12 August 1977
Supreme Court
Download

ORISSA MINING CORPORATION LTD. Vs PRANNATH VISHWANATH RAWLLEY

Bench: KAILASAM,P.S.
Case number: Appeal Civil 769 of 1976


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6  

PETITIONER: ORISSA MINING CORPORATION LTD.

       Vs.

RESPONDENT: PRANNATH VISHWANATH RAWLLEY

DATE OF JUDGMENT12/08/1977

BENCH: KAILASAM, P.S. BENCH: KAILASAM, P.S. CHANDRACHUD, Y.V.

CITATION:  1977 AIR 2014            1978 SCR  (1) 295  1977 SCC  (3) 535  CITATOR INFO :  R          1979 SC1977  (6)

ACT: Arbitration  Act,  1940 (10 of  1940)-S.  20-Scope  of-Extra claim, over and above the claim made in the plaint and shown in  the reference, made before the  arbitrator-Arbitrator-If competent  to entertain fresh claim without  reference  from court.

HEADNOTE: The  respondent entered into a contract with  the  appellant for  the  transport of iron ore from quarry Nos.   1  and  2 being  worked out by the appellant, to the  railway  siding. As  the  instance  of the  appellant  the  respondent  later transported  iron  ore  from  quarry No.  5  situated  at  a distance of about 2 KM from the other two quarries.   Having failed  to recover from the appellant the extra  cost  which was  Rs.  68,582 for transport and a sum of Rs.  25,000  for constructing a road between quarry Nos.  1 and 2 and  quarry No.  5,  the respondent filed in the  court  of  subordinate Judge  an  application under s. 20 of the  Arbitration  Act, 1940.  The dispute was referred to a sole arbitrator. Before  the  arbitrator the respondent made a claim  of  Rs. 68,582, apart from the claim for an identical amount made in the  plaint.   The  arbitrator  disallowed  the  claim   for construction of the road but allowed the additional claim of the respondent and gave an award for a sum of Rs. 1,16,570. The  appellant’s  application alleging that  the  arbitrator acted without jurisdiction in allowing the additional  claim of  Rs. 68,582 was rejected by the Subordinate Judge on  the ground  that there was no error apparent on the face of  the record   and  that  the  arbitrator  did  not   exceed   his jurisdiction. The High Court dismissed the appellant’s appeal. Allowing the appeal to this Court, HELD  :  When an agreement is filed in court  and  order  of reference is made, then. the claim as a result of the  order of  reference  is  limited to a particular  relief  and  the arbitrator  cannot  enlarge the scope of the  reference  and entertain fresh claims without a further order of  reference from the court. [299H] In  the  instant  case  the  arbitrator  has  exceeded   his

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6  

jurisdiction  in embarking on the extra claim.  put  forward before  him  by  the respondent.  When the  claim  had  been specified in the plaint and when the reference was  confined to  the claim made in the plaint, the arbitrator would  have to restrict his award only to that claim. [299F] The  High  Court has misconstrued the claim.  There  was  no claim for transport of iron ore between quarry Nos.  1 and 2 and the railway siding; the only claim was for the transport for the extra distance. [299A]

JUDGMENT: CIVIL APPELLATE JURISDICTION : Civil Appeal No. 769 of 1976. Appeal  by Special Leave from the Judgment and Decree  dated 20-2-76 of the Orissa High Court in M.A. 75/75. K.   Sawhney and M. K. Garg for the Appellant G.   B.  Pai,  Miss  Uma  Mehta and  R.  K.  Mehta  for  the Respondent. The Judgment of the Court was delivered by KAILASAM,  J.-This appeal is preferred by the Orissa  Mining Corporation  Ltd., (a Government of Orissa  undertaking)  by special 296 leave  against  the judgment and decree dated  February  20, 1976  of  the High Court of Orissa whereby  the  High  Court upheld  the  judgment  of the  Subordinate  Judge,  Rourkela refusing to set aside the award of the arbitrator  directing payment of certain moneys to the respondent herein. The respondent is a partnership firm carrying on business of transport, mining loading and unloading etc. with its office at Rourkela.  The appellant called for a tender for the work of raising of iron ore in Khandadhar Mines and  transporting it  to Barsuan Railway siding, including wagon loading.   An agreement  was entered into between the, appellant  and  the respondent for a period of one year with effect from May 25, 1971.  The estimated value of the contract was Rs. 6.77,040. The respondent under the terms of the contract was  required to  work  in  quarry Nos. 1 and 2 in  Khandadhar  Mines  but during  the progress of the work, on the directions  of  the appellant, the respondent worked in quarry No. 5 also  which was at a distance of about 2 K.M. from quarry Nos. 1 and  2. As  the  respondent had to cover an extra  distance  between quarry  Nos. 1 & 2 and quarry No 5 he demanded extra  cost for  the transport.  The respondent also demanded  cost  for construction of a road at the schedule rate provided by  the State  P.W.D., Orissa, and submitted two bills, Bill  No.  1 dated  March 31, 1972 and Bill No,. 2 dated May 1, 1972  for Rs. 62,477.50 and Rs, 6,104.60 respectively amounting to Rs. 68,582.00  in  all for the extra load  in  transporting.   A claim was also made towards the cost of constructing a  road from  quarry No. 5 for Rs. 25,000.  As in spite of  repeated reminders  the  appellant  did not pay  for  the  bills  the respondent  called upon the appellant to refer the  disputes for  arbitration according to the contract.  The  respondent filed an application under section 20 of the Arbitration Act for  a direction to the appellant to file the  agreement  in court  and for the appointment of a Superintending  Engineer of  the State P.W.D. as the sole arbitrator and a  reference to  him to give his award on the dispute.   The  respondent, for  the purpose of Court fee and jurisdiction,  valued  the suit  at Rs. 93,582, The Subordinate Judge, Rourkela,  after notice  to  the  appellant and  after  hearing  the  parties ordered "that the said agreement be filed, and it is further ordered  that the following matters in difference  specified

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6  

in the said agreement No. 4/F2 of 1971 arising in this  suit namely for demand of payment of Rs. 93,582.00 on account  of raising iron ore from quarry No. 1 and 2 at Khandadhar  Mine and  transporting  the same, to the Barsuan  Railway  siding including  loading of wagons and also for the same  work  as per  the subsequent order in respect of quarry No.  5  which was at a distance of 2 kilometers away from quarry No. 1 and 2 and for extra charges for this extra load of  transporting and for construction of a road from quarry Nos.  1 and 2  to the, quarry No. 5 be referred for determination...... of the Arbitrator." The  arbitrator on receipt of the order of reference  issued notice  to  the  parties calling upon  them  to  file  their respective  statements  and  the  documents  on  which  they intended  to rely on and to produce witnesses.  The  parties filed their respective statements and the arbitrator took up the hearing of the dispute.  The respondent in  297 these proceedings made a claim of Rs. 68,582 under the  head "4.  Extra as the distance came to 14 Km. after verification from the same quantity mentioned in the Bill No. 1 and  11." The   arbitrator  inspected  the  site  and   measured   the distances.       Regarding the claimof   Rs. 25,000  for construction of the road the arbitrator found that     the respondent is not entitled to it and rejected the claim. Regarding the claim for transport of the iron ore for the extra  distance  from quarry No. 5, the respondent  made  an additionalclaim     for Rs. 68,582 apart from the claim which he made in the plaintunder Bill Nos.  1 and 11  for Rs. 68,582 on the ground that the extra distance came to 1.4 Kms.  after verification.  The arbitrator found  the  actual distance  between  quarry  No.  1 and 2  and  quarry  No.  5 approximately  1.70 Kms. and allowed a sum of  Rs.  1,16,570 under this head.  He also directed the appellant to  release the  security  deposits and earnest money amounting  to  Rs. 32,954.48  and  pay the respondent on or before  August  31, 1974.  The award also provided that the appellant shall  pay interest  to the respondent at the rate of six per cent  per annum  on the amount of award and on the amount of  security and earnest money from the date of the passing of the  award i.e. May 31, 1974. Aggrieved  at this award the appellant filed an  application before  the Subordinate Judge, Rourkela, the court that  had made  the  reference to arbitration, for setting  aside  the award  or  in the alternative for remitting  the  award  for further consideration various contentions were raised in the application.  It is material for this appeal to ,refer  only to  the main ground of attack on the award, namely that  the arbitrator  had traversed beyond the reference made  by  the court by its order of reference in that though the claim was only  for  Rs.  93,582  inclusive  of  the  claim  for  road construction  for  Rs.  25,000 which was  negatived  by  the arbitrator, he acted without jurisdiction    in allowing any claim overRs. 68,582.It was also contended that   the arbitrator was in errorin  directing  the  return  of  the security deposits and earnest money. The Subordinate Judge, Rourkela, by his order dated February 11, 1975, found that there was no error apparent on the face of  the record which may make the, award unsustainable.   It also   found  that  the  arbitrator  did  not   exceed   his jurisdiction  and decreed the suit as per the terms  of  the award., Dissatisfied  with  the order of the Subordinate  Judge  the appellant,  Orissa  Mining  Corporation Ltd.,  took  up  the matter  in  appeal to the High Court of  Orissa.   The  High

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6  

Court  confirmed the order of the Subordinate Judge  holding that  the  order  of  reference made by  the  court  to  the arbitrator Was not only in respect of the respondent’s claim for Rs. 93.582 on account of raising of iron ore from quarry Nos.   1 and 2 and transporting the same to Barsuan  rialway station  but  also for the same work as per  the  subsequent order in respect of quarry No. 5 which was at a distance  of 2  kilometres  away  from quarry Nos.  1  and  2.  The  main contention  that was raised before the High Court  was  that the  reference to the arbitrator being for  determining  the correctness of the respondent’s claim of Rs. 93,582, 8-- 768SCI/77 29 8 only  the  arbitrator  went  beyond  his  jurisdiction   and authority  by  giving  an award  for  Rs.  1,16,570  towards transportation  charges  in favour of the  respondent.   The direction  as  to the refund of the  security  deposits  and earnest money was also challenged. The  High  Court held that "In the order  of  reference  Rs. 93,582  has  been  referred to as a dispute  on  account  of raising iron ores from quarry Nos. 1 and 2 and  transporting the same to Barsuan railway siding.  The dispute relating to extra claim on account of raising and transporting iron ores as per the, subsequent order from quarry No. 5 has also been specifically  referred to the arbitrator as it appears  from the  order of reference.  The correctness of  the  reference order  not  having been challenged the same is not  open  to question." It further held that "it is futile, to argue that the  reference made to the arbitrator was only  confined  to the respondent’s claim of Rs. 93,582 and that the arbitrator in   awarding  Rs.  1,16,570  exceeded  his  authority   and jurisdiction." We feel that the High Court has  misconstrued the  claim.   There was no dispute in regard to  raising  of iron ore from quarry Nos. 1 and 2 and transporting it to the railway  siding.  The whole dispute was regarding the  claim for  transporting the iron ore for the extra  distance  from quarry No. 5. Paragraphs 5, 6 and 7 of the plaint make  this position   clear.   Paragraph  5  states  that   while   the respondent was executing the work in quarry Nos.  1 and 2 he was ordered to work in quarry No. 5 which was at a  distance of  about  2  Kms from quarry Nos.  1 and  2.  According  to paragraph  6  the  respondent demanded extra  cost  for  the transport  from the said quarry as the  distance  increased. Paragraph   7  states  that  accordingly   the,   respondent submitted  bill  No. 1 dated March 31, 1972 and bill  No.  2 dated  May 1, 1972 making a total claim of Rs. 68,582.   The point  of attack on the award was therefore missed  by  the. High  Court.  it was that while the total  claim  under  the plaint  regarding  the  transport  of  extra  distance   was confined  to Rs. 68,582 and the reference to the  arbitrator was  also for the same amount, the arbitrator  acted  beyond the  scope  of the arbitration in taking  into  account  the claim  which was put forward by the respondent for an  extra sum  of  Rs. 68,582.  It was sought to be contended  by  Mr. Pai,  the learned counsel for the, respondent,  that  though the  plaint  claim was confined to Rs. 68,582 the  order  of reference is wider in scope and included other claims beyond the claim for Rs. 93,582.  The order of reference is  rather vague and not clear and is in the following terms :               "     and  it  is  further  ordered   that the               following  matters in difference specified  in               the said agreement No. 4/F2 of 1971 arising in               this suit namely for demand of payment of  Rs.               93,582  on  account of raising iron  ore  from               quarry  Nos.  1 and 2 at Khandadhar  Mine  and

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6  

             transporting  the same to the Barsuan  Railway               siding  including loading of wagons  and  also               for the same work as per the subsequent  order               in  respect  of quarry No. 5 which  was  at  a               distance of 2 K.M. away from quarry Nos. 1 and               2 and for extra charges for this extra load of                             transporting......." The  order of reference appears to have been an  attempt  by the  court to put all the reliefs claimed for in the  plaint in one sentence.  As  299 admittedly there was no claim for transport of the iron  ore between quarry Nos. 1 and 2 and the railway siding, the only claim  was for the transport of the iron ore for  the  extra distance.   The  view of the High Court was therefore  on  a misunderstanding of the relief prayed for by the  respondent in the plaint. Mr.  Pai while admitting that the reference to:  arbitration was  only as regards the transport of the iorn ore  for  the extra distance submitted that the claim was not confined  to Rs. 93,582 only but should be understood as a claim for  the extra  transport which may amount to more than  Rs.  93,582. We  refrain from going into the merits of the claim for  not only the extent of the extra distance covered is in  dispute but  also  the charges for transport for a  kilometer.   The plea of the respondent in that while he, submitted Bill Nos. 1 and 2 and claimed Rs. 68,582, the Bills were on the  basis that  the  extra distance was only 1 K.M. but  actually  the distance  was  2  Kms. and therefore he  claimed  twice  the amount.   The respondent submitted that the distance  should be  construed as 2 Kms. though it was found to be  1.4  Kms. On behalf ,of the appellant it was submitted that this  plea should not be entertained as, the original Bills were on the basis  of 2 Kms. and as the distance has been proved  to  be shorter he would not be entitled even to the claim made,  in the plaint.  The contentions on the merits need not be  gone into. On a reading of the plaint, we are, satisfied that the claim for  transporting  the iron ore for the  extra  distance  is limited  to Rs. 68,582 ,and the whole claim after  including the  claim for construction of the road is confined only  to Rs.  93,582.   The arbitrator having disallowed  Rs.  25,000 being  the  claim for construction of the road  should  have confined  his  award  only to.  Rs. 68,582.   The  claim  of additional  Rs.  68,582 before the  arbitrator  was  clearly beyond the order of reference which incorporated the reliefs prayed for in the plaint by the respondent herein.  It would have  been  different if the entire claim  relating  to  the transport  of the iron ore for the extra distance  was  made without specifying the amount of claim.  When the amount has been.  specified  in the plaint and when  the  reference  is confined  to  the claim made in the plaint,  the  arbitrator would have to restrict his award only to the claim.  We  are satisfied that in this case the arbitrator has exceeded  his jurisdiction  in embarking on the claim that was  the  first time  put  forward before him by the respondent.   There  is therefore an error ,apparent on the face of the award. Section  20(1) of the Arbitration Act, 10 of 1940,  provides that where a difference has arisen and where any person have entered into an arbitration agreement they may apply to  the court  having  jurisdiction  in  the  matter  to  which  the agreement  relates,  that the agreement be filed  in  court. Sub-section (4) to section 20 provides that the court  shall order the agreement to be filed, and shall make an order  of reference to the arbitrator appointed by the parties.   When

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6  

an  agreement  is filed in court and order of  reference  is made then the claim as a result of the order of reference is limited  to  a particular relief and the  arbitrator  cannot enlarge the scope of the reference and entertain fresh 300 claims without a further order of reference from the  court. On  a construction of section 20 of the Arbitration Act  the plea  on behalf of the appellant will have to  be  accepted. In  the circumstances of the case we do not think  that  the award  should be set aside,’ as the learned counsel for  the appellant has also no objection in accepting the award in so far as it relates to Rs. 68,582.  We feel that the award  to the  extent of Rs. 68,582 and interest at the rate of 6  per cent  per  annum from the date of the  award  be  confirmed. Regarding  the direction as to return of  security  deposits and  earnest money, as it is not the case of  the  appellant that the respondent is not entitled to the amount, we do not feel  called upon to interfere with the order directing  the appellant to pay the, amount to the respondent with interest at  6%  per annum from the date of the award  i.e.  May  31, 1974.  The parties will bear their own costs. P.B.R. Appeal allowed, 301