M/S SORATH BUILDERS Vs SHREEJIKRUPA BUILDCON LIMITED
Bench: ARIJIT PASAYAT,MUKUNDAKAM SHARMA, , ,
Case number: C.A. No.-001127-001127 / 2009
Diary number: 254 / 2009
Advocates: SHEELA GOEL Vs
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL N. 1127 OF 2009 (Arising out of SLP (C) No. 111 of 2009)
M/s. Sorath Builders ..…Appellant
Versus
Shreejikrupa Buildcon Limited & Anr. .….Respondents
JUDGMENT
Dr. Mukundakam Sharma, J.
1. Leave Granted.
2. In the present appeal what is under consideration is the
construction of Veterinary College building at Navsari Agricultural
University, Gujarat (hereinafter referred to as “University”). Since
construction of the aforesaid building was required to be done
immediately, University released the grant which was going to lapse on
31.03.2009. The University issued a Tender Notice No. 20/2008-09 on
21.11.2008 inviting tenders for construction of Veterinary College building
at Navsari Agricultural University, Gujarat. The tender notice was widely
advertised through publication in newspaper “Sandesh”, being the largest
local daily in the State of Gujarat. The tender notice was also published
on the internet. The notice inviting tenders required the following from
the bidders:
Page 1 of 12
a) Pre qualification documents had to be sent by 27.11.2008,
failing which the tender would be liable for rejection and
will not be opened;
i) “AA” Class certificate with minimum 80% of the project cost
turnover audited in the last financial year 2007-08;
ii) Bidding capacity value should be more than project cost;
iii) II Building category registration and above.
All the above documents have to be readily available with
any builder having continuous work for different
authorities.
b) Last date of “On Line” submitting of “Price bid” was
28.11.2008.
c) Tender fees, Earnest Money Deposit (EMD) and other
documents can be submitted by 04.12.2008.
3. Pursuant to the aforesaid advertisement three bids were received by
the University out of which one was disqualified at the threshold for not
having the requisite experience. Out of the remaining two, the bid of the
appellant – M/s. Sorath Builders was the lowest. One of the terms and
conditions of the bid was that pre-qualification documents were required
to be sent by 27.11.2008. Since the bid of respondent no. 1,
Shreejikrupa Buildcon Limited was sent on 01.12.2008 i.e. three days
after the last date of receiving these documents by the University the bid
of respondent no. 1 could not have been opened as it was received
Page 2 of 12
beyond the time stipulated and accordingly it was not taken into
consideration.
4. The University considered the following stipulation in the tender:
“Late date of “On Line” submission of price bid is dated 28/11/2008 upto 18.00 hrs. All documents, tender fees, registration, bank solvency, bank guarantee and EMD etc. duly scan along with the tender documents should be submitted “On Line”. Last date for submission of pre- qualification documents by R.P.A.D./Speed Post is 27/11/2008. Any violation in the above instructions, the tender will be liable for rejection and will not be opened”.
In terms of and in accordance with the mandate of the tender notice
the tender of respondent no. 1 - Shreejikrupa Buildcon Limited was not
opened. Being so situated, the respondent no. 1 filed a writ petition
before the High Court of Gujarat praying for quashing the decision of
respondent no. 2 – University dated 8.12.2008 considering the
respondent no. 1 as disqualified from participating in the tender selection
process for the construction of Veterinary College building at Navsari
Agricultural University, Gujarat.
5. The said writ petition was placed before the Division Bench and
after looking into the records and after hearing the parties the Division
Bench held that the University acted arbitrarily in requiring the pre
qualification documents to be sent physically so as to reach the University
by R.P.A.D./Speed Post by 27.11.2008, inasmuch as it meant that the
contractor had to send pre qualification documents by the aforesaid mode
Page 3 of 12
by dispatching the same latest by 25.11.2008. Consequently, the writ
petition was allowed and the decision of the respondent no. 2 - University
dated 10.12.2008 accepting the bid of the appellant was quashed and set
aside with a further direction that the University shall issue a fresh tender
notice with the same terms and conditions but it would also provide seven
days time for submitting the pre qualification documents after the end
date for downloading the bid documents.
6. Being aggrieved by the aforesaid Judgment and Order the present
appeal was filed in which several contentions were raised on behalf of the
parties.
7. It is the case of the appellant before us that the High Court has
wrongly set aside a settled contract pursuant to the tender issued by
respondent no. 2 – University on the ground that the terms of the tender
were arbitrary. It was also argued that the High Court has not only
interfered with the terms and conditions of the tender but has written the
terms of the tender itself by directing the University to issue a fresh
tender on the terms and conditions suggested in the said order. It was
also submitted that jurisdiction of the writ court to interfere in the terms
of a contract is very limited and that even if two views are possible and
the authorities granting tender takes a particular view, the courts should
not interfere. It was also submitted by the counsel appearing for the
appellant that the time period which was granted by the University cannot
Page 4 of 12
be said to be too short for it was possible for the respondent no. 1 to
submit the bid after satisfying all the requirements. It was also pointed
out that the respondent came to know about the tenders only on
27.11.2008 as he was undertaking various construction works, and
therefore could not submit the required pre qualification documents in
time within the stipulated date. It was also submitted that so placed and
situated, the respondent no. 1 was not entitled to and competent to take
up a plea that he did not receive sufficient time to submit the pre
qualification documents.
8. The case of respondent no. 1 on the other hand was that by
providing arbitrary time limit to submit pre qualification documents the
University tried to shut out competition and permitted only two eligible
parties to enter the fray. It was also submitted that the price bid offered
by respondent no. 1 was much lower than the appellant, being only
6.38% above the estimated contract value while bid offer of appellant
was 21.21% above the estimated contract value, which would mean that
the University would be unnecessarily spending public money to the tune
of more than Rs. 1 crore.
9. We have carefully considered the aforesaid submissions of the
counsel appearing for the parties. So far as the issue with regard to
stipulation that pre qualification documents to be sent latest by
27.11.2008 for the estimated contract value of Rs. 8.40 crores, is
Page 5 of 12
concerned, three parties applied and submitted their tenders and on
scrutiny it was found that one out of the three did not satisfy the
requirements, and therefore, his tender was rightly rejected by the
parties. So far as the tenders of the appellant and respondent no. 1 are
concerned, on going through the record we find that the respondent no. 1
never specifically raised the issue regarding paucity and shortage of time
as one of the grounds for challenging the decision of the University. The
only stand that was taken by respondent no. 1 for late submission of his
pre qualification documents is that he came to know about the tenders
only on 27.11.2008 as he was undertaking various construction works,
and therefore, could not submit all the required pre qualification
documents in time stipulated in the notice inviting tenders. The aforesaid
stand makes it crystal clear that respondent no. 1 was prevented in
submitting the required documents in time due to his personal difficulty
and not for the time schedule attached to the notice inviting tenders.
That was also not one of his grounds taken specifically in the writ petition
at any stage. But only during the course of hearing such a contention
seems to have been raised which found favour with the High Court. No
other intending bidder came to the court on any such plea that they were
deprived of an opportunity of submitting their tender due to paucity of
time and that any prejudice is caused to anyone due to time schedule
provided by the University. It appears that only during the hearing stage
a plea was raised which found favour with the High Court but as stated
above the aforesaid plea is without any merit for the advertisement was
Page 6 of 12
issued on 21.11.2008 requiring the parties to submit their pre
qualification documents only by 27.11.2008. Therefore, sufficient time
was provided to submit tender papers. The University also permitted pre
qualification documents to be submitted “On Line”. Therefore, the
contention that the time was too short for submission of pre qualification
documents by 27.11.2008 is without any merit.
10. We also find on record that the tender submitted by the appellant
was the lowest and the same was accepted as the same was found to be
reasonable, tenable, plausible and valid. The High Court went beyond its
jurisdiction in setting aside the decision of the University in accepting the
bid of the appellant. We are of the opinion that there is no fault or
arbitrariness in the decision making process of the University. The said
decision cannot be said to be in any manner arbitrary or unreasonable.
The respondent no. 1 submitted his pre qualification documents late for
which he is only to be blamed. The University has taken a specific stand
before us that the price settled for the tender is neither unreasonable nor
excessive in comparison with the project. It was also stated before us
that the main interest of the University is to get a good quality Veterinary
College within the stipulated time because the grant out of which the
payment of construction of the college is to be made would lapse on 31st
March, 2009 and that the University has already started the process of
admission to the batch of students for the coming academic year.
Page 7 of 12
Consequently we feel that a time bound completion of a good quality
Veterinary College has become a necessity.
11. We are of the considered opinion that there is definitely urgency in
the aforesaid project, and therefore, the process of awarding the contract
of construction should be expedited and the same should not be stalled in
between. The process which is suggested by the High Court in its
Judgment and Order if allowed to be gone through the same would mean
prolonged delay in the completion of the project. The project is time
bound and money must be utilized by 31st March, 2009. The process of
re-tendering and allotment of fresh tender would mean delay and would
also be time consuming.
12. The Supreme Court in number of decisions has held that there is a
vital distinction between administrative and contractual law. In
Puravankara Projects Ltd. vs. Hotel Venus International and
Others, reported in (2007) 10 SCC 33, in which one of us, namely,
Justice Arijit Pasayat was a party, it was held as follows:
“tender terms are contractual and it is the privilege of the Government which invites its tenders and courts do not have jurisdiction to judge as to how the tender terms should be framed. By observing that there was an implied term which was not there in the tender, and postponing the time by which the bank guarantee had to be furnished, in essence the High Court directed modification of a vital term of the contract”.
It further held that
Page 8 of 12
“the statutory parameters have to be kept in view and the High Court can never alter or amend a contract entered into between the parties”.
In Raunaq International Ltd. vs. I.V.R. Construction Ltd. and
Others, reported in (1999) 1 SCC 492, this Court had occasion to dispose
of a case of paramount importance of Government contract. In the said
decision this Court has observed as follows:
“where rational non-discriminatory norms have been laid down for granting of tenders, a departure from such norms can only be made on valid principles. The award of contract cannot be by stopping the performance of the contract so awarded, there is a major detriment to the public because the construction of two thermal power units is held up on account of the dispute”.
The court further held:
“the award of a contract, whether it by a private party or by a public body or the State, is essentially a commercial transaction. In arriving at a commercial decision, considerations which are of paramount importance are commercial considerations, and the same would be:
(1) The price at which the other side is willing to do the work;
(2) Whether the goods or services offered are of the requisite specifications;
(3) Whether the person tendering has the ability to deliver the goods or services as per specifications. When large works contracts involving engagement of substantial manpower or requiring specific skills are to be offered, the financial ability of the tenderer to fulfil the requirements of the job is also important;
(4) The ability of the tenderer to deliver goods or services or to do the work of the requisite standard and quality;
Page 9 of 12
(5) Past experience of the tenderer and whether he has successfully completed similar work earlier;
(6) Time which will be taken to deliver the goods or services; and often
(7) The ability of the tenderer to take follow-up action, rectify defects or to give post-contract services”.
It was also held in the said decision:
“the public would also be interested in the quality of the work undertaken or goods supplied by the tenderer for poor quality of goods can lead to tremendous public hardship and substantial financial outlay either in correcting mistakes or in rectifying defects or even at times in re-doing the entire work – thus involving larger outlays of public money and delaying the availability of services, facilities or goods”.
13. The prime consideration on which the High Court set aside the
award of contract in favour of the appellant is that if the bid of respondent
no. 1 was considered in the tender process there would have been saving
of public money. However, that would not in any manner justify in going
through once again the same tender process, which is always time
consuming. Any delay in awarding the contract would only mean increase
in the cost of expenditure for cost of construction would go up with the
passage of time.
14. In W.B. State Electricity Board vs. Patel Engineering Co. Ltd.
and Others, reported in (2001) 2 SCC 451, this Court while considering
the issue with regard to the process of tender held:
“where bidders who fulfil prequalification alone are invited to bid, adherence to the instructions cannot be given a go-by by
Page 10 of 12
branding it as a pedantic approach, otherwise it will encourage and provide scope for discrimination, arbitrariness and favouritism which are totally opposed to the rule of law and constitutional values”.
It was also held:
“the very purpose of issuing rules/instructions is to ensure their enforcement lest the rule of law should be a casualty”.
It was further held:
“the contract is awarded, normally, to the lowest tenderer which is in public interest and that it is equally in public interest to adhere to the rules and conditions subject to which bids are invited”.
15. Following the aforesaid legal principles laid down by this Court, we
are of the considered opinion that the respondent no. 1 was negligent and
was not sincere in submitting his pre qualification documents within the
time schedule laid down despite the fact that he had information that
there is a time schedule attached to the notice inviting tenders. Despite
being aware of the said stipulation he did not submit the required
documents within the stipulated date. Pre-qualification documents were
received by the respondent no. 2 – University only after time schedule
was over. The terms and conditions of the tender as held by the Supreme
Court are required to be adhered to strictly, and therefore, the
respondent no. 2 – University was justified in not opening the tender
submitted by respondent no. 1 on 01.12.2008, which was late by three
days. According to us no grievance could also be made by the respondent
no. 1 as lapse was due to his own fault. The High Court proceeded to
interfere with the entire process as if acting as an appellate authority over
Page 11 of 12
the decision of the University which was beyond the jurisdiction of the
Court. The High Court was not justified in accepting the contentions of
respondent no. 1 and thereby upsetting the entire process of inviting
tenders by interfering with the terms and conditions of inviting the
tenders and by rescheduling and directing the process of re-tendering,
which would only cause further delay and would increase the burden on
the exchequer of the University.
16. In that view of the matter, we set aside the Judgment and Order of
the High Court and upheld the decision of the University in awarding the
contract in favour of appellant. Accordingly, the appeal stands allowed.
……………….……………………..J. [Dr. Arijit Pasayat]
……………....………………………J. [Dr. Mukundakam
Sharma]
New Delhi, February 20, 2009
Page 12 of 12