wherein,it has been  stated  inter alia in para 6 that:               "The claims made in this petition under  paras               6(ii), (iii), (iv), (v), (vi) (vii) and (viii)               are  barred  by resjudicata  and  constructive               resjudicata. No work was done by the  claimant               after termination of the contract on June  24,               1980.               403               The  claim  petition in Arbitration  case  No.               132/80  was filed by the claimant  before  the               Hon’ble Arbitrator on 2.7.1980. It was open to               him to raise these claims-in that  Arbitration               petition.  Having  not  done-this  raising  of               these  claims  now  which are  all  bogus  and               imaginary is barred by constructive resjudica-               ta.  He  had not raised  these  claims  before

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9  

             Chief  Engineer (next Superior Authority)  and               also  before  the Hon’ble  Arbitrator  in  his               petition dated 27.10.1980. Hence it is  prayed               that the above claims may not be taken up  for               arbitration and they may be rejected."               It  has also been stated in sub-para  (iv)  of               para 6 that:               "(iv)  As above. Also there had been no  error               in  the  rates. The claimant was paid  at  his               agreed rates, and he had received it and  also               no dispute lies on it. Claim may be  rejected.               Work  done was recorded as per item No.  7  of               Appl. of agreement and was paid as per  agree-               ment."     The  Sub-Judge  by order dated March 18, 1982  made  the award a rule of the court dismissing the plea of res-judica- ta raised by the respondents in O.P. (Arb.) No. 296 of 1981. The respondents filed two appeals being FMA Nos. 291 of  304 of  1982 before the High Court of Kerala at Ernakulam  which held  that the Arbitrator could not review its order on  the facts of the present case and so allowed F.M.A. No. 291  and 1982.  The  High Court also allowed F.M.A. No. 304  of  1982 holding  that principles of constructive res-judicata  would apply  to  the arbitration case. Feeling  aggrieved  by  the aforesaid  judgment and order passed in F.M.A. Nos. 291  and 304  of  1982, the appellant-contractor  has  preferred  the instant appeals on special leave.     Mr.  Bhatt, learned counsel appearing on behalf  of  the appellant  has  submitted in the first place that  the  High Court  was wrong in reversing the judgment and order of  the trial  court without considering the provisions  of  Section 114 as well as Order 47, Rule 1 of the Code of Civil  Proce- dure  in as much as Order 47, Rule 1 clearly  provides  that review  of  an order may be made either on account  of  some mistake  or enor apparent on the face of the record, or  for any-other sufficient reason. In the instant case, the  first award  was set aside by the Trial Court on the  ground  that the counter claim filed on behalf of the respondents was not considered by the Arbitrator and so it remitted the same for consideration  afresh.  It has been held by the  High  Court that the refusal to consider the counter claims had rendered the prior 404 award liable to be set aside for mis-conduct of the Arbitra- tor  and the proceedings. It has been urged by  the  learned counsel that the counter claim has been fully considered  in the  second  award made by the Arbitrator and  as  such  the first award cannot be set aside on the ground of non-consid- eration of a counter claim and it cannot be treated as  mis- conduct of the Arbitrator/and the proceedings for nonconsid- eration of the counter claim in the first award. It has been further contended in this connection that the finding of the High Court to the effect that the subsequent award passed by the Arbitrator dealing with the counter claims did not  have the  effect of mitigating the mis-conduct of the  Arbitrator or of condoning the error on the face of the award, is  also not sustainable in as such as the counter claim filed by the respondents  was  duly considered by the Arbitrator  in  the second award made by him.     It  has also been submitted by the learned  counsel  for the  appellant that the principles of res-judicata and  con- structive res-judicata are not applicable to the award  made in  Arbitration case No. 291 of 1981 in as much as the  dis- putes  that were raised were not ripe for being referred  to Arbitration  in view of the terms of the contract  that  the

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9  

contractor had to raise the dispute before the  Superintend- ing  Engineer and thereafter before the Chief  Engineer  and had  to wait till the end of the stipulated period.  It  has been  further submitted that since the period was not  over, the claims that have been raised subsequently in the  second claim petition before the Arbitrator could not be raised  in the  first claim petition before the Arbitrator and as  such the  second award made by the arbitrator cannot be  said  to have  been barred by res-judicata as provided in Section  11 of the Code of Civil Procedure or by the rules of  construc- tive res-judicata. The judgment and order of the High  Court in  allowing F.M.A. No. 304 of 1982 setting aside the  award made in Arbitration case No. 296 of 1981 is unwarranted  and as  such it is not sustainable. It has also  been  contended that the claim made in the second claim petition before  the Arbitrator  is not barred by order 2, rule 2 of the Code  of Civil  Procedure  in as much as the disputes raised  in  the second  claim petition before the Arbitrator were  not  ripe for  reference as the appellant had to wait till the end  of the  stipulated period in accordance with the terms  of  the contract. The judgment and order of the High Court in allow- ing the F.M.A. No. 304 of 1982 is not legal and valid and is liable to be set aside.     Mr. Abdul Khadir, learned counsel appearing on behalf of the  respondents on the other hand urged before  this  Court that the SubJudge acted legally in directing the  Arbitrator to dispose of the arbitra- 405 tion  case  No. 132/80 in the light of the judgment  of  the Sub-Court in O.P. (Arb.) No. 81 of 1981 and in setting aside the  order  of  review because no case for  review  nor  any sufficient cause has been made out for exercising the  power of  review under Section 114 read with Order 47, Rule  1  of the  Code  of Civil Procedure. The High Court, it  has  been submitted, was right in holding that the order of review was unwarranted and in setting aside the same and directing  the Arbitrator  to dispose of the reference in  accordance  with law  considering the claim of the  contractor-appellant  and the  counter claim of the respondents. It has  been  further submitted by Mr. Abdul Khadir that in view of the provisions of  Section  41 of the Arbitration  Act  which  specifically provides that the provisions of the Code of Civil  Procedure shall  apply to arbitration proceedings, the  principles  of res-judicata  or of constructive res-judicata will apply  to arbitration  proceeding. The appellantcontractor having  not raised  all his claims in his first claim petition  made  to the  Arbitrator  for  decision and award  having  been  made thereon,  the  second claim petition before  the  Arbitrator making  certain other claims in Arbitration Case No. 276  of 1980 is barred by the principles of constructive res-judica- ta in as much as on the termination of the contract by order dated  April 26, 1980 the contractor could have  raised  all his  disputes arising out of the contract at that time,  but the appellant chose to take only some of the issues  arising from the said breach of contract before the Arbitrator.  The second  claim petition raising some issues before the  Arbi- trator  is therefore, hit by the principles of  constructive res-judicata  and the High Court rightly allowed the  appeal setting aside the award made in Arbitration Case No. 276  of 1980.  It  has also been submitted that  the  provisions  of Order 2, Rule 2 of the Code of Civil Procedure apply to  the arbitration case and the appellant having not sought  refer- ence of all the issues, he should be deemed to have  surren- dered  those  issues and he is debarred from  raising  those issues in a subsequent claim petition made before the  Arbi-

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9  

traror.  In  this  connection, he has cited  the  ruling  in Muhammad Hafiz and Anr. v. Mirza Muhammad Zakaria and  Ors., AIR 1922 (PC) 23. The learned counsel drew our attention  to para  2(i)  of the objections filed by  the  respondents  in Arbitration Case No. 132 of 1980 wherein it has been  stated that:               "   ........  As per agreement the rates  once               agreed will not be enhanced. The department is               not  bound to pay the claimant a  revision  of               schedule."     It has been further submitted by the learned counsel  on behalf  of the respondents that the appellant was not  enti- tled to an increase in 406 the rates as he claimed increase with the agreement and  the claim that has been made is untenable.     It  has been lastly submitted on behalf of the  respond- ents  that the Arbitrator has mis-conducted himself and  the proceedings  by not deciding the counter claim filed by  the Government  while considering the claim filed by the  appel- lant  and  making a award. The High Court has  rightly  held that  the Arbitrator mis-conducted himself and the  proceed- ings and allowed the appeal, setting aside the second  award made by the Arbitrator in Arbitration Case No. 276 of 1980.     The first question that falls for consideration in  this case is whether the finding of the High Court setting  aside the  order of review made in I.A. No. 3780 of 1981 and  set- ting  arise  the order made in O.P. (Arb.) No.  81  of  1981 dated  August 18, 1981 whereby the case was remanded to  the Arbitrator is sustainable or not. Admittedly, the  appellant filed  a  claim petition being Arbitration Case No.  132  of 1980  making certain claims before the Arbitrator.  The  re- spondents  filed the counter claims. The Arbitrator  without considering  the counter claims kept the counter claims  for subsequent consideration and made an award. The Trial  Court set aside the award and remitted the same to the  Arbitrator for  making  a  fresh  award  considering  the  claims   and counter-claims  filed by the parties. On an application  for review,  the  Trial Court set aside the order and  passed  a decree  in terms of the award. It is not disputed  that  the Arbitrator  did not at all consider the counter  claims  and kept  the same for consideration subsequently  while  making award  in  respect  of the claims filed  by  the  appellant. Undoubtedly,  this award made by the Arbitrator is not  sus- tainable in law and the Arbitrator has mis-conducted himself and  in the proceedings by making such an award. It  is  the duty  of the Arbitrator while considering the claims of  the appellant to consider also the counter claims made on behalf of  the respondents and to make the award after  considering both  the claims and counter claims. This has not been  done and  the  Arbitrator  did not at all  consider  the  counter claims  of the respondents in making the award. As such  the first award dated January 22, 1981 made by the Arbitrator in Arbitration  Case  No.  132 of 1980 is  wholly  illegal  and unwarranted and the High Court was right in holding that the Arbitrator  mis-conducted  himself and  the  proceedings  in making  such  an  award and in setting aside  the  same  and directing  the  Arbitrator to dispose of  the  reference  in accordance with law considering the claim of the  contractor and the counter claim of the respondents. The order allowing the application for review by the Trial Court is also bad in as much as there was no mistake or error 407 apparent on the face of the order dated August 18, 1981 made in O.P. .(Arb.) No. 81 of 1981 nor any sufficient reason has

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9  

been made out for review of the said order. The order  dated August 18, 1981 is legal and valid order and the order dated March  18, 1982 allowing the, application for  review  being I.A.  No. 3780 of 1981 and setting aside the order  in  O.P. (Arb.)  81 of 1981 dated August 18, 1981 is, therefore,  bad and unsustainable.     With regard to the submission that the issues that  have been raised in the second claim petition before the Arbitra- tor is barred under the provisions of Order 2, Rule 2 of the Code  of  Civil Procedure, it is convenient to  refer  to  a passage  in  Mulla’s  Code of Civil  Procedure  (Volume  II, Fourteenth Edition) at page 894:               "  ....  This rule does not require that  when               several causes of action arise from one trans-               action,  the plaintiff should sue for  all  of               them  in one suit. What the rule lays down  is               that  where there is one entire cause  of  ac-               tion, the plaintiff cannot split the cause  of               action  into  parts so as  to  bring  separate               suits in respect of those parts."     It  is  pertinent  to refer in this  connection  to  the decision in Muhammad Hafiz and Anr. v. Mirza Muhammad  Zaka- riya  and  Ors., AIR 1922 (PC) 23 wherein  a  mortgage  deed provided  that if the interest was not paid for  six  months the  creditor  should  be competent to  realise  either  the unpaid  amount of the interest due to him or the  amount  of principal and interest, by bringing a suit in court  without waiting for the expiration of the time fixed, and the Plain- tiff,  more than 3 years after (i.e. time fixed), brought  a suit  for interest alone and got a decree. It was held  that the  second suit for principal and arrears of  interest  was not maintainable as under Order 2, Rule 2, C.P.C. he must be deemed to have relinquished his claim for further relief, he having exercised the option of suing for interest alone.  It was further held that the cause of action referred to in the rule  is  the case of action which gives  occasion  to,  and forms the foundation of, the suit, and if that cause enables a man to seek for larger and wider relief than that to which he  limits his claim, he cannot afterwards seek  to  recover the balance by independent proceedings.     In the instant case, the contract was terminated by  the respondents  on  April 26, 1980 and as such all  the  issues arised out of the termination of the contract and they could have  been raised in the first claim petition  filed  before the Arbitrator by the appellant. This having 408 not been done the second claim petition before the  Arbitra- tor raising the remaining disputes is clearly barred.     With regard to the submission as to the applicability of the principles of res-judicata as provided in Section 11  of the Code of Civil Procedure to arbitration case, it is to be noted that Section 41. of the Arbitration case provides that the provisions of the Code of Civil Procedure will apply  to the Arbitration proceedings. The provisions of  res-judicata are  based on the principles that there shall be  no  multi- plicity  of proceedings and there shall be finality of  pro- ceedings. This is applicable to the arbitration  proceedings as well. It is convenient to refer to the decision in Daryao and  Ors. v. The State of U.P. & Ors., [1962] 1 SCR  574  at 582-83 wherein it has been held that the principles of  res- judicata will apply even to proceedings under Article 32 and 226 of the Constitution of India. It has been observed that:               "Now, the rule of res-judicata as indicated in               s.  11 of the Code of Civil Procedure  has  no               doubt some technical aspects, for instance the

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9  

             rule of constructive res-judicata may be  said               to  be technical; but the basis on  which  the               said  rule rests is rounded on  considerations               of public policy. It is in the interest of the               public at large that a finality should  attach               to the binding decisions pronounced by  Courts               of  competent jurisdiction, and it is also  in               the  public interest that  individuals  should               not be vexed twice over with the same kind  of               litigation.  If these two principles form  the               foundation of the general rule of res-judicata               they cannot be treated as irrelevant or  inad-               missible  even  in  dealing  with  fundamental               rights in petitions filed under Art. 32."                   In Satish Kumar and Ors. v. Surinder Kumar               and  Ors,, AIR 1970 (SC) 833 it has  been  ob-               served that:               "The  true  legal position in  regard  to  the               effect  of an award is not in dispute.  It  is               well  settled  that  as a  general  rule,  all               claims  which  are  the  subject-matter  of  a               reference  to arbitration merge in  the  award               which is pronounced in the proceedings  before               the  arbitrator  and that after an  award  has               been pronounced, the rights and liabilities of               the parties in respect of the said claims  can               be  determined only on the basis of  the  said               award. After an award is pronounced, no action               can be started on the original claim which had               been     the     subject-matter     of     the               reference  ...........  This con-               409               clusion,  according to the learned  Judge,  is               based  upon the elementary principle that,  as               between  the  parties and  their  privies,  an               award is entitled to that respect which is due               to judgment of a court of last resort.  There-               fore,  if the award which has been  pronounced               between  the parties has in fact, or  can,  in               law, be deemed to have dealt with the  present               dispute, the second reference would be  incom-               petent.  This position also has not  been  and               cannot be seriously disputed."     Considering the above observations of this Court in  the aforesaid  cases we hold that the principle of res  judicata or  for  that the principles of  constructive  res  judicata apply to arbitration proceedings and as such the award  made in the second arbitration proceeding being Arbitration  Case No.  276 of 1980 cannot be sustained and is  therefore,  set aside. The High Court has rightly allowed the F.M.A.  No.304 of 1982 holding that the appellant-contractor was  precluded from  seeking-the  second reference. No  other  points  have raised before us by the appellant.     In the premises aforesaid, we dismiss these appeals with costs  quantified  at Rs.5,000 and affirm the  judgment  and order dated April 10, 1987 made by the High Court. Y. Lal                                 Appeals dismissed. 410