COAL LINKER Vs COAL INDIA LTD.
Bench: MARKANDEY KATJU,ASOK KUMAR GANGULY, , ,
Case number: C.A. No.-001146-001146 / 2003
Diary number: 5616 / 2002
Advocates: NAVIN CHAWLA Vs
SUNIL ROY
REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1146 OF 2003
Coal Linker ...Appellant(s)
- Versus -
Coal India Limited ..Respondent(s)
J U D G M E N T
GANGULY, J.
1. The appellant herein, a proprietary
concern, was given a work order on or about
5.7.1982 by Coal India Limited (hereinafter
referred to as “the respondent”) for
transportation of coal/coke by road to the
respondent’s stockyard at Kanpur and also
for operation of the said stockyard. 1
2. Pursuant to such work order a formal
agreement was entered into between the
appellant and the respondent and the said
agreement contained an arbitration clause.
As disputes and differences arose between
the parties, a reference was made to the
sole arbitrator for resolving the dispute
and an award dated 30.4.1993 was passed
awarding an amount of Rs.51,77,600/- in
favour of the appellant. Appellant was
granted interest of Rs.11,39,560/-
calculated at the rate of 15% from October,
1990 to April, 1993. Interest was also
granted for the pre-reference period to the
extent of Rs.10,97,250/- but in the award
no interest was granted from the date of
the award till the date of the decree.
3. Challenging the said award, the respondent
filed an application, but the same was
dismissed by the learned Single Judge of
2
the Calcutta High Court by a judgment and
order dated 3.11.1995. Thereafter, an
appeal was preferred before the Division
Bench of the Calcutta High Court and the
Division Bench also dismissed the appeal of
the respondent on 25.04.1996. Thereafter,
a decree was passed by the learned Single
Judge of the Calcutta High Court confirming
the said award. The said decree directed
payment of interest @ 18% per annum from
the date of the said award till the date of
the decree.
4. The respondent filed a special leave
petition before this Court challenging the
order of the Division Bench of the Calcutta
High Court dated 25.04.1996. On that
special leave petition, this Court by an
order dated 10.5.1996 directed the
respondent to deposit an amount of Rs.40
lakhs within 6 weeks with the Registrar,
3
Original Side of the Calcutta High Court
and permitted the appellant to withdraw the
same on furnishing a bank guarantee.
Ultimately, by order dated 22.7.1996 this
Court dismissed the special leave petition
filed by the respondent.
5. Thereafter, execution proceeding was
initiated by the appellant for execution of
the unsatisfied portion of the decree dated
2.5.1996. Against the said execution
proceeding, an application was filed by the
respondent under Section 47 of the Code of
Civil Procedure contending inter alia that
the decree dated 2.5.1996 insofar as the
same directs payment of interest from the
date of the award till the date of the
decree is a nullity and the same is not
executable against the respondent.
6. Learned Single Judge of the Calcutta High
Court by judgment and order dated
4
13.12.1996 held that insofar as the decree
was passed providing for grant of interest
from the date of the award till the passing
of the decree, is a nullity and is
inexecutable and the appellant was directed
to refund the amount representing the same
pendente lite interest. Against the same
judgment and order the present appellant
filed an appeal before the Calcutta High
Court and the Division Bench of the
Calcutta High Court by judgment and order
dated 8.3.2001 was pleased to dismiss the
appeal.
7. Challenging the said appeal this special
leave petition has been filed.
8. The question in this appeal is whether the
Division Bench was correct in setting aside
the order of the Executing Court directing
payment of interest at the rate of 18% from
5
the date of the award till the date of the
decree.
9. Few facts of the case are relevant to
understand issues involved herein.
Admittedly, in the award, interest from the
date of the award till the date of the
decree has not been granted. What has been
granted is pre-reference interest and the
interest from October 1990 to April 1993
i.e the interest during the pendency of the
arbitration proceedings. The award is
dated 30.04.1993. No post award interest
has been granted.
10. The appellant herein-the awardee did not
raise any objection under Section 30 of the
Arbitration Act (hereinafter referred to as
“the Act”) to the award about denial of
such interest. On the other hand, the
appellant filed an application under
6
Section 17 of the Act for passing of a
decree in terms of the award. Therefore,
the Executing Court while passing a decree
in terms of the award should not go beyond
what has been given in the award.
11. In this connection certain decisions have
been cited which are not strictly attracted
in the facts situation of the instant case.
Reference was made to the decision of this
Court in the case of Executive Engineer (Irrigation), Balimela and others Vs. Abhaduta Jena and others – (1988) 1 SCC 418. In that case the question was about
the competence of arbitrator to award
interest on a reference made without
intervention of the Court and the three-
Judge Bench of this Court held that in
cases coming after the commencement of the
Interest Act of 1978 an arbitrator has the
same power as the Court to award interest
7
up to the date of institution of the
proceedings. In cases which arose prior to
the commencement of the Interest Act 1978,
the arbitrator has no such power under
provisions of the previous Interest Act of
1839. In the instant case, as pointed out
above, there is no dispute about the
competence of the arbitrator to grant
interest. The arbitrator, as noted above,
granted interest but did not grant any
interest after the date of the award till
the date of the decree. Therefore, the
decision in Abhaduta Jena (supra) has no relevance. Reference was also made to the
decision of this Court in the case of
Gujarat Water Supply and Sewerage Board Vs. Unique Erectors (Gujarat) (P) Ltd. and another - (1989) 1 SCC 532, wherein a two-Judge Bench of this Court relied on the
previous decision of this Court in Abhaduta Jena (supra) and dealt with the aspect of
8
grant of interest by the arbitrator in
paragraphs 14, 15 and 16 of the said
judgment. In Gujarat Water Supply (supra), this Court held that an arbitrator can
award the interest which can cover three
periods namely; (a) the period prior to the
commencement of the arbitration proceeding,
(b) period during which the arbitration
proceeding was pending and (c) the period
between the date of the award to the date
of the decree i.e the post award period.
The learned Judge has held that in the
light of the decision in Abhaduta Jena (supra) the arbitrator could not have
awarded interest “for the period between
August 22, 1984 and till the date of the
publication of the award i.e. July 1985”.
That was the period during which the
arbitration proceeding was pending.
Ultimately, the Court deleted the interest
awarded by the arbitrator for the period
9
from August 22, 1984 till the date of the
award. (See para 16 of the report). It may
be again pointed out here that in this case
the award in which interest has been given
by the arbitrator has been finally upheld.
Therefore, the principles decided in
Gujarat Water Supply (supra) have no application to the facts of the case.
12. However, in the case of Secretary, Irrigation Department, Government of Orissa and others Vs. G.C. Roy – (1992) 1 SCC 508, the Constitution Bench of this Court
overruled the decision of the Abhaduta Jena (supra) and held on construction of
Section 14 and 29 of the said Act that the
arbitrator can grant pendente lite
interest. In paragraph 8 in the judgment
of G.C. Roy (supra) the Constitution Bench of this Court clearly mentioned three
periods for which the question of award of
10
interest by the arbitrator may arise. The
said periods have been clearly pointed out
in paragraph 8 of G.C. Roy (supra) and the same is set out as below:
“...(i) for the period commencing from the date of dispute till the date the arbitrator enters upon the reference; (ii) for the period commencing from the date of the arbitrator’s entering upon reference till the date of making the award; and (iii) for the period commencing from the date of making of the award till the date the award is made the rule of the court or till the date of realisation, whichever is earlier...”
13. Admittedly, in the instant case interest
has been granted by the arbitrator in the
award for the first two periods. But
interest has not been granted by the
arbitrator in the award for the last
period.
14. As noted above, the awardee-appellant
herein, filed an application under Section
17 of the Act for pronouncing a judgment in
11
terms of the award. So there is no scope
for the Executing Court to go beyond the
award and grant interest for the post award
period which was not granted in the award.
15. Here the Executing Court has gone beyond
the award and thus had gone beyond its
jurisdiction and passed a decree which thus
becomes a nullity.
16. Similar principles have been laid down by
this Court in the case of Visakapatnam Municipal Corporation Vs. K. Satyanarayana & Co. – (1995) 2 SCC 385. In paragraph 3 of the report, the Court held:
“On the admitted facts, viz., that the respondent had not preferred any objection to the award in question under Section 30 of the Act and, in fact, had applied for a decree in terms of the award, the trial court could not have granted pendente lite interest which was not a part of the award. To that extent, the trial court had exceeded its jurisdiction”.
12
17. The same facts are present here. Here also
the appellant herein has not filed any
objection under Section 30 of the Act to
the award. Rather the appellant had
applied for a decree in terms of the award
under Section 17 of the Act.
18. In view of such clear factual position, we
find no merit in this appeal and which is
accordingly dismissed. There is no order as
to costs.
.......................J. (MARKANDEY KATJU)
.......................J. New Delhi (ASOK KUMAR GANGULY) September 07, 2009
13