UNION OF INDIA Vs CHANDALAVADA GOPALAKRISHNA MURTHY .
Case number: C.A. No.-000926-000927 / 2002
Diary number: 14290 / 2001
Advocates: ANIL KATIYAR Vs
ANJANI AIYAGARI
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs. 926-927 OF 2002
UNION OF INDIA Appellant (s)
VERSUS
CHANDALAVADA GOPALAKRISHNA MURTHY & ORS. Respondent(s)
O R D E R
These appeals are directed against the judgment and order dated 8th May,
2001 passed by the Division Bench of the Andhra Pradesh High Court.
We have heard the parties at length.
In view of the order that we propose to pass, it is not necessary to recite the
entire facts leading to the filing of the present appeal. Suffice it to say that a contract
was entered into between the appellant and the respondent regarding the construction
of laboratory, Officers' room and class room at Indian Railway Institute,
Secunderabad. Agreement was entered into on 31.01.1981. According to the
agreement, the contract was to be completed within a period of 9 months i.e. upto 27th
October, 1981. It is stated that
-2-
on request made by the contractor/respondent extension of time was granted under
clause 17(3) of the general conditions of the contract. Ultimately, the contract was
completed on 31st August, 1983. A dispute arose between the parties and the the
respondent made various claims under 7 heads and demanded for arbitration. The
arbitrator granted Award under all 7 heads. The Award was filed before the City
Civil Court. The City Civil Court made the award a rule of the court in respect of
claim No.2 to 6 but set aside the Award regarding item No. 1 and 7. Aggrieved
thereby, the respondent filed an appeal before the Division Bench of the High Court
and by the impugned order the Division Bench maintained the order of the Civil
Court with regard to item No.7. However, the Division Bench allowed the claim
under item No.1. Hence, the present appeals.
The dispute now to be resolved is confined only to item No.1 of the claim. To
answer this question, we may refer to clause 17(3) of the contract. Clause 17(3) reads:
“Clause 17(3): In the event of any failure or delay by the Railway to hand over to the contractor possession of the lands necessary for the execution of the works or to give the necessary notice to commence the works or to provide the necessary drawings or instructions or any other delay caused by the -3-
Railway due to any cause, whatsoever, the said failure or delay shall in no way effect or vitiate the Contract or alter the character thereof or entitle the contractor to damages of compensation thereof but in any such case, the Railway may grant such extension of extensions of the completion date as may be considered reasonable.“
Clause 17(3) reads thus clearly shows that if there is delay by the Railways the
terms of the contract can be extended as has been done in the present case. However,
the contractor shall not be entitled to damages or compensation.
A similar question raised before this Court was considered by a three-Judge
Bench of this Court in Ch. Ramalinga Reddy Vs. Superintending Engg. & Anr. 1999
(9)SCC 610. This Court held in that case that if the contract is extended under the
terms of the contract, compensation cannot be awarded by the Arbitrator. The
aforesaid judgment has been followed in another decision of this Court in General
Manager (Northern Railway) & Anr. Vs. Sarvesh Chopra 2002(4)SCC 45.
Learned counsel for the respondent referred to the judgment rendered by this
Court in the case of K.R. Raveendranathan Vs. State of Kerala 1998(9) SCC 410.
The
-4-
said decision is not applicable in the facts of the present case. For the reasons
aforestated, the case in hand is squarely covered by two decisions of this Court. In the
result, the order of the High Court is not tenable in law and is accordingly set aside.
The appeals are allowed.
No costs.
.........................J (H.K. SEMA)
.........................J (MARKANDEY KATJU)
New Delhi; April 10, 2008.