BANK OF INDIA Vs NANGIA CONSTRUCTIONS (I) PVT.LTD..
Case number: C.A. No.-001315-001315 / 2001
Diary number: 18829 / 1999
Advocates: BINA GUPTA Vs
KANCHAN KAUR DHODI
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPEALLTE JURISDICTION
CIVIL APPEAL NO.1315 OF 2001
Bank of India .. Appellant
Versus
Nangia Constructions (I) Pvt. Ltd. & Others .. Respondents
WITH
CIVIL APPEAL NO. ......... OF 2008
(Arising out of SLP (CIVIL) No.3644 OF 2007)
JUDGMENT
Dalveer Bhandari, J.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9
2
1. This appeal is directed against the judgment and order
dated 26.10.1999 of the High Court of Delhi at New Delhi in
FAO (OS) No.81 of 1999.
2. The learned Single Judge of the High Court has taken
the view that the invocation of bank guarantee was within the
validity period of the bank guarantee and the bank cannot
decline to make the payment. The Division Bench in the
impugned judgment while dismissing the appeal has clearly
observed that the bank guarantee was invoked on 19th May,
1989 within the validity period of the guarantee. The bank
guarantee was merely renewed under orders of the court as
there was a stay order against encashment of the bank
guarantee. Once the stay order was vacated there was no
question of any invocation of the bank guarantee. In the
instant case, the invocation had already taken place within
the validity period. Thereafter, all that was to be done was to
intimate the Bank that the stay has been vacated and that
now payment had to be made under the bank guarantee.
3. The Division Bench in great anguish has observed thus:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9
3
"It is surprising that a nationalized bank, which has given an unconditional on demand bank guarantee takes up such a contention. No ground to refuse payment was shown to the Lower Court or to us. It is surprising that Nationalized Bank wants to use delays of law in order not to comply with its unconditional obligations under a bank guarantee. The nationalized bank should know that it is such conduct which is adversely affecting the faith of the public in banking institutions and in transaction of bank guarantee."
The Court dismissed the appeal with costs.
4. The nationalized bank despite the concurrent findings of
both the courts and such a strong observation of the Division
Bench of the High Court has still chosen to file this appeal
before this Court. Even before this Court, this is not disputed
that the bank guarantee was invoked within the validity period
of the bank guarantee.
5. Mr. K.N. Bhat, the learned senior counsel appearing for
the appellant bank submitted that there was a substituted
agreement of contract, therefore, the invocation of the bank
guarantee by respondent no.2 on 19th May, 1989 was of no
consequence.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9
4
6. It may be relevant to mention here that after the bank
guarantee was invoked, an application was filed in the court
for stay of payment under the bank guarantee. To that
application, the bank was not a party. Initially, an injunction
was granted by the High Court on 29th May, 1989. This was
on a condition that the bank guarantee should be kept alive.
This injunction was confirmed on 23rd April, 1990 again on the
condition that the bank guarantee should be kept renewed.
The constituent who had obtained injunction and who was to
keep the bank guarantee alive, did not pay the charges of the
Bank in respect of renewals of the bank guarantees.
Consequently, the appellant bank refused to renew the bank
guarantee after 26.5.1996. Thus, the beneficiary of the bank
guarantee took out an application wherein the following
prayer was made:
"In the circumstances it is, therefore, most humbly and respectfully prayed that the petitioner be directed to extend the bank guarantee for an initial period of one year and the petitioner be directed to continue to extend the bank guarantees and furnish the same to the respondent at least fifteen days before the expiry till the disputes are finally adjudicated upon by arbitration and on the failure of the petitioner to renew the bank guarantees as aforesaid the respondent may be permitted to encash the above bank guarantee."
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9
5
7. As the question was whether the bank guarantee was to
be renewed, notice was issued to the appellant bank to remain
present in the court. This was in order to find out whether
they would be willing to renew the bank guarantee. The
appellant bank appeared and made it clear to the court that
they were not ready to renew the bank guarantee as according
to them the charges are not being paid.
8. The appellant bank has reiterated the same argument
before this court that since the bank guarantee has not been
renewed, therefore, the bank is under no obligation to pay the
amount under the bank guarantee.
9. Learned counsel for the appellant has placed reliance on
two judgments of this court, on The Union of India v.
Kishorilal Gupta & Brothers 1960 (1) SCR 493 and
Makharia Brothers v. State of Nagaland & Others (2000)
10 SCC 503.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9
6
10. In Kishorilal Gupta (supra), this court has held that it
was well settled that the parties to an original contract could
by mutual agreement enter into a new contract in substitution
of the old one.
11. There is no quarrel with this proposition. The parties are
always at liberty to enter into afresh contract but this case has
no application to the facts of the present case.
12. In Makharia Brothers (supra), the question was : what
was the State’s remedy against the contractor when the
contractor failed to furnish the security deposit in cash or, in
lieu thereof, by a bank guarantee. The State could not have
filed a suit requiring the contractor to do these things for it
would have tantamount to asking for a decree of specific
performance, a decree which would have been incapable of
enforcement if the contractor was unable or unwilling to pay
out money or put a bank in funds to provide a bank
guarantee. When the contractor declined to extend the terms
of the bank guarantee, the proper course for the State was to
terminate the contract on the ground of breach of the terms
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9
7
thereof, make a claim for damages and recover on the bank
guarantee, if necessary by filing a suit.
13. We are afraid that even this case is of no help to the
appellant because the facts of the instant case are quite
different. Admittedly, the bank guarantee has been invoked
during the validity period of the bank guarantee. The bank
guarantee was unconditional on demand bank guarantee.
The bank was bound to honour its commitment and pay the
amount of guarantee.
14. It is unfortunate that a nationalized bank is finding
excuses for refusing to make the payment on totally untenable
and frivolous grounds. The Division Bench was fully justified
in making observations regarding the conduct of the
nationalized bank. The entire trust, faith and confidence of
people depend on the conduct and credibility of the
nationalized bank. In the present day world, the national and
international commercial transactions largely depend on bank
guarantees. In case the banks are permitted to dishonour
their commitments by adopting such subterfuges, the entire
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9
8
commercial and business transactions will come to a grinding
halt. This principle has been reiterated in large number of
cases by this court. We do not deem it appropriate to burden
this judgment by reiterating all those judgments.
15. This appeal being devoid of any merit is accordingly
dismissed with costs to be paid to respondent nos. 1 & 2.
CIVIL APPEAL NO. ......... OF 2008 (Arising out of SLP (CIVIL) No.3644 OF 2007)
16. Leave granted.
17. In view of our aforesaid decision, this appeal is also
dismissed with costs.
........................................J. (Tarun Chatterjee)
.......................................J. (Dalveer Bhandari) New Delhi; May 15, 2008.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9
9