EXEC.ENGINEER,UTTARANCHAL POWER CORPN. Vs M/S KASHI VISHWANATH STEEL LTD..
Bench: HARJIT SINGH BEDI,T.S. THAKUR, , ,
Case number: C.A. No.-001106-001106 / 2007
Diary number: 4357 / 2007
Advocates: NIRAJ SHARMA Vs
VIKAS MEHTA
EXECUTIVE ENGINEER, UTTARANCHAL POWER CORPORATION v.
M/S. KASHI VISHWANATH STEEL LTD. & ORS. (Civil Appeal No. 1106 of 2007)
MAY 12, 2010
[Harjit Singh Bedi and T.S. Thakur, JJ.] [2010] 6 SCR 1086
The Judgment of the Court was delivered by
T.S. THAKUR, J. 1. This appeal by special leave arises out of an order dated 17th January, 2007 passed by the High Court of Uttaranchal at Nainital
whereby Writ Petition No.936 of 2001 filed by respondent M/s Kashi
Vishwanath Steels Ltd. has been allowed and order dated 7th December,
2001 passed by the Executive Engineer (Electricity) Distribution Division,
District Udham Singh Nagar, quashed.
2. Uttar Pradesh State Electricity Board was established by the State of
Uttar Pradesh in terms of the provisions of the Electricity (Supply) Act, 1948.
With the enactment of Uttar Pradesh Electricity Reforms Act, 1999 the
Government constituted Uttar Pradesh Electricity Regulatory Commission. In
terms of a Notification dated 7th August, 2000 the Commission stipulated the
tariff for the supply of electricity effective from 9th August, 2000. The rate
schedule for large and heavy power, inter alia, provided that consumers who
opt for power supply during the restricted/peak hours shall pay an additional
surcharge of 15% on the amount billed at the “Rate of Charge” under item-4A
of the Schedule. It further provided that consumers getting power supply from
independent feeders emanating from 400/220/132 KV sub-stations shall pay
an additional surcharge of 15% on demand and energy charges subject to the
condition that these consumers will get assured electricity supply of minimum
500 hours in a month. In case of shortfall in the guaranteed hours of
electricity supply, the consumers were entitled to a rebate @ 1% for each 10
hours shortfall on the bill amount computed under “Rate of Charge”. Relevant
portion of the Tariff Rate Schedule HV-2 forming part of Notification dated 7th
August, 2000, reads as under:
“...........
Notes:
(a) In respect of consumers who opt for power supply during
restricted/peak hours an additional surcharge of 15% on the amount billed
at the “Rate of Charge” under item 4-A above, i.e. Demand Charge and
Energy Charge shall be levied.
However, in respect of consumers getting power supply on
independent feeders emanating from 400/220/132 KV sub-stations an
additional surcharge of 15% on demand and energy charges shall be
charged further subject to the condition that these consumers will get an
assured supply of minimum 500 hours in a month. In case of short fall in
above guaranteed hours of supply a rebate @ 1% for each 10 hours short
fall will be admissible on the bill amount computed under “Rate of
Charge”.
.......................”
3. Respondent- Kashi Vishwanath Steels Ltd. (hereinafter referred to as
the ‘KVSL‘ for short) is a public limited company registered under the
Companies Act. On 9th November, 1995 it had entered into an agreement
with Uttar Pradesh Power Corporation Ltd., Lucknow (respondent no.4 in this
appeal) for the supply of electrical energy ipfor the production of Furnace and
Steel Rolling Manufacturing (Process) unit at Narayan Nagar Kashipur in the
form of three phase Alternating Current at a declared pressure of 33000 Volts
and a power of not exceeding 4800 K.V. amperes. The said agreement was
followed by a fresh agreement executed on 28th March, 2000 between the
company and the Uttar Pradesh Power Corporation Ltd., inter alia, providing
that the company shall pay for the supply of energy at the rates stipulated by
the supplier from time to time and that the rate schedule applicable at the
time of execution of the agreement could be revised at the discretion of the
supplier. With the tariff prescribed by the U.P. Electricity Regulatory
Commission becoming effective for the supply received by the consumer-
company the latter became liable to pay in terms of the said tariff. Some
confusion, however, appears to have arisen in regard to the interpretation of
the tariff prescribed by the Commission particularly in relation to the levy of
15% surcharge upon consumers who drew power from independent feeders.
The Corporation purported to clear the mist by issuing a circular dated 8th
September, 2000 whereunder it purported to give certain guidelines to the
concerned subordinate officers and demanded strict compliance thereof. The
circular, inter alia, provided that if consumers connected to independent
feeders did not want electricity supply for the guaranteed period of 500 hours,
no such surcharge of 15% could be levied provided they intimate to the
Executive Engineer that they do not want the guaranteed supply for 500
hours. The relevant portion of the circular reads as under:
“2.(a) In the rate schedule HV-2, as a result of the guarantee of 500 hours
electricity supply of independent feeder from 400, 220 and 132 KV sub
stations, 15% surcharge shall be levied. Consumers of this category shall
be ensured 500 hours electricity supply per month. Due to lesser
electricity supply than 500 hours, they shall be given 1% deduction for
every ten hours in their electricity bill. If consumers connected with these
independent feeders do not want guarantee of 500 hours electricity
supply then, in that event, they shall not be imposed 15% surcharge in
their bills. Such consumers shall intimate the Executive Engineer
distribution by registered post that they do not want guarantee of 500
hours electricity supply. The Executive Engineer shall issue office memo
in this regard. If any consumer of this category does not give any option
then he shall be ensured 500 hours electricity supply and 15% surcharge
shall be taken. S.S.O./Junior Engineer shall be responsible to ensure that
the consumer in question does not use electricity during the restricted
period. If consumers of this category use electricity in the restricted period
also then they shall be charged 15+15 = 30% surcharge.”
4. It was pursuant to the above circular that the KVSL addressed two
letters one dated 6th October, 2000 and the other dated 16th October, 2000
to the Executive Engineer of the Corporation to the effect that the former did
not require the assured supply of electrical energy for 500 hours and that they
may not be required to pay surcharge at the stipulated rate of 15%. On
receipt of the said letters the Executive Engineer issued an office memo
dated 24th October, 2000 granting exemption to the KVSL from payment of
15% surcharge subject to the unit complying with the other conditions
stipulated in the memo.
5. In the meantime M/s L.M.L. Limited who had also entered into an
agreement with U.P. State Electricity Board for supply of electrical energy for
its factory at Kanpur filed Writ Petition No.40692 of 2000 in the High Court of
Judicature at Allahabad challenging levy of surcharge on the total energy bill
payable by it. The petitioner’s case in that petition was that it was not only
observing the peak hour restrictions but was not consuming power during the
restricted hours hence was not liable to pay the surcharge of 15% being
demanded from it. In the reply filed on behalf of the electricity supply
company it was on the other hand stated that power was being supplied to
the petitioner from an independent feeder emanating from 400/220/132 KVS
and consequently the petitioner was liable to pay 15% surcharge under the
tariff determined by the U.P. Electricity Regulatory Commission. It was also
stated that payment of 15% surcharge by consumers drawing energy from an
independent feeder was not subject to the observance of peak hours
restrictions because those who consume power between 6 p.m. to 1 p.m. had
to pay an additional amount of 1% surcharge on the energy charge.
6. A Division Bench of the High Court of Allahabad dismissed the writ
petition mentioned above holding that there was absolutely no confusion of
any kind in the tariff approved by the Regulatory Commission to call for any
clarification in the form of the circular referred to earlier. It was also declared
that for consumers drawing power from independent feeders emanating from
400/220/132 KVS sub- stations there existed no provision in the tariff
prescribed by theCommission requiring them to exercise any option in the
matter. The only benefit that the consumers who drew power from such
independent feeders but who do not get supply for the minimum 500 hours in
a month were granted a rebate @ 1% for every 10 hours or part thereof if the
continuous supply had failed. The High Court observed:
“There is absolutely no ambiguity or confusion of any kind in the tariff as
approved by the Commission. It clearly contemplates two categories of
consumers. One category is of consumers who get power supply on
independent feeders emanating from 400/220/132 KV sub stations. The
two categories are wholly independent and distinct and they are not inter
linked with each other. The third condition mentioned at the bottom of the
box clearly shows that a consumer cannot get power supply in restricted
hours as a matter of right and he shall have to take permission from
UPPCL with intimation to the Commission. It follows that if a consumer
does not apply for permission from UPPCL and such a permission is not
granted he shall not get power supply in restricted hours and he will not
be required to pay 15 per cent surcharge. However, so far as consumers
getting power supply on independent feeders emanating from
400/220/132 KV sub stations are concerned, they have to pay 15 per cent
surcharge on demand and energy charges. This levy of 15 per cent
surcharge is dependent only upon the fact that the consumer is getting
power supply on an independent feeder emanating from 400/220/132 KV
sub stations and it is not dependent upon getting power supply in
restricted hours. It is also noteworthy that for such category of consumers
there is no provision for taking any option to the effect that he does not
want an assured supply of 500 hours in a month. The only benefit
provided to him in the tariff is that he is assured of supply of minimum 500
hours in a month and in case of shortfall in the guaranteed hours of the
supply, a rebate @ 1 per cent 10 hours or part thereof shall be admissible
on the total amount computed under “Rate of Charge”.
7. Relying upon the view taken by the High Court in the above writ
petition the Uttarakhand Power Corporation established upon bifurcation of
the U.P. Power Corporation in terms of Section 63 of the U.P. Reorganisation
Act issued an order dated 7th December, 2001 withdrawing the exemption
granted to KVSL by the erstwhile U.P. State Power Corporation Ltd. The
withdrawal order is in the following terms:
“In the aforesaid context, in the light of judgment of the Hon’ble High
Court, Allahabad the Uttar Pradesh Power Corporation Ltd. vide order
No.1423/HC/UPCL/Five- 1974+204 C/2000 dated 8.9.2000 has been
cancelled from the date of its issuance itself. Accordingly, Memo
No.3184/Vi.Vi.kha/dated 24.10.2000 is cancelled from the date of
issuance 24.10.2000. The bills of M/s Kashiviswanath are ordered to be
amended in accordance with the concerned billing tariff since 8.9.2000.”
8. Aggrieved by the above order KVSL filed writ petition No.936 of 2001
before the High Court of Uttaranchal challenging Note (a) of Clause IV, Rate-
Schedule in Category HV-2 List II of the tariff to be unconstitutional and for
quashing the revised bill issued to KVSL. A mandamus directing Uttaranchal
Corporation not to levy any surcharge on the supply energy to the consumer
was also prayed for.
9.The above petition was allowed by the High Court of Uttaranchal by its
order dated 17th January, 2007. The High Court took the view that since the
petitioner KVSL did not require assured supply of 500 hours electricity in a
month it was not liable to pay 15% surcharge and that the exemption granted
by the U.P. Power Corporation Ltd. was valid and in accordance with the
provisions of the Notification dated 8th September, 2000. The demand raised
by the Corporation was accordingly struck down. Aggrieved by the said order
the Uttaranchal Power Corporation filed Civil Appeal No.1106 of 2007 in this
Court which was heard alongwith Civil Appeal No.5789 of 2002 filed by LML
Ltd. against the order passed by the High Court of Allahabad dismissing Writ
Petition No.40692 of 2000 filed by the said company. Similar other appeals
filed by other units against identical orders passed by the High Court of
Allahabad were also heard and disposed of by this Court by a common order
dated 13th December, 2007. This Court held that in so far as the U.P. Power
Corporation had made a promise to anyone of the consumers the same was
enforceable. In the case of Uttarakhand Power Corporation, however, this
Court found no such promise to have been made to the consumer. Civil
Appeal No.1106/2007 filed by the Uttarakhand Power Corporation against the
judgment of the High Court of Uttarakhand was accordingly allowed on that
basis. In so far as appeals arising out of the judgment of the Allahabad High
Court and touching the question of surcharge on consumers drawing power
from independent feeders were concerned the same were allowed to be
withdrawn in view of the fact that several matters involving the said question
were pending before the Regulatory Commission. The appellants were
permitted to agitate the said point before the Commission. The relevant
portion of the order passed by this Court may at this stage be extracted:
“50. Similarly Uttaranchal Power Corporation also does not appear to
have made such a promise. The doctrine of promissory estoppel in those
cases also will have no application.
51. In view of the fact that several matters are pending before the
Commission on question of independent feeder we need not express any
opinion thereupon. If any appeal is pending before the Commission on
the said question it would decide the same independent of the same
irrespective of the result of this decision. We, therefore, without
expressing any opinion on the said question, permit the appellants to
agitate the same point before the Commission.
52. We, therefore, allow these appeals only to the extent mentioned
hereinbefore in terms of the promise made by U.P. Power Corporation
and allow the appeals on question of independent feeder to be withdrawn
subject to the observations made by us hereinabove. 53. Civil Appeal No.
5789 of 2002 which relates to Kanpur Electricity Supply Company is
dismissed.
54. Civil Appeal No. 1106 of 2007 filed on behalf of Uttaranchal Power
Corporation is allowed.
55. There shall, however, be no order as to costs.
SLP (C) No. 6721 of 2007
The only issue involved in this petition is the question of independent
feeder and the appeal being pending before the Commission, this special
leave petition is permitted to be withdrawn.
Sd/-
(S.B. SINHA)
Sd/-
(HARJIT SINGH BEDI)”
10. I.A.No.2 of 2008 in Civil Appeal No.1106 of 2007 was filed in this
Court for seeking clarification/modification of the above order primarily on the
ground that the observations made in para 50 are erroneous since
Uttarakhand Power Corporation was non-existent during the relevant period.
There was according to the applicants no question of any such promise
having been made to respondent-KSVL by a non-existent entity. The promise
was according to the applicant made by U.P. Power Corporation which was
binding upon the Corporation as also its successor in-interest, namely,
Uttarakhand Power Corporation after the same came into existence w.e.f. 9th
November, 2001. It is further stated that the dispute in the instant case was
with regard to the period between September 2000 when the exemption of
surcharge was granted to the consumer and 1st September, 2001 when the
same was discontinued.
11. In substance the case of the applicant was that a
representation/promise had been made to it by the U.P. Power Corporation
which promise having been held enforceable qua other units similarly situated
as the applicant, could not be ignored in so far as the applicant was
concerned. The promise was according to the applicant binding even upon
the successor-Corporation, namely, Uttarakhand Power Corporation and the
very fact that no promise was made by Uttarakhand Power Corporation did
not make any difference so long as the liability arising out of the promise
made by the U.P. State Corporation was clear and legally enforceable.
12. The above application was heard and finally disposed of by a Bench
of Hon’ble Harjit Singh Bedi and Hon’ble Aftab Alam, JJ. with the following
direction:
“Learned counsel for the parties agree that the judgment dated
13.12.2007 of this Court be recalled in C.A. No.1106 of 2007. We order
accordingly. C.A. No.1106 of 2007 will be heard on its own merit.”
13. It is in the light of the above order that this appeal has been heard for
disposal afresh.
14. The order of discontinuing the surcharge w.e.f. 1st September, 2001
reads:
“The U.P.E.R.C. in terms has recorded that discontinuation of 15%
surcharge is due to (i) inability/incapability on the part of UPPCL for
technical and operational reasons to ensure the guaranteed supply of 500
hours, (ii) it was difficult for UPPCL even to distinguish between the two
consumers on independent feeder who asked for assured supply and
who do not, (iii) most of the consumers having opted against this
agreement and (iv) the financial implication was also negligible if the
scheme was discontinued.”
15. Appearing for the appellant Mr. Shanti Bhushan, learned senior
counsel strenuously argued that the circular issued by the U.P. State
Corporation modifying the tariff prescribed by the Regulatory Commission
was wholly without any jurisdiction and could be recalled by the Uttarakhand
Power Corporation w.e.f. the date the same was issued. Inasmuch as such a
withdrawal was ordered by the Corporation it committed no illegality
especially when the withdrawal was supported by clear and authoritative
pronouncement of the High Court of Allahabad stating that the grant of
exemption tantamounted to modifying the tariff which modification the
corporation was not legally competent to make. It was further argued by Mr.
Shanti Bhushan that there was no question of any promise having been made
either by U.P. State Corporation or the Uttarakhand Power Corporation. In the
absence of any such promise and in the absence of any material to show that
the petitioner had acted upon any such promise and changed its position,
there was no question of interfering with the order withdrawing the exemption
on the basis of the principles of equitable estopple.
16. On behalf of the respondent-KVSL, it was on the other hand,
submitted that since a promise was found to have been made by the U.P.
Power Corporation to other consumers and since the said promise has been
held to be enforceable, there was no justification for taking a different view
insofar as the respondent-company is concerned. It was also submitted that
once U.P. Corporation is held to be bound by the promise made by it the
Uttarakhand Corporation which came into existence upon reorganization of
the State had no option but to make the said promise good. It could not
retrospectively withdraw the same only with a view to recover money which
even the U.P. State Power Corporation would not have been entitled to
recover.
17. In Writ Petition No.942 of 2001 filed by the respondent-KVSL the
material facts were not disputed. It was unequivocally admitted that the
respondent-company was a consumer getting supply from an independent
feeder emanating from 400/220/132 KV sub station. It was also not in dispute
that with the coming into existence of State of Uttarakhand w.e.f. 9th
November, 2000 a new Power Corporation for the said State was established
on 1st April, 2001. The respondent-company’s further case is that
Uttarakhand Power Corporation did not charge 15% surcharge on monthly
demand and energy charges for the period April 2001 to October, 2001 and
that it is only on 7th December, 2001 that the applicant received an intimation
that circular dated 8th September had been revoked and letter dated 24th
October cancelled. That the U.P. Electricity Regulatory Commission had
approved a new tariff by order dated 1st September, 2000 and U.P. State
Power Corporation had issued a consequential Notification dated 10th July,
2001 is also not in dispute. The said notification, it is noteworthy, does not
any longer provide for 15% surcharge from consumers getting supply of
energy from independent feeders. Suffice it to say that while according to the
applicant-KVSL circular issued by the U.P. Power Corporation dated 8th
September, 2001 giving an option to the consumers was valid and in
accordance with law, there is not even a murmur in the writ petition filed by
the respondent-company to the effect that either the U.P. Power Corporation
or its successor had at any point of time made any promise to the company
that supply of energy would be without any surcharge notwithstanding the fact
that the tariff prescribed by the Regulatory Commission envisaged the levy of
surcharge on electricity supplied directly from an independent feeder. There
is similarly no averment whatsoever in the writ petition to the effect that the
respondent-KVSL had altered its position acting upon any such promise. Not
only that the agreements executed between the parties, namely, KVSL on the
one hand and Power Corporation on the other also did not contain any
unequivocal promise for supply of energy, no matter the supply was made
from an independent feeder. In the absence of even an averment to the effect
that there was a promise made by the U.P. State Power Corporation
regarding supply of energy without payment of surcharge and in the absence
of any material to show that the respondent-KVSL had indeed acted upon any
such promise it is difficult to see how the said company can insist upon any
such non-existent promise being made good. It is trite that before a party can
rely upon on the doctrine of promissory estoppel it must make a specific
averments and place material on record to demonstrate that a promise was
indeed made to it. There is neither any averment nor any material to support
the plea of promissory estoppel in the case at hand.
18. It is also noteworthy that the High Court of Uttarakhand did not find a
case in favour of the respondent-KVSL on the ground which is now sought to
be urged in the present appeal. It is one thing to say that the plea of
promissory estoppel is available to a consumer but an entirely different thing
to say that such a plea has been made good by the material on record.
19. We have, therefore, no hesitation in repelling the contention that any
promise was made by the U.P. State Power Corporation to the respondent-
KVSL which could justify the grant of any mandamus in its favour for making
good any such promise.
20. We allow this appeal and set aside the order 17 th January, 2007 passed by the
High Court of Uttaranchal in Writ Petition No.936 of 2001 filed by respondent-
KVSL with costs of Rs.50,000/-.