21 October 2005
Supreme Court
Download

M/S.SUBHASH PROJECT & MKT.LTD. Vs W.B.POWER DEV.CORPN. LTD.&ORS

Bench: CJI R.C. LAHOTI,G.P. MATHUR,P.K. BALASUBRAMANYAN
Case number: C.A. No.-005030-005030 / 1999
Diary number: 12703 / 1998


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8  

CASE NO.: Appeal (civil)  5030 of 1999

PETITIONER: M/s Subhash Projects & Marketing  Ltd.           

RESPONDENT: West Bengal Power Development Corporation       Ltd. & Ors.

DATE OF JUDGMENT: 21/10/2005

BENCH: CJI R.C. LAHOTI,G.P. MATHUR & P.K. BALASUBRAMANYAN

JUDGMENT: J U D G M E N T  (with C.A. No.5031/1999 and C.A. No.5032/1999)

P.K. BALASUBRAMANYAN, J.

                1.              These appeals arise from Writ Petition No.886 of 1997 filed  by M/s Larson & Toubro (’L & T’ for short), in the High Court of  Calcutta.  Respondent No.11 in the Writ Petition M/s Subhash Projects  and Marketing Limited (’Subhash Projects’ for short) was the contesting  respondent.  By judgment dated 3.10.1997, a learned single Judge of the  High Court dismissed the Writ Petition.  The Writ Petitioner thereupon  filed appeal No. 559 of 1997 before the Division Bench.  By judgment  dated 14.7.1998, the Division Bench came to the conclusion that the  appeal was liable to be allowed and the Writ Petitioner granted relief.   Still, it did not grant the full relief to the Writ Petitioner, the appellant  before it, but directed the contesting respondent, Subhash Projects, to  pay a compensation of Rs.1 crore to the Writ Petitioner.  This was on the  finding that the contract based on the tender floated by respondent No.1,  the West Bengal Power Development Corporation Limited (hereinafter  referred to as ’the Power Corporation’) ought to have been awarded to  the writ petitioner-L & T and the award of the same to respondent No.11  Subhash Projects was illegal, but it was inexpedient at that stage to set  aside the award of the contract and the least that should be done was to  direct Subhash Projects to disgorge at least some portion of the profit it  would have earned out of the illegally awarded contract and make over  the same as compensation to the writ petitioner-L & T, who ought to  have been awarded the contract.  Feeling aggrieved, respondent No.11 in  the Writ Petition, Subhash Projects, has filed Civil Appeal No. 5030 of  1999.  M/s Larson & Toubro, the writ petitioner and the appellant before  the High Court has filed C.A. No. 5031 of 1999 submitting that the High  Court having found that the award of the contract to Subhash Projects  was illegal, and it should have been awarded to L & T, ought to have  gone ahead and struck down the award of the contract to Subhash  Projects and ought to have directed it to be awarded to L & T.  The  Union of India, the Director (Thermal), Ministry of Power and the  Central Electricity Authority, who were respondents 8, 9 and 10 in the  Writ Petition have filed Civil Appeal No. 5032 of 1999 challenging the  judgment of the Division Bench, but essentially complaining, as was  disclosed at the hearing, about the remarks made by the Division Bench  of the High Court about the interference of the Ministry of Power and  that of the Minister of State for Power and about its impropriety.  Since  all the appeals arise from the same judgment, they have been heard  together.

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8  

2.              With the aid of the Overseas Economic Corporation Fund,  Japan (hereinafter referred to as ’OECF’), the Power Corporation,  decided to take up the construction of Bakereshwar Thermal Power  Project.  Pursuant to that decision, the Power Corporation issued a notice  dated 19.7.1995 inviting tenders for the work of water intake and plant  water system package for 3 x 20 m.w. units of Bakereshwar Thermal  Power Project.  The bid was required to be submitted in three separate  covers, the first containing the earnest money deposit, the second, the  techno-commercial evaluation and the third, the price bid.  Pursuant to  the tender notice, five bidders including Subhash Projects and L & T  submitted tenders.  As per the instructions issued to the bidders, bidders  were not to be allowed to deviate from the principal requirements of the  tender specifications.  It was provided that the price quoted should  remain firm throughout the period of the contract.  In other words, no  price variation was permissible.  The procedure for opening of the  tenders was also set out.  Pursuant thereto, Cover-I containing the  earnest money deposit and Cover-II containing the techno-commercial  evaluation, were opened and the tenderers were found technically  qualified.  It was found that some vagueness had crept into the notice  inviting tenders and that the scope of certain works remained vague or  unclear.  The technically qualified tenderers were called for discussion.   Conferences were held.  Ultimately, at a Technical Evaluation  Committee meeting on 21.5.1996 for techno-commercial evaluation, it  was decided to suggest seven modifications. The proposed modifications  were forwarded to OECF.  OECF suggested that the bidders may be  allowed to submit price implications strictly limited to the seven aspects  suggested at the techno-commercial evaluation and that bidders who  agreed to withdraw the price variation clause must submit a positive  price implication for the same.  It may be noticed here that while L & T  claims to have made a firm bid as per its original tender, Subhash  Projects had resorted to price variation clause and had not indicated the  positive price implication in its tender.

3.              Pursuant to the communication in that behalf issued by the  Power Corporation regarding the seven deviations and the clarifications  relating to the work made at the conferences, Subhash Projects made a  firm bid but increased its tender amount.  L & T indicated an increase of  Rs. 35 lakhs in view of the seven deviations mentioned in the  communication, but indicated that it was willing to reduce the original  tender amount by Rs. 64 crores in view of the clarifications issued about  the work and in view of the proper understanding of the real scope of the  work.  Thereafter, the price bids were opened.  As per the original price  offered, L & T was placed as the fifth lowest and Subhash Projects  though it had resorted to price variation in the original tender, was found  the lowest bidder on the basis of the firm valuation offered by it  subsequent to the clarificatory letter issued by the Power Corporation.   But on taking note of the reduction proposed by L & T, while  responding to the subsequent communication, its bid was found to be the  lowest.

4.              The tenders were evaluated by the Tender Evaluation  Committee.  They were also scrutinized by the technical experts  appointed by the Power Corporation and by OECF.  Based on the  assessment of all the three, it was decided at the level of the Power  Corporation, that L & T with its reduced offer, was the lowest tenderer  and it was recommended that the contract be awarded to L & T. At this  stage, Subhash Projects handed over a letter to the Minister of State for  Power in the Union Government, in person complaining that the placing  of L & T as the lowest tenderer, was not justified in view of the fact that  the acceptance of the reduction of Rs. 64 crores from its original bid was  against the tender conditions and that no such deviation could have been  permitted after the earnest deposit cover and the techno-commercial  evaluation offers had been opened, even though the price bids

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8  

themselves had not been opened.  Based on this letter, a letter was  written by a Secretary in the Minister of State for Power to the Power  Corporation, to look into the complaint of Subhash Projects.  When the  Power Corporation stuck to its position and the Government of West  Bengal also agreed with the Power Corporation that the contract be  awarded to L & T, it being the lowest tenderer, the Minister of State for  Power and his ministry persisted in its direction seeking a fresh  evaluation to be made on the basis of the original bids, even going to the  extent of writing directly to the Government of West Bengal in that  regard.  Ultimately, the Government of West Bengal and the Power  Corporation were compelled to make a fresh evaluation ignoring the  reduction of Rs.64 crores offered by L & T and to recommend the award  of the contract to Subhash Projects.  On the letter in that behalf being  issued to Subhash Projects, L & T approached the High Court with the  Writ Petition.  No stay of the working of the contract was granted, but  the High Court permitted Subhash Projects to continue the work, making  it clear that it would not be entitled to claim any equity, in case the Writ  Petition was allowed.  Thus, pending the Writ Petition, Subhash Projects  did a part of the work, obviously without any claim in equity and subject  to the result of the Writ Petition.  Though, the learned single Judge stated  that, although he had no doubt that the Power Corporation, ought not to  have succumbed to the pressure of the Minister of State for Power, and  awarded the contract to Subhash Projects, it was not necessary to  interfere with the award of the contract in the peculiar circumstances of  the case, since before the contract was actually awarded to Subhash  Projects, Subhash Projects was persuaded to reduce the tender amount to  just below that of the sum quoted by L & T and it was not in public  interest to interfere since a part of the work had already been done by  Subhash Projects.  This judgment was modified by the Division Bench  which also found that the award of contract to Subhash Projects was at  the pressure of the Union Minister of State for Power, undue pressure at  that, and that though the contract itself was not liable to be interfered  with, Subhash Projects which had secured the contract by dubious  means, was liable to be compelled to disgorge at least a portion of the  profits that it would have earned from working the contract.  The  Division Bench assessed the same as Rs. 1 crore which it found would  be less than 10 per cent of the profits that Subhash Projects would have  earned and directed its payment to L & T.

5.              It was argued by the learned Senior Counsel for the  appellant-Subhash Projects that the Division Bench of the High Court  was in error in finding that the award of the contract to Subhash Projects  was illegal and that the due award of the contract to L & T, was unduly  interfered with by the Minister of State for Power in the Union  Government  and that such interference by him was unwarranted and  uncalled for.  Learned counsel submitted that the Minister’s Secretariat  and the notings of the Minister had only directed the following of the  guidelines and norms and issuance of such a direction could not be  considered to be undue or improper interference in the matter of the  award of the contract.  As a representative of the public, nothing stood in  the way of the Minister receiving a representation made to him  personally on behalf of Subhash Projects and there was nothing sinister  in the Minister receiving it or directing it to be forwarded to the Power  Corporation for action.  There was also nothing improper in the Minister  taking up the matter with the State Government and seeking its  intervention to have the directions issued by him obeyed by the Power  Corporation.  That apart, the offer of L & T as originally made, was  higher than that of Subhash Projects and if the rebate offered by L & T  of Rs. 64.40 crores was kept out, no fault could be found with the award  of the contract to Subhash Projects.  Learned counsel submitted that the  guidelines were mandatory and clause 5.03 thereof justified the rejection  of the reduced offer of L & T and in that situation, the High Court was  not justified in inferring that the award of the contract to Subhash  Projects was not justified in this case.  There was also nothing illegal or

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8  

improper in permitting Subhash Projects to reduce its offer to below that  of L & T once it was found that Subhash Projects was the lowest  tenderer and there was a decision to award the contract to it.  Learned  counsel submitted that in the matter of award of contracts, the  ‘jurisdiction of the High Court was limited and it was not as if the High  Court was sitting in appeal over the evaluation and award of the contract.   There was, therefore, no justification in the High Court directing  Subhash Projects to pay compensation to L & T on the basis that the  contract ought to have been awarded to L & T.  To a question put to him  specifically, he has submitted that in case, at the end of it, this court  came to the conclusion that the submissions on behalf of the Subhash  Projects are not sustainable, he would prefer the judgment of the  Division Bench of the High Court to be left as it is, rather than the  accepting of the appeal filed by L & T and setting aside the award of the  contract to Subhash Projects since the adoption of such a course may  lead to other consequences which would be more serious as far as  Subhash Projects is concerned.  

6.              On behalf of the Union of India, the learned Additional  Solicitor General submitted that the inference by the High Court that  there was undue interference by the Minister of State for Power in the  Union Government  was not justified.  Learned counsel submitted that  the strong observations made are not warranted in the circumstances of  the case.  He submitted that the Minister had acted only in public interest  and he had no axe to grind in the matter.  The receiving of a  representation personally, or the forwarding of it for being considered  could not be said to be acts not befitting a Minister, a representative of  the people.  Thus, he submitted that C.A. No.5032 of 1999 filed by the  Union of India was liable to be allowed at least to the extent of removing  the observations about the role played by the Minister of State for Power  in the Union Government and his Ministry.

7.              On behalf of L & T, which has also filed the appeal C.A.  No. 5031 of 1999, it was submitted that this was a case where the  original tender notification was not clear, the scope of the work was not  precisely made known; that conferences had to be held, discussions had  to take place, clarifications had to be issued, scope of the work had to be  defined and the tenderers apprised of the real extent and nature of the  work.  In that situation, the tenderers had necessarily to clarify their  offers especially since firm offers were not made by some of the  tenderers, including Subhash Projects who had resorted to price variation  clause.  He submitted that the consultants appointed by the Power  Corporation, the OECF, and the Tender Evaluation Committee had  recommended the award of the contract to L & T and the Central  Electricity  Authority on being apprised of all the relevant facts, had also  agreed with that view and the State Government had concurred with the  proposal and it was only the undue and persistent interference by the  Minister of State for Power in the Union Government, without even  seeking properly, the opinion of the OECF in that regard by apprising it  of all the factors relevant to the issue and without taking into account the  opinion of the Central Electricity Authority, that had resulted in the  contract being awarded to Subhash Projects and in that situation, the  High Court ought to have struck down the award of the contract to  Subhash Projects and should have directed the award of the contract to L  & T.  He pointed out that clause 5.03 relied on had been given the go-by  and had no application to the case on hand and if one were to go strictly  by the tender conditions, the bid of Subhash Projects was liable to be  rejected and Subhash Projects should not have been permitted to sub- contract or directed to sub-contract, against the terms of the original  notice inviting tenders.  He pointed out that whereas the stand was taken  that the reduction offered by L & T should not be taken note of, Subhash  Projects was permitted to reduce its offer to a figure little below that  offered by L & T and that the whole exercise was mala fide and was at

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8  

the instance of the Minister of State for Power in the Union Government  and the action in that behalf has been rightly found to be not proper by  the High Court.  He pointed out that the learned single Judge has also  held that pressure had been brought to bear on the Power Corporation by  the Minister of State for Power in the Union Government.  He submitted  that logically, the award of contract to Subhash Projects should be set  aside and it should be directed that the contract be awarded to L & T.  As  regards the appeal C.A. No. 5030 of 1999 filed by the Subhash Projects,  learned counsel submitted that in any event, there was no reason to  interference with the judgment of the High Court awarding a sum which  was not even 10 per cent of the profits that Subhash Projects would have  earned out of the contract.  He referred to the decision in M/s A.T. Brij  Paul Singh & Ors. Versus State of Gujarat  [(1984)4 SCC 59] to  submit that in such cases, the profit could be normally estimated at 15  per cent of the contract amount and here, the High Court had taken a  gross figure, which was only two-thirds of that.

8.              The voluminous correspondence and materials produced by  the parties have been adverted to and evaluated both by the learned  single Judge and by the Division Bench of the High Court.  The learned  single Judge of the High Court, in fact, found that clause 5.03, Part II of  the guidelines of OECF, had no application in the case in the  circumstances referred to by him.  He also found that contemporaneous  documents clearly showed that all concerned preceded on the basis that  clause 5.03, part II of the guidelines, would not be applicable.  This view  was not disagreed to by the Division Bench.  It appears to us that while  issuing the notice inviting tenders, the Power Corporation had not  clarified the scope and the extent of the work that was being tendered.   Offers were made by the tenderers.  Obviously, there was considerable  confusion and clarificatory meetings and conferences had to be held,  clarifying the scope of the work and clarifying other technical details.   Ultimately seven deviations were also proposed in writing and the offers  of the bidders invited based on those seven variations.   This was,  therefore a case where considerable confusion prevailed and the bidders,  including Subhash Projects were forced to make renewed offers  including the deletion of the price variations clause.  It must be noticed  that the price bids had not been opened when these negotiations were  being carried on and the tenderers were given an opportunity to make  revised offers in the light of the clarifications and in the light of the  seven deviations made.  In that sense, the bids had not been opened,  since the relevant bid, the price bid, still remained to be opened.  If, at  that stage, the tenderers, on understanding the real scope of the work and  the magnitude of the work, offered to reduce the amount that had  originally been offered on the basis of misconceptions arising out of the  confusion created by the vagueness in the notice inviting tenders, it  could not be said that such offers were liable to be rejected on the  ground that they were variations against the terms of clause 5.03 of the  guidelines.  This aspect has also been found by the learned single Judge  in his judgment.  The argument on behalf of Subhash Projects that the  variation in the offers should have been ignored cannot, therefore, be  accepted.   In any event, when after consulting its own consultants and  the independent consultants appointed by OECF and based on the  evaluation of its own Tender Evaluation Committee, the Power  Corporation placed L & T as the lowest tenderer, there was no  justification at all in the Ministry of State for Power harping on that  aspect, on the facts of the case, even without obtaining a proper opinion  from OECF and Central Electricity Authority after appraising them of all  the relevant facts.  The persistence of the Ministry of State for Power  and the manner of it, in the circumstances, looks strange.  

9.              Even as regards Subhash Projects, it was given an  opportunity to make a firm offer which, in fact, it was bound to do on the  terms of the notice inviting tenders and it was also given an opportunity

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8  

to reduce its price even from the one subsequently quoted by it as its  firm offer, before the award of the contract to it.  Therefore, this was a  case where in any event, all the tenderers should have been invited and  given an opportunity to reduce their bids before accepting the most  competitive of them in public interest and in the interest of the project.   The learned single Judge has, in fact, stated, "A revised bid also became  necessary in view of the changed situation, namely, alterations,  amendments and clarification in the schedules and the drawings,  resulting in alternations and amendments both in respect of part-A i.e.  supply of materials and part-B i.e. service."  The said finding could not  be successfully assailed by Subhash Projects or by the Union of India, in  their appeals.

10.             It is in this context that the Division Bench of the High  Court came to the conclusion that the consultants of the Power  Corporation, the foreign consultants of OECF, the tender evaluation  committee and the Central Electricity Authority, were justified in  coming to the conclusion that the offer of L & T as revised, was the  lowest and in recommending that its tender be accepted.  It was in this  context that the court also found that approval of this recommendation  by the State Government was also justified.  It is in this context that we  have to consider the act of the Minister of State for Power and his  Ministry, in persisting in the stand that clause 5.03 should be adhered to.   The Division Bench of the High Court called for the relevant records  from the Ministry and has noticed that the concerned file was never put  up before the Minister for Power and there was nothing to show that  Minister of State for Power had been delegated any function in such  matters.  In fact, the Division Bench found that except as involving  public interest, the matter concerned, might not even have been within  the purview of the Minister of State for Power.  We do not want to go  further into that aspect, but we must notice that the Ministry of State for  Power, was not fair in not apprising OECF of the entire facts with  reference to the documents and seeking its advice before taking a stand  on the matter of identification of the lowest tenderer on the facts and in  the circumstances of the case.  The manner in which the Minister of  State for Power in the Union Government  went about it, has led to the  observations of the High Court, complained of in the appeal by the  Central Government.  On the materials, we are not in a position to say  that the Division Bench of the High Court was not justified in drawing  the inference it had drawn.  

11.             We were taken elaborately through a large number of  documents including the valuation process undertaken by the evaluation  committee and the opinions expressed by the other responsible bodies  and a reappraisal of those materials, only supports the conclusion of the  Division Bench on the matters in controversy.  It may be noticed that the  learned single Judge had also rejected the contentions of Subhash  Projects, and had held that it was difficult to understand as to how the  Power Corporation overlooked the original defect in the tender of  Subhash Projects which included a price variation clause and not a firm  price as stipulated and how it held negotiations only with it at the price  bid stage when Subhash Projects admittedly lowered its bid so as to  make its offer nearer to the offer of L & T, despite the restriction in that  regard as contained in OECF letter dated 1.7.1996 made much of to  support the contract given to it and how Subhash Projects was permitted  to enter into sub-contracts with other contractors, and that too, even prior  to the entering into an agreement by Subhash Projects itself.  The learned  single Judge had also found that in any event, price variation became  necessary in view of the alterations, amendments and clarifications to the  tender schedule.  The Division Bench had, by and large, agreed with that  finding.  These findings are seen to be justified on the materials available  on record and there is no justification in this Court interfering with those  findings in these appeals.  Thus, it was a case where different yardsticks

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8  

were being used at different stages and the persistence of the Ministry of  State for Power in raising objections until Subhash Projects was chosen  as the lowest tenderer does look strange.  

12.             Thus, on a reappraisal of the relevant materials in the light  of the submissions before us, we are not satisfied that any interference is  called for with the judgment of the Division Bench in these appeals.   Since we are inclined to agree with the conclusion of the Division Bench  that the award of the contract to Subhash Projects was not legal, we see  no reason to interfere with the course adopted by the Division Bench in  the matter of awarding compensation to L & T payable by Subhash  Projects.  We also find the sum fixed reasonable and to the advantage of  Subhash Projects.  We are not inclined to entertain the plea of L & T in  its appeal that the award of the contract to Subhash Projects itself must  be set aside and the contract directed to be awarded to L & T or to order  a fresh tender to be invited for the work.  The adopting of such a course  would be counter productive in the circumstances, considering the nature  of the project and the steps that had already been taken and the  completion of the project itself during the pendency of these appeals.  

13.             One aspect remains to be considered.  The Division Bench  had directed the Power Corporation to pay out the sum of rupees one  crore to L & T out of the payments to be made to Subhash Projects. This  Court while issuing notice on 31.8.1998 on the petition for special leave  to appeal filed by the Subhash Projects, stayed the direction regarding  the payment of compensation.  Thereafter, on 10.9.1999, leave to appeal  was granted.  According to Subhash Projects, the project was completed  and the final bill was submitted for payment.  The payment was not  made by the Power Corporation without Subhash Projects depositing the  sum of one crore in a Fixed Deposit and handing over that receipt to the  Power Corporation.  Thereafter, Subhash Projects filed a petition for  release of the Fixed Deposit receipt for Rs.1 crore retained by the Power  Corporation.  On 8.8.2003, this Court permitted the Power Corporation  to return the Fixed Deposit Receipt to Subhash Projects "subject to the  condition that Subhash Projects through its Managing Director will  execute an undertaking before the Registry of this Court to refund any  amount that becomes payable in the event of the above appeal being  dismissed by this Court within four weeks from that date."  The Subhash  Projects has, thus, got back the Fixed Deposit Receipt for Rs. 1 crore in  the light of the undertaking given by Subhash Projects through its  Managing Director.  Pursuant to the order of 8.8.2003 and in view of our  conclusions, Subhash Projects has to be directed to deposit a sum of Rs.  1 crore in this Court, so that the same could be disbursed to L & T.   Subhash Projects has had the benefit of the money which should have  been disbursed to L & T in the light of the directions of the High Court,  which we have confirmed.  So, Subhash Projects should be directed to  pay some reasonable interest to L & T for the amount.  We feel that  interest at the rate of five per cent per annum would be reasonable under  the circumstances.  We, therefore, direct Subhash Projects to deposit in  this Court within four weeks from today the sum of rupees one crore  with interest thereon at five per cent per annum from 8.8.2003 till the  date of its deposit.  The amount will then be disbursed to L & T.  It will  be open to Subhash Projects to pay the sum of rupees one crore with  interest as aforesaid by way of a bank draft to L & T within four weeks  and to file an affidavit in this Court testifying to that fact.  The affidavit  should be filed within six weeks from today.  In case Subhash Projects  does not pay the amount of Rs. 1 crore with interest as ordered to L & T  by way of draft or deposit the same in this Court within four weeks as  originally undertaken by it, the amount of Rs. 1 crore will carry interest  at the rate of 10 per cent per annum (instead of five per cent per annum  as stipulated) from the date of the judgment of the Division Bench of the  High Court till the date of its recovery.  L & T would be entitled to  execute this order for recovery as if it were a decree through the

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8  

concerned district court in Calcutta, charged on the assets of Subhash  Projects and on the properties of its Directors and personally from them.

14.             In the result, C.A. No. 5030 of 1999 filed by Subhash  Projects is dismissed with costs.  C.A. No. 5032 of 1999 filed by the  Union of India is dismissed with no order as to costs.  C.A. No. 5031 of  1999 filed by L & T is also dismissed, subject to the direction regarding  the payment of Rs. 1 crore with the provision for interest and the  recovery of the amounts as provided hereinbefore.  In this appeal also,  the parties will suffer their respective costs.