11 November 1998
Supreme Court
Download

STATE OF U.P. Vs HARISH CHANDRA & CO.


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5  

PETITIONER: STATE OF U.P.

       Vs.

RESPONDENT: HARISH CHANDRA & CO.

DATE OF JUDGMENT:       11/11/1998

BENCH: S.B. Majmudar, S. Saghir Ahmad, K. Venkataswami.

JUDGMENT:

MAJMUDAR, J.

       Leave granted in S.L.P.(C) No. 6307 of 1995.

       We have heard learned senior counsel for the parties in these two appeals.

       Both these appeals by special leave arise out of one and  the  same  judgment  rendered  by  the  High  Court  of Judicature at Allahabad.

       In Civil   Appeal   No.      7643   of   1995,   the appellant-State of  U.P.    has  brought  in  challenge  the aforesaid order of the  High  Court  dismissing  its  appeal against  the  award decree passed by the learned Trial Judge subject to a slight modification in favour of the  appellant -  State to which we will make a reference while considering the cross-appeal arising out of S.L.P.(C) No.  6307 of 1995. The cross-appeal is filed by the respondent Harish Chanra  & Co.   in Civil Appeal No.7643 if 1995 who has felt aggrieved by the modification regarding rate of interest as ordered by the High Court in the impugned judgment  to  the  extent  it reduced  interest  from  15 per cent per annum as awarded by the trial court from the date of decree till  payment  to  6 per cent.

       A  few  facts leading to the controversy in question may be stated at the outset.    On  26th  October,  1979  an agreement   was  entered  into  between  the  Superintending Engineer, Irrigation Construction Circle, Dehradun on behalf of the appellant-State on the one  hand  and  M/s.    Harish Chandra  &  Co., New Delhi (respondent herein) on the other. The work entrusted  to  the  respondent-contractor  was  for excavation of Khara  Power Channel from K.M.  8 to K.M.  9.8 and also the construction of drainage  crossings  at  Chhoti Lui at K.M.  9.2 and Bari Lui at K.M.  9.6.  The work was to be  started  on  1.12.1979 and was to be completed latest by 31.5.1982.  It is the case of the appellant-State  that  the respondent-contractor  did  not complete the work within the specified time, that is, by 31.5.1982.   Time  was  extended and  still  he did not complete and left the work incomplete on 31.5.1986.  That required  the  State  to  get  the  work completed through other agencies which resulted in incurring of additional cost by the State in completing the said work. Disputes  arose  between  the parties in connection with the work which was carried  on  by  the  respondent  before  the

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5  

aforesaid date, i.e.    31.5.1986.    It  appears  that  the respondent  issued  a  letter  dated  16.11.1983   regarding various  claims  put  forward in the said letter and seeking arbitration of the said disputes as per the clause contained in the Special  Conditions  of  the  Contract.    The  Chief Engineer,  Yamuna  Valley  Projects,  Irrigation Department, Dehradun responded to the said letter of the respondent  and referred the  claims  Nos.    1,  2,  4  &  8, 13, 15 and 16 contained in the claimant’s aforesaid letter for arbitration to  the  sole  arbitrator  -  Chief   Engineer,   Irrigation Department of  the  State.    After hearing the parties, the arbitrator rendered his award  dated  24th  February,  1992. The  arbitrator awarded interest on the amounts found due by him to the respondent at  the  rate  of  15  per  cent  from 16.11.1983,  that  is,  the  date  on which the claimant had sought  for  reference,  to  5.1.1988  on  different  items. Interest pendente lite was also allowed at 15 per cent and 6 per  cent interest was allowed on the amounts found due from the date of the award to the date of actual payment or  date of decree  whichever was earlier.  The said award was sought to be made rule  of  the  court  by  the  respondent.    The appellant-State raised various objections to the award being made rule  of  the  court.    The  learned Trail Judge/Civil Judge, Dehradun, after hearing the parties, by  order  dated 11th  March,  1993  made  the  award  rule  of the court and further directed that the claimant shall be entitled to  get the  ordinary  interest  of  15.5  per cent per annum on the amount of award with effect from the date of the order  upto the satisfaction of the decree.  It is this decree passed by the  trial  court  that  resulted  into  an  appeal  by  the appellant-State before the  High  Court  which  came  to  be disposed of by the impugned judgment.

       Learned  senior counsel for the appellant State Shri Avadh Behari Rohtagi in support  of  the  appeal  vehemently submitted that the arbitrator had no power to grant interest prior  to the reference in view of clause 1.9 of the Special Conditions of the Contract which clearly prohibited granting of such interest.  He also submitted  that  the  two  claims which  were  granted  by  the  arbitrator regarding hardrock cutting were also not sustainable on the evidence on record. In the cross-appeal, it  was  submitted  by  learned  senior counsel  Shri  Harish N Salve while supporting the main part of the  judgment  under  appeal  that  the  High  Court  had committed  a  patent  error in reducing the rate of interest from 15.5 per cent to 6 per cent from the date of the  trial court’s order  till  satisfaction of the decree.  He further submitted  that  interpretation  of  Clause   1.9   by   the arbitrator  could  not  have  been  made a subject matter of objections under Section 30 of the Arbitration Act.

       In view of  the  aforesaid  rival  contentions,  the following points arise for our determination :-

       (1)  Whether the award of interest prior to the date of the reference was within the power  and  jurisdiction  of the arbitrator ?

       (2)  Even  if  it was within the jurisdiction of the arbitrator, whether Clause 1.9 barred such consideration ?

       (3) Whether such an objection could have been raised before the court in objections under Section 30 of the Act ?

       (4) Whether the reduction of interest from 15.5  per

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5  

cent  to  6  per  cent  from  the  date  of  the decree till satisfaction of the decree as ordered by the High Court  was justified ?

Point No.1

       So far  as  this  point  is  concerned,  we  note  a decision  of  the  3-Judge  Bench  of this Court in State of Orissa vs.  B.N.Agarwalla,  1997  (2)  SSC  469,  which  has clearly ruled in the light of the earlier Constitution Bench judgment  of  this  Court  in  Secretary, Irrigation Deptt., Govt.  of Orissa vs.  G.C Roy, 1992 (1) SCC  508,  that  the claim  for  interest  even  for the pre-reference period was also within the power and authority of the arbitrator  after the Interest  Act,  1978.  It is also not in dispute between the parties that in the present cases the  cause  of  action for  reference arose after coming into force of the Interest Act, 1978.  It is also not in dispute  between  the  parties that  in the present cases the cause of action for reference arose after coming into force of  the  Interest  Act,  1978. Consequently,  it  cannot  be  effectively  urged by learned senior counsel for the appellant-State that  the  arbitrator had  no  power  to grant such pre-reference period interest. The first point is, therefore, answered in affirmative.

Points Nos. 2. and 3.

       However,  it  was  vehemently contended that even if arbitrator and power to  award  interest  for  pre-reference period,  Clause  1.9  prohibited  the  consideration of such claim by the arbitrator.  Now it must be kept in  view  that the  arbitrator  has interpreted Clause 1.9 and has rejected the contention that claim of interest would not  survive  by virtue of  the  said Clause.  Shri Salve submitted that once the  arbitrator  has  so  decided,   it   was   within   his jurisdiction  to  decide  one  way or the other and when the question of interest itself was a subject matter of  dispute referred  to  him,  it was for the arbitrator to decide that question and that could not have been made subject matter of any objection under Section 30 of the Arbitration Act.    It is  not  necessary for us to closely examine this contention of Shri Salve for the simple reason that when we turn to the Clause itself, we find that even on merits  learned  counsel for  the  appellant-State  cannot  effectively  support  his contention in the light of the said Clause.  The  reason  is obvious.  The said Clause reads as under :-

                       "1.9 No claim for delayed payment         due to dispute etc.

                       No claim for interest or  damages         will be entertained by the Government with         respect  to  any  moneys or balances which         may be lying with Government owing to  any         dispute,  difference;  or misunderstanding         between the Engineer-in-charge in  marking         periodical  or  final  payments  or in any         other respect whatsoever."

       A  mere  look at the Clause shows that the claim for interest by way of damages was not to be entertained against the Government with respect to  only  a  specified  type  of amount,  namely,  any  moneys or balances which may be lying with the Government owing to any dispute, difference between

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5  

the    Engineer-in-Charge    and    the    contractor;    or misunderstanding  between  the  Engineer-in-Charge  and  the contractor in marking periodical or final payments or in any other respect whatsoever.    The  words  "or  in  any  other respect  whatsoever" also referred to the dispute pertaining to the moneys  or  balance  which  may  be  lying  with  the Government   pursuant   to  the  agreement  meaning  thereby security deposit or retention  money  or  any  other  amount which  might  have  been  with  the Government and refund of which might have been withheld by the Government.  The claim for damages or claim for payment for the work done and which was not paid for would not obviously cover any  money  which may be  said to be lying with the Government.  Consequently, on  the  express  language  of  this  Clause,  there  is  no prohibition   which   could   be   called  out  against  the respondent-contractor that he could not raise the claim  for interest  by  way  of  damages  before the arbitrator on the relevant items placed for adjudication.   In  fact,  similar contention  has  been  repelled by the aforesaid decision of the 3-Judge Bench of this Court  in  paragraphs  25  of  the Report  that under Clause 4 which was pressed in service, no interest was payable on the  amount  withheld.    The  claim which  was  made  in  that  case by Durga Parshad before the arbitrator was for the non-payment of the full amount as per final bill submitted by him and the interest so  awarded  on the  said  amount was clearly not covered by Clause 4 of the contract.  Similar is the facts  situation  in  the  present case and the working of the Clause in question is also of an identical nature.    Therefore,  the  contention  of learned senior counsel  for  the  appellant-State  that  Clause  1.9 barred the consideration of such a claim for interest cannot be sustained.    The  High Court, therefore, rightly came to the conclusion that that Clause was not  a  bar  to  such  a claim.  Further contention of learned senior counsel for the appellant that the claims regarding cutting of hardrock were wrongly  granted,  cannot  be  made  subject  matter  of  an objection under Section 30  of  the  Arbitration  Act  which could  have  been  agitated for getting any reduction of the amount as awarded by the arbitrator.    It  was  a  question purely on merits of the award which could not be agitated in objections  as  they  were  not  in  the nature of an appeal against the award before the court below.  Civil Appeal  No. 7643 of 1995 is disposed of accordingly.

Point No.4

       In  the  cross-appeal being Civil Appeal arising out of Special Leave Petition (Civil) No.6307 of  1995,  learned senior counsel for the respondent-State vehemently submitted that as  per Section 24 of the U.P.  Civil Laws (Reforms and Amendment) Act, 1976, paragraph  7-A  was  inserted  in  the First Schedule to the Arbitration Act, 1940 which barred the power  of  the  arbitrator  in granting more than 6 per cent interest on the awarded  amount  and,  therefore,  the  High Court  was justified in reducing 15.5 per cent interest to 6 per cent in the light of the said provision.  The  aforesaid contention  of the learned counsel has to be examined in the light of what the  High  Court  stated  in  para  9  of  the impugned judgment.  It has observed that when the arbitrator has found interest at the rate of 6 per cent per annum to be reasonable,  the  trial court ought to have adopted the same rate of interest for being awarded to the  contractor.    In our  view,  the  said  reasoning cannot be sustained for the simple reason that even if aforesaid Paragraph 7-A which was not pressed in  service  before  the  High  Court  could  be

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5  

resorted  to, it only barred the power of the arbitrator and not of the court.  Further, it could not be  said  that  the arbitrator  had found the interest at the rate of 6 per cent per annum to be reasonable.  In fact, he had no authority or power to go beyond 6 per cent interest.  So far as the court is concerned, it is in its discretion to award 15.5 per cent interest on the decretal amount from the date of the  decree till satisfaction  of  the  decree.   As that was within the realm of the discretionary jurisdiction of the  trial  court it  could  not  have  been  set  aside  by the High Court in appeal.  The cross-appeal will stand allowed to this  extent by  modifying  the  judgment  and order of the High Court by substituting 15.5 per cent interest instead of  6  per  cent interest per annum from the date of the decree till payment.

       Consequently, Civil  Appeal  No.    7643  of 1995 is dismissed and the Civil Appeal arising out of Special  Leave Petition (Civil)  No.    6307  of  1995  is  allowed  to the aforesaid limited extent.  In the net result,  the  impugned judgment  of  the  High  Court  is  modified  to  the extent indicated and the order of the trial court will stand wholly confirmed.  In the facts and circumstances  of  the  present case, there will be no order as to cost.

       Interim  orders  will  stand  vacated.  The security furnished by the respondent-contractor  in  compliance  with the earlier interim order will stand discharged.