ESTEEM PROPERTIES P.LTD. Vs MUN.CORP.OF GR.MUMBAI .
Case number: C.A. No.-004363-004363 / 2010
Diary number: 31051 / 2009
Advocates: E. C. AGRAWALA Vs
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO……………/2010 (ARISING OUT OF SLP(C) NO. 27069/2009)
Esteem Properties Private Ltd. .. Appellant
Versus
Municipal Corpn. of Greater Mumbai & Ors. ...Respondents
J U D G M E N T
Dr. B.S. CHAUHAN, J.
1. Leave granted.
2. This appeal has been preferred against the interim order
passed by the High Court of Bombay dated 8.10.2009 in
Appeal from Order No.1040 of 2009. Facts and circumstances
giving rise to this case are that appellant/plaintiff filed the
Civil Suit No.1177/08 for determination of the site of
demolished structure and to determine the area thereof to be
reconstructed pursuant to the order dated 21.6.2008 passed
by the Respondent-Authority.
1
3. The predecessor-in-interest of respondent no.3 was an
unauthorised occupant of a hut/structure in the slum area
measuring about 600 sq. ft. Respondent No.3 vide Deed of
Assignment dated 15.7.2006 assigned her rights to the
respondent no.4. The partner of the present appellant
submitted a list of persons to the B.M.C.-Respondent who had
to be evicted. In the said list one Shri Gupta Ram Rekha Ram
Bakhash was shown occupying room no.14, behind S.H.
Compound, near DTC Hotel, Saraswati Nagar, Sahar Road,
Andheri (East), Mumbai. The show cause notices under
Section 55 of the Maharashtra Regional Town Planning Act,
1966 were issued to all such occupants for eviction. The notice
was sent to Shri Gupta Ram Rekha Ram Bakhash and not to
the respondent No.3. The aforesaid structure was demolished
on 11.6.2008. Immediately after demolition of the said
structure, a representation dated 17.6.2008 was made by
respondent no.3 through her Advocate Smt. Sangeeta
Lanjewal alleging that her structure had wrongly been
demolished by the respondents and it was requested to restore
the same. Documents in support of her case were also filed.
2
The Statutory Authority considered the said representation
and allowed the same vide order dated 21.6.2008. Being
aggrieved by the said order of restoration of the demolished
structure, appellant filed Suit No.1177/08 in Bombay City
Civil Court along with Notice of Motion No.1342/08 which was
dismissed by the Court vide order dated 8.6.2009. Being
aggrieved, appellant preferred an appeal, however, the High
Court vide order dated 30.7.2009 rejected the appeal and
directed the respondents to restore the structure. However, it
was clarified that restoration would be subject to the final
result of the suit. The appellant preferred SLP (C)
No.21977/09 challenging the order dated 30.7.2009 passed by
the High Court. The said SLP was dismissed by this Court
vide order dated 18.9.2009.
4. The respondent no.4 in the meanwhile filed an
application for impleadment as a party making it explicit that
vide Deed of Assignment dated 15.7.2006, respondent no.4
had been assigned all rights in respect of the structure by
respondent no.3. The said application was allowed vide order
dated 12.9.2008. The present appellant being aggrieved by
3
the order of impleadment challenged the said order dated
12.9.2008. The High Court vide order dated 10.11.2008 held
that respondent no.4 was necessary party and appeal was
dismissed. The said order also stood affirmed by this Court
as SLP(C) No.28084/08 against the said order has been
dismissed vide order dated 5.12.2008.
5. In the matter of restoration of the demolished structure,
new issues have been raised by the present appellant by filing
Notice of Motion in the pending suit on 22.9.2009 for
determination of the above referred two issues. The Trial Court
vide order dated 25.9.2009 rejected the said application and
did not restrain the respondent nos.3 and 4 for carrying out
reconstruction. Against the said Order, an appeal was
preferred before the High Court and the High Court vide its
order dated 8.10.2009 dismissed the said appeal. Hence, the
present appeal.
6. Shri Harish N. Salve and Shri Mukul Rohatgi, learned
Senior counsel appearing for the appellant have submitted
that the aforesaid two questions are very essential for
determination for the reason that unless the area is
4
determined, identified and demarcated specifically, the said
respondents cannot be permitted to raise the construction at
any place. The report of the Court Commissioner as well as
the B.M.C.-respondent had been to the effect that it was not
possible to determine the exact location of the demolished
structure. On behalf of appellant, Mr. Salve made an offer to
have a constructed area at the cost of the appellant with CST
Survey No.229 with a right of ingress and egress and handover
the same to respondent no.3 within a period of 3 months.
However, this would be subject to the final orders to be passed
in Civil Suit No.1177/08.
7. On the other hand, Dr. A.M. Singhvi and Shri C.A.
Sundaram, learned Senior counsel appearing for Respondent
Nos. 3 & 4 have opposed the prayer contending that the title
of the appellant on the suit land is itself in dispute as a Public
Interest Litigation i.e. W.P. No.1657 of 2006 has been filed
giving backdrop in respect of the title of the land, therefore, no
offer made by the appellant at this stage would be acceptable
to them. A declaration had been sought in the said Writ
Petition that suit land belongs to Govt. of Maharashtra and
5
not the appellant or its predecessors–in-interest. In the said
writ petition final arguments have been heard and judgment is
reserved. The High Court has also passed an interim order to
maintain the status quo with liberty to the parties to move an
application in case there is any change in the circumstances.
It is further submitted that the land has been identified by the
Court Commissioner as well as by the BMC and therefore, the
petition is liable to be rejected.
8. Mr. Goolam E. Vahanvati, learned Attorney General
appearing for the BMC, has submitted that none of the reports
submitted so far is sufficient to find out the location of
demolished structure exactly and it requires a fresh exercise to
determine the same.
9. We have considered the rival submissions made on
behalf of the parties and perused the record.
10. Large number of documents have been filed by both the
parties to substantiate their respective claims and counter-
claims regarding identification/location of the demolished
structure. This is the only issue involved in this case as
6
number of offers made by the appellant are not acceptable to
the respondent nos.3 and 4.
11. We have compared the maps prepared by the Court
Commissioner and BMC, however, they do not match each
other. The reports submitted by both of them regarding the
identification are also far from satisfaction.
The Court Commissioner, Shri M.D. Narvekar concludes
his report as under:
“The suit site is a vast land without any demarcation as to survey or city survey number. I further noticed hundreds of huts on the land I visited.
In the absence of latest Map it was difficult for me to ascertain and identify the boundaries of the suit site in question.
At this stage parties and advocates on both the
sides requested to execute the Commission with the assistance of a Govt. Approved Surveyor.
I, therefore, seek directions from this Hon’ble Court.”
The report of the BMC is also to the same effect as
its relevant part reads as under:
“The tentative location as per plan was marked where no structure was seen. Hence, the suit
7
structure No.14 had been demolished totally and no structure could be seen at the location marked on CTS No.229.
Copy of plan ‘markings’ attached on CTS Sheet as annexed ‘B’.
Court Commissioner’s plan as annexed ‘C’.
As per the court receiver plan and City Survey Plan, there was no suit structure seen on the plot bearing CTS No.229. The photographs were taken of the plot bearing CTS No. 229 and all the representatives agreed that there is no suit structure no.14 on the plot bearing CTS No. 229, the question of taking measurement did not arise as plot was vacant.”
12. This is not the stage for the court to decide any issue on
merit as whatever interim order is passed it would be subject
to the final outcome of the Suit as well as the PIL wherein the
judgment has been reserved. In such a fact situation, it is
desirable that BMC may undertake an exercise in respect of
identification/determination to the location of the demolished
structure giving due opportunity of hearing to both sides and
determine the location of the demolished structure
expeditiously, preferably within a period of 3 months from
today. It is further clarified that on such identification, the
8
work of restoration may be carried out by the respondents. In
deciding so, the BMC may also consider the convenience of the
parties in fixing the location especially with regard to ingress
and egress to such site. However, it shall be subject to the
outcome of the Suit.
13. The appeal stands disposed of accordingly. No costs.
……………………….CJI.
.………………………. J.
(DEEPAK VERMA)
.………………………. J.
(Dr. B.S. CHAUHAN)
New Delhi May 10, 2010
9
10