14 August 1995
Supreme Court
Download

RUSTEES OF THE PORT OF MADRAS Vs ENGINEERING CONSTRUCTIONS CORPORATION LIMITED

Bench: JEEVAN REDDY,B.P. (J)
Case number: Appeal Civil 1175 of 1976


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11  

PETITIONER: RUSTEES OF THE PORT OF MADRAS

       Vs.

RESPONDENT: ENGINEERING CONSTRUCTIONS CORPORATION LIMITED

DATE OF JUDGMENT14/08/1995

BENCH: JEEVAN REDDY, B.P. (J) BENCH: JEEVAN REDDY, B.P. (J) AGRAWAL, S.C. (J)

CITATION:  1995 AIR 2423            1995 SCC  (5) 531  JT 1995 (6)    48        1995 SCALE  (4)742

ACT:

HEADNOTE:

JUDGMENT:                       J U D G M E N T B.P.JEEVAN REDDY.J.      The facts  of this  case remind  us of  what this Court observed in  M/s.Guru Nanak  Foundation V.  M/s.Rattan Singh and Sons (1981 (4) S.C.C.634):      "Interminable, time  consuming,  complex      and expensive  court procedures impelled      jurists to  search  for  an  alternative      forum, less  formal, more  effective and      speedy  for   resolution   of   disputes      avoiding procedural  claptrap  and  this      led them  to Arbitration  Act, 1940 (Act      for short).  However, the  way in  which      the  proceedings   under  the   Act  are      conducted  and   without  an   exception      challenged in  courts, has  made lawyers      laugh  and   legal  philosophers   weep.      Experience shows  and law  reports  bear      ample  testimony  that  the  proceedings      under  the   Act  have   become   highly      technical   accompanied    by   unending      prolixity, at  every stage  providing  a      legal trap to the unwary. Informal forum      chosen by  the parties  for  expeditious      disposal of  their disputes  has by  the      decisions of  the  courts  been  clothed      with    legalese     of     unforseeable      complexity.This case  amply demonstrates      the same ".      The facts speak for theselves.      The Board  of  Trustees,  Madras  Port  Trust,  invited tenders in  the year  1957 for  certain works  at the  port. Clause (4)  of the  Instructions for  tender stipulated that the tenderer  is required  to indicate clearly in the letter forwarding the  tender any deviation from the conditions and

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11  

specifications mentioned  in the  Instructions.  Clause  (7) provided that until a formal agreement was entered into, the tender together  with the  Board’s acceptance  thereof shall constitute the  binding contract  between the  parties,  The respondent submitted  its tender  on November 11, 1957 along with  a  letter  specifying  certain  deviations.  The  main deviation suggested  was  that  the  thirty  months’  period specified for  completing the  work shall be subject to such delays as are due to causes beyond their control. In case of such delays,  the respondent  claimed to  be entitled to not only extension  of time but also to compensation. It further specified that  the Board  should make  available to  it the requisite foreign  exchange  for  importing  the  plant  and machinery required  for executing the work. Soon thereafter, it was  realised by  both the  parties that foreign exchange would not  be released  to  the  respondent  for  purchasing machinery on  its own account. Then parties then agreed that the Board  should import  the  said  machinery  on  its  own account and  should  hire  it  out  to  the  respondent  for execution of  the said  work. The  respondent’s  tender  was accepted by  the Board on October 6, 1958. A formal contract was sent  by the  Board to the respondent for its signature. The   respondent    suggested   several   modification   and alternations which  according to  it were necessary to truly reflect  the   consensus  arrived   at  between   them.  The modifications  and  alternations  pertained  mainly  to  the supply of  imported plant  and  machinery  and  the  spares. Certain correspondence  passed between  the parties  but the Board refused to agree to any change in the draft agreement. On April 9, 1960 the respondent signed the agreement without incorporating the modifications suggested by it.      There  were  delays  in  importing  the  machinery.  As against a  period of  about  six  months  envisaged  by  the parties, it  took about  twelve  months  for  importing  the entire machinery.  It was hired out to the respondent and it completed the  work within  the extended period, asked by it and granted  by the  Board. The  total  contract  value  was Rupees one  crore and  sixty three lakhs. After the work was completed,  the   respondent  raised   a  dispute   claiming additional amount  on account  of the delay in supplying the machinery and  on certain  other counts.  It claimed a total amount of  Rs.14,93,654.78p. In  terms  of  the  arbitration clause contained  in the  contract, the respondent nominated Sri W.S.Krishnaswamy  Naidu, a  retired judge  of the Madras High Court  as its  arbitrator. The  Board nominated another retired Judge of the Madras High Court, Sri Somasundaram, as its nominee.  Since the  arbitrators could  not agree  among themselves, they  designated Dr.  P.V.  Rajamannar,  retired Chief Justice  of the  Madras High Court, as the umpire. The learned umpire  heard both  the parties,  took the  material adduced by  them and  made a  speaking award  on October 30, 1965.      Though the  amount claimed  by the respondent was under several heads,  the main  head - and with which alone we are concerned in these appeals - is the delay on the part of the Board in  importing the  machinery which  according  to  the respondent has caused loss to it and for which, it says, the Board is  bound to  compensate. The  Board  denies  that  it undertook  an   obligation  to  import  machinery  within  a particular period.  According to  them, the  period  of  six months’ was  only a  rough estimate or an expectation, as it may be called. They submitted that the extra payment of nine percent of  the contract  price agreed upon by the Board and the contractor  was not only intended to cover delays caused due to  causes such  as suspension  of work, failure to give

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11  

possession of  site,  failure  to  supply  in  time  primary material and  services etc.  but also  the delays,  if  any, caused in  supplying the imported machinery and spares. They denied their  liability to  compensate the contractor on any of the grounds claimed by it.      In view  of  the  statements  of  claim  filed  by  the parties, the arbitrators settled as many as fourteen issues. When the  matter was  referred to  the  learned  umpire,  he adopted the said issues and recorded the following findings: (a) Issues  1 and  2: The  offer of  the Board to import the equipment and spares was not by way of gratuitous service to the contractor as contended by the Board. (b) Issues 3 and 7: There was no undertaking by the Board to supply to  the respondent  the imported  machinery within  a period of  six months  from the  date of  acceptance of  the tender (from October 6, 1958). The Board was not responsible for the delay in the supply of plant and machinery. (c) Issue  Nos.8  and  12:  The  reservations  made  by  the contractor in respect of the disputed claims were unilateral but even so the said claims fall within the ambit of matters in  dispute   for  arbitration.  The  contractors  were  not precluded from  putting forward their claim for compensation on the  ground of  delayed  supply  of  imported  plant  and machinery. (d) Issue No.13: The matters in dispute under reference fell within the  scope of the arbitration clause contained in the agreement between the Parties. (e) Issue  No.9: The grant of extension of time by the Board was only  to relieve  the contractor from payment of penalty under the  contract and  to enable  it to draw its bills and obtain payments without audit objections. (f) Issues  10,11 and 14: The contractor was not entitled to payment of any compensation.      (The learned  umpire did  not record  any  findings  on issues 4 to 6.)      The learned  umpire  further  held  that  in  case  the respondent was  found entitled to any compensation, a sum of Rupees five  lakhs would  represent a  fair compensation for the delays in the supply of imported plant and machinery and that another  sum of Rupees one lakh would be the reasonable compensation for  the delay  on other grounds like inclement weather, break-down etc.      O.P.No. 276  of 1965  was filed  by the appellant-Board for making  the award  a rule  of the court. The respondent- contractor filed  O.P.No. 213  of 1966 for setting aside the award under  Sections 16,  30 and 33 of the Arbitration Act. The objections  raised by  the  respondent  fell  under  two heads, viz., (i) mis-conduct of the umpire in conducting the proceedings and  (ii) error  apparent on  the  face  of  the award. Both  the O.Ps.  were considered  by a learned Single Judge  of   the  Madras   High  Court,  Palaniswamy,J.,  who substantially agreed  with the  reasoning contained  in  the award and  made it  a rule  of  the  court  over-ruling  the objections raised  by the respondent. The respondent carried the matter in Letters Patent Appeal to the Division Bench of the High Court which allowed the appeal, set aside the award and remitted  the matter  to the  learned umpire  for  fresh consideration of  the matter in the light of their judgment. Since the  judgment of  the  Division  Bench  is  questioned herein, it is necessary to notice first the several findings recorded by the Division Bench:      (i) the  learned umpire  was right  in holding that the respondent-contractor was  entitled to  and was  well within its  rights  in  seeking  a  decision  on  their  claim  for compensation  under  the  disputed  heads  by  reference  to

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11  

arbitration.      (ii) The  learned umpire  was equally  right in holding that the  undertaking by  the appellant_Board  to import the machinery  and  parts  was  not  a  gratuitous  one  but  an undertaking which  had the effect of creating certain rights and obligations.      (iii) the learned umpire was also right in holding that the supply  of imported  machinery did  not fall  within the ambit of  ’services’ contemplated by the contract, though it is true that the learned umpire did not record a  finding on the question  whether the extra payment of nine percent over the contract  price was  relatable to the respondent’s claim for compensation  on account  of the  delay in supplying the imported machinery.      (iv)   It is  true that  the claim  of the  respondent- contractor did  not arise  from the  contract but  only from other correspondence  that passed  between the parties. Even so, "the  undertaking by  the Board  to secure the plant and equipment from  abroad was  undoubtedly an obligation in the nature of  a promise  and was  an event which had a material bearing on the completion of the project and the time-factor relating to  the contract.  So much depended upon the making available of  the plant  to the Contractors, as without such machinery, some  of the  items of  the contract  work  could never  have  been  executed  by  the  Contractors.  In  such circumstances, the  undertaking given by the Board to import and supply  the plant  cannot be  left out of reckoning when the rights  and obligations  of the  contracting parties  in terms of  the contract  arise for determination. Even so, it would  be   futile  for   the  Board  to  contend  that  its undertaking was  not related to any time-stipulation and its obligation was an unfettered one". The letter written by the Chief Engineer  (Exh.33) did state "that it would take about six  months  from  the  date  of  intimation  of  order  for procurement of  .........machinery". In view of this letter, the Board  cannot now  contend that  its undertaking "was an unfettered one  and free of all time limit. Even if the time stipulation of  six months  is not  to be rigidly construed, yet the  rule in Section 46 of the Contract Act would govern the situation  and the  Board must  be held  obliged to make available the machinery within a reasonable time. A delay of 12-1/2 months  in the  supply of  the  machinery  which,  as already stated  above,  has  been  certified  by  the  Chief Engineer of  the  Board,  can  never  be  construed  as  due compliance with the obligations within a reasonable time".      (v)    "on  an analysis of the situation, we are of the opinion that  the undertaking  given by  the Board to import the plant  and equipment  and make  them  available  to  the Contractors was  in the nature of an implied undertaking and though, in  the very  nature of  things, the Board could not have supplied  the machinery  within a  precise and accurate time limit,  yet the  Board was under a bounden duty to have supplied the  machinery within  a reasonable  time. When the Board failed  to supply  the machinery  within a  reasonable time, the  Contractors were  left with no other alternatives but to  complete the  work and  then call  upon the Board to compensate them for the loss occasioned by it."      (vi)  The   respondent-contractor  was   in  error   in contending that  the failure  of the  Board  to  supply  the machinery within  the prescribed  time was  a breach  of  an express provision  of the  terms  of  contract  between  the parties. It  is really  a breach of an implied promise which is indeed the stand taken by the counsel for the respondent- contractor before  them (Division  Bench). On  the basis  of implied contract  theory, the  stand of  the respondent  "is

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11  

unassailable and  the Board  has  necessarily  to  face  the situation which  developed on  account of  its inability  to supply the  machinery in  time and the resultant loss to the Contractors".      On the basis of the above findings, the judgment of the learned Single  Judge was  set  aside  and  the  matter  was remitted to  the learned umpire for a fresh consideration in the light of the said judgment.      The findings  recorded by  the Division  Bench  clearly disclose that  they set  aside the award made by the learned umpire not  on the  ground mis-conduct  on the  part of  the learned umpire but on the ground that the learned umpire did not  correctly  appreciate  the  nature  of  the  obligation undertaken   by the  Board in  the matter  of importing  and supplying the machinery to the respondent for completing the work. The  Division Bench  recognised that there was no firm commitment by  the Board  to import and supply the machinery within six  months from the date of acceptance of the tender or from  the date  of intimation of order for procurement of the said  machinery, as  the case  may  be,  yet  it  found, applying   the    principle   of    Section   46*   of   the ------------------------------------------------------------ *Section  46   of  the  Contract  Act  reads:"Where  by  the contract, a  promisor is  to  perform  his  promise  without application by  the promisee, and no time for performance is specified,  the   engagement  must  be  performed  within  a reasonable time . EXPLANATION:  The question what is a reasonable time is , in each particular  case, a question of fact."Contract Act that the said  obligation had to be performed within a reasonable time. It  opined that  since the  machinery was not supplied within, what  ins opinion  was,  the  reasonable  time,  the contractor is entitled to compensation for the loss suffered by its   opinion was, the reasonable time, the contractor is entitled to  compensation for  the loss  suffered by it. The Bench opined  that inasmuch  the respondent  was obliged  to maintain his  staff and  other paraphernalia  for some extra period on  account  of  the  said  delay  in  supplying  the machinery, he must have incurred extra expense, for which he must be reimbursed by the appellant.      We called  upon the  learned counsel for the respondent to tell us on which recognised ground did the Division Bench set aside  the award.  This was  for  the  reason  that  the Division Bench did not itself specify the ground on which it was   setting aside  the award.  The answer  of the  learned counsel was, "error apparent on the face of the award". This necessitates an  examination of  the parameters  of the said ground particularly in the context of a reasoned award.      In the  decision, frequently  referred to  in the later decisions both in England and in this country,    Hodokinson v. Fernie (140 English Reports 712), Williams,j., observed:      "I am  entirely of the same opinion. The      law has for many years been settled, and      remains so  at this  day, that,  where a      cause  or   matters  in  difference  are      referred to  an  arbitrator,  whether  a      lawyer or  a layman,  he is  constituted      the  sole   and  final   judge  of   all      questions both  of law and of fact. Many      cases  have   fully   established   that      position,   where   awards   have   been      attempted to  be set aside on the ground      of  the   admission  of  an  incompetent      witness or  the rejection of a competent      one. The  court has invariably met those

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11  

    applications   by   saying,   you   have      constituted your  own tribunal;  you are      bound  by   its   decision.   The   only      exceptions to that rule, are cases where      the award is the result of corruption or      fraud, and  one other,which though it is      to be regretted, is now, I think, firmly      established, viz., where the question of      law necessarily  arises on  the face  of      the   award,    or   upon   some   paper      accompanying and  forming  part  of  the      award. Thought  the  propriety  of  this      latter may very well be doubted, i think      it may be considered as established."      This decision  was followed by the privy Council in yet another of_cited  decision, Champsey  Bhara and  Company  V. Jivraj Balloo  Spinning  and  Weaving  Co.Ltd  (A.I.R.  1923 P.C.66). The Privy Council observed:      "An error  in law  on the  face  of  the      award means,  in their  Lordship’s view,      that you  can find  in the  award  or  a      document actually  incorporated thereto,      as for  instance a  note appended by the      arbitrator stating  the reasons  for his      judgment, some  legal proposition  which      is the  basis of the award and which you      can then  say is  erroneous. It does not      mean that  if in a narrative a reference      is made  to a  contention of  one party,      that opens the door to seeing first what      that contention  is ,  and then going to      the contract on which the parties rights      depend to  see  if  that  contention  is      sound. Here  it is  impossible  to  say,      from what  is shown  on the  face of the      award,  what   mistake  the  arbitrators      made. The  only  way  that  the  learned      judges have  arrived at finding what the      mistake was  is by  saying: inasmuch  as      the arbitrators  awarded so-and-so’  and      inasmuch as  the letter  shows that  the      buyer   rejected    the   cotton,    the      arbitrators can  only  have  arrived  at      that result  by totally  misinterpreting      Rule 52  But they  were entitled to give      their own  interpretation to  Rule 52 or      any other  article, and  the award  will      stand unless,  on the  face of  it, they      have  tied   themselves  down   to  some      special legal  proposition  which  then,      when examined, appears to be unsound."      Both the  above decisions  were cited  with approval by the constitution  Bench of  this Court in Raipur Development Authority  V.   Contractors  (1989   (3)   S.C.R.144).   The Constitution Bench clarified that "the ground arising out of an error of law apparent on the face of the award prima face appears to  fall either  under Section 16(1) (c) of the Act, which  empowers   the  Court  to  remit  the  award  to  the arbitrator where  an objection  to the legality of the award if it is otherwise invalid’"Certain earlier decision of this Court supporting  the said view were then referred to by the Constitution Bench,  which it  is unnecessary  for us to re- produce.      The above  decisions  make  it  clear  that  the  error apparent on  the face  of the  award contemplated by Section

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11  

16(1) (C) as well as Section 30(c) of the Arbitration Act is an error of law apparent on the face of the award and not an error of  low on the face of the award means an error of law which can  be discovered  from the  award itself  or from  a document  actually   incorporated  therein,     A   note  of clarification may be appended viz., where the parties choose to refer  a question  of law  as  a  separate  and  distinct matter, then  the Court cannot interfere with the award even if the award lays down a wrong proposition of law or decides the question  of law referred to it in an erroneous fashion, Otherwise, the  well settled  position is that an arbitrator "cannot ignore  the law  or mis-apply it in order to do what he thinks is just and reasonable". [See Thawardas Perumal v. union of India (1955 (2) S.C.R.48)].      We may  now refer  to a  few decisions to point out how the said concept of error of law apparent on the face of the award has  been understood  in the case of a reasoned award. In other  words, we  have to  examine whether  an  erroneous interpretation placed  by the  arbitrator upon  the relevant terms/clauses of  the contract can be treated as an error of law apparent on the face of the award. In Raipur Development Authority, the  Constitution  Bench  opined  that  an  award cannot be  set aside in India on the ground that it does not contain reasons therefor. But, at the same time,it observed, "of course, where reasons are given in support of the awards and those reasons disclose any error apparent on the face of the record  people have  not refrained from questioning such awards before the courts". The said principle was reiterated by a three judge Bench of which of one us (S.C. Agrawal, J.) was a member, in S.Harcharan Singh V. Union of India (A.I.R. S.C.945).   Referring to  Raipur Development  Authority, the observed:      "It has  been held that an arbitrator or      umpire is  under no  obligation to  give      reasons  in   support  of  the  decision      reached  by   him   unless   under   the      arbitration agreement  or  the  deed  of      submission he  is required  to give such      reasons and  if the arbitrator or umpire      chooses to  give   reasons insupport  of      his decision  it is open to the Court to      set aside  the award if it finds that an      error of  law has  been committed by the      arbitrator or  umpire on the face of the      record on going through such reasons..."      The Court Further observed:      "While  considering  the  claim  of  the      appellant the arbitrator was required to      consider the  terms of  the contract and      to construe the same. It was, therefore,      permissible  for   the   arbitrator   to      consider whether  C1.12 of  the contract      enables   the    Engineer-in-charge   to      require   the   appellant   to   execute      additional work  without any  limit or a      reasonable limit should be placed on the      quantity of  the additional  work, which      the appellant may be required to execute      at the rate stipulated for the main work      under   the   contract   ............The      Arbitrator  was   entitled  to   do   so      (awarding  additional   amount  to   the      contractor) on  the construction  placed      by him  on C1.12  of the  contract and ,      and therefore, it cannot be said that in

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11  

    awarding the  sum of Rs.52,800/- for the      additional work, Arbitrator has exceeded      his  jurisdiction   and  the   award  is      vitiated by an error of jurisdiction."      This was  so observed  in the  context of the principle that "the  jurisdiction of  the arbitrator is limited by the reference and if the arbitrator has assumed jurisdiction not possessed by  him, the  award to  the extent  to which it is beyond the  arbitrator’s jurisdiction  would be  invalid and liable to be set aside".      In Hindustan  Construction Co.  Ltd. v.  State of Jammu and  Kashmir  (1992  (4)  S.C.C.217),  a  Three-Judge  Bench comprising one of us (B.P. Jeevan Reddy, J.), dealing with a non-speaking award  observed thus:  "even if,  in fact,  the arbitrators and  interpreted the  relevant  clauses  of  the contract in  making their  award on  the impugned  items and even if  the interpretation  is erroneous,  the Court cannot touch the  award as  it is  within the  jurisdiction of  the arbitrators  to   interpret  the   contract.   Whether   the interpreters is  right or  wrong, the parties will be bound; only if  they set  out their  line of  interpretation in the award and  that is found erroneous can the Court interfere". The  above   principle,  of   course,  is   subject  to  the proposition aforesaid,  viz., that  the Arbitrator  being  a creature of  the  contract  must  operate  within  the  four corners of  the contract  and cannot travel beyond it either by mis-interpreting the terms of the contract or otherwise.      In Bijendra  Nath Srivastava  v. Mayank  Srivastava and Ors. (1994 (6) S.C.C.117), it was held by us:      "If the  arbitrator or umpire chooses to      give reasons  in support of his decision      it would  be open  to the  court to  set      aside the  award if  it  finds  that  an      error of  law has  been committed by the      arbitrator umpire  on the  basis of  the      recording   of    such   reasons.    The      reasonableness of  the reasons  given by      the  arbitrator   cannot,  however,   be      challenged. The  arbitrator is  the sole      judge of the quality of the evidence and      it will  not be  for the  court to  take      upon itself the task of being a judge of      the evidence  before the arbitrator. The      court should  approach an  award with  a      desire  to   support  it,   if  that  is      reasonably  possible,   rather  than  to      destroy it  by calling  it illegal. [See      Champsey Bhara  and Co. v. Jivraj Balloo      Spq. and Wvg. Co. Ltd. (AIR 1923 PC 66);      Jivarajbhai     Ujamshi     Sheth     v.      Chintamanrao Balaji  (1964 (5) SCR 480);      Sudarshan Trading  Co.v. Govt. of Kerala      (1989 (2)  SCC 38);  Raipur  Development      Authority v. Chokhaman Contractors (1989      ((2) SCC  721); and  Santa Sila  Devi V.      Dhirendra Nath Sen (1964 (3) SCR 410)."      Reference may  also be  made  to  the  observations  in Champsey  Bhara,   quoted  hereinabove,   holding  that  the arbitrators were  entitled to place their own interpretation upon Rule  52 or  any other  article (of  the Bombay  Cotton Trade Association  Limited) and  that the  award would still stand unless  on the  face of  it, they have tied themselves down to  some legal  proposition which when examined appears to be unsound.      The proposition that emerges from the above decision is

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11  

this: in  the case  of  a  reasoned  award,  the  court  can interfere if  the award  is based  upon a proposition of law which is  unsound in  law. The  erroneous proposition of law must be established to have vitiated the decision. The error of law  must appear  from  the  award  itself  or  from  any document or note incorporated in it or appended to it. It is not permissible  to travel  beyond and consider material not incorporated in or appended to the award. Now let us examine the award  concerned herein from the above point of view and see whether it suffers from any error or law apparent on the face of  the award.  We have  gone through  the award of the learned umpire-  a man  of great  learning and eminence, Dr. P.V. Rajmannar - very carefully. All that the learned umpire has done  is to refer extensively to the correspondence that passed between  the parties  and the  other material  placed before him and infer therefrom that the appellant- Board did never make  a firm  commitment nor  did it ever undertake to import and  supply the  machinery within a particular period much less  within a period of six months. The learned umpire remarked:      "There is  no mention  of this period of      six months  in the  relevant minutes  of      the meetings  of the  Tender  Committee;      but it  is fairly clear that this period      was mentioned  during  the  discussions.      The Board’s  case which  we find set out      in some  of their  letters is  that  the      period  of   six  months   was  only  an      approximate  time   within  which   they      expected the  plant and  machinery might      be available.  But the  Board would  not      and  did  not  undertake  definitely  to      supply the plant and machinery not later      than six  months from 6.1.1058, the date      of the  order to commence work. There is      no oral evidence relating to this matter      and there  is no  sufficient material in      the  correspondence   to   warrant   the      conclusion that  there was a term of the      contract which  bound the  Port Trust to      deliver to the Contractors the plant and      machinery within six months. Even at the      time when  the two alternative proposals      were placed  before the  Contractors, it      was impressed on them that the proposals      for the Board itself to import the plant      and  machinery   would  involve   delay.      Obviously, it  was not  for the Board to      be certain  of the  extent of the delay.      The Board  might have  thought  that  it      would not  take longer  than six  months      for the  arrival of  the equipment. I am      unable it find any default or remissness      on the part of the Board in taking steps      to get  the equipment. It was as much to      their interest  as to  the  Contractor’s      that the  plant should  be available  as      early  as   possible.   Otherwise,   the      completion of the work would be delayed.      There is  no suggestion  of any malafide      act or  negligence on  the part  of  the      Board  in   the   procurement   of   the      equipment. It  should also  be mentioned      that  the  Contractors  themselves  took      some  time   before  they   could   give

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11  

    detailed specifications.  Taking all the      circumstances into consideration, I hold      that there  has been  no breach  of  any      Board because of the late arrival of the      plant and machinery."      The finding  of the  learned umpire  is thus based upon the material placed before him by both the parties and was a pure finding  of fact.  Now, the Division Bench does not say that the  correspondence that  passed between the parties or that the materials placed before the arbitrator and referred to in  the award establishes that the Board undertook a firm commitment to  supply the  machinery within  six months from the date  of acceptance  of the  tender (October  6, 1958) - assuming that  it could  say so.  (We are, of course, of the firm opinion  that it  was not open to the Division Bench to re-appraise the  evidence/material before the learned umpire and come top a different finding of fact.) What the Division Bench says is that though there was no such firm commitment, "the Board  was under  a bounden  duty to  have supplied the machinery within  a reasonable  time" applying the principle of Section  46 of the contract Act. The Bench finds that the delay that  has  occurred  in  supplying  the  machinery  is unreasonable and  on that basis holds that the contractor is entitled to  compensation. With great respect, we are unable to agree  with this  approach. Apart from the fact that this theory of  duty to  supply within  a reasonable time was not put  forward  before  the  learned  umpire-  it  is  neither referred to  by the  learned umpire,  nor does it constitute the basis of his award - the finding recorded by the learned umpire (viz., that the period of six months was only a rough estimate, an  expectation, within which the Board thought it could import  the machinery) is inconsistent with the theory of obligation  to  import  within  a  reasonable  time.  The learned  umpire   has  also   found  that   the  contractors themselves took  some time  before they  could give detailed specifications of  the  machinery  and  parts  required  for carrying out  the work. The Bench did not also find - it was not even  suggested by anyone - that the Board was guilty of any deliberate  delay or  of any  negligence or  that it was remiss  in   taking  steps  required  for  importing  and/or importing and/or supplying the machinery. The master did not lay in its hands. In such a situation, there was no room for importing the  theory of  reasonable time  and for punishing the  Board  for  something  of  which  it  was  not  guilty. Secondly, the explanations to Section 46 makes it abundantly clear that  "the question  what is  a reasonable time is, in each particular  case, a  question of  a fact". The question whether the  machinery was  imported  and  supplied  to  the contractor within  a reasonable  time  or  not  was  thus  a question of  fact  and  not  a  question  of  law.  No  such contention was  raised before  the learned umpire nor did he record a  finding on the said aspect. it was not open to the Division Bench  to record  the said finding of fact, for the first time,  at the  stage of letters patent appeal and hold on that basis that the Board is guilty of not performing its obligation within a reasonable time. In short, this is not a case where  the Division  Bench has interfered on the ground that the  award suffers from an error of law apparent on the face of  award. This is a case where a new ground - and that too factual  in nature  - was made out for the first time at the letters patent appeal stage for setting aside the award, a reading  of the  judgment of the Division Bench shows that the Bench  approached the  matter as  if it  was sitting  in first appeal  over the  award. The  judgment does  not  even indicate on  which recognised ground is it setting aside the

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11  

award. It  does not say either that the award is vitiated by an error  of law  apparent on the face of it nor does it say that the  learned umpire  was guilty  of any  misconduct  in conducting the  proceedings or otherwise. We are of the firm opinion that this could not have been done.      For the  above reasons,  the appeals  are allowed,  the impugned judgment of the Division Bench is set aside and the judgment of  the  learned  Single  Judge  is  restored.  The respondent shall pay the costs of the appellant throughout.