16 July 2009
Supreme Court
Download

UNION OF INDIA Vs SARASWAT TRADING AGENCY .

Case number: C.A. No.-004427-004427 / 2009
Diary number: 32874 / 2006
Advocates: D. S. MAHRA Vs RUBY SINGH AHUJA


1

                     REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.  4427 OF 2009 [Arising out of SLP (C) No.3501/2007]

Union of India … Appellant

Versus

Saraswat Trading Agency & Ors. … Respondents  

J U D G M E N T  

AFTAB ALAM,J.

Leave granted.

1

2

This  appeal,  at  the  instance  of  Union  of  India,  arises  from  an  

arbitration award dated September 9, 2000 made in favour of the respondent.  

The appellant challenged the award before the Calcutta High Court by filing  

an  application  under  section  34  of  the  Arbitration  and Conciliation  Act,  

1996.  A  learned  Single  Judge  of  the  High  Court  upheld  the  challenge  

substantially and by judgment and order dated November 20, 2001 passed in  

G.A.No.87/01, arising out of AP No.325/98, sustained the award only on  

one issue and set it aside on two of the three issues under reference. Against  

the judgment of the Single Judge the respondent preferred an internal court  

appeal and the Division Bench of the High Court by its judgment and order  

dated July 4, 2006 passed in G.A.No.87/01: APOT No.792/01 with APO  

No.362/01 allowed the appeal, set aside the judgment of the Single Judge  

and fully restored the arbitrator’s award in favour of the respondent on all  

the three issues in dispute. Against the judgment of the Division Bench of  

the High Court the appellant has come in appeal to this Court.

The facts of the case are brief and simple and may be stated thus. For  

the work of “handling of goods, parcels and booked luggage” at a group of  

six  stations  falling  in  its  Nagpur  Division,  the  South  Eastern  Railway,  

Calcutta,  invited tenders  that  were  opened on May 16,  1990.  The tender  

submitted by the respondent was the lowest. Hence, after some negotiations  

2

3

and extension of the validity of offer the respondent’s tender was accepted  

on August 2, 1991 and it was given the work for a period of three years  

commencing from August 3, 1991. The grant of the contract was formalized  

in  an  agreement  executed  by  the  parties  on  December  3,  1991.  The  

agreement was deemed to have come into force with effect from August 3,  

1991 and it was to remain in force for a period of three years, till August 2,  

1994  unless  determined  by  either  of  the  parties  in  terms  of  clause  1(1)  

(authorizing the appellant to determine the contract by giving three months  

notice) and its proviso (giving the same right to the contractor, after expiry  

of the period of one year of the contract). Clause 2 of the agreement dealt  

with the nature of the work the contractor was required to do. Clause 4 of the  

agreement along with a detailed schedule mentioned fixed rates for every  

piece of work covered by the contract. Clause 7 stated that the contractor  

would not be entitled to any increase in the accepted rates of remuneration or  

compensation due to fluctuations in the traffic (increase or decrease) due to  

any  reason.  Under  clause  13  the  contractor  indemnified  the  Railway  

Administration against all claims that might be made under the Workmen’s  

Compensation Act, 1923 in consequence of any accident or injury sustained  

by any labourer/servant  or person in his employment and engaged in the  

performance of the contract. Clause 14 bound the contractor to pay to the  

3

4

labourers engaged by him not less than the fair wage. It further provided that  

‘fair wage’ would be the wage including the allowances, notified at the time  

of inviting tenders for the work. Clause 15 made the contractor responsible  

for compliance with the provisions of the Payment of Wages Act, 1936, and  

the rules made thereunder in respect of the staff employed by him. Clause 16  

similarly made the contractor responsible for compliance with the provisions  

of the Contract Labour (Regulation and Abolition) Act, 1970 and the rules  

made thereunder and required him to obtain the statutory license from the  

licensing  authority.  Clause  18  made  the  contractor  responsible  for  

compliance with the provision of the Hours of Employment Regulations in  

respect of the staff employed by him in the manner decided upon by the  

appropriate  authorities.  Clause  19  stipulated  that  no  labourer  would  be  

unfairly treated or removed from work except for valid reasons and further  

provided  that  the  porters  engaged  in  the  handling  of  goods,  parcels  and  

booked  luggage  under  the  terms  of  the  agreement  would  be  deemed  as  

employees of the contractor within the meaning of the Industrial Disputes  

Act,  1947 or  any other  enactment that  might  be applicable.   This  clause  

further stated that the contractor would comply with all the laws, regulations  

and rules for the benefit  of labour that were in force or might come into  

force  and  he  would  indemnify  and  keep  the  Railway  Administration  

4

5

indemnified against all loss, damage, claims and costs arising in any manner  

whatsoever. Clause 20 reserved the right of the Railway Administration to  

deduct from the moneys due to the contractor or from his security deposit  

any  sum required  or  estimated  to  be  required  for  making  good  the  loss  

suffered by the labour or labourers or any other person in his employment  

for the reasons of non-fulfillment of the conditions for the benefit  of the  

labourers,  non-payment  of  wages  or  deductions  made  from him or  their  

wages which were unjustified or illegal. Clause 31 stipulated that no interest  

or damage would be paid to the contractor for delay in payment of the bill  

‘for  any  reason  whatsoever’.  Clause  32  with  its  various  sub-clauses  

contained  the  provision  for  arbitration  and  provided  that  the  General  

Manager of the South Eastern Railway or a person appointed by him would  

be the sole arbitrator in respect of any dispute as to the respective rights,  

duties  and  obligations  of  the  parties  to  the  agreement  or  as  to  the  

construction  or  interpretation  of  any  of  the  terms  and conditions  of  this  

agreement or as to its applications.   

We next come to what is at the root of the dispute between the parties.  

It  needs  to  be  noted  that  at  the  time  of  submission  of  tender  by  the  

respondent the base fair rate of wages for the casual labour was Rs.31=15  

paise as per the Circular dated January 17, 1990. During the period of the  

5

6

contract the Railway authorities are said to have issued circulars/guidelines  

revising the rates of casual labourers from retrospective dates. The manner  

in which rates were revised by the circulars/guidelines issued by the Railway  

authorities is noted in the arbitrator’s award as follows:

PARTICULARS

Circular No. Circular  dated

Effect  from

Average  rate  of  unskilled  labour

P/EN/C- RAT/1/90

17.1.90 1.7.89 Rs.31.15

P/EN/NGP/  P/EN/NGP/ Casual Labour 90-91

16.4.92 1.7.91 Rs.42.40

P/EN/NGP

Casual  Labour/MS/92

10.2.93

10.2.93

1.1.92

1.7.92

Rs.47.45

Rs.50.50

P/EN/NGP

Casual  Labour  93

15.2.94

15.2.94

1.1.93

1.7.93

Rs.51.10

Rs.53.50

P/EN/NGP/MS

/94

16.3.95 1.1.94

1.7.94

Rs.57.45

Rs.62.0

6

7

On August  25,  1992,  the  respondent  wrote  a  letter  to  the  Railway  

authorities  demanding  enhancement  of  rates  under  the  contract  on  the  

ground that the rates stated in the agreement were based on the circular dated  

January 17, 1990 that had undergone a number of revisions and as a result  

the  contract  rates  had  become  unrealistic  and  unviable.  The  Railway  

authorities  rejected  the  respondent’s  demand  for  enhancement  and/or  

revision  of  rates  taking  the  stand  that  the  contract  was  a  “fixed  price  

contract”  and it  had no clause  for  enhancement  of  rates.  Faced with  the  

authorities’ refusal to revise the contract rates the respondent terminated the  

contract  by  giving  three  months  notice  as  provided under  the  proviso  to  

clause  1(1)  of  the  agreement.  The  Railway  authorities  accepted  the  

termination of the contract with effect from December 31, 1992 but in order  

to avoid any dislocation requested the respondent to carry on the work on the  

same  terms  and  conditions,  promising  that  its  claim  would  receive  due  

consideration. On the appellant’s request the respondent continued with the  

work under the contract, though under protest, till august 1994.

At  the  time of  the  final  settlement  of  the  respondent’s  claims  the  

Railway  authorities  offered  to  it  a  sum  of  Rs.6,848=00  as  additional  

payment  for  the  period  January  1993  to  August  1994.  The  respondent  

7

8

naturally declined to accept the paltry amount offered by the authorities and  

requested  for  a  proper  consideration  of  its  claim  as  earlier  promised.  

Finally,  the  Railway  authorities  appointed  a  high  level  committee  to  

consider  the  respondent’s  claim  for  enhanced  payment  for  the  period  

January 1, 1993 to August 31, 1994. The committee fixed the respondent’s  

claim at Rs.3, 61,058=00 but it was not acceptable to the respondent.

A departmental arbitrator was then appointed in order to resolve the  

disputes  and  differences  arising  between  the  parties.  The  departmental  

arbitrator gave his award on June 4, 1998. Not being satisfied with the award  

the respondent challenged it by filing an application under section 34 of the  

Act before the High Court. The High Court by its order dated February 12,  

1999 upheld the award on items 1 & 2 but set it aside in respect of items 3, 4  

& 5 and appointed a certain advocate, a member of the bar to decide afresh  

in  regard  to  the  respondent’s  claim  under  those  three  items.  On  an  

application  made under  section 11,  the Acting Chief  Justice  of  the  High  

Court, by order dated July 1, 1999, substituted another advocate as arbitrator  

in place of the one appointed by the Court on the application under section  

34 of the Act.

8

9

The three issues/claims that came up before the arbitrator appointed  

by the High Court were as follows:

“Claim No.3: Claim for increase in rates from

3.8.91 to 31.12.92 during the  

                                                             Contractual period being sum  

of Rs.10,74,408/-

Claim No.4: Claim for increase in rates from

1.1.93 to 31.8.94 during the  

extended period being sum of

Rs.14, 454,581/-

Claim No.5: Payment of 18% interest on  

Claim of contractor claim  

         No.3 and 4 on the (sic and)  

from 1.11.94 till the (sic)date.”

The arbitrator appointed vide order dated July 1, 1999 passed by the  

Court took up the proceedings on August 3, 1999 and made and published  

his award on September 9, 2000. The award held the respondent entitled to  

9

10

receive from the appellant the sum of Rs. 32, 71,774=00 along with interest  

on that amount @ 18% per annum from the date of the award till the date of  

payment.

    The appellant challenged the award by filing an application under section  

34 of the Act before the High Court on January 2, 2001.  As noted above, a  

learned Single Judge of the High Court substantially upheld the appellant’s  

challenge and set aside the award on items 1 and 3, upholding it only insofar  

as the respondent’s claim under item 4 was concerned. Against the judgment  

and order passed by the learned Singe Judge the respondent preferred an  

appeal before the Division Bench of the High Court. Here it is significant to  

note that the appellant did not prefer any appeal against the judgment of the  

Single Judge insofar as it upheld the arbitrator’s award on item no.4.  Thus  

before the Division Bench of the High Court there was no challenge to the  

arbitrator’s award in regard to the respondent’s claim for enhanced payment  

from January 1, 1993 to August 31, 1994, that is to say, for the period after  

the parties had agreed on the cancellation of the agreement.

The Division Bench of the High Court after an elaborate consideration  

of the matter and after referring to a host of decisions of this Court and the  

Calcutta High Court allowed the appeal, set aside the judgment and order  

1 0

11

passed by the learned Single Judge and restored the arbitrator’s award fully  

on all the three items.

Mr.  S.  Wasim  Qadri,  learned  counsel  appearing  on  behalf  of  the  

appellant,  submitted  that  in  the  absence  of  any  escalation  clause  in  the  

agreement  the  respondent’s  claim for  enhanced  payments  for  the  period  

August 3, 1991 to December 31, 1992 during which the agreement was in  

force was quite unfounded and both the arbitrator and the Division Bench of  

the  High Court  were  in  error  in  granting  the  claim for  that  period.  The  

submission made by Mr.  Qadri  is  fully answered by the decision of  this  

Court in Tarapore & Co. vs. State of M.P., (1994) 3 SCC 521, (noticed both  

by the arbitrator and the Division Bench of the High Court).  In paragraph 27  

of the judgment this Court observed as follows:      

“27.  But then, the terms at hand did require the  appellant  (who is  the  contractor)  not  to pay less  than  fair  wages  as  would  appear  from what  has  been stated in Para 2.10 and Para 1 of Annexure-B.  The Explanation to latter Para states that where fair  wages have not been notified these wages would  be  the  one  “prescribed  by  the  PWD  (Irrigation  Department) for the division in which the work is  done”.   Now these  wages  were  being  increased  from  time  to  time  as  would  appear  from  the  decisions of the wage committee referred to above;  and  if  the  appellant  was  being  required  to  pay  wages as per these decisions, we do read a meeting  of mind insofar as the claim of escalated payment  on account of increase of fair wages is concerned.  

1 1

12

It has to be assumed that when the appellant was  required to pay fair wages at increased rates, the  authorities  did visualize  that  the appellant  would  not do so by cutting down its profit. By asking the  appellant to give tender by taking into account the  fair wages notified at the time of inviting tenders,  the  authorities  did  give  an  impression  that  fair  wages  to  be  paid  would  be  the  one  then  notified/prescribed, a 1a the explanation to para 1.  In  such  a  situation,  if  rates  of  fair  wages  were  raised  afterwards,  the  tendered  sum  cannot  be  taken  to  be  agreed  amount  for  completing  the  contract,  in  the  face  of  the  directions  of  the  authorities requiring the appellant to pay wages at  rates higher than those prescribed or notified at the  time of inviting tenders.  On this fact situation, we  hold that  the  State  had by  necessary  implication  agreed to reimburse this increased payment.”

In  a  more  recent  decision  in  Food Corporation  of  India vs.  M/s.  A.  M.  

Ahmed & Co. & Anr., AIR 2007 SC 829, the Court reiterated the same view  

and in paragraph 32 of the judgment observed as follows:

“Escalation,  in  our  view,  is  normal  and  routine  incident  arising  out  of  gap  of  time  in  this  inflationary age in performing any contract of any  type.   In  this  case,  the  arbitrator  has  found that  there  was  escalation  by  way  of  statutory  wage  revision and, therefore, he came to the conclusion  that it was reasonable to allow escalation under the  claim.  Once it was found that the arbitrator had  jurisdiction  to  find  that  there  was  delay  in  execution of the contract due to the conduct of the  FCI,  the  Corporation  was  liable  for  the  consequences  of  the  delay,  namely,  increase  in  statutory wages.  Therefore, the arbitrator, in our  opinion, had jurisdiction to go into this question.  

1 2

13

He has gone into that question and has awarded as  he did.  The Arbitrator by awarding wage revision  has not mis-conducted himself.   The award was,  therefore, made rule of the High Court, rightly so  in our opinion.”      

    Mr. Qadri next questioned the grant of interest on the amounts arrived at by  

allowing the respondent’s claim for higher rates for the work done by it.  

Learned counsel submitted that clause 31 of the agreement expressly barred  

the claim of any interest by the contractor and hence, the award was clearly  

unsustainable insofar as the grant of interest was concerned.

The arbitrator gave to the respondent pre-reference, pendente lite and  

post-award interest on both its claims under items 3 & 4 as would be evident  

from the following passages from the award:  

“However, I am allowing interest to the claimant at  the  rate  of  16%  per  annum  on  and  from  1st  November, 1994 till 9th September, 2000 the date  of  award  amounting  to  Rs.15,  85,359.85  on  the  following basis.

Interest calculated from 1.11.94 to 9.9.2000 as per  demand notice dated 19th September, 1994 till the  date of award on Rs.16, 85,234.14 being the total  amount of claim item Nos.3 and 4.”

**** **** ****

Therefore,  I,  hereby award to  the  claimant  (1)  a  sum of Rs.6,05,777.34 for the claim item No.3 (ii)  a sum of Rs.10,79,456.80 for the claim Item No.4  

1 3

14

and (iii) a sum of Rs.15,86,539.85 towards interest  on Item No.3 and 4 for the claim Item No.5.  The  aggregate sum of Rs.32, 71,773.99 (Rupees Thirty  two  lacs  seventy  one  thousand  seven  hundred  seventy three and ninety nine paise only) rounded  to Rs.32, 71,774/-.  I further award an interest @  18% per annum on the aforesaid sum till the date  of payment.”

It  is  thus  to  be  seen  that  the  arbitrator  allowed  interest  on  the  amounts  

determined under Items Nos.3 and 4 both for the pre-reference period and  

pendente lite at the rate of 16% per annum.  He further allowed interest on  

the consolidated amount for the post-award period at the rate of 18% per  

annum till the date of payment.

The question of interest for the pre-reference period stands settled by  

the Constitution Bench decision in  Executive Engineer, Dhenkanal Minor  

Irrigation Division, Orissa & Ors. Vs. N. C. Budharaj, 2001 (2) SCC 721.  

The majority judgment (3:2) in that case held in paragraph 26 as follows:

“For all the reasons stated above, we answer the  reference by holding that the arbitrator appointed  with or without the intervention of the court, has  jurisdiction to award interest,  on the sums found  due and payable,  for the pre-reference period,  in  the  absence  of  any  specific  stipulation  or  prohibition in the contract to claim or grant any  such interest.  The decision in  Jena case taking a  contra view does not lay down the correct position  and stands overruled, prospectively, which means  that  this  decision  shall  not  entitle  any  party  nor  shall it employer any court to reopen proceedings  

1 4

15

which have already become final, and apply only  to any pending proceedings.  No costs.”                                                       (emphasis added)

The legal position in regard to interest  for the different periods has been  

summed  up,  with  reference  to  the  earlier  decisions,  in  the  decision  in  

Bhagawati Oxygen Ltd. Vs.  Hindustan Copper Ltd., 2005 (6) SCC 462. In  

paragraphs 38, 39 and 40 of the judgment it was observed as follows:

                      

“38. So far as interest for pre-reference period is  concerned, in view of the conflicting decisions of  this  Court,  the  matter  was  referred  to  a  larger  Bench  in  Executive  Engineer,  Dhenkanal  Minor  Irrigation  Division vs.  N.C.  Budharaj, 2001  (2)  SCC 721.   The Court, by majority, held that an  arbitrator  has  power  to  grant  interest  for  pre- reference period provided there is no prohibition in  the arbitration agreement excluding his jurisdiction  to  grant  interest.   The  forum  of  arbitration  is  created by the consent of parties and is a substitute  for  conventional  civil  court.   It  is,  therefore,  of  unavoidable necessity that the parties be deemed to  have  agreed  by  implication  that  the  arbitrator  would have power to award interest  in the same  way and same manner as a court.”     “39. Regarding interest pendent lite also, there was  cleavage of opinion.  The question was, therefore,  referred  to  a  larger  Bench  in  Secy.,  Irrigation  Deptt.,  Govt.  of  Orissa  vs.  G.  C.  Roy,  1992 (1)  SCC 508.  The Court considered several cases and  laid  down  the  following  principles:  (pp.532-33,  para 43)           

1 5

16

43.  The  question  still  remains  whether  arbitrator has the power to award the interest  pendente  lite,  and if  so  on what  principle.  We must reiterate that we are dealing with  the situation where the agreement does not  provide for grant of such interest nor does it  prohibit such grant.  In other words, we are  dealing with a case where the agreement is  silent  as  to  award  of  interest.  On  a  conspectus of aforementioned decisions, the  following principles emerge:

(i) a person deprived of the use of money  to  which  he  is  legitimately  entitled  has a right to be compensated for the  deprivation,  call  it  by  any  name.  It  may be called interest,  compensation  or damages.  This basic consideration  is as valid for the period the dispute is  pending before the arbitrator  as  it  is  for  the  period  prior  to  the  arbitrator  entering  upon  the  reference.  This  is  the  principle  of  Section  34,  Civil  Procedure Code and there is no reason  or principle  to hold otherwise in the  case of arbitrator.

(ii) An arbitrator  is  an alternative forum  for  resolution  of  disputes  arising  between  the  parties.   If  so,  he  must  have  the  power  to  decide  all  the  disputes  or  differences  arising  between the parties.  If the arbitrator  has  no  power  to  award  interest  pendente  lite,  the  party  claiming  it  would have to approach the court for  that  purpose,  even  though  he  may  have  obtained  satisfaction  in  respect  of  other  claims  from  the  arbitrator.  

1 6

17

This  would  lead  to  multiplicity  of  proceedings.

(iii) An  arbitrator  is  the  creature  of  an  agreement.  It is open to the parties to  confer  upon  him  such  powers  and  prescribe  such  procedure  for  him to  follow,  as  they  think  fit,  so  long  as  they  are  not  opposed  to  law.  (The  proviso to Section 41 and Section 3 of  the  Arbitration  Act  illustrate  this  point).   All  the same,  the agreement  must be in conformity with law.  The  arbitrator must also act and make his  award in accordance with the general  law of the land and the agreement.

(iv) Over the years, the English and Indian  courts  have acted on the assumption  that  where  the  agreement  does  not  prohibit  and a party to the reference  makes  a  claim  for  interest,  the  arbitrator  must  have  the  power  to  award  interest  pendente  lite.  Thawardas  has  not  been followed in  the later decisions of this Court. It has  been  explained  and distinguished on  the basis that in that case there was no  claim for interest but only a claim for  unliquidated  damages.  It  has  been  said  repeatedly  that  observations  in  the said judgment were not intended  to  lay  down  any  such  absolute  or  universal  rule  as  they  appear  to  on  first  impression.  Until  Jena  case  almost  all  the  courts  in  the  country  had upheld the power of the arbitrator  to  award  interest  pendente  lite.  Continuity  and  certainty  is  a  highly  desirable feature of law.

1 7

18

(v) Interest pendente lite is not a matter of  substantive  law,  like  interest  for  the  period  anterior  to  reference  (pre- reference period). For doing complete  justice  between  the  parties,  such  power has always been inferred.”

“40. As to post-award interest, the point is covered  by  the  decision  of  this  Court  in  Hindustan  Construction Co. Ltd. vs. State of J & K , 1992 (4)  SCC 217.  It  was held there that an arbitrator is  competent to award interest for the period from the  date of the award to the date of decree or date of  realization, whichever is earlier.”

In the case in hand, the respondent’s claim was in regard to two periods; one  

from  August  3,  1991  to  December  31,  1992  when  the  agreement  was  

subsisting  and  the  parties  were  bound  by  its  terms,  and  the  other  from  

January 1, 1993 to August 31, 1994 when the agreement was admittedly  

terminated and the respondent was carrying on the work on the request of  

the appellant. In our view the fact that the first period was covered by the  

agreement while the second fell beyond it is significant and on that score the  

two periods must receive different treatments.   

Clause 31 of the agreement provided as follows:

“31. No interest or damage for delay in payment  –  No interest  or  damage  shall  be  paid  to  the  Contractor for delay in payment of the bill or any  other amount due to the contractor for any reason  whatsoever.   The  Railway  Administration  will,  however,  make  every  endeavour  for  payment  of  

1 8

19

the  bills  or  other  amount  due  to  the  contractor  within a reasonable time.”                                                      (emphasis added)

The Division Bench of the High Court took the view that Clause 31 of the  

agreement operated as a bar only between the parties but it would not affect  

the authority of the arbitrator to grant interest for the pre reference period  

and  pendente  lite.  In  this  connection  the  High Court  has  referred  to  the  

decisions of this Court in Executive Engineer, Dhenkanal Minor Irrigation  

Division, Orissa (supra), Executive Engineer (Irrigation) vs. Abhaduta Jena,  

(1988) 1 SCC 418 (which was overruled by Executive Engineer, Dhenkanal)  

and Secretary, Irrigation Department, Govt. of Orissa vs. G.C. Roy, (1992) 1  

SCC 508, (which was referred to in Executive Engineer, Dhenkanal). But in  

Executive Engineer, Dhenkanal it is not even remotely said that a clause in  

the agreement like clause 31 (quoted above) would only act as a bar between  

the  parties  to  the  agreement  and  would  not  restrict  the  powers  of  the  

arbitrator to allow interest for pre-reference period and  pendente lite. The  

High Court has then relied upon another decision of this court in The Board  

of Trustees for the Port of Calcutta vs. Engineers-De-Space-Age, AIR 1996  

SC 2853. The High Court has observed that in this case a similar clause in  

the agreement was held not restrictive of the arbitrator’s powers to allow  

interest  pendente  lite and  for  pre  reference  period.  We  have  closely  

1 9

20

examined  the  decision  in  Engineers-De-Space-Age and  we  find  that  the  

relevant  clause  in  the  agreement  in  that  case  was  completely  differently  

worded and the view taken by the High Court cannot be supported on the  

basis  of  that  decision.  In  Engineers-De-Space-Age the  court  was  dealing  

with a case in regard to award of interest for the post-reference period and  

clause 13(g), the relevant clause in the agreement, was as follows:

“No claim for interest  will  be entertained by the  Commissioners  with  respect  to  any  money  or  balance which may be in their hands owing to any  dispute between  themselves and the Contractor or  with  respect  to  any  delay  on  the  part  of  the  Commissioners in making interim or final payment  or otherwise.”

In that  context  this court  held that  clause 13(g) of the agreement merely  

prohibited the Commissioners from entertaining any claim for interest and  

did not affect the arbitrator’s powers to award interest.  

In the case in hand clause 31 of the agreement is materially different.  

It bars payment of any interest or damage to the contractor for any reason  

whatsoever.  We are, therefore, clearly of the view that no pre-reference or  

pendente lite interest was payable to the respondent on the amount under  

Item No.3 and the arbitrator’s award allowing pre-reference and  pendente  

lite interest on that amount was plainly in breach of the express term of the  

agreement.  The  order  of  the  High  Court  insofar  as  pre-reference  and  

2 0

21

pendente  lite interest  on  the  amount  under  Item  No.3  is  concerned  is,  

therefore, unsustainable.

The  position  with  regard  to  the  claim  under  Item  No.4  is  quite  

different. That relates to the period after the termination of the agreement  

and hence, the bar of clause 31 would not apply to it in the same way as it  

would apply to Item No.3. We, therefore, find no infirmity in grant of pre-

reference and pendente lite interest on the amount under Item No.4.   

In light of the discussions made above, the respondent shall be entitled  

to interest  only on the sum of Rs.10,  79,456=80, the amount determined  

under Item No.4, at the rate of 16% per annum for the period November 1,  

1994 to  September  9,  2000.  The  final  amount  under  the  award  shall  be  

accordingly worked out. The consolidated amount of the award after being  

re-calculated shall carry, as provided in the award, interest at the rate of 18%  

from the date  of  the  award till  the  date  of  payment.  In  working out  the  

amount of interest  for the post-award period, the period(s)  for which the  

operation of the award was stayed by the court would be excluded.   

In  the  result  the  appeal  is  allowed  to  the  limited  extent  indicated  

above. There shall be no order as to costs.     

………………………………J.

2 1

22

[Tarun Chatterjee]

……………………………..J. [Aftab Alam]

New Delhi, July 16, 2009.

2 2