28 October 1988
Supreme Court
Download

U.P. HOTELS ETC. Vs U.P. STATE ELECTRICITY BOARD

Bench: MUKHARJI,SABYASACHI (J)
Case number: Appeal Civil 756 of 1988


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 15  

PETITIONER: U.P. HOTELS ETC.

       Vs.

RESPONDENT: U.P. STATE ELECTRICITY BOARD

DATE OF JUDGMENT28/10/1988

BENCH: MUKHARJI, SABYASACHI (J) BENCH: MUKHARJI, SABYASACHI (J) RANGNATHAN, S.

CITATION:  1989 AIR  268            1988 SCR  Supl. (3) 670  1989 SCC  (1) 359        JT 1988 (4)   478  1988 SCALE  (2)1235

ACT:    Arbitration  Act,  1940:  Sections 14, 17,  30  and  33- Award- Setting aside of- Wrong proposition of law laid  down in award as basis of award.

HEADNOTE:     On taking over the Agra Electric Supply Co. in  December 1973,   the  respondent-  U.P.  State   Electricity   Board- intimated  to  the  appellant- U.P. Hotels-  that  the  Bulk Supply Agreement between the appellant and the Agra Electric Supply Co. would continue to be in force until such time the agreement  was  determined in accordance with  its  relevant provisions.   The  agreement  contained  terms   of   rates, discounts, minimum sum payable and increase in the rates and sums  payable once a year on account of increase in cost  of production and distribution of electrical energy (clause  9) and also contained an arbitration clause (clause 18).     In November 1976, the appellant received a communication from the respondent informing that the uniform tariff  rates issued under section 49 of the Electricity Supply Act,  1949 would  be  applicable to them. The Board also  withdrew  the contractual discount and rebates. While sub-sections (1) and (2)  of section 49, stipulate a uniform tariff for  electric supply,   sub-section  (3)  authorises  the  Board  to   fix different tariffs for the supply of electricity.     The   appellant   protested  against   this   unilateral increases and withdrawal, but without success. The appellant then  informed  the  respondent that it  was  referring  the disputes  for  decision by the arbitrator  and  appointed  a retired  High Court Judge as its arbitrator. The  respondent in  turn  appointed another retired High Court  Judge  as  a joint arbitrator. The joint arbitrators appointed Justice V. Bhargava,  a  retired  Judge of the Supreme  Court,  as  the Umpire.  The  arbitrators  having  failed,  the  proceedings started before the Umpire.     The Umpire gave his award in June 1983 and held that the Board  having accepted the agreement, it became  binding  on the  Board  and once the agreement was  binding,  its  terms under  sub-section (3) of section 49 could not be varied  by                                                   PG NO 670                                                   PG NO 671

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 15  

fixation of uniform tariff under sub-sections (1) and (2). The  Umpire  further held that the present  case  was  fully covered  by  the  decision of the Supreme  Court  in  Indian Aluminium  Co. wherein it was held that where a  stipulation in  a  contract was entered into by a  public  authority  in exercise  of  a  statutory  power  then,  even  though  such stipulation   fettered  subsequent  exercise  of  the   same statutory power, it would be valid and the exercise of  such statutory  power would pro tanto stand restricted.  In  that view of the matter the Umpire held that in terms of clause 9 the increase in unit rate was permissible and the fuel  cost variation  charges  which  were  variable  every  month  was contrary to clause 9 as increase was permitted only once  in a  year  of  accounts, and further that  the  appellant  was entitled  to discount of 50% of the charges for  electricity and also to discount for prompt payment of bills.     Objections were filed by the respondent before the  IInd Additional  District Judge during the proceedings  initiated for  making  the  award  the Rule of  the  Court.  The  IInd Additional  Distt. Judge set aside the award on  the  ground that  the reference made to arbitration was  unilateral.  In appeal,  the  High Court, while holding  against  the  above finding of the IInd Addl. Judge, set aside the award on  the ground  that the Indian Aluminium Co. case was  inapplicable to the present case, and the mistake committed by the Umpire in this regard was error of law apparent on the face of  the award. The High Court held that even if the stipulation   as to  the tariff structure in the agreement be taken  to  have been  Continued in existence in view of sub-section  (3)  of section  49 of the Act, the same was not  unrestricted,  and that  the stipulation was expressly made subject to  certain reservations as would be clear from the opening sentence  of clause  9 of the agreement the main clause was  "subject  to the  provisions hereinafter contained". It was further  held that  in drawing distinction between ‘rates’ and  ‘discount’ and  upholding  the right of the Board to  tamper  with  the former and negating similar right in respect of the  latter, the Umpire had committed an error.     Before  this  Court it was contended on  behalf  of  the appellant  that a specific question of law being a  question of  construction had been referred to the Umpire and  hence, his decision, right or wrong, had to be accepted.     On behalf of the respondent it was contended that  there was  no specific question of law referred to the Umpire  but it was a general reference in which a question of law arose, and  that  it  was a question in  the  proceedings  and  the question of law, as such, did not arise.                                                   PG NO. 672     Allowing the appeal, it was,     HELD:  (1)  Even  assuming that there was  an  error  of construction  of  the agreement or even that  there  was  an error  of a law in arriving at a conclusion, such  an  error was not an error which was amenable to correction even in  a reasoned award under the law. [683B]     (2)  Where  the question referred for arbitration  is  a question  of  construction, which is, generally  speaking  a question  of law, the arbitrator’s decision can not  be  set aside  only  because the court would itself have come  to  a different  conclusion, but if it appears on the face of  the award  that the arbitrator has proceeded illegally, as,  for instance, by deciding on evidence which was not  admissible, or  on  principles of construction which the  law  does  not countenance,  there is error in law which may be ground  for setting aside the award. [683G-H; 684A]     (3)  In  order to set aside an award, there  must  be  a

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 15  

wrong proposition of law laid down in the award as the basis of the award. [684D]     (4)  In  the  instant  case, a  question  of  law  arose certainly  during  the  course of the  proceedings.  Such  a question has been decided by the Umpire on a view which is a possible  one  to  take.  Even  if  there  was  no  specific reference of a question referred to the Umpire, there was  a question of law involved. Even on the assumption that such a view is not right, the award is not amenable to interference or  correction  by  the  Courts  of  law  as  there  was  no proposition  of law which could be said to be the  basis  of the award of the Umpire, and which was erroneous. [689B-Cl     (5) The Umpire in his award stated that the decision  of this Court covered and supported the claim of the  claimant. In  the present case the only difference was that there  was only  an  agreement  which was held by the  Umpire  to  have become  operative.  Once that agreement was binding  on  the Board,  its terms could not be vaired from the uniform  rate under sub-sections (1) and (2) of section 49. The Umpire was right.  The  Umpire committed no error in arriving  at  such conclusion. Further-more, such a conclusion was certainly  a possible view of the interpretation of the decision of  this Court in Indian Aluminium Co.’s case, if not the only  view. [688G-H; 689A]     Indian  Aluminium Co. Ltd. v. Kerala Electricity  Board, [1976]  1  SCR  70; Coimbatore Distt. P.T.  Sangam  v.  Bala                                                   PG NO 673 Subramania  Foundry,  AIR (1987) SC  2045;  Delhi  Municipal corpn.  v. M/s Jagan Nath Ashok Kumar, AIR (1987)  SC  2316; M/s. Hindustan Tea Co. v. M/s. K. Sashikant & Co., AIR  1987 SC 81; Kanpur Nagar Mahapalika v. M/s. Narain Das Haribansh, [1970]  2  SCR  28; Champsey Bhara & Co.  v.  Jivraj  Balloo Spinning & Weaving Co. Ltd., [1923] AC 480; Dr. S.B. Dutt v. University of Delhi, [1959] SCR 1236; M/s. Kapoor  Nilokheri Co-op.  Dairy Farm Society Ltd. v. Union of lndia, [1973]  1 SCC  708;  Tarapore & Co. v. Cochin  Shipyard  Ltd.  Cochin, [1984] 3 SCR 118; Hitchins & Anr. v. British Coal  Refining, [1936] 2 A.E.R. Reprint 191; Pioneer Shipping Ltd. & Ors. v. ETP Tioxide Ltd., [1981] 2 AER 1030, referred to.

JUDGMENT:     CIVIL  APPELLATE JURISDICTION: Civil Appeal No.  756  of 1988.     From the Judgment and Order dated 21.7.1987 of the  High Court of Allahabad in F.A.F.O. No. 106 of 1984.     F.S. Nariman, M.L. Verma, Jeet Mahajan and Ranjit  Kumar for the Appellats.     B.  Sen, Gopal Subramanium and Mrs. Shobha  Dikshit  for the Respondent.     The Judgment of the Court was delivered by     SABYASACHI MUKHARJI, J. This appeal by special leave  is from  the judgment and order of he High Court of  Allahabad, dated  21st  July, 1987. The High Court has  set  aside  the award  of  the Umpire. To appreciate the  decision  and  the contentions urged, a few facts are necessary.     On  or about 20th October, 1962 there was a Bulk  Supply Agreement entered into between Agra Electric Supply Co. Ltd. and the appellant herein, for supply of electrical energy to the  latter’s hotel, inter alia, containing terms of  rates, discounts, minimum sum payable and increase in the rates and sums  payable once a year on account of increase in cost  of production  and distribution of electrical energy. Clause  9 of the said agreement contained terms of the rate of  supply

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 15  

and   the  contingencies  in  which  such  rates  could   be increased. The said Clause provided as follows:                                                   PG NO. 674     "The   consumer   shall,  subject  to   the   provisions hereinafter contained, pay to the Company for all electrical energy  supplied  and  registered  or  estimated  as  herein provided  at  the rate of Rs.0.20 (Rupees zero  decimal  two zero)  per  unit per month for all energy  so  supplied  and registered and/or estimated in the case of a defective meter installation  in  accordance with the proviso  to  clause  6 thereof.  The charge for all energy shall be subject to  the scale  of special discounts in accordance with the  schedule annexed thereto.     Provided that, (without regard to the quantity of units supplied)  if  the payment made or to be made  for  any  one English  Calendar year ending 31st March in respect  of  the electricity  consumed shall fall short of a minimum  sum  of Rs. 38640 (Rs. Thirty eight thousand six hundred and  forty) the  consumer  shall nevertheless pay to  the  Company  such amount  in addition to the payments already made in  respect of the electricity consumed for such Calendar year as  will, being  the  total payment made in this respect to  the  said minimum  of Rs.38640 (Rs. Thirty eight thousand six  hundred and forty).     Provided  Further  that, in the event of the  first  and last  years  of this Agreement not being  complete  calendar year  as  aforesaid the Company shall make  a  proportionate reduction on the aforesaid annual Maximum Demand and Minimum charges  in respect of the period for which the  said  first and  last  year  as the case may be shall  be  less  than  a complete calendar year.     Provided   also  that.  if  and  whenever   during   the subsistence of this Agreement the Company is satisfied  that there  has  been an increase in the cost of  production  and distribution  of  electrical energy it shall be  at  liberty (but not more than once in any year of accounts) to increase the  rates  and  sums  payable by  the  Consumer  under  the foregoing provision of this present clause 9 by such  amount as it shall in its sole and absolute discretion decide."     There was a clause providing for arbitration i.e. clause 18 which read as follows:     "If  any question or difference whatsoever  shall  arise between   the   parties  to  these  presents   as   to   the                                                   PG NO 675 interpretation  or effect of any provision or clause  herein contained  or  the construction thereof or as to  any  other matter  in  anyway connected with or arising  out  of  these presents  or the operation thereof or the rights, duties  or liabilities  of either party in connection  therewith,  when unless   the  means  for  deciding  any  such  question   or difference  is provided for by the Indian  Electricity  Act, 1910  or the Electricity (Supply) Act, 1948 as the case  may be, or by the rules made respectively under the said Acts or by  a  specific provision of this Agreement, in  every  such case  the  matter  in difference shall be  referred  to  the Arbitration of two Arbitrators, one to be appointed by  each party  hereto,  and  an  Umpire  to  be  appointed  by   the Arbitrators  before  entering  upon the  reference  and  the decision or award of the said Arbitrators or Umpire shall be final  and binding on the parties hereto and  any  reference made under this clause shall be deemed to be a submission to arbitration under the Indian Arbitration Act, 1940 (Act X of 1940) or any statutory modification or re-enactment  thereof for the time being in force.     The  Arbitrators  or  the Umpire  giving  their  or  his

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 15  

decisions  shall also decide by which party the cost of  the Arbitration  and award shall be paid and if by both  parties in what proportion."     On or from 26th September, 1973 the Agra Electric Supply Co. Ltd. increased per unit rate of electricity from 0.20  P to  21.5  P  in terms of clause 9  of  the  said  agreement. Thereafter,  the  bills were sent @ 21.5 P per  unit,  after giving  discounts  and rebates as per the agreement.  On  or about  17/18th  December, 1973, the respondent  herein  took over the undertaking of the Agra Electric Supply Co. Ltd. On or  about  16th January, 1974, the respondent  informed  the appellant  by a written communication that  consequent  upon the  expiry of licence granted to Agra Electric  Supply  Co. Ltd.  to generate and supply electricity the respondent  had taken it over and would supply electric energy to the  hotel and that the Bulk Supply Agreement with Agra Electric Supply Co.  Ltd. will continue to be in force with  the  respondent until  such time the agreement is determined  in  accordance with its relevant provisions. All bills received  subsequent to  the  take over were billed at the agreed  rate  allowing discounts and rebates.     On or about 23rd November, 1974, the appellant  received a  communication from the respondent informing that  uniform                                                   PG NO 676 tariff  rates  issued under section 49  of  the  Electricity Supply Act, 1949 will be applicable to the electrical energy supplied  to the hotel w.e.f. 12.10.1974. Section 49 of  the Electricity  (Supply)  Act, 1948  (hereinafter  called  ‘the Act’), is to the following effect:     "49. Provision for the sale of electricity by the  Board to  persons  other  than  licensees.  -(1)  Subject  to  the provisions  of this Act and of regulations, if any, made  in this behalf, the Board may supply electricity to any  person not  being a licensee upon such terms and conditions as  the Board  thinks  fit and may for the purposes of  such  supply frame uniform tariff.     (2) In fixing the uniform tariffs, the Board shall  have regard to all or any of the following factors, namely:     (a)  the nature of supply and the purposes for which  it is required:     (b)  the  co-ordinated  development of  the  supply  and distribution  of  electricity within the State in  the  most efficient  and economical manner, with particular  reference to  such development in areas not for the time being  served or adequately served by the licensee:     (c)  the simplification and standardisation  of  methods and rates of charge for such supplies;     (d)   the  extension  and  cheapening  of  supplies   of electricity to sparsely developed areas.     (3) Nothing in the foregoing provisions of this  section shall derogate from the power of the Board, if it  considers it  necessary or expedient to fix different tariffs for  the supply  of electricity to any person not being  a  licensee, having regard to the geographical position or any area,  the nature  of  the  supply, and purpose  for  which  supply  is required and any other relevant factors.     (4)  In fixing the tariff and terms and  conditions  for the  supply of electricity, the Board shall not  show  undue preference to any person."                                                   PG NO. 677     After the said date the bills were sent at the  enhanced rate of 0.30 P per unit, adding fuel cost variation  charges and  without  allowing any discount or rebate. On  or  about 28th  November,  1974,  the  appellant,  however,  protested against  the unilateral withdrawal of  contractual  discount

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 15  

and  rebates  and  enhancement in the  rates  and  drew  the attention  of the respondent to the existing and  subsisting bulk supply agreement, but the respondent took no action. On or  about  31st August, 1976, a Circular was issued  by  the Chief Engineer of the respondent advising all  Engineers-in- charge  of  the undertakings to bill  the  consumers  having special  agreements  with  the  ex-licensees  as  per  those agreements   and  steps  be  taken  to  terminate  the   old agreements with new agreements providing for application  of tariff.     On  7th  October, 1977, vide written  communication  the appellant informed the respondent that upon latter’s failure to resolve the disputes and differences arising between them consequent  to  the  illegal  increase  in  the  rates   and discontinuation of discounts and rebates w.e.f.  12.10.1974, the appellant was referring the disputes for decision by the arbitrator and appointed Justice Manchanda, a retired  Judge of  the  Allahabad  High Court, as the  arbitrator  and  the respondent appointed Justice Nigam, another retired Judge of the  same  High Court, as its arbitrator. On  or  about  8th April,  1977,  the joint arbitrators  appointed  Justice  V. Bhargava, a retired Judge of this Court, as an Umpire.     Between 3rd November, 1979 and 4th March, 1980,  several sittings  were held before the arbitrators but  the  parties were  unable  to  agree  and  upon  their  disagreement  the disputes  were referred to the learned Umpire for  decision. From 4th March, 1980 onwards, proceedings started before the Umpire  and  there  was a plea for de novo  hearing  of  the proceedings  before  the  Umpire,  by  the  respondent.  The learned  Umpire started de novo proceedings taking  evidence of the parties. On 21st March, 1980, the respondent filed an application,  being Case No. 59 of 1980 under section 33  of the  Arbitration  Act,  1940  before  the  District   Judge, Lucknow,  denying the existence of the agreement dated  20th October, 1962. The respondent also denied the acceptance and adoption of the agreement consequent upon the take over  and sought  a  declaration from the Court that  the  arbitration agreement did not exist. The Vth Addl. District Judge by his order  dated  27.5.1983  held that the  agreement  was  duly executed,  accepted  and adopted by the respondent  and  was binding  on  it and that the  arbitration  proceedings  were pursuant  to  the  arbitration  clause  and,  as  such,  the application  under  section 33 of the Arbitration  Act,  was rejected.                                                   PG NO. 678     On  1st  June, 1983, the award was made by  the  learned Umpire holding that in terms of clause 9 the increase in the unit  rate  was  permissible and  the  fuel  cost  variation charges  which  were variable every month  was  contrary  to clause  9 as increase was permitted only once in a  year  of accounts,  and further held that the appellant was  entitled to  discount of 50% on the charges for electricity; and  was also entitled to 0.03 paise per rupee for prompt payment  of bills. The learned Umpire in his award set out the facts and therein recited these as follows:     "The main terms of the agreement were that in respect of the bulk electric supply to the petitioner the Hotel was  to be  charged at the rate of twenty paise per unit per  month. There  was also a clause for granting a special discount  to the  petitioner to the extent of 50% and in addition a  cash discount of three paise per whole rupee was to be allowed to the petitioner in case the petitioner paid the bills of  the Company  within  the stipulated period. The  bills  for  the electric energy supplied by the Supply Company continued  on these  contractual rates till October 1974, even  after  the

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 15  

Supply  Company  was  acquired  by  the  opposite  party  in December 1973, and the bills were accordingly paid.     However, in October 1974, the opposite party under s. 49 of the Electricity (Supply) Act, 1948 (hereinafter  referred to as the Act) unilaterally and according to the  petitioner illegally and arbitrarily purported to replace the  original terms  in the agreement and revised the charges with  effect from 12th October, 1974. The Board, under this notification, increased  the rate of electricity supplied to 30 paise  per unit and further refused to grant the discount to which  the petitioner  was entitled under the agreement as well as  the cash  discount of three paise per rupee. The opposite  party further   levied   a  fuel  cost  adjustment   charges   and subsequently  the rate was raised to 31 paise per unit  with effect from June 1976."     Thereafter,  the learned Umpire set out the  history  of the  negotiations  between  the  parties  resulting  in  the agreement  dated  20.10.1962. After referring  to  the  bulk supply  agreement the learned arbitrator set out  the  terms upon  which supply was made to the appellant. The  appellant was to make an initial payment of Rs.35,326 towards  service connection for the purpose of supply, though irrespective of                                                   PG NO 679 the payment the service connection was to continue to be the property  of the Supply Company. The Supply Company  was  to make  provision in the appellant’s monthly bill  granting  a rebate  of  Rs.  147.20 for each month  that  the  agreement remained inforce upto a maximum of 20 years. Under para 9 of the  agreement the appellant was to pay the Company for  all electric  energy supplied, registered, and estimated at  the rate  of 20 paise p.m. The charges for energy consumed  were subject  to special discount according to the scale  in  the schedule which permitted a maximum discount of 50% in case a minimum  of  41,000 units were consumed in each  month.  The consumption  as  shown  by the record was  never  less  than 41,000  units p.m. In addition, there was a provision  under clause  (ii) of the agreement for cash discount of  3  paise per  whole  rupee  in  case  payment  was  made  within  the stipulated  period. Under the first proviso to para  9,  the appellant  had  to  pay  a  minimum  sum  of  Rs.38,640  for electricity  consumed  in  any English  calendar  year.  The provision  made was that in addition to the amount  paid  in accordance with the bills, the appellant was to make payment in  such  cases  so  as  to make  up  the  said  minimum  of Rs.38,640. The second proviso laid down that if and whenever during  the subsistence of the agreement the Supply  Company was  satisfied  that there was an increase in  the  cost  of production  and distribution of electric energy it shall  be at  liberty (but not more than once a year) to increase  the rates and sums payable by the consumer under the  provisions of clause 9 by such amount as the Company shall, in its sole and  absolute discretion, decide. Hence, it was held by  the Umpire on the oral and documentary evidence that the payment was made at the enhanced rate under protest.     Challenging the Award, several contentions were  raised, namely,  (i)  that there was no agreement in  existence  and that   neither  the  Umpire  nor  the  arbitrator  had   any jurisdiction to make the award. This contention was rejected and  no  argument was advanced before  us  challenging  this finding of the Umpire, (ii) that the appellant should  prove the  terms and conditions upon which the Supply Company  was supplying the electricity to the appellant. This the  Umpire held,  had  been duty proved and there was no  challenge  to either  of the findings of the Umpire. (iii) it was  thirdly contended  that the agreement even if in existence, was  not

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 15  

binding  upon the respondent. and that while admitting  that the   respondent  under  section  49  of  the  Act,   issued Notification  under  which  the tariff  was  revised  w.e.f. 12.10.1974, it was claimed that the opposite party had  not, in any way, failed to fulfil its obligations on the  alleged agreement  and that the opposite party was  fully  competent under  law  to fix a uniform tariff and also  to  levy  fuel                                                   PG NO 680 adjustment  charges.  This  is  the  main  and   substantial question involved in this matter.     It  was then contended that the respondent was  entitled even  under  the agreement and under its second  proviso  to clause  9  to revise the tariff and the  appellant  was  not entitled  to  any  relief. It was  further  urged  that  the payments  were  made  after coming  into  operation  of  the Electricity (Supply) Act, under protest. In respect of these contentions  the learned Umpire held that the plea was  that even  if the agreement was in existence, it was not  binding on  the  opposite  party and that  the  opposite  party  was competent under section 49 of the Electricity Supply Act, to fix  revised charges w.e.f. 12.10.1974 and had not  violated any terms of the agreement. The appellant had also relied on the alternative provisions of section 49(3) of the Act,  set out  hereinbefore.  The said sub-section (3)  provides  that nothing  contained in sub-sections (1) & (2) of  section  49 shall derogate from the power of the Board, if it happens to enter  into an agreement at different rates of  tariff  with any  person other than a licensee. It appears that when  the Supply Company was taken over on l7/18.12.1973, the resident Engineer  wrote a letter on 16.1.1974 in which  he  informed the appellant that the licence of M/s. Agra Electric  Supply Co. Ltd. having expired and the U.P. State Electricity Board having taken over the supply, it was to supply energy to the appellant  at the aforesaid date. Their  further  contention was  that the bulk supply agreement which the appellant  had with  M/s. Agra Electric Supply Co. Ltd., would continue  to be in force with the State Electricity Board until such time as  the  agreement  was determined in  accordance  with  the relevant  provisions thereof. The learned Umpire  held  that the letter clearly laid down that the U.P. Electricity Board had  accepted the agreement which was in  existence  between the  Supply  Company  and  the  appellant,  and  the  Umpire proceeded  on that basis. The learned Umpire further  stated as follows:     "The  Board thus having accepted the agreement with  the claimant,  it  became binding on the Board  and  under  sub- section  (3)  of s. 49 of the Electric  Supply  Act  nothing contained  in  sub-sections (1) & (2) of s. 49  of  the  Act could  have any bearing on the terms of the  agreement.  The result  was that the uniform tariff fixed by the Board  with effect from 12th October, 1974 did not apply to the claimant and the claimant had to be granted the various rebates  laid down in the agreement. The decision of the Supreme Court  in Indian  Aluminium  Co.  Ltd. v.  Kerala  Electricity  Board,                                                   PG NO 681 [1976]  1 SCR pa. 70 fully covers the case and supports  the claim of the claimant. In the case before the Supreme  Court an  agreement had been entered into by the State  Government and  it was held that under s. 60 of the Electricity  Supply Act, 1940 it became binding on the Kerala State  Electricity Board and further that that agreement was enforceable  under sub-section  (3)  of s 49 irrespective of  the  fixation  of uniform  tariff under sub-sections (I) and (2) of s. 49.  In the present case the only difference is that instead of  the agreement  being first binding between the consumer and  the

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 15  

State  Government,  the  agreement  became  binding  on  the Electricity  Board,  because it accepted the  agreement  and became a party to it by letter dated 16th January 1974  (Ex. R)."     The  aforesaid basis of the decision, it was  contended, was the error of law which vitiated the award. This question will  require further consideration later. It was held  that the decision in Indian Aluminium Co., (supra) fully  covered the dispute on this aspect in the instant case. The  learned Umpire further held as follows:     "Once  the agreement was binding on the Board its  terms under  sub-section  (3)  of s. 49 could  not  be  varied  by fixation of uniform tariff under sub-sections (1) and (2) of S.  49.  The opposite party in these circumstances  must  be held  to  have failed to fulfil its  obligations  under  the agreement".     On 1st July, 1983. an application was made under section 12  [2] of the Arbitration Act before the  learned  District Judge, Lucknow, for filing of the award and making the  same Rule  of the Court. Objections were filed by the  respondent against the said award. The learned kind Addl. Distt. Judge, Lucknow, held that the award was legal, valid and binding on the parties and the alleged grounds of  misconduct were  not maintainable.  The  award  was. however, set  aside  on  the ground   that   the  reference  made  to   arbitration   was unilateral. The appellant filed an appeal. The Lucknow Bench of the Allahahad High Court held against the finding of  the Ilnd Additional Distt. Judge Lucknow that the reference  was unilateral. but set-aside the award on the ground that there was  an error of law apparent on the face of it in  view  of the  agreement  dated  20.10.  1962 and  the  ratio  of  the decision of this Court in Indian Aluminium Co., (supra). The revision filed by the respondent against the judgment of the Vth  Addl.  Distt  Judge, Lucknow was  also  rejected.  This appeal  is from the aforesaid decision of the High Court  by special leave.                                                   PG NO 682     The  two learned Judges of the High Court gave  separate judgments.  The High Court was of the view that the  instant case  was  distinct  from the facts in the  case  of  Indian Aluminium  Co.,  (supra).  There it was held  that  where  a stipulation  in  a  contract is entered  into  by  a  public authority in exercise of a statutory power then, even though such  stipulation  fetters subsequent exercise of  the  same statutory power, it would be valid and the exercise of  such statutory power would pro tanto stand restricted. Mr Justice Loomba was of the view that in the instant case even if  the stipulation  as to the tariff structure in the agreement  by taken  to have been continued to be in existence in view  of sub-section  (3) of section 49 of the Act, the same was  not unrestricted. The stipulation was expressly made subject  to certain   reservations  as would be clear from  the  opening sentence  of clause 9 of the agreement, the main clause  was "subject to the provisions hereinafter contained".     Mr  Justice Loomba was of the view that the decision  of the  Indian Aluminium Co., (supra) case was inapplicable  to the  present   case.  According to the  learned  Judge,  the mistake committed by the Umpire was a manifest error. It was further  stated that it is well-settled proposition  of  law that  if  the reasons are stated on the basis of  which  the award  was made and such reasons are found to be  erroneous, the  errors  become apparent on the face of  the  award  and constitute  legal  misconduct  on the  part  of  the  Umpire vitiating  the  award. The other  learned Judge  Mr  Justice Mathur also held that there was error of law apparent on the

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 15  

face of the award of the Umpire. He was of the opinion  that the  expression  "sum  payable by  the  consumer  under  the foregoing provision of this present clause 9" was subject to the  discounts  mentioned in the subsequent clauses  of  the agreement.  In view of the discounts, the sum payable  under clause 9 was altered and the altered amount becomes the  sum payable  under  clause 9. According to  the  learned  Judge, since the amount determined after allowing discounts is also sum payable under clause 9, it followed that in exercise  of the  power conferred under the third proviso,  the  discount could only be tampered with in the same way the unit  charge could be tampered with. Beyond this it was not  permissible. In permitting this the Umpire committed an error in  drawing distinction between ’rates’ and ’discount’ and upholding the right  of the Board to tamper with the former  and  negating similar  right  in respect of the latter. According  to  the learned  Judge,  this  was  a  wrong  understanding  of  the decision  of  the Indian Aluminium’s case  (supra).  In  the aforesaid view of the matter, the learned Judge agreed  with the  other  learned  Judge  and  held  that  the  award  was vitiated.                                                   PG NO 683     It  appears  that  the main  question  that  arises  is: whether  the  decision of this Court in  Indian  Aluminium’s case (supra) was properly understood and appreciated by  the learned Umpire and whether he properly applied the agreement between the parties in the light of the aforesaid  decision. It  was  contended that the question was  whether  the  sums payable under clause 9 included discounts. On the  aforesaid basis  it was contended that there was an error of  law  and such  error  was  manifest on the face of  the  award.  Even assuming,  however, that there was an error of  construction of  the agreement or even that there was an error of law  in arriving  at  a conclusion, such an error is  not  an  error which  is  amenable to correction even in a  reasoned  award under the law. Reference may be made to the observations  of this  Court  in  Coimbatore  Distt.  P.T.  Sangam  v.   Bala Subramania   Foundry,  AlR  1987  SC  2045,  where  it   was reiterated  that an award can only be set aside if there  is an error on its face. Further, it is an error of law and not mistake  of  fact  committed  by  the  arbitrator  which  is justiciable  in the application before the Court. Where  the alleged mistakes or errors, if any, of which grievances were made were mistakes of facts if at all, and did not amount to error  of  law  apparent  on the face  of  the  record,  the objections  were not sustainable and the award could not  be set aside. See also the observations of this Court in  Delhi Municipal Corpn. v. M/S. Jagan Nath Ashok Kumar, AIR 1987 SC 2316, where this Court reiterated that reasonableness of the reasons given by an arbitrator in making his award cannot be challenged.  In  that case before this Court, there  was  no evidence  of violation of any principle of natural  justice, and  in  this  case  also  there  is  no  violation  of  the principles  of natural justice. It may be possible  that  on the  same  evidence some court might have  arrived  at  some different  conclusion  than  the  one  arrived  at  by   the arbitrator but that by itself is no ground for setting aside the  award  of an arbitrator. Also see the  observations  of Halsbury’s Laws of England, 4th Edn., Vol. 2, at pages 334 & 335, para 624, where it was reiterated that an  arbitrator’s award  may  be set aside for error of law appearing  on  the face  of it, though that jurisdiction is not lightly  to  be exercised. If a specific question of law is submitted to the arbitrator for his decision and he decides it, the fact that the decision is erroneous does not make the award bad on its

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 15  

face  so  as  to permit it being set aside;  and  where  the question   referred  for  arbitration  is  a   question   of construction,  which is, generally speaking, a  question  of law,  the  arbitrator’s decision cannot be  set  aside  only because  the  court would itself have come  to  a  different conclusion; but if it appears on the face of the award  that the arbitrator has proceeded illegally, as, for instance, by deciding  on  evidence  which  was  not  admissible,  or  on principles   of   construction  which  the  law   does   not                                                   PG NO 684 countenance, there is error in law which may be ground for setting aside the award.     It  was  contended by Mr F.S. Nariman, counsel  for  the appellant, that a specific question of law being a  question of construction had been referred to the Umpire and,  hence, his decision, right or wrong, had to be accepted. In view of clause  18,  it was submitted that in this case  a  specific reference  had  been  made  in  the  interpretation  of  the agreement between the parties, hence, the parties were bound by  the decision of the Umpire. Our attention was  drawn  to the observations of this Court in M/s. Hindustan Tea Co.  v. M/s.  K. Sashikant &  Co., AIR 1987 SC 81, where this  Court held  that under the law, the  arbitrator is made the  final arbiter of the dispute between the parties, referred to him. The  award is not open to challenge on the ground  that  the arbitrator  has reached a wrong conclusion or has failed  to appreciate  facts. Where the award which was a reasoned  one was  challenged on the ground that the arbitrator had  acted contrary to the provisions of s. 70 of the Contract Act,  it was held that the same could  not be set aside.     In  order to set aside an award, there must be  a  wrong proposition  of law laid down in the award as the  basis  of the  award. For this see the observations of this  Court  in Kanpur Nagar Mahapalika v. M/s. Narain Das Haribansh, [1970] 2  SCR  28. In that case the appellant had  entered  into  a contract with the respondent for certain construction  work. The contract contained an arbitration agreement between  the parties.  The  respondent  filed a  suit  in  1946  claiming certain  moneys  due  against its final bills  but,  at  the instance  of  the  appellant, the suit was  stayed  and  the matter referred to arbitration. The arbitrator made an award in  March 1960 in favour of the plaintiffs  determining  the amount  payable by the appellant. Thereafter  the  appellant made  an  application  for setting aside the  award  on  the ground  that the arbitrator had misconducted himself in  not properly  considering that the claim of the  respondent  was barred by limitation under section 326 of the U.P. Act 2  of 1916. Although the trial court set aside the award, the High Court, in appeal, reversed this decision. In appeal to  this Court it was contended for the appellant that the award  was bad by reason of an error apparent on its face.     Dismissing the appeal, it was held that there could  not be predicated of the award that there was any proposition of law forming the basis of the award, and, therefore, it could not be said that there was any error apparent on the face of the award.                                                   PG NO 685     The  Judicial  Committee  in  the  famous  decision   of Champsey Bhara & Co. v. Jivraj Balloo Spinning & Weaving Co. Ltd., [ 1923] AC 480 held that the error of law on the  face of  the  award means that one can find in the  award  or  in document  incorporated  thereto  as, for  instance,  a  note appended  by  the  arbitrator stating the  reasons  for  his judgment,  some legal proposition which is the basis of  the award  and which is erroneous. The same view was  reiterated

12

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 15  

by  this  Court  in Dr. S.B. Dutt v.  University  of  Delhi, [1959] SCR 1236.     In  this case. Mr. Nariman appearing for  the  appellant contended  that  there  was no proposition of  law  as  such stated by the Umpire which could be said to be the basis  of his   decision.  Hence,  the  award  was  not  amenable   to corrections  on  the ground that there was an error  of  law apparent on its face. Mr. Nariman further submitted that the Umpire  had decided the specific question of law and such  a decision, right or wrong, is binding on the parties. In  aid of  his submission Mr. Nariman referred to the  decision  of this  Court  in  M/s. Kapoor  Nilokheri  Co-op.  Dairy  Farm Society  Ltd. v. Union of India & Ors., [ 1973] 1  SCC  708, where  it was held that in a case of arbitration  where  the appellants  had sepcifically stated that their  claims  were based on the agreement and on nothing else and all that  the arbitrator  had  to  decide  was as  to  the  effect  of  an agreement  between  the appellant and  the  respondent,  the arbitrator  had really to decide a question of law  i.e.  of interpreting  the document, the agreement. Such  a  decision his, is not open to challenge.     Our  attention  was drawn to the  observations  of  this Court  in  Tarapore & Co. v. Cochin Shipyard Lld.  Cochin  & Anr., [l984] 3 SCR 118, where Desai J., spoke for the  Court and  Justice Chinnappa Reddy agreed with him. It was  stated that a question of law might figure before an arbitrator  in two ways. It may arise as an incidental point while deciding the  main dispute referred to the arbitrator or in  a  given case  parties  may refer a specific question of law  to  the arbitrator for his decision. This Court reiterated that  the arbitration has been considered a civilised way of resolving disputes avoiding court proceedings. There was no reason why the  parties should be precluded from referring  a  specific question of law to an arbitrator for his decision and  agree to  be bound by the same. This approach manifests  faith  of parties  in the capacity of the tribunal of their choice  to decide even a pure question of law. If they do so, with eyes wide  open,  there is nothing to preclude the  parties  from doing so. If a question of law is specifically referred  and it  becomes  evident  that the parties  desired  to  have  a decision on the specific question from the arbitrator rather than  one from the Court, then the court will not  interfere                                                   PG NO 686 with  the award of the arbitrator on the ground  that  there was  an error or law apparent on the face of the award  even if  the view of law taken by the arbitrator did  not  accord with  the  view of the court. A long line of  decisions  was relied upon by this Court for that proposition.     Mr. B. Sen, learned counsel for the respondent, however, contended  that in the present case, there was  no  specific question of law         referred to the Umpire. He submitted that  it was a general reference in which a question of  law arose.  It  was  any question in  the  proceedings  and  the question  of law, as such, did not arise. According  to  Mr. Sen,  the  mistake that the Umpire, has committed  is  clear from his following statement:     "The  Board thus having accepted the agreement with  the claimant,  it  became binding on the Board  and  under  sub- section  [3] of s. 49 of the Electricity Supply Act  nothing contained  in  sub-section ( 1) & (2) of s. 49  of  the  Act could  have any bearing on the terms of the  agreement.  The result  was that the uniform tariff fixed by the Board  with effect from 12th October, 1974 did not apply".     It  was  stated that no specific  question  having  been referred to, this mistake was fatal.

13

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 15  

   We are unable to accept this submission. Our   attention was  drawn  by Mr. Nariman to the  observations  of  Justice Macnaghten  in  Hitchins  & Anr. v.  British  Coal  Refining Processes  Ltd., [1936] 2 A.E.R. Reprint 191. Ihere,  by  an agreement the applicants were to act as consulting Engineers in connection with a certain coal refining process owned  by the  respondents.  While the plant for the  working  of  the process was being erected, a dispute arose. the  respondents wanting  the applicants to attend every day at the  site  of the plant and the applicants considering this to be no  part of  their  duty. The respondents  thereupon  terminated  the agreement  and the matter was referred to  arbitration.  The applicants pleaded that the termination of the agreement was unjustified;  the  respondents pleaded that  the  applicants should have attended every day and that they had been quilty of  negligence in respect of certain matters set out in  the counterclaim.  The arbitrator found the termination  of  the agreement to be unjustified and also negligence on the  part of  the appellants in respect of the matters set out in  the counterclaim,  and he awarded the appellants  damages  after setting   off   an  unspecified  amount  for   damages   for negligence. The respondents moved to set aside the award  on                                                   PG NO 687 the  ground of error of law apparent on the face of  it.  At the hearing the respondents contended that the whole of  the pleadings   in   the  arbitration   were   admissible.   The respondents  contended  that  for the  purpose  of  deciding whether  there was an error of law apparent on the  face  of the  award, the court could not look at any document  except the award itself. The respondents further contended that the arbitrator  had committed an error of law in  deciding  that the  negligence found did not afford sufficient  ground  for the  termination of the agreement, and further that  on  the true  consideration of the agreement, the refusal to  attend daily  was  as a matter of law a sufficient ground  for  the termination  of the agreement. It was held that inasmuch  as the  arbitrator in his award referred to certain  paragraphs in  the  counterclaim,  such  paras  ought,  in  considering whether  there was an error on the face of the award, to  be regarded  as forming part of the award.  Whether  misconduct justifies   dismissal  is  a  question  of  fact,  and   the arbitrator’s  decision was final. It was further  held  that the light to terminate the agreement because the  applicants refused   to  attend  daily  was  a  question   specifically submitted  to  the  arbitrator  and  the  court  could   not interfere  with  his decision, even if the  question  was  a question  of law. Mr. Justice Macnaghten at page 195 of  the report observed that it was permissible to look at the whole of  the  pleadings  delivered in  the  arbitration,  and  it appears  therein  that  the  respondents  affirmed  and  the applicants  denied  that the respondents  were  entitled  to terminate the agreement as the applicants refused to  attend daily  at  the site, and that this was a  specific  question submitted  to the decision of the arbitrator. Our  attention was  also  drawn to the observations of House  of  Lords  in Pioneer Shipping Ltd. and Ors. v. ETP Tioxide Ltd., [1981] 2 AER 1030. In that case by a charterparty dated 2nd November, 197 the owners of a vessel chartered her to the  charterers. It was held by the House of Lords that having regard to  the purpose  the Arbitration Act, 1970 of England which  was  to promote greater finality in arbitration awards then had been the   case  under  the  special  case   procedure   judicial interference with the arbitrator’s award was only  justified if it was shown that the arbitrator had misdirected  himself in  law  or  had  reached a  decision  which  no  reasonable

14

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 15  

arbitrator could have.     In the instant case, the view taken by the Umpire on the interpretation  of the agreement between the parties in  the light of the observations of this Court in Indian  Aluminium Co.’s  case (supra) was at best a possible view to take,  if not  the correct view. If that was the position then such  a view,  even if wrong, cannot be corrected by this  Court  on the basis6is of long line of decisions of this Court. In the                                                   PG NO 688 aforesaid view of the matter it is necessary to examine  the aforesaid  decision  in  the  Indian  Aluminium  Co’s   case (supra). There under section 49(1) & (2) of the  Electricity Supply  Act, 1948, the Legislature had empowered  the  State Electricity  Board  to frame uniform tariffs  and  had  also indicated  the  factors to be taken into account  in  fixing uniform  tariffs.  Under  sub-section  (3),  the  Board  was empowered,  in the special circumstances mentioned  therein, to fix different tariffs for the supply of electricity,  but in doing so, sub-section (4) directed that the Board was not to  show undue preference to any person. Under s. 59 it  was stipulated that the Board shall not, as far as  practicable, carry  on  its  operations at a loss and  shall  adjust  its charges accordingly from time to time. Certain consumers  of electricity  had entered into  agreements for the supply  of electricity  for their manufacturing purposes  at  specified rates  for  specified period. Some of  the  agreements  were entered into with the State Governments and the others  with the State Electricity Boards. In one of the agreements there was an arbitration clause. On account of the increase in the operation and maintenance cost, due to various causes  which caused  loss  to the State  Electricity Boards,  the  Boards wanted  to  increase  the  charges in  all  the  cases.  The consumers  challenged the competency of the Boards to do  so by  petitions in the respective High Courts. The High  Court sustained  the Board’s claim, in some cases, under  sections 49 & 59, and in others, held that the Board was  incompetent to  do so. In the case of the consumer where there  was  the arbitration clause. the High Court refused to entertain  the petition  on  account of the clause. This  Court  held  that fixation  of  special  tariffs  under s. 49  (3)  can  be  a unilateral Act on the part of the Board but more often it is the  result  of  negotiations  between  the  Board  and  the consumer  and  hence  a matter of  agreement  between  them. Therefore, the Board can, in exercise of the power conferred under  the  sub-section,  enter into  an  agreement  with  a consumer  stipulating  for  special  tariff  for  supply  of electricity  for a specific period of time.  The  agreements for supply of electricity to the consumers must therefore he regarded  as  having  been  entered into by  the  Boards  in exercise  of  the statutory power  conferred  under  section 49(3).  The Umpire in his award stated that the decision  of this Court covered and supported the claim of the  claimant. In  the present case the only difference is that  there  was only  an agreement by which the Electricity  Board  accepted the  agreement which was held by the Umpire to  have  become operative. Once that agreement was binding on the Board, its terms  could not be varied from the uniform rate under  sub- sections (1) and (2) of s. 49. The Umpire was right. In  our opinion,  the Umpire committed no error in arriving at  such conclusion.  Furthermore, such a conclusion is  certainly  a possible view of the  interpretation of the decision of this                                                   PG NO 689 Court  in Indian Aluminium Co’s case, if not the only  view. We need go no further than that.     We,  are, therefore, of the opinion that the view  taken

15

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 15  

by the Umpire on section 49 was a possible view in the light of the decision of this Court in Indian Aluminium’s case. In the  premises, a question of law arose certainly during  the course of the proceedings. Such a question has been  decided by  the  Umpire on a view which is a possible one  to  take. Even if there was no specific reference of a question of law referred  to  the  Umpire,  there  was  a  question  of  law involved.  Even  on the assumption that such a view  is  not right,  the  award  is  not  amenable  to  interference   or correction  by the courts of law as there is no  proposition of  law which could be said to be the basis of the award  of the Umpire, and which is erroneous.     In  the  premises, we are of the opinion that  the  High Court and the learned IInd Additional District Judge were in error in the view they took of the award of the Umpire.  The appeal  must, therefore, be allowed and the decision of  the High  Court, dated 21st July, 1987 as well as the  order  of the IInd Additional Judge, Lucknow, dated 30th May, 1984 are set aside. No other point was urged challenging the award of the Umpire. The award of the Umpire is confirmed and let the award  be made Rule of the Court under section 14(2) of  the Act. The appeal is allowed with costs. R.S.S.                                       Appeal allowed.