M/S. UNISSI (INDIA) PVT. LTD. Vs P.G. INSTITUTE OF MED. EDN. & RESEARCH
Bench: TARUN CHATTERJEE,DALVEER BHANDARI, , ,
Case number: C.A. No.-006039-006039 / 2008
Diary number: 6950 / 2006
Advocates: KAILASH CHAND Vs
ARPUTHAM ARUNA AND CO
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6039 OF 2008 (Arising out of SLP(C) No. 9204 of 2006)
M/s. Unissi (India) Pvt. Ltd. …Appellant
VERSUS
Post Graduate Institute of Medical Education & Research …Respondent
J U D G M E N T
TARUN CHATTERJEE,J.
1. Delay in filing this special leave petition is
condoned.
2. Leave granted.
3. This appeal is directed against the Judgment
and order dated 3rd of August, 2005 in Arbitration
Case No. 45 of 2004 passed by the Additional District
Judge, Chandigarh, dismissing the application filed
1
by the appellant for appointment of an Arbitrator on
the ground that no Arbitration Clause was in
existence between the parties.
4. The brief facts leading to the filing of this appeal
may be summarized as under :-
A tender was floated by the Post Graduate
Institute of Medical Education and Research (in
short, “the PGI”) on 21st of December, 2000 for the
purchase of Pulse Oxymeters, the format of which
contained an arbitration clause. The appellant gave
an offer for the tender on 15th of January, 2001,
which was accepted by the PGI. Purchase orders
were placed and in compliance with the said order,
the appellant had supplied equipments. The delivery
of equipments was also accepted by the PGI and the
machineries were installed. The PGI demanded the
execution of an agreement containing an arbitration
clause on a non-judicial stamp paper duly signed.
The appellant signed the agreement and sent it to the
PGI but the signature of the authorities of the PGI
2
was never acquired. It is true that although the
appellant duly signed the agreement and sent it to
PGI but the signature on the agreement had never
reached the appellants. According to the appellant,
an agreement containing an arbitration clause was
executed between the parties. No payment was made
by the PGI against delivery of goods worth Rs.
22,16,853.60 though the equipments were installed
and put in use. The PGI, on the other hand,
however, forfeited the earnest money of
Rs.2,12,160/-, which was encashed by them.
Eventually, the PGI got the equipments lifted and it
was found by the appellant that the equipments had
been mis-handled and were no longer fit to be
used/resold in the market. A notice was served on
behalf of the appellant of the matter to the PGI but
no reply was received. It was the case of the PGI that
no agreement was executed. The appellant was
alleged to have committed fraud on the PGI by
representing themselves of being the manufacturers
3
of the equipments, which were in fact, according to
the PGI, were imported from Korea. A Technical
Committee of the PGI on 14th of January, 2003,
however, did not approve the purchase and
installation of the equipments and thus, by a letter
issued in the year 2003, the appellant was informed
that the tender was rejected. According to the PGI,
the supply, not being in accordance with the
specification, was rejected after use and the
appellant was debarred from dealing with the PGI for
the next two years. Therefore, it was alleged by the
PGI that no arbitration agreement was executed
between the parties and, therefore, question of
appointing an Arbitrator in the present case could
not arise at all.
5. Finding no other alternative, the appellant filed
an application before the Additional District Court at
Chandigarh under Section 11(4) (a) of the Arbitration
and Conciliation Act, 1996 (in short, “the Act”) for a
direction upon the PGI to appoint an Arbitrator. The
4
Additional District Judge, Chandigarh, by the
impugned order dated 3rd of August, 2005, held that
as there was no agreement executed between the
parties, the question of appointing an Arbitrator
under the Act could not arise at all. It was held by
the learned Addl. District Judge, Chandigarh that
since the photocopy of the proposed agreement bears
the signature of only the appellant and not that of
the PGI, it could not be held that an arbitration
agreement was executed between the parties and
since there was no signature of the PGI on the said
agreement, which was sent after signature of the
appellant, remained only as an offer. Therefore,
according to the learned Additional District Judge,
Chandigarh, in the agreement containing an
arbitration clause, it could not be held that the
appellant was entitled to ask for appointment of an
Arbitrator under Section 11 of the Act. It is this
order, which is under challenge in this Court, which
on grant of leave, was heard in presence of the
5
learned counsel for the parties.
6. This special leave petition, as initially filed,
came up for consideration for admission on 9th of
May, 2006 when a question arose whether the said
special leave petition was maintainable in this court
against an order of the Additional District Judge,
Chandigarh purported to have acted in the exercise
of its power under Section 11 (4)(a) of the Act. While
issuing notice, this Court passed the following order:-
“This special leave petition has been filed by the petitioner against the order dated 3.8.2005 passed by the Addl. District Judge, Chandigarh in Arbitration Case No.45 dated 2.6.2004. According to the learned counsel for the petitioner, the special leave petition is maintainable in view of the recent judgment of the Constitution Bench in SBP & Co. vs. Patel Engineering Ltd. & Anr. Reported in (2005) 8 SCC 618. In this regard, he invited our attention to paragraph 47 sub-clause (vii), (x) and (xi). In our view, there is a clear indication in the said judgment that against the order passed by the Additional District Judge, the special leave petition under Article 136 of the Constitution of India is entertainable by this Court. (emphasis supplied)
We, therefore, issue notice to the respondent on the question of maintainability
6
of the special leave petition in this Court against the order passed by the Additional District Judge, Chandigarh.
Issue notice on the application for condonation of delay also.”
7. On a plain reading of this order passed by this
Court on 9th of May, 2006, it is evident that this
Court was of the view that an application under
Article 136 of the Constitution was maintainable
against an order passed by the Additional District
Judge, Chandigarh. Furthermore, the learned
counsel appearing for the parties have also argued
the case before us on merits, that is to say, on the
question whether an arbitration agreement exists
between the parties for which an Arbitrator could be
appointed. Such being the stand taken by the
learned counsel for the parties and in view of the
aforesaid order passed by this Court, we do not
intend to go into the question whether a petition
under Article 136 of the Constitution would at all be
entertainable by this Court as the Special Leave
7
petition was entertained and notice was issued.
However, keeping this question open for decision in
an appropriate case, we would like to go into the
merits of the case, that is to say, whether an
Arbitrator can be appointed in view of existence of an
arbitration agreement between the parties, although
in such agreement the PGI had not executed
agreement by putting their signature on the same.
8. In view of the aforesaid stand being taken by
the learned counsel for the parties, let us now
examine the merits of this appeal. As noted herein
earlier, the learned Additional District Judge,
Chandigarh held that their did not exist any
arbitration agreement between the parties and,
therefore, question of appointing an Arbitrator could
not arise at all. Therefore, in order to decide whether
the order of the Additional District Judge was correct
or not, we have to consider the relevant facts as well
as Section 7 of the Act for the purpose of coming to a
8
proper conclusion whether the agreement containing
an arbitration clause did exist between the parties or
not. Before we proceed further, we may examine
Section 7 of the Act which runs as under :
“Section 7 - Arbitration agreement
(1) In this Part, "arbitration agreement" means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.
(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.
(3) An arbitration agreement shall be in writing.
(4) An arbitration agreement is in writing if it is contained in-
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement; or
(c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.
9
(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.”
9. We have carefully examined the provisions
made under Section 7 of the Act which deals with
arbitration agreement. In Smita Conductors Ltd. vs.
Euro Alloys Ltd. [2001 (7) SCC 728], Article II Para
2 of New York Convention came up for consideration
before this Court. The provisions of Article II, Para 2
of New York Convention is in pari materia to the
aforequoted provisions of Section 7 of the Act. The
provisions of Article II, Para 2 of New York
Convention is being quoted herein now. Para 2 runs
as under :-
“Para 2 - The term “agreement in writing” shall include an arbitral clause in a contract or an arbitration agreement, signed by the parties or contained in an exchange of letters or telegrams.”
10
10. This Court, while interpreting the aforequoted
para 2 in the New York Convention held in para 6 at
pages 734-735 in Smita Conductors (supra) the
following : –
“6. What needs to be understood in this context is that the agreement to submit to arbitration must be in writing. What is an agreement in writing is explained by para 2 of Article II. If we break down para 2 into elementary parts, it consists of four aspects. It includes an arbitral clause (1) in a contract containing an arbitration clause signed by the parties, (2) an arbitration agreement signed by the parties, (3) an arbitral clause in a contract contained in exchange of letters or telegrams, and (4) an arbitral agreement contained in exchange of letters or telegrams. If an arbitration clause falls in any one of these four categories, it must be treated as an agreement in writing. In the present case, we may advert to the fact that there is no letter or telegram confirming the contract as such but there is certain correspondence which indicates a reference to the contract in opening the letters of credit addressed to the Bank to which we shall presently refer to. There is no correspondence between the parties either disagreeing with the terms of the contract or arbitration clause. Apart from opening the letters of credit pursuant to the two contracts, the appellant also addressed a telex message on 23.4.1990 in which there is a reference to two contracts bearing
11
Nos. S.142 and S. 336 in which they stated that they want to invoke force majeure and the arbitration clauses in both the contracts which are set forth successively and thus it is clear that the appellant had these contracts in mind while opening the letters of credit in the bank and in addressing the letters to the bank in this regard. May be, the appellant may not have addressed letters to the respondent in this regard but once they state that they are acting in respect of the contracts pursuant to which letters of credit had been opened and they are invoking the force majeure clause in these two contracts, it obviously means that they had in mind only these two contracts which stood affirmed by reason of these letters of credit. If the two contracts stood affirmed by reason of their conduct as indicated in the letters exchanged, it must be held that there is an agreement in writing between the parties in this regard.
11. Again in Nimet Resources Inc. vs. Essar
Steels Ltd. [2000 (7) SCC 497 at Para 5], this
Court observed as follows:-
“If the contract is in writing and the reference is made to a document containing arbitration clause as part of the transaction, which would mean that the arbitration agreement is part of the contract. Therefore, in a matter where there has been some transaction between the parties and the
12
existence of the arbitration agreement is in challenge, the proper course for the parties is to thrash out such question under Section 16 of the Act and not under Section 11 of the Act.”
12. Keeping the aforesaid principles, as quoted
hereinabove, in the aforesaid decisions of this Court
in kind, in fact what constitutes an arbitration
agreement between the parties, we have to examine
whether there exists an arbitration agreement
between the parties or not in the facts and
circumstances of the case. Let us, therefore, consider
the gist of the facts involved in this case. A tender
enquiry No.2PGI/OGL/2K/6281 dated 21.12.2000
for purchase of Pulse Oxymeters was floated by the
PGI. It is an admitted position that the appellant
submitted their tender vide their offer
No.UIPL/331177/00-01 dated 15.2.2001. The
tender of the appellant was accepted by the PGI vide
their letter No.PGI/P-61/02/477/11936-51 dated
29.9.2002 for supplying 41 Pulse Oxymeters to their
13
different departments. The tender documents itself
contain an arbitration clause and by reason of
acceptance of the tender of the appellant by the PGI,
it must be held that there was a valid arbitration
agreement between the parties. The appellant
supplied 41 Pulse Oxymeters and the receipt thereof
was duly acknowledged on behalf of the PGI on the
delivery challans. The service/installation reports of
the aforesaid machines were duly signed on behalf of
the PGI. In the letters issued by the PGI, there was
an apparent acknowledgement of supply of the
aforesaid meters by the appellant and also reference
to the aforementioned tender enquiry number. It is
an admitted position that the appellant had sent the
agreement containing the arbitration clause, as per
the format provided by the PGI, after duly signing the
same on requisite value of stamp paper for signing of
the same by the PGI. The PGI though admittedly
received the same, did not send back the agreement
to the appellant after signing it as per the agreement
14
between the parties. The PGI admittedly had used
the machines for about an year and thereafter
returned the same to the appellant. Subsequently,
the bank guarantee furnished by the appellant for
Rs.2,13,160/- and the earnest money deposit of
Rs.45,000/- was encashed and forfeited by the PGI.
In view of the aforesaid facts and the
correspondences between the parties, particularly
the tender offer made by the appellant dated
15.1.2001 and supply order of the PGI dated
29.9.2002, and, in our view, to constitute an
arbitration agreement between the parties and the
action taken on behalf of the appellant and in view of
Section 7 of the Act and considering the principles
laid down by the aforesaid two decisions of this
Court, as noted herein earlier, we are of the view that
the arbitration agreement did exist and therefore the
matter should be referred to an Arbitrator for
decision. That apart, as we have already noted
herein earlier that in this case, the documents on
15
record, in our view, apparently show supply of
materials by the appellant and acceptance thereof by
the PGI in pursuance of the tender enquiry by the
PGI, wherein tender of the appellant containing an
arbitration clause was admittedly accepted by the
respondent. In that view of the matter, it cannot be
said that the PGI should now be allowed to wriggle
out from the arbitration agreement between them.
13. We may reiterate that in this case admittedly
the documents which are on record apparently show
supply of the material by the appellant to the PGI
and acceptance thereof by the PGI in pursuance of
the tender enquiry by them wherein tender of the
appellant containing the arbitration clause was
admittedly accepted by the PGI. Accordingly, we hold
that arbitration agreement did exist and, therefore,
dispute between the parties would be referred to an
Arbitrator for decision.
14. Therefore, considering the above aspects of the
matter in this case, we must come to this conclusion
16
that although no formal agreement was executed, the
tender documents indicating certain conditions of
contract contained an arbitration clause. It is also an
admitted position that the appellant gave his tender
offer which was accepted and the appellant acted
upon it. Accordingly, we are of the view that the
learned Additional District Judge, Chandigarh erred
in holding that their did not exist any arbitration
agreement between the parties and, therefore, the
order passed by him is liable to be set aside.
15. For the reasons aforesaid, the impugned order
is set aside and the appeal is allowed. We now direct
that the matter may be placed before the Hon’ble
Chief Justice of the High Court of Chandigarh to
appoint an Arbitrator in accordance with law to
resolve the dispute between the parties. The appeal
is thus allowed. There will be no order as to costs.
…………..………………J. [TARUN CHATTERJEE ]
17
NEW DELHI: …..………………………J.
October 01, 2008 [DALVEER BHANDARI]
18