ASSISTANT ENGINEER (D1) AJMER VIDYUT VITRAN NIGAM LIMITED Vs RAHAMATULLAH KHAN ALIAS RAHAMJULLA
Bench: HON'BLE MR. JUSTICE UDAY UMESH LALIT, HON'BLE MS. JUSTICE INDU MALHOTRA, HON'BLE MR. JUSTICE HEMANT GUPTA
Judgment by: HON'BLE MR. JUSTICE UDAY UMESH LALIT
Case number: C.A. No.-001672-001672 / 2020
Diary number: 33890 / 2018
Advocates: PRATIBHA JAIN Vs
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6
Page 7
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15
Page 16
Page 17
Page 18
Page 19
Page 20
1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.1672 OF 2020
(Arising out of SLP (Civil) No. 5190 of 2019)
Assistant Engineer (D1), Ajmer Vidyut …Appellant(s)
Vitran Nigam Limited & Anr.
versus
Rahamatullah Khan alias Rahamjulla …Respondent(s)
WITH C.A.NO.1673/2020 @ SLP©NO.4721/2020 @
D.NO.33892/2018
J U D G M E N T
INDU MALHOTRA, J.
Delay condoned. Leave granted.
a) The issues which have arisen for consideration in the
present Civil Appeal are : –
2
b) What is the meaning to be ascribed to the term “first due”
in Section 56(2) of the Electricity Act, 2003?
c) In the case of a wrong billing tariff having been applied on
account of a mistake, when would the amount become “first
due”?
d) Whether recourse to disconnection of electricity supply may
be taken by the licensee company after the lapse of two
years in case of a mistake?
1. The factual matrix in which the aforesaid issues have arisen
for our consideration is : –
1.1 In the present case, for the period July, 2009 to
September, 2011, the Respondent along with other
consumers were billed by the licensee company (the
Appellant herein) under Tariff Code 4400 @Rs.1.65 per
unit.
1.2 During the course of a regular audit being conducted by
the Internal Audit Party, it was discovered that in 52
cases, including that of the Respondent, the bills were
raised under the wrong Tariff Code 4400, instead of
3
Tariff Code 9400, under which the prescribed tariff rate
was Rs.2.10p. per unit.
1.3 On 18.03.2014, the licensee company issued a show
cause notice to various consumers, including the
Respondent, raising an additional demand for
consumption of electricity for the past period from July,
2009 to September, 2011. It was mentioned in the notice
that the amount was payable in view of the internal
audit conducted by the department.
1.4 On 25.05.2015, the licensee company raised a bill
demanding payment of Rs.29,604/- from the
Respondent under Tariff Code 9400 for the period July,
2009 to September, 2011.
1.5 Aggrieved by the said demand, the Respondent filed a
Consumer Complaint before the District Consumer
Forum, Ajmer.
The District Forum vide Order dated 21.06.2016,
allowed the Consumer Complaint, and held that the
additional demand was time-barred.
1.6 Thereafter, the State Commission vide Order dated
30.05.2017, allowed the Appeal of the licensee
4
company, and set aside the Order dated 21.06.2016
passed by the District Forum.
1.7 In the Revision Petition filed by the Respondent before
the National Consumer Disputes Redressal
Commission, the Order passed by the State Commission
was set aside. The National Commission held that the
additional demand was barred by limitation under
Section 56(2) of the Electricity Act, 2003 (“the Act”).
1.8 The licensee company has filed the present Civil Appeals
before this Court to challenge the final judgment dated
28.05.2018 passed by the National Commission.
1.9 This Court vide Order dated 05.03.2019 appointed Mr.
Devashish Bharuka as Amicus Curiae to assist this
Court on the issues raised for determination.
It was further directed that the Appellant –
Corporation would not be entitled to recover the
additional demand from the Respondent in this case,
and only the questions of law would be determined.
2. We have heard the learned Counsel on behalf of the Appellant
– Corporation and the learned Amicus Curiae.
5
3. Mr. Puneet Jain represented the licensee company, and
submitted that the power to disconnect electricity supply
under Section 56(1) of the Act may be exercised by the licensee
company when a consumer neglects to pay the electricity
charges, or any other sums due and payable by him. The
neglect to pay the “sum due” by a consumer, necessarily
requires that there should be a “demand” of the sum due from
the consumer, which he is required to pay within the period
stipulated. If the demand is not paid within the stipulated
time, then the power of disconnection under Section 56(1) may
be resorted to.
3.1 It was further submitted that when a bill or demand is
raised, which is disputed by the consumer, he may raise
the dispute before the Authorities as provided by Section
42(5) or 42(6) of the Act, or avail such other remedies as
may be available in law, such as a suit for declaration
and injunction; consumer dispute before the consumer
fora; arbitration if provided by the governing agreement.
3.2 Section 56(1) of the Act confers the power of
disconnection of electricity supply for default of
6
payment upon a licensee, and provides the conditions
when such a power may be invoked, the procedure and
manner of the exercise of such power, the period for
which such power can remain effective, and the
circumstances under which such a power cannot be
exercised.
3.3 Sub-section (2) of Section 56 bars the remedy of
disconnection of supply for default of payment, if the
consumer deposits the amount demanded under
protest, or if the demand has been raised two years after
the sum became “first due”, albeit the same had been
continuously shown to be recoverable as arrears of
charges.
3.4 The word “due” has been used under Section 56(1) as
well as under Section 56(2). The term “due” refers to the
amount for which the demand is raised by way of a bill.
The term “first due” would therefore imply when the
demand is raised for the first time. The bill raised by the
licensee company would be the starting point for the
exercise of power under sub-section (1) of Section 56.
7
3.5 The starting point of limitation would be from the date
when the bill is raised by the licensee company. The bar
of limitation is applicable only on the exercise of power
of disconnection. As per sub-section (2) of Section 56,
the bar of limitation would be two years from the date
when the first bill is raised.
3.6 It was further submitted that in case of a mistake, the
starting point of limitation should be the date when the
mistake is discovered.
In the present case, during a regular internal audit
conducted on 18.03.2014, it was discovered that a
mistake had occurred in 52 cases, including that of the
Respondent, as the bills were raised under the wrong
Tariff Code. The Appellant–Corporation raised
additional demands on 25.05.2015, i.e., within two
years from the discovery of the mistake.
4. The learned Amicus Curiae submitted that Section 56(1) of the
Act empowers the licensee to disconnect the electricity supply
if the consumer neglects to pay his dues. The disconnection
would take place only after the consumer has consumed the
8
electricity, and the bill has been generated. If the consumer
neglects to pay the bill served on him within the stipulated
period, the licensee can resort to coercive modes of recovery
provided in the Act.
4.1 The words “first due” used in the first part of sub-section
(2) of Section 56 is used in the context of the sum
quantified by the licensee in the bill; while the second
part of sub-section (2) of Section 56 indicates the date
when the first bill for the supply of electricity was raised
by the licensee under the applicable State Electricity
Supply Code.
4.2 By treating the words “first due” to mean the date of
detection of mistake, would dilute the mandate of the
two year limitation period provided by Section 56(2),
since a mistake may be detected at any point of time.
Furthermore, the words “recoverable as arrears of
charges” would be rendered completely otiose and
nugatory.
4.3 The period of limitation under Section 56(2) cannot be
extended by raising a supplementary bill. The “sum due”
raised in the original bill, and not paid by the consumer,
9
must be continuously shown as arrears of charges in
subsequent bills, for it to become recoverable by taking
recourse to the coercive mode of disconnection of
electricity supply.
4.4 If after the expiry of two years of the original demand,
any genuine or bona fide mistake is detected by the
licensee in the original bill, it would be entitled to raise
a supplementary bill. The licensee company would be
entitled to resort to other modes of recovery, but not by
disconnection of supply under sub-section (1) of Section
56 of the 2003 Act.
6. Findings and Analysis
The Electricity Act, 2003 is a consumer-friendly statute.1 The
Statement of Objects and Reasons to the Act notes that over a
period of time, the performance of State Electricity Boards had
deteriorated on account of various factors, and the need was
felt to frame a self-contained comprehensive legislation, which
led to the enactment of the Electricity Act, 2003.
1 Tata Powers v. Reliance Energy, (2008) 10 SCC 321.
10
6.1 Electricity has been held to be “goods” by a Constitution
Bench in State of Andhra Pradesh v. National Thermal
Power Corporation Ltd.2 Under the Sale of Goods Act,
1930 a purchaser of goods is liable to pay for it at the
time of purchase or consumption. The quantum and
time of payment may be ascertained post facto either by
way of an agreement or the relevant statute.
In the case of electricity, the charges are
ascertained and recovered as per the tariff notified by
the State Electricity Board, or under an electricity
supply agreement between the parties read with the
tariff under Section 62(1)(d), and the Electricity Supply
Code framed under Section 50.
6.2 The present Civil Appeal pertains to the interpretation
of Section 56 of the Act which reads as follows : –
“Section 56. Disconnection of supply in default of payment – (1) Where any person neglects to pay any charge for electricity or any sum other than a charge for electricity due from him to a licensee or the generating company in respect of supply, transmission or distribution or wheeling of electricity to him, the licensee or the generating company may, after giving not less than fifteen clear days’ notice in writing, to such person and
2 (2002) 5 SCC 203.
11
without prejudice to his rights to recover such charge or other sum by suit, cut off the supply of electricity and for that purpose cut or disconnect any electric supply line or other works being the property of such licensee or the generating company through which electricity may have been supplied, transmitted, distributed or wheeled and may discontinue the supply until such charge or other sum, together with any expenses incurred by him in cutting off and reconnecting the supply, are paid, but no longer: Provided that the supply of electricity shall not
be cut off if such person deposits, under protest, - a) an amount equal to the sum claimed from him, or b) the electricity charges due from him for each month calculated on the basis of average charge for electricity paid by him during the preceding six months, whichever is less, pending disposal of any dispute between him and the licensee. (2) Notwithstanding anything contained in any other law for the time being in force, no sum due from any consumer, under this section shall be recoverable after the period of two years from the date when such sum became first due unless such sum has been shown continuously as recoverable as arrear of charges for electricity supplied and the licensee shall not cut off the supply of the electricity.”
(emphasis supplied)
Section 56 provides for disconnection of supply in
the case of default in payment of electricity charges.
Sub-section (1) of Section 56 provides that where any
person “neglects” to pay “any charge” for electricity, or
“any sum” other than a charge for electricity due from
12
him to a licensee or generating company, the licensee
after giving 15 days’ written notice, may disconnect the
supply of electricity, until such charges or other sums
due, including the expenses incurred, are paid.
However, the disconnection cannot continue after the
amounts are paid.
6.3 The obligation of a consumer to pay electricity charges
arises after the bill is issued by the licensee company.
The bill sets out the time within which the charges are
to be paid. If the consumer fails to pay the charges
within the stipulated period, they get carried forward to
the next bill as arrears.
6.4 The proviso to Section 56(1) carves out an exception by
providing that the disconnection will not be effected if
the consumer either deposits the amount “under
protest”, or deposits the average charges paid during the
preceding six months.
6.5 Sub-section (2) of Section 56 by a non obstante clause
provides that notwithstanding anything contained in
any other law for the time being in force, no sum due
from any consumer, shall be recoverable under Section
13
56, after the expiry of two years from the date when the
sum became “first due”, unless such sum was shown
continuously recoverable as arrears of charges for the
electricity supplied, nor would the licensee company
disconnect the electricity supply of the consumer.
The effect of a non obstante clause was explained
by this Court in Chandavarkar Sita Ratna Rao v.
Ashalata S. Guram.3 It was held that : –
“69. A clause beginning with the expression ‘notwithstanding anything contained in this Act or in some particular provision in the Act or in some particular Act or in any law for the time being in force, or in any contract’ is more often than not appended to a section in the beginning with a view to give the enacting part of the section in case of conflict an overriding effect over the provision of the Act or the contract mentioned in the non-obstante clause. It is equivalent to saying that in spite of the provision of the Act or any other Act mentioned in the non-obstante clause or any contract or document mentioned the enactment following it will have its full operation or that the provisions embraced in the non-obstante clause would not be an impediment for an operation of the enactment.”
(emphasis supplied)
6.6. The liability to pay arises on the consumption of
electricity. The obligation to pay would arise when the
3 (1986) 4 SCC 447.
14
bill is issued by the licensee company, quantifying the
charges to be paid.
Electricity charges would become “first due” only
after the bill is issued to the consumer, even though the
liability to pay may arise on the consumption of
electricity.
7. The next issue is as to whether the period of limitation of two
years provided by Section 56(2) of the Act, would be applicable
to an additional or supplementary demand.
7.1 Prior to the coming into force of the Electricity Act, 2003,
the Indian Electricity Act, 1910 governed the law
pertaining to the use and supply of electricity in India.
Section 24 of the Indian Electricity Act, 1910 read as
follows :–
“24. Discontinuance of supply to consumer neglecting to pay charge.
(1) Where any person neglects to pay any charge for energy or any sum, other than a charge for energy, due from him to a licensee in respect of the supply of energy to him, the licensee may, after giving not less than seven clear days’ notice in writing to such person and without prejudice to his right to recover such charge or other sum by suit, cut off the supply and for that purpose cut or disconnect any electric supply-line or other works being the
15
property of the licensee, through which energy may be supplied, and may discontinue the supply until such charger or other sum, together with ally expenses incurred by him in cutting off and reconnecting the supply, are paid, but no longer. (2) Where any difference or dispute which by or under this Act is required to be determined by an Electrical Inspector, has been referred to the Inspector before notice as aforesaid has been given by the licensee, the licensee shall not exercise the powers conferred by this section until the Inspector has given his decision:
Provided that the prohibition contained in this subsection shall not apply in any case in which the licensee has made a request in writing to the consumer for a deposit with the Electrical Inspector of the amount of the licensee’s charges or other sums in dispute or for the deposit of the licensee’s further charges for energy as they accrue, and the consumer has failed to comply with such request.”
The Standing Committee of Energy in its Report
dated 19.12.2002 submitted to the 13th Lok Sabha,
opined that Section 56 of the 2003 Act is based on
Section 24 of the 1910 Act.
The Standing Committee further opined that a
restriction has been added for recovery of arrears
pertaining to the period prior to two years from
consumers, unless the arrears have been continuously
shown in the bills. Justifying the addition of this
restriction, the Ministry of Power submitted that : –
16
“It has been considered necessary to provide for such a restriction to protect the consumers from arbitrary billings.”
7.2 In Swastic Industries v. Maharashtra State Electricity
Board,4 this Court while interpreting Section 24 of the
Indian Electricity Act, 1910 held that : –
“5. It would, thus, be clear that the right to
recover the charges is one part of it and right to discontinue supply of electrical energy to the consumer who neglects to pay charges is another part of it.”
(emphasis supplied)
7.3 Sub-section (1) of Section 56 confers a statutory right to
the licensee company to disconnect the supply of
electricity, if the consumer neglects to pay the electricity
dues.
This statutory right is subject to the period of
limitation of two years provided by sub-section (2) of
Section 56 of the Act.
7.4 The period of limitation of two years would commence
from the date on which the electricity charges became
“first due” under sub-section (2) of Section 56. This
4 (1997) 9 SCC 465.
17
provision restricts the right of the licensee company to
disconnect electricity supply due to non-payment of
dues by the consumer, unless such sum has been
shown continuously to be recoverable as arrears of
electricity supplied, in the bills raised for the past
period.
If the licensee company were to be allowed to
disconnect electricity supply after the expiry of the
limitation period of two years after the sum became “first
due”, it would defeat the object of Section 56(2).
8. Section 56(2) however, does not preclude the licensee company
from raising a supplementary demand after the expiry of the
limitation period of two years. It only restricts the right of the
licensee to disconnect electricity supply due to non-payment
of dues after the period of limitation of two years has expired,
nor does it restrict other modes of recovery which may be
initiated by the licensee company for recovery of a
supplementary demand.
18
9. Applying the aforesaid ratio to the facts of the present case,
the licensee company raised an additional demand on
18.03.2014 for the period July, 2009 to September, 2011.
The licensee company discovered the mistake of billing
under the wrong Tariff Code on 18.03.2014. The limitation
period of two years under Section 56(2) had by then already
expired.
Section 56(2) did not preclude the licensee company from
raising an additional or supplementary demand after the
expiry of the limitation period under Section 56(2) in the case
of a mistake or bona fide error. It did not however, empower
the licensee company to take recourse to the coercive measure
of disconnection of electricity supply, for recovery of the
additional demand.
As per Section 17(1)(c) of the Limitation Act, 1963, in case
of a mistake, the limitation period begins to run from the date
when the mistake is discovered for the first time.
In Mahabir Kishore and Ors. v. State of Madhya Pradesh,5
this Court held that :–
5 (1989) 4 SCC 1.
19
“Section 17(1)(c) of the Limitation Act, 1963, provides that in the case of a suit for relief on the ground of mistake, the period of limitation does not begin to run until the plaintiff had discovered the mistake or could with reasonable diligence, have discovered it. In a case where payment has been made under a mistake of law as contrasted with a mistake of fact, generally the mistake become known to the party only when a court makes a declaration as to the invalidity of the law. Though a party could, with reasonable diligence, discover a mistake of fact even before a court makes a pronouncement, it is seldom
that a person can, even with reasonable diligence, discover a mistake of law before a judgment adjudging the validity of the law.”
(emphasis supplied)
In the present case, the period of limitation would
commence from the date of discovery of the mistake i.e.
18.03.2014. The licensee company may take recourse to any
remedy available in law for recovery of the additional demand,
but is barred from taking recourse to disconnection of supply
of electricity under sub-section (2) of Section 56 of the Act.
10. We extend our appreciation to Mr. Devashish Bharuka,
Advocate who has very ably assisted this Court as Amicus
Curiae.
20
The present Civil Appeals are accordingly disposed of in the
aforesaid terms.
All pending Applications, if any, are accordingly disposed of.
Ordered accordingly.
.....................................J. (UDAY UMESH LALIT)
.…...............………………J. (INDU MALHOTRA)
New Delhi, February 18, 2020