10 September 2008
Supreme Court
Download

U.P. COOPERATIVE FEDERATION LTD. Vs M/S. THREE CIRCLES

Case number: C.A. No.-002732-002732 / 2001
Diary number: 10925 / 2000
Advocates: RANI CHHABRA Vs MANJULA GUPTA


1

      REPORTABLE

       IN THE SUPREME COURT OF INDIA          CIVIL APPELLATE JURISDICTION

         CIVIL APPEAL NO.2732 OF 2001

U.P. Cooperative Federation Ltd.                                      …Appellant

VERSUS

M/s Three Circles                                                           …Respondent

J U D G M E N T

TARUN CHATTERJEE, J.

1. On or about 14th of December, 1983, a tender was floated by  

the U.P. Cooperative Federation Ltd. (hereinafter referred to as “the  

Federation”)  for  construction  of  4000  Metric  Ton  cold  storage  at  

Vashi, New Mumbai.  The tender document mentioned the time of  

completion as twelve months.  M/s Three Circles – the respondent  

herein, submitted a tender to get the contract.  In the year 1984, a  

contract was executed with M/s Three Circles.  Clause 10[f] of the  

Contract Agreement reads as follows:

“It  is  further  agreed  that  all  disputes  or  differences arising out of the provisions as contained  in  the  preceding paragraphs,  [a]  to  [f]  of  Clause 10  shall  be  referred  to  the  Managing  Director  of  Employer,  whose  decision  shall  be  final,  conclusive  

1

2

and binding and shall not be referred to arbitration or   to any court of law.”

Clause 11 of the contract reads as follows:

“All disputes and differences between the parties   regarding the construction or interpretation of any of   the  terms  and  conditions  herein  contained  or  conditions  of  contract  being  the  integral  part  of  this   contract [except those which are subject matter of the  decision of Managing Director of the Employer or/are  expressly forbidden and excluded from being referred  to  arbitrator  under  any  clause  by  the  contract  documents and such decision shall be final, conclusive  and binding upon the parties hereto] or determination  of  and  liability  or  any  disputes  of  whatever  nature  whether  during  the  course  of  progress  or  work  or   thereafter or after recession of the contract,  shall  be  referred to the arbitration as provided in the condition  No.51 of the Heading “scope and performance” in the  Tender  documents  and  shall  be  deemed  to  be  reference within the relevant provisions of the Indian  Arbitration Act, 1940, and or any statutory modification  of enactment there under.”

Clause 51 of the General Conditions of contract provided for  

arbitration.  This clause reads as follows:

“51. The contractor will become nominal member of  the  Federation  and  will  abide  by  the  rules  and  regulation laid down from time to time.  Except where  otherwise provided for in the contract all questions and  disputes relating to the meaning of the specifications,  designs,  drawings  and  instructions  herein  before  mentioned  and  as  to  the  quality  of  workmanship  or   materials  used  on  the  work  or  as  to  any  other   questions, claim, right, matter or thing whatsoever in   any  way  arising  out  of  or  relating  to  the  contract,   designs,  drawings,  specifications,  estimates,  

2

3

instructions,  order  or  these  conditions  or  otherwise  concerning  the  works,  or  the  execution  or  failure  to  execute the same whether arising during the progress  of  the work or  after  the completion or  abandonment  thereof shall be referred to the sole arbitration of the  Registrar Cooperative Societies Uttar Pradesh and if   the Registrar is unable to or unwilling to act, to the sole   arbitration  of  some  other  person  appointed  by  the  Managing  Director,  willing  to  act  as  such  arbitrator.   There will be no objection if the arbitrator so appointed  is an employee of Federation and that he had to deal   with the matters to which the contract relates and that   in the course of his duties as such he had expressed  views  on  all  or  any  of  the  matters  in  dispute  or  difference.   The  arbitrator  to  whom  the  matter  is   originally  referred  being  transferred  or  vacating  his  office  or  being  unable  to  act  for  any  reason,  such  Managing  Director  as  aforesaid  at  the  time  of  such  transfer vacation of office or liability to act shall appoint   another person to act as arbitrator in accordance with   the  terms  of  the  contract.   Such  person  shall  be  entitled to proceed with the reference from the stage at   which it was left by his predecessor.  It is also a term  of  this  contract  that  no  person  other  than  a  person  appointed  by  such  Managing  Director  as  aforesaid  should act as arbitrator and if for any reason, that is   not  possible  the  matter  is  not  to  be  referred  to   arbitration at all.  Cases where the amount of the claim  in  dispute  is  Rs.25,000/-  [Rupees  twenty  five  thousand] and above, the arbitrator shall give reasons  for the award.  Subject as aforesaid the provisions of   the Arbitration Act, 1940 or any statutory modification  or  reenactment  thereof  and  the  rules  made  there  under and for the time being in force shall apply to the  arbitration proceeding under this clause.

It is a term of the contract that the party invoking   arbitration shall  specify the dispute or disputes to be  referred to arbitration under this clause together with  

3

4

the  amount  or  amounts  claimed  in  respect  of  each  such dispute.

The  arbitrator[s]  may  from  time  to  time  with  consent of the parties enlarge the time, for making and  publishing the award.

The work under the contract  shall,  if  reasonably  possible,  continue during  the  arbitration  proceedings  and no payment due or payable to the contractor shall   be withheld on account of such proceedings.

The Arbitrator shall be deemed to have entered  on the reference on the date he issues notice to both   the parties fixing of the date of the first hearing.

The  Arbitrator  shall  give  a  separate  award  in  respect of each dispute or difference referred to him.

The venue of arbitration shall be such place as  may be fixed by the Arbitrator in his sole discretion.

The  award  of  the  Arbitrator  shall  be  final,   conclusive and binding on all parties to this contract.”

2. The respondent was given extension of time for execution and  

completion  of  the  project  pursuant  to  Clause  13  of  the  General  

Conditions of  Contract.   It  may be kept  on record that  Clause 32  

clearly postulates that the extended time was also to be the essence  

of  the  contract.   After  the  expiry  of  stipulated  period  of  time,  the  

respondent submitted certain claims to the Managing Director of the  

appellant in terms of Clause 10 of the Contract.  A compensation of  

4

5

Rs.87,000/- was awarded to the respondent.  In this connection, it  

may  be  stated  that  the  respondent  had  also  suspended  work  for  

some time.

3. The  respondent  thereafter  filed  a  suit  being  Arbitration  Suit  

No.3212 of 1986 before the High Court of Bombay under Section 20  

of the Arbitration Act, 1940 [in short ”the Act”] praying for appointment  

of an Arbitrator.  By an order dated 7th of January, 1988, the High  

Court appointed one Shri N.N. Shrikhande as the sole Arbitrator to  

decide  the  disputes  raised  by  the  parties.   Subsequently,  the  

appellant filed a notice of motion praying for setting aside the order of  

appointment dated 7th of January, 1988 and also prayed for stay of  

the arbitration proceedings.  The said notice of motion was, however,  

dismissed by the High Court. The appellant filed an appeal which was  

also dismissed on the ground of delay.   

4. The appellant, feeling aggrieved, filed a special leave petition  

being SLP [C] No.11703 of 1988 in which this Court granted leave,  

which came to be registered as Civil Appeal No.3585 of 1988.  By an  

order dated 4th of October, 1988, this Court had set aside the order  

5

6

dated  7th of  January,  1988 and  remanded  the  matter  to  the  High  

Court for nominating another Arbitrator.  Again by an order dated 2nd  

of November, 1988, the High Court appointed one Shri S.N. Mishra  

as the sole Arbitrator. On 1st of March, 1989 the learned Arbitrator  

entered  upon the  reference.  On 2nd of  March,  1989,  statement  of  

claim was filed by the respondent.  Various claims were made, inter  

alia,  for  escalation,  purchase  of  additional  material  and  transport  

charges.   Reply to show cause notice was filed on 16th of  March,  

1989 by the appellant and rejoinder to the same was also filed by the  

respondent.  The learned Arbitrator thereafter by a reasoned award  

dated 20th of October, 1989 directed the appellant to pay a sum of  

Rs.32,68,805.80 to the respondent along with interest at the rate of  

15% till  the date of final payment.  On or about 14th of December,  

1989,  the  appellant  filed  an  application  for  setting  aside  the  said  

award before the High Court.  By a judgment and order dated 19th of  

October, 1994, a learned Judge of the High Court dismissed the said  

petition of the appellant, inter alia, on the following findings:

[1] The claim of  the  appellant  that  they were  entitled  to  deduct  

certain amounts from the final payment to the respondent on account  

of his having consumed extra cement was rejected.

6

7

[2] The Arbitrator did not have any jurisdiction in rejecting the claim  

in view of Clause 10 of the agreement.

[3] The claim of the appellant that it was entitled to deduct certain  

amount from the final bill on account of non utilization of steel was  

rejected.  

[4] The Arbitrator awarded escalation price to the respondent on  

account  of  increase  in  prices  even  after  the  stipulated  time  of  

completion.

[5] The  Arbitrator  disallowed  the  claim  of  the  appellant  for  

deduction  of  amounts  from  the  final  bill  on  account  of  poor  

workmanship.

[6] The claim towards purchase of surplus wood by the respondent  

was allowed along with the claim for filling of earth.

[7] The  claim  of  the  respondent  towards  transport  charges  for  

carrying wood was allowed despite the fact that the contract provided  

for local wood to be used.

[8] Expenses towards litigation and interest at the rate of 18% prior  

to the reference were also allowed.

5. Feeling aggrieved, an appeal was carried to the Division Bench of  

the Bombay High Court and by a judgment and order dated 11th of  

7

8

February,  2000,  the  Division  Bench  partly  allowed  the  appeal  

limited to the question of interest but rejected all other contentions  

of the appellant.  Feeling aggrieved by the aforesaid order of the  

Division Bench of the High Court, a special leave petition was filed,  

which  on grant  of  leave  was  heard in  the  presence of  learned  

counsel for the parties.

6. We have heard the learned counsel for the parties and examined  

the impugned order of the High Court as well as the application for  

setting  aside  the  award  passed  by  the  Arbitrator  filed  at  the  

instance of the appellant and other materials on record.  On behalf  

of  the  appellant,  Mr.  Rakesh  Dwivedi,  learned  senior  counsel,  

contended at the first instance that there was an error apparent on  

the face of the award on the issue of ‘balance steel recovery’.  Mr.  

Dwivedi contended that the respondent was having balance steel  

with it which was not consumed or returned and the respondent  

should, therefore, pay interest on it as per penal rates in terms of  

Clause 15[2][6]  of  the Contract.   At  this stage we may refer  to  

Clause 15 [2][6] which runs as under :-

8

9

“if  on  completion  of  work,  the  contractor  fails  to  return surplus materials out of those supplied by the  Federation,  then,  in  addition  to  any  other  liability   which the contractor would incur, the Engineer In- charge may, by a written notice to the contractor,   require  him to  pay within  a fortnight  of  receipt  of   notice,  for  such  unreturned  surplus  materials  at  double the issue rates.”  

7. On this score, the finding of the Arbitrator was that there was no  

clear  evidence  put  forward  by  either  of  the  parties  as  to  what  

happened to the balance steel and under that circumstances the  

claimant, namely, the respondent was directed to pay at the issue  

rates and not at the penal rates.  However, though this was the  

observation  in  the  body  of  the  award,  in  Appendix  ‘C’,  the  

Arbitrator  had  given certain  deductions  based on balance steel  

under  three  heads.   Mr.  Dwivedi,  therefore,  contended that  the  

appendices were part of the award itself which is to be interpreted  

in  conjunction  with  Appendix  ‘C’  and,  therefore,  in  the  light  of  

Appendix ‘C’ where a finding of unutilized steel under three heads  

lying unutilized the Arbitrator should have awarded the respondent  

to  pay  at  penal  rates  and  by  not  doing  so  and  directing  the  

payment  at  issue rates it  was against the express terms of the  

contract  and  liable  to  be  interfered  with.   In  response  to  this  

9

10

argument,  the  learned  counsel  for  the  respondent,  however,  

contended that Appendix ‘C’ could not be construed to be a part of  

the award, since, in the award the observation was that there was  

no clear evidence as to the balance steel, payment at penal rates  

could  not  have  been  awarded.   It  was  further  contended  by  

learned  counsel  for  the  respondent  that  if  anyone,  it  was  the  

respondent  who  should  be  aggrieved  and  at  any  rate,  the  

appendix did not give the appellant to contend that there was a  

finding  of  unutilized  balance steel.   The Arbitrator  in  his  award  

clearly stated that in the absence of a positive finding of the same,  

the penal rate cannot be awarded.  The Court, therefore, rightly  

held that Appendix ‘C’ did not mean to be a positive finding by the  

Arbitrator  that  such  steel  was  unutilized  and  had  been  

appropriated by the respondent.  Accordingly, we do not find any  

infirmity either in the award of the Arbitrator or in the findings of the  

Division  Bench  as  well  as  of  the  learned Single  Judge on  this  

ground.   

8. It  was  next  contended  by  the  learned  senior  counsel  for  the  

appellant that there was inferior quality of workmanship as a result  

10

11

of  which it  was entitled to  make deduction from the bills.   The  

learned Arbitrator had refused to accept this submission from the  

side of the appellant that under the contract the respondent was  

obliged to use local materials including local bricks, that the bricks  

in the Bombay region were of inferior quality and further that all the  

bills presented had been passed by the Architect of the appellant  

without any objection, therefore, the appellant was estopped from  

raising the issue and no recovery could be allowed.  We do not  

find any infirmity in the aforesaid findings of the Arbitrator as well  

as  the  findings  arrived  at  by  the  High  Court.  Mr.  Dwivedi  had  

drawn our attention to the fact that under the contract this was an  

issue which was left to the sole discretion of the Managing Director  

of the appellant and, therefore, was not within the jurisdiction of  

the Arbitrator to arbitrate upon.  In this connection, Mr. Dwivedi  

placed reliance on Clause 10[b], [c] and [f] and Clause 11 of the  

Articles of Agreement.  The learned Single Judge as well as the  

Division  Bench,  after  examining  the  Clauses,  as  indicated  

hereinabove, held that these Clauses did not include within their  

purview  ‘bad  workmanship’  and,  therefore,  it  was  beyond  the  

jurisdiction of the Arbitrator to decide it.  In respect of Clause 10  

11

12

[c], the Court, in our view, has rightly rejected the argument of the  

appellant that ‘negligence or lack of proper care’ was synonymous  

to bad workmanship.  Accordingly, we do not find any ground to  

interfere  with  the  findings  of  the  High  Court  in  rejecting  the  

submissions  of  the  learned  counsel  for  the  appellant  on  this  

ground.  In any view of the matter, the Arbitrator had considered  

the  entire  materials  on record  and the  rival  submissions  of  the  

parties  and  then  came  to  the  conclusion  of  fact,  which  was  

accepted  by  the  courts  below,  it  is  not  open  to  this  Court  to  

interfere with such conclusions until and unless it is manifest that  

such conclusions are perverse or arbitrary.  That apart, we are of  

the  view that  this  would  not  be  a  ground  for  setting  aside  the  

award under the Arbitration Act, 1940.  

9. That apart, in our view, the High Court was justified in holding that  

the poor workmanship did not fall under any of the sub-clauses of  

Clause 10 of  the  Articles  of  Agreement,  which enumerates  the  

matters  in  which the  Managing  Director  will  have the  exclusive  

authority to decide the dispute as per Clause 11 of the Agreement.  

Clause  10(b)  provides   that  all  special  losses  and  damages  

12

13

suffered  by  the  Employer,  as  certified  by  the  certificate  of  the  

Engineer-in-charge, shall be final, conclusive and binding. Clause  

10(c) of the agreement makes “losses suffered by the employer or  

damages due to negligence or lack of proper care” on the part of  

the contractor shall be liable to be reimbursed and the certificate of  

the Engineer-in-charge as to the extent of damage and its value is  

declared to be final, conclusive and binding upon the contractor.  

Clause 11 provides that all disputes and differences arising out of  

the contract as contained in the proceedings in paragraphs (a) to  

(f)  of  Clause  10  shall  be  referred  to  the  Managing  Director  of  

Employer whose decision shall  be final,  conclusive  and binding  

and shall not be referred to arbitration or to any Court of law. In  

this connection, as noted herein earlier, the High Court was fully  

justified  in  holding  that  “lack  of  proper  care  or  negligence”  

appearing  in  Clause  10(c),  was  not  synonymous  to  bad  

workmanship  by  which  the  respondent  had  based  its  claim.  

Workmanship refers to skill or talent displayed in the performance  

of a work and is not related to the care or diligence showed in the  

work  or  choosing the materials.  Accordingly,  this  submission of  

Mr.Dwivedi, learned senior counsel appearing for the appellants is  

13

14

not worthy of consideration and, therefore, it is rejected.  

10. We also find from the impugned judgment of the High Court that  

both the parties had admitted before the Arbitrator that the format  

to be used for analysis of extra items shall be the CPWD Format  

and that both the parties had indicated to the Arbitrator that there  

was no difference between them as to the format used by them in  

analyzing the extra items. However, the parties are not at ad idem  

on the actual rates to be taken for labour and  material, referred to  

in the format. It also appears from the judgment of the High Court  

that  while  the  appellant  insisted  that  the  rates  prescribed  by  

CPWD in respect of the labour and material had to be used, the  

respondent  insisted  that  local  rates  would  have  to  be  used.  

Considering the resolution approved in a meeting on 6th of March,  

1986, where the Architect approved extra items 1 to 6 at the rates  

that were put forward by the respondent and with regard to extra  

items 7 and 8 the rates analysis put forward by the appellant was  

not even contested by the respondent.  With regard to the analysis  

of item No.9 pertaining to transportation and wages, the Arbitrator  

denied the claim of the respondent. With regard to item No.10, the  

14

15

rate put forward by the appellant was accepted by the Arbitrator. In  

these circumstances, it is no longer open to hold the contention  

that  there  was  any  requirement  that  the  CPWD rates  must  be  

accepted and that no deviation therefrom was permissible under  

the Contract. In this view of the matter, it is difficult to agree that  

the Arbitrator had acted beyond the terms and conditions of the  

contract while coming to the findings of fact relating to the extra  

items on rates other than the CPWD rates also.  

11. The  next  ground  of  attack  of  the  impugned  judgment  rests  on  

payment of interest. From the impugned judgment, it appears that  

three limbs of the argument of the parties were dealt with by the  

Division  Bench  of  the  High  Court.  It  is  not  in  dispute  that  the  

learned  Arbitrator  entered  upon  the  reference  on  1st of  March,  

1989. The Arbitrator having found that the appellant was liable to  

pay a  total  sum of  Rs.32,68,805.80  p.  directed  that  if  the  said  

amount is not paid by the appellant to the respondent on or before  

15th of December, 1989, the same would carry interest  @ 15% per  

annum  till  the  payment  was  made.  The  total  sum  of  

15

16

Rs.32,68,805.80 as found by the learned Arbitrator included the  

following three claims :-

Claim No.1 :    Rs.17,36,994.97

Claim No.2 :    Rs.2,40,615.96

Claim No.8 :    Rs.2,68,000.000

So far as Claim No.1 was concerned, the Arbitrator found that  

what was due was Rs.13,62,349/- to which he added interest from  

January  1987  to  October,  1989  @  15%  which  worked  out  to  

Rs.3,74,645.97. Thus the total amount in respect of Claim No.1 as  

mentioned  above  worked  out  to  Rs.17,36,645.97   (there  is  an  

apparent inconsistency in the figures of claim No.1 reproduced with  

this  figure),  but  the  thing  remains  that  the  learned  Arbitrator  

calculated  interest  @  15%  for  the  period  from  January  1987  to  

October, 1989 and added it to make up the claim No.1.  Similar was  

the exercise carried out by the learned Arbitrator in regard to claim  

No.2  in  which  the  Arbitrator  having  found  that  a  total  sum  of  

Rs.1,88,718.40  p.  was  due,  added  interest  for  the  period  from  

January 1987 to  October,  1989 again @ 15% which amounted to  

Rs.51,897.56  making  the  total  under  the  head  of  CPWD  as  

Rs.2,40,615.96 p. So far as Claim No.8 as mentioned by the learned  

16

17

Arbitrator  is  concerned,  it  appears  that  the  learned  Arbitrator  re-

calculated  the  amount  of  interest  and  awarded  Rs.2,68,000/-  as  

interest  on  delayed  payment.  It  is  not  in  dispute  that  the  learned  

Arbitrator in his final analysis had allowed interest @ 15% per annum.  

So far as the payment of interest is concerned, the Division Bench of  

the High Court after analyzing the decisions of this Court,  namely,  

Executive  Engineer,  (Irrigation)  Balimela  & Ors.  Vs.  Abhaduta  

Jena & Ors. [1988 (1) SCC 418], Secretary, Irrigation Department,  

Government of Orissa & Ors. vs. G. C. Roy  [1992 (1) SCC 508]  

came  to  the  conclusion  of  law  which  was  that  the  Arbitrator  has  

power to award pendente lite interest  and where the contract  was  

silent as to the awarding of interest, the Arbitrator has the power to  

award interest for the pre-reference period if there is a substantive  

law which empowers him to do so or if there is a usage of trade for  

payment which has the force of law. In our view, the High Court was  

perfectly justified in holding that the Arbitrator has the power to award  

interest for the pre-reference period. It needs to be repeated at this  

juncture  that  the  arbitration  in  question  was  governed  not  by  the  

present Act of 1996 but by the provisions of Arbitration Act,  1940.  

However, as this power emanates from Section 3 of the Interest Act,  

17

18

1978, the High Court noted that the rate of interest cannot be more  

than ‘the current rate of interest’  as stipulated by the said Section.  

Accordingly the High Court had reduced the rate of interest for pre-

reference period from 18% to 15%. It was, however, argued on behalf  

of  the  appellant  that  the High Court  was not  justified  in  awarding  

interest for pre-reference period in view of Section 3 of the Interest  

Act, 1978 which was pursuant to a special clause in the Contract. As  

in the present case there was no such clause in the agreement and  

hence it was not within the power of the Arbitrator to make an award  

with respect to interest.  

12. In our view, this argument lacks substance. The position of law,  

as  found  by  the  High  Court  in  its  impugned  judgment  on  

consideration of various other judgments of this Court, would clearly  

show that in those judgments the High Court relied on also did not  

stipulate  any  express  agreement  with  respect  to  interest  as  a  

precondition to the authority of the Arbitrator to award interest for the  

pre-reference  period.  The  matter  would  have  a  different  issue  

altogether if there had been a specific provision prohibiting grant of  

interest which was, of course, not the case of the appellant.  

18

19

13. In the case of State of Rajasthan and Anr v. Ferro Concrete  

Construction Pvt. Ltd, [2009 (8) SCALE 753], the same work was  

advanced in which this Court observed:  

“But this Court has held that in the absence of an   express bar, the arbitrator has the jurisdiction and  authority to award interest for all the three periods -   pre  reference,  pendente  lite  and  future   (vide  decisions  of  Constitution  Bench  in  Secretary,   Irrigation Department,  Government of Orissa vs. G.  C. Roy -  1992 (1)  SCC 508,  Executive Engineer,   Dhenkanal  Minor  Irrigation  Division  vs.  N.  C.   Budharaj - 2001 (2) SCC 721  and the subsequent   decision  in  Bhagawati  Oxygen  vs.  Hindustan  Copper  Ltd  -2005 (6)  SCC 462).  In  this  case as  there was no express bar in the contract in regard  to interest, the Arbitrator could award interest.”

14. In view of the above decision in law now settled by this Court,  

we are unable to hold that the Arbitrator was not entitled to award  

interest on the pre-reference period because there was no clause in  

the agreement  prohibiting such awarding of  interest.  However,  the  

High Court  had reduced the rate of  interest  to the ‘current  rate of  

interest’ and, therefore, it is not open for us to interfere with such rate  

of  interest  at  this  stage  in  this  appeal.  Therefore,  there  is  no  

substance in this argument, accordingly it is rejected.

19

20

15. Now  the  question  comes  which  is  related  to  awarding  of  

‘interest  on interest’.  According to  the appellant,  they have to pay  

interest  on  an  amount  which  was  inclusive  of  interest  and  the  

principal  amount  and,  therefore,  this  amounts  to  a  liability  to  pay  

‘interest  on  interest.  This  question  is  no  longer  res  integra  at  the  

present point of time. This Court in McDermott International Inc. v.   

Burn Standard Co. Ltd, & Ors. [2006 (11) SCC 181] has settled this  

question in which it had observed as follows :

“The Arbitrator has awarded the principal amount   and interest thereon upto the date of award and  future interest thereupon which do not amount to  award on interest on interest as interest awarded  on the principal amount upto the date of award  became  the  principal  amount  which  is  permissible in law.”

16. The  High  Court  on  this  question  has  also  rightly  relied  on  a  

decision  of  this  Court  in  the  case  of Oil  and  Natural  Gas  

Commission vs. M/s. M .C. Clelland Engineers S.A. [1999 AIR  

SCW 1224]. That being the position, we are unable to find any  

ground to set aside the judgment of the Division Bench of the High  

Court while considering the ground of ‘interest on interest’. So far  

as  the  ground  relating  to  the  power  of  the  Arbitrator  to  award  

20

21

interest on the cost of arbitration is concerned, we are of the view  

that we do not find any infirmity in the said findings of the High  

Court relating to that ground. Since the legislature by way of an  

amendment in the year 1956 deleted Section 35(3) of the Code of  

Civil Procedure which empowered the court to award interest, the  

Arbitrator, on analogy, cannot have the power to award interest on  

costs. Therefore, the High Court has failed to justify in holding that  

the powers of the Arbitrator are not effected by changes made to  

the Code of Civil Procedure. The power of the Arbitrator, if any,  

shall  be located from the act itself.  We may note that awarding  

costs is a matter of discretion of the Arbitrator under the 1940 Act.  

Sir Mohd. Akbar Khan vs. S.Attar Singh (deceased) [AIR 1945  

PC 170] is an answer to the aforesaid ground.  Paragraph 8 of the  

First Schedule to the Arbitration Act, 1940 which contains “Implied  

Conditions of Arbitration Agreements” lays down that –  

“the costs of the reference and award shall be in the  discretion  of  the  arbitrators  or  umpire  who  may  direct to, and by, whom, and in what manner, such  costs or any part thereof shall be paid, and may tax   or settle the amount of costs to be so paid or any  part  thereof  and  may  award  costs  to  be  paid  as   between legal practitioner and client.”

21

22

17.A  plain  reading  of  this  paragraph  would  show  that  there  is  a  

provision  in  this  clause  which  does  not  permit  or  prohibit  the  

imposition of interest on costs of arbitration.  

18. The High Court has also observed in the impugned judgment that  

the  principles  in  relation  to  payment  of  interest  on  interest  will  

apply  in  this  context  as  well  and  that  there  is  no  principle  or  

precedent prohibiting award of interest on cost. It may be noted  

that the Law Commission of India in its 55th Report submitted in  

1973 discussed the rationale behind grant of interest on interest  

and on costs. Though the Commission found it fit not to disturb the  

position of law that emerged after the deletion of Section 35(3) of  

the Code of Civil Procedure, but Law Commission had expressed  

its opinion in favour of grant of interest on costs. The logic behind  

it  was that  the  cost  incurred  in  the  litigation  were  actually  and  

rightfully incurred by the successful litigant which he would have  

invested but for the lengthy litigation proceedings. Interest, which  

is  damages  for  wrongful  retention  of  money  that  rightfully  

belonged to one, thus can be paid on costs as well. This may also  

be considered that costs of arbitration are actually incurred by the  

22

23

respondent and it  is only that it  becomes payable only with the  

award in its favour. Accordingly, we do not find any infirmity in the  

judgment of the Division Bench except in that we are of the view  

that the rate of interest from 15% should be reduced to 7%.  In  

McDermott  International  vs.  Burn  Standards (supra),  it  had  

summarized the practice of this Court on this issue in the following  

words :-

“The 1996 Act provides for award of 18% interest.   The  arbitrator  in  his  wisdom  has  granted  10%  interest both for the principal amount as also for   the interim. By reason of the award, interest was  awarded  on  the  principal  amount.  An  interest   thereon was upto the date of award as also the  future interest at the rate of 18% per annum.

However, in some cases, this Court was resorted  to  exercise  its  jurisdiction  under  Article  142  in  order to do complete justice between the parties.  

In pure Helium India (P) Ltd.  [2003 8 SCC 593]  this  Court  upheld  the  arbitration  award  for  payment of money with interest at the rate of 18%  p.a.  by  the  respondent  to  appellant.  However,  having regard  to  long lapse of  time,  if  award is   satisfied in entirety, respondent would have to pay  a huge amount by way of interest. With a view to  do complete justice to the parties, in exercise of  jurisdiction under Article 142 of the Constitution of  India,  it  was  directed  that  award  shall  carry   interest at the rate of 6% p.a. instead and in place  of 18% p.a.

23

24

Similarly  in  Mukand Ltd.  vs.  Hindustan Petroleum  Corpn.  [2006  (4)  SCALE  453],  while  this  Court   confirmed  the  decision  of  the  division  bench  upholding the modified award made by the learned  single  Judge,  the  court  reduced  the  interest   awarded by the learned single judge subsequent to  the decree from 11% per annum to 7% per annum  observing  that  7%  per  annum  would  be  the  reasonable rate of interest that could be directed to  be paid by the appellant to the respondent for the  period subsequent to the decree.  

In this case, given the long lapse of time, it will be in  furtherance of justice to reduce the rate of interest to  7%.”   

  19. Following the aforesaid decision and considering the fact that  

there was a long lapse of time and for the ends of justice, we are,  

therefore, of the view that the judgment of the Division Bench can be  

modified only to the extent that the rate of interest should be reduced  

from 15% to 7%. As we also find in this case that such reduction of  

interest  is  warranted  because  the  award  was  passed  on  20th of  

October, 1989, now 20 years have passed since then.  

20. This  Court  in  Mcdermott  International  Inc.  vs.  Burn  

Standard Co.Ltd. & Ors. (supra) S.B.Sinha,J., (as His Lordship then  

was), following the two earlier decisions of this Court in the case of  

Pure  Helium  India  (P)  Ltd.  vs.  ONGC  [(2003)  8  SCC 593] and  

24

25

Mukand Ltd. vs. Hindustan Petroleum Corpn. Ltd. [(2006) 9 SCC  

383] and considering the fact that due to long lapse of time if  the  

entire award is satisfied, the appellant would have to pay a huge sum  

of money by way of interest.  Therefore, in that decision, this court  

directed reduction of rate of interest in order to do complete justice  

between the parties in the exercise of its jurisdiction under Article 142  

of the Constitution of India and that is the reason we also reduce the  

rate of interest from 15% to 7%.

21. Before  parting  with  this  judgment,  we  may  refer  to  two  

decisions of this Court which were cited at the bar in the case of T.N.  

Electricity Board vs. Bridge Tunnel Constructions & Ors. [1997 4  

SCC 121]  and  Trustees of the Port of Madras vs.  Engineering  

Constructions Corpn. Ltd. [1995 5 SCC 531]. So far as the case of  

T.N.  Electricity  Board  is  concerned,  we  have  no  quarrel  with  the  

principle laid down in the aforesaid decision. In that decision, it was  

held that one of the question that was decided was that the Arbitrator  

cannot clothe himself conclusively with the jurisdiction to decide or  

omit to decide the arbitrability of a particular item or the claim made  

by the parties. It was held that when a specific reference has been  

25

26

made to the Arbitrator and the parties raise the dispute of arbitrability,  

with the leave of the court/by a direction of the court in a proceeding  

under Section 33, he is to decide the arbitrability of the dispute and  

make  a  decision  while  giving  reasons  in  support  thereof.  It  was  

further held that the decision of the Arbitrator in granting a particular  

sum by a non-speaking award, therefore, hinges upon the arbitrability  

of  a  dispute  arising  under  the  contract  or  upon  a  particular  item  

claimed thereunder. It was further observed that he was required to  

give the decision thereon. Therefore, it was held that the question of  

decision by implication does not arise since his jurisdiction to decide  

the  dispute  on  merits  hinges  upon  his  jurisdiction  to  decide  the  

arbitrability of the dispute.  

22. The  aforesaid  decision  of  this  Court,  therefore,  in  our  view  

cannot come to help the appellant.  

23. So far as the decision in the case of  Trustees of the Port of  

Madras  vs.  Engineering  Constructions  Corpn.  Ltd. (supra)  is  

concerned, this case also has no application in the facts of this case.  

In  that  case,  the principles have been laid down in the case of  a  

26

27

reasoned award and the court can interfere if the award is passed  

upon a proposition of law which is unsound in law. The error apparent  

on the face of the award contemplated by Section 16(1)( c) as well as  

Section 30 (c ) of the Arbitration Act is an error of law apparent on the  

face of the award and not an error of fact. Therefore, this decision, in  

our view, is also of no help. The Arbitrator has passed his award on  

the  basis  of  the  conditions  of  the  clauses  in  the  agreement  and  

passed an award and nothing could be shown from which it could be  

held that the court  could interfere with the award if  the same was  

passed upon the proposition of law which is unsound in law.

24. For the reasons aforesaid and subject to the modification as  

noted hereinabove, this appeal has no merit and the same is hereby  

dismissed. There will be no order as to costs.   

……………………J. [Tarun Chatterjee]

New Delhi; …………………...J. September 10, 2009. [Harjit  Singh  Bedi]

           

27