WEST BENGAL ELECT.REGULATORY COMMN. Vs HINDALCO INDUSTRIES LTD..
Case number: C.A. No.-000805-000805 / 2008
Diary number: 37395 / 2007
Advocates: MALINI PODUVAL Vs
ANIL KUMAR TANDALE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.805 OF 2008
WEST BENGAL ELECTRICITY REGULATORY COMMISSION .….APPELLANT(S)
VERSUS
HINDALCO INDUSTRIES LTD. & ORS. …RESPONDENT(S)
W I T H
CIVIL APPEAL NO.3341 OF 2008
J U D G M E N T
SURINDER SINGH NIJJAR, J.
1. In these two appeals the appellants are aggrieved by the order
passed by the Appellate Tribunal for Electricity (hereinafter referred to
as ‘the Tribunal’) in Appeal No.3/2007 dated October 31, 2007. The
present Appeal No. 805 of 2008 is at the instance of West Bengal
Electricity Regulatory Commission (hereinafter referred to as ‘the
Commission’). Appeal No.3341/2008 has been filed by the Calcutta
1
Electricity and Supply Company Limited (hereinafter referred to as
‘CESC’).
2. We propose to decide the two appeals by this common judgment
as they arise out of the aforesaid common order passed by the
Tribunal.
3. The controversy between the parties revolves around the
methodology, criteria/formula that has to be applied in determining
the wheeling charges in accordance with the applicable Rregulations
framed under the Electricity Act 2003.
4. We may notice here the skeletal facts which are necessary for
the purpose of disposal of these two appeals. HINDALCO Industries
Limited, formerly known as Indian Aluminum Company Limited
(hereinafter referred to as respondent No.1) has an aluminum and
copper products factory at Belurmath in West Bengal within the
distribution licence area of CESC. It had an existing Contract
Demand Agreement for 8.5 MW with CESC drawing power at the
voltage of 33 KV through dedicated lines from the Belurmath receiving
Sub-Station of CESC. For this purpose, respondent No.1 has
installed a 33 KV Sub-Station at its premises. It has a captive power
plant at Hirakud, Orissa. On 31.10.2003 respondents filed an
application under Section 9 and 42 of the Electricity Act, 2003 before
2
the Commission seeking permission for open access to wheel surplus
captive power of an approximately 9 MW from its power plant to its
Belur factory. The distance between the captive power plant at
Hirakud, Orissa and Belurmath plant in West Bengal is about 555
kilometers, out of which 550 kilometers falls within the jurisdiction of
West Bengal State Electricity Board (for short WBSEB), OPTCL and
Eastern Region. We may also notice here that out of these five
kilometers, respondent No.1 had at its own cost put up 2 kilometers
long dedicated transmission line, thus using only 3 kilometers of the
CESC network. Respondent No.1 paid wheeling charges for
transmission of power at the rate of 9.57 paise per unit for 550
kilometers. However, in respect of remaining five kilometers, which
also fall within the State of West Bengal, respondent No.1 has to pay
wheeling charges at the rate of 83.54 paise/kWh as fixed by the
Appellate Commission by its order dated 21.11.2005. In its order
dated 21.11.2005 the Commission had observed as follows:
“26.0 Thereafter, actual of working of open access should follow, naturally depending-upon availability of capacity as laid down in the Regulations on open access. Payments of various charges / fees should follow the provisions of the Regulations dealing with fees, charges and formats. There are still two items on which specific orders from the Commission will be required. The first one concerns the quantum / rate of additional surcharge, while the second one concerns the wheeling charge which will have to be determined by the Commission in terms of Regulation 14.3(b) and Regulation 14.5(b) respectively of the West Bengal Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2005. We have since determined the wheeling charges applicable to CESC Limited for the year 2005-06 based on
3
factors like distribution network cost, units saleable by the distribution licensee to its consumers, units to be wheeled by the open access customer etc. and the same has worked out to 83.54 paise per kWh. This will be revised appropriately, needless to add, by the Commission every year.”
5. Aggrieved by the aforesaid order, respondent No.1 challenged
the same before the Tribunal by way of an appeal being Appeal
No.1/2006. The aforesaid appeal was allowed by the Tribunal by its
order dated 11.7.2006. The impugned order of the Commission was
quashed and set aside. The matter was remanded back to the
Commission for a fresh determination of wheeling charges with the
following observations:
“35. It follows that in calculating wheeling charges for the distribution system or associated facilities are to be assessed on applicable distribution network cost, units saleable and units wheeled by all open access customers in the network. The learned counsel for appellant contends that as per CERC (Open Access in Inter-State Transmission) Regulations and WBERC (Terms & Conditions for Open Access –Schedule of Charges, Fees & Formats for Open Access) Regulation, the wheeling charges of the Distributing system should be 0.25 time for short term open access. However, we find from Para 26.0 of the order appealed against, there is no detailed discussion in this respect except holding that 83.54 paisa/kWh shall be the wheeling charges. No particulars been disclosed is the main grievance and Regulations governing wheeling charges have not been applied correctly. The second respondent has stated in its submission that the WBERC determined the wheeling charges in case of WBSEB for 2005-06 at the rate of 56 paisa/kWh and a copy also was filed. In the circumstances with respect to fixation of wheeling charges the matter deserves to be remitted back to WBERC for fresh consideration in the light of the relevant Rules and affording opportunity to appellant. The
4
authority shall take note of the fact that open access within the Distribution area of CESC is applied to a distance of 5 KM and out of 5 KM, 2 KM distance is appellant’s dedicated transmission line put up at its costs.”
6. Upon remand, the matter was again heard, and decided by the
Commission vide order dated 16.11.2006. By this order the
Commission sought to demonstrate and detail the methodology for
determining the wheeling charges payable by respondent No.1. The
wheeling charges were re-determined by the Commission
at 83.54 paisa per KWH. Again being aggrieved by the aforesaid
order, respondent No.1 impugned the same before the Tribunal by
way of Appeal No.3/2007.
7. We may notice here that in both the matters before the
Tribunal, respondent No.1 had challenged the determination of
wheeling charges for the year 2005-06. Initially, respondent No.1 had
challenged the order passed by the Commission on 21.11.2005 in
Appeal No.1/2006. By order dated 11.7.2006 Appeal No.1/2006 was
allowed and the matter was remanded back to the Commission for
fresh determination of wheeling charges. It was observed that there
was no detailed discussion in the order which would throw light upon
the manner and methodology behind determination of wheeling
charges. The grievance made by respondent No.1 which was noticed
by the Tribunal was that “no particular wheel disclosed is the main
5
grievance and regulation governing wheeling charges have not been
applied correctly.”
8. Taking note of the aforesaid observations, the Commission
re-determined the wheeling charges. It is the case of the appellants
herein that wheeling charges had been correctly re-determined on the
basis of the total distribution network cost as mandated under the
Commission (Terms and Conditions for Open Access –Schedule of
Charges, Fees & Formats for Open Access) Regulations, 2005; the
West Bengal Electricity Regulatory Commission (Terms and
Conditions for Open Access) Regulations 2005 as well as the West
Bengal Electricity Regulatory Commissions (Terms and Conditions of
Tariff) Regulations, 2005.
9. It is claimed by the appellants that the formula/
methodology/criteria for determining wheeling charges has to be in
terms of form 1.27 attached to the Tariff Regulations, 2005. In spite
of the clear and categorical statutory provisions contained in the
applicable regulations, the appellants have been wrongly directed by
the Tribunal to re-determine the wheeling charges on the basis of
applicable network of 33 KVW distribution system on which the
electricity is being rolled by respondent No.1. The appellants had laid
considerable emphasis on the submissions that the determination of
wheeling charges based on the interpretation directed by the Tribunal
6
would be ex facie contrary to the scheme contemplated under the
applicable regulations framed under the Electricity Act, 2003
governing determination of wheeling charges. A combined reading of
all the applicable regulations, according to the appellants, leads to the
irresistible conclusion that for determining wheeling charges total
distribution cost of the network and not the voltage-wise cost would
be the determining factor. The interpretation made by the Tribunal, if
accepted, would render the regulation framed by the appellant otiose.
The Tribunal incorrectly understood and interpreted the expressions
applicable distribution network as the distribution network cost
which is to be determined at the relevant voltage level.
10. At this stage we need not decide any of the issues raised by the
appellants as, in our opinion, the appeals have to be allowed on the
short ground that the Tribunal has failed to consider the objection
raised by the appellants with regard to the maintainability of the
appeal filed by respondent No.1, before the Tribunal.
11. Both the appellants had categorically stated before the Tribunal
that respondent No.1 has sought to challenge the wheeling charges
for the year 2005-06 as determined by the Tribunal in the order dated
16.11.2006. During the year 2005-06 not a single unit of energy was
wheeled by respondent No.1 and therefore no wheeling charges were
paid/payable. Therefore, the appeal filed by respondent No.1 herein
7
was at best of an academic interest only, as at the relevant point of
time when Appeal No.03/2007 was filed the wheeling charges for the
year 2006-07 had already been determined. It was also mentioned
that for reasons best known to respondent No.1 herein the wheeling
charges for 2006 were not challenged in the appeal before the
Tribunal. In any event since respondent No.1 had not wheeled any
power during the period 2005-06, it did not have to pay any wheeling
charges in the first place. Thus, the appeal ought to have been
dismissed as having become infructuous. It is emphasised by the
counsel for the appellant that detailed written notes were submitted
before the Tribunal during the course of hearing in Appeal No.3/2007.
Thereafter also written submissions were filed detailing the scope of
the issues before the Tribunal. Copies of these written submissions
have been placed before us as an annexure to the grounds of appeal.
12. The specific submission made by the appellant with regard to
the maintainability of the appeal was an important issue which
needed consideration by the Tribunal. Numerous issues, which have
been raised in these appeals on merits, were also raised before the
Tribunal which seem to have escaped the notice of the Tribunal
rendering its decision vulnerable. In our opinion, it would be in the
interest of justice to remand the matter back to the Tribunal for fresh
consideration of all the issues after taking into consideration the
factual and legal submissions made by the appellant. In view of the
8
above both the appeals succeed and are allowed. The order passed by
the Tribunal is set aside. The appeals are remanded back to the
Tribunal to be decided afresh on merits, in accordance with law
preferably within a period of three months of the receipt of a certified
copy of this order.
13. Appeals are allowed as indicated above with no order as to
costs.
.....…...…………………………J.
[ B. SUDERSHAN REDDY ]
..……….………………………….J. NEW DELHI; [ SURINDER SINGH NIJJAR ] APRIL 22, 2010.
9