M/S PARAG CONSTRUCTION Vs STATE OF MAHARASHTRA .
Bench: LOKESHWAR SINGH PANTA,V.S. SIRPURKAR, , ,
Case number: C.A. No.-006712-006712 / 2008
Diary number: 17708 / 2007
Advocates: MANIK KARANJAWALA Vs
SUNIL KUMAR VERMA
“REPORTABLE”
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.6712 OF 2008 (Arising out of SLP(C) No. 16825 of 2007)
Parag Construction …. Appellant
Versus
State of Maharashtra & Ors. …. Respondents
J U D G M E N T
V.S. SIRPURKAR, J.
1. Leave granted.
2. A Division Bench Judgment passed by the Bombay High Court,
dismissing the Writ Petition filed by the appellant herein is in challenge
before us. By the said petition, the petitioners/appellants had
challenged the acquisition of land, bearing Final Plot No. 22A, 22B and
22C of the Town Planning Scheme (hereinafter referred to as ‘TPS’ for
short) of Borivali (East). In this Writ Petition, the following prayers were
made:
“(a) that this Hon’ble Court be pleased to issue a writ of Certiorari or a writ in the nature of certiorari or any other
1
appropriate writ, order or direction under Article 226 of the Constitution of India calling for the records of the proceeding adopted by the Respondent No. 7 under the Provisions of Maharashtra Regional Town Planning Act, 1966 in respect of land bearing final plots 22A, 22B and 22C admeasuring 13980 sq. yards of Town Planning Scheme Borivali-II, Borivali (E) and consider the propriety of the action taken by the Respondent No. 7 and quash and set aside the proceedings adopted by the Respondent No. 6 and 7 for the said land in year 1996;
(b) that this Hon’ble Court be pleased to issue a writ of Mandamus or a writ in the nature of Mandamus or any other appropriate writ, order or direction under Articles 226 of the Constitution of India directing the Respondents to forthwith stay their action pursuant to Letter of Intent issued by the Respondent No. 6 in favour of the Respondent No. 4 for development of land mentioned in the said letter dt. 18.04.2006 annexed as Exh. ‘F’ hereto and set aside the permission granted in the Letter of Intent issued in favour of the Respondent No. 4;
(c) that this Hon’ble Court be pleased to restrain the Respondent No. 2 from taking action pursuant to notice dt. 21.08.2006 issued to the Petitioners/appellants as Exh. ‘P’ hereto;
(d) pending the hearing and final disposal of the Petition this Hon’ble Court be pleased to grant interim order restraining the Respondents, their servants, subordinates, officers and agents from in any manner acting upon the Letter of Intent dt. 18.04.2006 issued by the Respondent in favour of the Respondent No. 4 for development of the land mentioned therein under Slum Redevelopment Scheme:
(e) Not relevant.
2
(f) Not relevant. (g) Not relevant.”
3. The petitioners/appellants, inter alia, claimed that they had
become the owner of land admeasuring 11944 sq. yards, bearing Final
Plot No. 7A1, 7A3 and 7B and bearing Survey Nos. 88 and 89, (2) Final
Plot No. 13A, bearing Survey No. 8 admeasuring 22,635 sq. yards and
(3) Final Plot No. 22A, 22B and 22C bearing Survey No. 6 admeasuring
13,980 sq. yards in village Kanheri, Taluka Borivali, Mumbai Suburban
District, total admeasuring 48569.59 sq. yards. The petition was in
respect of land bearing Final Plot No. 22A, 22B and 22C admeasuring
13,980 sq. yards.
4. The petitioners/appellants claimed to have purchased the said
property under the certificate of sale dt. 24.9.1981 issued by the
Prothonotary and Senior Master, High Court of Bombay in suit No. 42 of
1972 pursuant to the Orders passed by the Learned Single Judge of the
High Court on 11.10.1982 in Chamber Summons No. 450 of 1982.
5. The petitioners/appellants restricted their claim to a plot
admeasuring 1485.89 sq. mtrs., shown by red colour boundary in a map
attached to the petition. The petitioners/appellants further claimed that
out of the total property purchased from the Court Receiver, land
bearing Final Plot No. 13A of TPS of Borivali-II was acquired by the
Land Acquisition Officer and they had been paid a sum of Rs.2,80,984/-
3
by way of compensation for the said acquisition. They further pointed
out that there was some litigation in respect of land bearing Final Plot
No. 7B, which was settled by filing Consent Terms in this very Court.
They claimed that the land bearing Final Plot No. 7A1 and 7A3 of TPS
of Borivali-II was used by the petitioners/appellants for construction of a
building, namely, ‘Ghanshyam Towers’ and that the present petition was
in respect of part of land which bears Final Plot No. 22A, 22B and 22C.
6. The petitioners/appellants further claimed that they came to know
in May, 2006 that someone was trying to develop a portion of the said
land under the Slum Rehabilitation Authority Scheme and hence, they
had written a letter dt. 2.5.2006 to the Chief Executive Officer, Slum
Rehabilitation Authority (hereinafter referred to as ‘SRA’ for short) to
furnish the information. They claimed to have obtained a copy of the
Letter of Intent dt. 18.4.2006, which was in favour of Respondent No. 4
Siddhivinayak Developers. It was claimed that the said letter was in
respect of the land admeasuring 1485.89 sq. mtrs. under the Slum
Development Scheme. It is precisely in respect of this land that the Writ
Petition was filed. The petitioners/appellants further pointed out that this
Letter of Intent in favour of Respondent No. 4 Siddhivinayak Developers
was illegal, as the property in respect of which the rights were given to
develop the same land, belonged to the petitioners/appellants and it was
without any notice to the petitioners/appellants that the said property
came to be allegedly acquired by the respondent No. 6, Municipal
4
Corporation of Greater Mumbai (hereinafter referred to as ‘the
Corporation’ for short), and was further intended to be given away in
favour of Siddhivinayak Developers for development. The
petitioners/appellants further claimed that they received a notice dt.
27.6.2006 from the City Survey Officer Borivali, informing the
petitioners/appellants that the said Authority would take measurements
and would fix boundary of the disputed property on 5.7.2006, for which
the petitioners/appellants had already raised objections vide letter dt.
1.6.2006 and thereafter, also by letter dt. 24.7.2006. The
petitioners/appellants also pointed out that the whole exercise was
illegal and that they had also filed a Small Causes Suit No. 3233 of 2006
in Bombay City Civil Court at Bombay. They pointed out that they tried
to obtain ad-interim injunction on 14.7.2006, when it was pointed out by
the defendants/respondents that the property {described in civil suit as
part of Final Plot 22B (Pt.) in para 2 and in prayer clause (c)} was
already acquired under the provisions of Maharashtra Regional Town
Planning Act, 1966 (hereinafter referred to as ‘the Act’ for short) way
back in the year 1996 and in the Revenue records also, the said
property stood in the name of the Corporation except the Final Plot No.
22A, which was already allotted to one Shri Anant P. Velkar and 6
others. They averred that the City Civil Court refused to grant ad-interim
injunction. They claimed that it was then, that they came to know that
Final Plot Nos. 22B and 22C were allotted to the Corporation after the
acquisition and the Corporation had paid the compensation of
5
Rs.91,214.35 to Shri Anant P. Velkar and 6 others, which could not have
been given to them. The petitioners/appellants, therefore, challenged
the entire action of the acquisition of the land bearing Final Plot No. 22B
and 22C of TPS of Borivali-II by respondent No. 7, the Arbitrator under
the provisions of the Act, on the ground that it was contrary to the
provisions of the said Act.
7. In short, the petitioners/appellants claimed the right to a notice on
the basis of their ownership through the sale certificate mentioned in
the earlier part of the judgment and claimed the right to a notice on the
basis of that all the further actions without any notice to the
petitioners/appellants, were illegal and non-est. It was on this basis, that
the whole proceedings of acquisition were challenged before the High
Court. The petition was opposed by the SRA, the Corporation, as also
by the Arbitrator, so also by 2 other respondents, namely, Ashtavinayak
Cooperative Housing Society Ltd. and Siddhivinayak Developers on
various grounds. Ultimately, the High Court has come to dismiss the
Writ Petition, which judgment is in challenge before us.
8. Before the High Court, the respondents had raised the defence
that the petitioners/appellants had already resorted to alternative
remedy by filing Small Causes Suit No. 3233 of 2006 in Bombay City
Civil Court at Bombay and when they failed to obtain any interim relief,
they have approached this Court. The further plea raised was about the
6
laches. It was further pleaded that the concerned land had become a
part and parcel of the TPS of Borivali-II and was never available for the
Court sale. It was further pleaded that by the TPS, which came into
effect on 15.04.1996, the concerned plot of land was allotted to
respondent No. 6, the Corporation and under the said TPS, the said plot
was reserved for public purpose and the compensation thereof was also
paid to the owners after its acquisition and, therefore, there was no
question of the petitioners’/appellants’ right, title or interest in the land.
It was pointed out that even prior to the publication of TPS of Borivali-II,
an Arbitrator was already appointed under Section 72(1) of the Act and
in pursuance of that, ultimately a scheme was finalized and published by
him, which came into force from 15.4.1996 and, therefore, the
petitioners/appellants could not claim any interest in that land.
9. The High Court traced the history and found on the basis of the
affidavit filed by the Corporation along with the documents that when the
arbitration proceedings in respect of the Scheme were initiated in the
year 1972, then the concerned land was original plot No. 22, which
ultimately became Final Plot Nos. 22A, 22B and 22C. It was found that
Final Plot No. 22B was reserved in the TPS for Health Centre, while
Final Plot No. 22C was reserved for garden and the Final Plot No. 22A
had been allotted in lieu of original plot No. 22 to Shri Anant P. Valkar
and 6 Ors. The High Court found that the arbitration proceedings were
initiated by notification No. TPB-4762-M dt. 18.10.1962 and one
7
Mr. J.G. Keskar was appointed as Town Planning Officer. A public
notice dt. 3.1.1963 was also given and hearing was also conducted by
the Arbitrator on 29.4.1972. After Mr. J.G. Keskar, Mr. K.S. Keswani
came to be appointed as Arbitrators, who again gave an opportunity to
the interested parties for hearing on 22.4.1975 and the minutes of the
said hearing dt. 22.4.1975 were signed by all the interested parties.
After Mr. Keskar, Mr. Keswani dealt with the matter as an Arbitrator and
thereafter, the final decision was issued by Mr. V.D. Kulkarni. Firstly,
the draft Scheme was finalized on 07.07.1978 and then the final scheme
was submitted by Mr. G.D. Karkare, the Arbitrator to the State of
Maharashtra on 15.4.1983 for final sanction. It was so sanctioned by a
Government Notification dt. 7.3.1996 w.e.f. 15.4.1996. The High Court
noted that the occupants of the structures were also noticed and they
had also appeared on 27.10.1975 and were heard in the matter. The
High Court found that originally, the TPS of Borivali-II was sanctioned on
27.1.1931 and came into force w.e.f. 15.3.1931. The first variation of
the TPS was initiated by Borivali Municipality on 11.9.1956 and on
1.2.1957, the area of Borivali Municipality merged in Bombay Municipal
Corporation (‘the Corporation’ herein) and on 29.2.1960, the
Corporation decided to vary the principal scheme. The State
Government had also authorized the Collector of Bombay and Bombay
Suburban District to make and publish a draft variation scheme and
thus, on 26.9.1962, the draft variation scheme was sanctioned by the
Government. There were, in all, five Arbitrators appointed, whose
8
names have come earlier in this judgment and ultimately, the last
Arbitrator Mr. V.D. Kulkarni had finalized the draft scheme on 7.7.1978.
The High Court noted that the matter was also dealt with by the
Appellate Tribunal, which decided the appeal on 4.11.1982 and
thereafter, the then Arbitrator Mr. G.D. Karkare submitted the Scheme to
the State Government on 15.4.1983 after incorporating the decisions of
the Appellate Tribunal, which was approved by the Government of
Maharashtra on 7.3.1996 w.e.f. 15.4.1996. Thus, the High Court came
to the conclusion that the Arbitrator had submitted the final Scheme to
the Government, as required by Section 82(2) of the Act and it stood
sanctioned. The High Court also took notice of the fact that the
petitioners/appellants had filed a Civil Suit and they failed to obtain the
injunction and thereafter, the present petition was filed. The High Court
also noted the fact that Shri Anant P. Velkar and 6 others, who were the
original owners, were allotted plot No. 22A in lieu of whole original plot
No. 22, which was divided into plot Nos. 22A, 22B and 22C. The High
Court further noted that the Suit in respect of that property was pending
as Civil Suit No. 42 of 1972, in which there was a settlement on
27.6.1978 and it was only after the settlement and judgment in this Suit,
that the petitioners/appellants allegedly purchased the property.
However, even prior to this, the land in question got divested as per the
TPS of Borivali-II of the Corporation and it was only then, that Shri Anant
P. Velkar and 6 others were allotted Final Plot No. 22A and also
accepted the compensation in lieu of the entire plot No. 22. The High
9
Court also noted that when the draft Scheme was finalized, the owners
were already informed and they had fully participated. In short, the High
Court came to the conclusion that even before the petitioners/appellants
purchased the property from the Court Receiver on 24.9.1981, much
water had flown under the bridge, in the sense that the draft Scheme
was finally prepared and as such, the petitioners/appellants had no right
or claim, so as to insist upon a notice, while taking over the possession
of the property in question. The High Court also found that the
petitioners/appellants could not have purchased this property, since it
had already vested with the Corporation in terms of the order passed by
the Arbitrator. The claim of the petitioners/appellants that they were in
possession of the property, which was given to them by the Court
Receiver, was also disputed by the respondents and rejected by the
High Court. The High Court, ultimately, observed that if at all the
petitioners/appellants had any claim, title or interest, it can be only
against Velkar & Family, who were the original owners of the land and
were parties in the Civil Suit No. 42 of 1972. However, the
petitioners’/appellants’ claim regarding Final Plot Nos. 22A, 22B and
22C, admeasuring 13,980 sq. yards, could not be entertained. This is
how the petition came to be dismissed.
10. Shri Shyam Diwan, Learned Senior Counsel, appearing for the
appellant, basically urged that the petitioners/appellants have and had
good title and they alone were entitled to develop the property. In
10
support of this, the Learned Senior Counsel heavily relied on the Sale
certificate dt. 24.9.1981, issued by the Bombay High Court, as also
other incidental facts that at the time of acquiring Final Plot No. 13A, the
petitioners/appellants’ right was recognized in those land acquisition
proceedings. He also pointed out that the petitioners/appellants had
undertaken development and construction of plot No. 7B in pursuance
to the Consent Terms entered in this very Court on 23.10.2002 and in
those proceedings, the Corporation was a party. The Learned Senior
counsel further invites our attention that a commercial building known as
‘Ghanshayam Towers’ was constructed by the petitioners/appellants on
Final Plot Nos. 7-A1 and 7-A3 after duly obtaining the sanction from the
Corporation. Lastly, the Learned Senior Counsel urged that the property
cards maintained by the City Survey Office were also maintained by
posting a suitable mutation entry dt. 23.1.1986, showing the name of the
petitioners/appellants as a holder in place of Velkar & Family in respect
of plot No. 22B and 22C.
11. After this assertion of ownership, the Learned Senior Counsel
develops his further argument that there could be no lawful vesting of
plot Nos. 22B and 22C, incorporated under Section 88 of the Act. The
Learned Senior Counsel suggested that it was consistently the case of
the Corporation that this vesting took place only from 15.4.1996 and in
support of this stand three affidavits were filed before the High court, in
which this very case was pleaded. The Learned Senior Counsel took
exception to the proceedings before the Arbitrators, which were relied
11
upon by the Corporation. The Learned Senior Counsel went to the
extent of saying that the record appeared to be concocted and did not
represent a true state of affairs. On that basis, the case pleaded was
that once there was lawful prior acquisition of the rights by the
petitioners/appellants from the Court Receiver, there was no question of
the petitioners/appellants not being given any notice and hence, the
subsequent land acquisitions must fail, thereby, there would further be
no question of the vesting of the property in the Corporation. The
Learned Senior Counsel also took exception to the huge delay on the
part of the State Government to sanction the Scheme, which was about
13 years. The Learned Senior Counsel, therefore, assailed the sanction
to the proposed Scheme by the Arbitrator, also. The Learned Senior
Counsel also suggested that there was no lawful vesting of plot Nos.
22B and 22C in the Corporation, even under Section 83 of the Act. The
Counsel buttressed his arguments by suggesting that Section 83 was
never resorted to or relied upon by the Corporation and there was
nothing on record to suggest that the possession of the initial Final Plot
No. 22B was ever taken by the Corporation. The Learned Senior
Counsel also assailed the theory of advance possession taken under
Section 83, on the ground that there was no lawful arbitral award or
decision or sanction. Lastly, the Counsel argued that there was no
document to show vesting of Final Plot No. 22C through the advance
possession procedure. The so-called possession receipts, which were
filed by the Corporation, were also seriously disputed and ultimately, the
12
Counsel argued that unless the Scheme was finally sanctioned by the
State Government under Section 86, there could be no finality with
respect to the TPS. In short, the contention was that since there was no
vesting of the land under Section 83(3) and since before the alleged
vesting on 15.4.1996, the property was purchased by the
petitioners/appellants from the Court Receiver in whose custody the
property was, the petitioners’/appellants’ rights could not be jeopardized.
Lastly, it was contended that respondent No. 3 and 4 had no rights,
whatsoever, as they had no title and, therefore, the Letter of Intent dt.
18.4.2006 was liable to be withdrawn. We were taken through the
various provisions of the Act. While commenting on the High Court
judgment, the Learned Senior Counsel contended that the High Court
had ignored the principles of natural justice, secondly, it had given
palpably erroneous factual references and the High Court had also
given an incorrect finding on the vesting of the property.
12. Shri Arvind V. Sawant, Learned Sr. Counsel, Shri Sanjay V.
Kharde, Shri Pallav Shishodia, as also Shri Arun Pednekar, Learned
Counsel, appearing on behalf of the contesting respondents like
Ashtvinayak Cooperative Housing Society Ltd., SRA, the Corporation
and the Arbitrator respectively, supported the judgment of the High
Court. Again by relying on various provisions of the Act, the parties
traced the history of the proceedings, which ultimately led to issue of a
notification in 1996. The respondents also took us through the various
13
Sections, Rules, as also the Scheme Rules under the Act. Before we
take up the rival contentions and the considerations, we would have to
trace the history even at the cost of repetition and also consider the
various provisions of the Act and the schemes thereunder.
13. The disputed land is, undoubtedly, a part of the TPS Borivali-II,
which was sanctioned on 27.1.1931. On 26.9.1962, Draft TPS Borivali-
II, which was of First Variation came into existence and ultimately, the
earlier plot No. 22 was divided in 3 plots, being Final Plot No. 22A, 22B
& 22C. The Final Plot No. 22A was allotted to Anant P. Velkar and six
others, who were the original owners of the property, Final Plot No. 22B
was reserved for health centre and Final Plot No. 22C was reserved for
a recreational ground by sanction of Government dated 4.5.1993. The
arbitration proceedings started on 18.10.1962. However, since the
earlier proceedings were inconclusive, they were recommenced under
the Act, which came on the anvil in 1966. Before the Arbitrator, a
Vakalatnama was filed on behalf of the Velkar Family and they all
appeared through advocate. They did not take any objection to the
possession, being taken of Final Plot No. 22B. We find from the record
that Mr. Vakil, Advocate, appearing on behalf of the Velkar Family was
agreeable to possession of Final Plot No. 22B and 22C being taken over
by the Corporation immediately under Section 83 of the Act. Civil Suit
No. 42 of 1972 was filed for partition between the members of the Velkar
Family and amongst the other properties, these three plots (Final Plot
14
Nos. 22A, 22B and 22C) came to be included. An endorsement was
found by the Arbitrator on 22.04.1975 to the effect that plot No. 22A was
allotted to Shri Velkar & 6 others, while rest of the land was acquired
under the Scheme for Health Centre and garden, being Final Plot Nos.
22B and 22C respectively. In the Civil Suit, a consent decree came
to be filed on 27.6.1978 and this decree also included the disputed
properties, namely, all the three plots. A Court Receiver was
appointed for effecting the partition as per respective share of the
parties to the Suit. An order is found on the record of the Civil Suit to the
effect that in the event, the Commissioner could not conveniently allot
the properties to the concerned parties, such property should be sold by
way of auction. Sh. Shishodia, learned counsel for the respondents,
brought to our notice that there is no document or material evidence to
show that the Court Receiver ever took even a symbolic possession of
the property and thus, the property continues to be in possession of the
parties.
14. On 4.10.1979, a notification appeared in the Gazette in exercise
of powers under Section 83(2), directing the arbitrator to take
possession of the original plot No. 22 (part), being Final Plot No. 22B.
The Arbitrator took the possession of the Final Plot No. 22B (Pt.) and
handed over the same to the Corporation. This happened on 16.6.1980.
Even before this, notices were also sent on 8.2.1980 for taking the
possession under Section 83(3). This date, i.e., 8.2.1980 is extremely
15
important, as it suggests that the action for taking the possession was
already initiated, even before the auction by Civil Court. Though on
24.9.1981, the present appellant claimed to have acquired the property
in the auction of this property along with other properties, there does not
appear to be any document or evidence to show any follow up action,
suggesting the taking of possession of Final Plot No. 22B or 22C on
behalf of the petitioners/appellants from the Court Receiver. Some
persons had filed the appeals before the Appellate Tribunal on
4.11.1982, but nothing happened to that. Ultimately, on 15.4.1983, the
then Arbitrator drew the final scheme and tendered it to the Government
for grant of sanction. It was on 22.6.1985, that these areas were
declared as slums under the Maharashtra Slum Areas (Improvement
Clearance and Redevelopment Act, 1971) (hereinafter called “Slum Act”
for short). The Government exercised its power of extending the time
on 6.3.1996 and ultimately, a notification came to be issued by the
Government of Maharashtra on 7.3.1996, granting approval under
Section 86(2) to the TPS with effect from 15.4.1996. By operation of
Section 86(3), the TPS became part of the Act and under Section 88(a),
all lands required by the planning authority vest absolutely in planning
authority, i.e., the Corporation, free from all encumbrances and all the
other rights in the original plot shall determine. It was on 18.4.2006 that
the SRA issued a Letter of Intent in favour of the 4th Respondent herein.
It was then that the Civil Suit was filed by the petitioners/appellants in
the Civil Court, being Civil Suit No. 3233 of 2006 for cancellation of
16
above Letter of Intent and it was then that the petitioners/appellants
asserted his ownership over the property described as Final Plot No.
22B(Pt.). The petitioners/appellants were informed that land bearing
Final Plot Nos. 22B and 22C stood allotted to the Corporation, for which
the compensation of Rs.91,214.35 was paid to the Velkar Family. As
has already been suggested, the Trial Court did not grant injunction,
wherein, the claim was made by the petitioners/appellants that the
plaintiff’s right in the land subsisted and was not affected by the
acquisition thereof in favour of the Corporation. It was then that the Writ
Petition came to be filed purportedly, challenging the Letter of Intent dt.
18.4.2006.
15. Shri Shishodia pointed out that there is one other Letter of Intent
issued on 12.9.2006, which was in supercession of earlier Letter of
Intent dt. 18.4.2006, however, the petitioners/appellants have not so far
challenged the Revised Letter of Intent. We have deliberately stated the
history in order to test the claim of the petitioners/appellants that they
had acquired the title to the land in dispute and, therefore, any
acquisition proceedings without notice to them, could not materialize.
When we see the development of the proceedings under the Act, it
would be seen that the first Arbitrator was Shri J.G. Keskar, who had
issued notice to the concerned parties like Shri Velkar & 6 others. It
must be noted here that at that juncture, petitioners/appellants were
nowhere in the picture. In fact, petitioners/appellants came on the
17
picture only on the day when they purportedly purchased the property
involved in the Suit on 24.9.1981, which was way beyond the earlier
mentioned date of 8.2.1980, when the notices were already issued
under Section 83(3) for taking possession. Learned Counsel Shri
Shishodia, as well as Shri V. Savant and Shri Kharde, appearing for the
respondents asserted before us that on 27.6.1978, this property,
particularly, the Final Plot No. 22 could not have been in the hands of
the Receiver as the Receiver could only hold the property, which
belonged to the Velkar Family and much before that, the proceedings
were concluded, at least the Draft final Scheme was passed, and the
advance possession procedure was also adopted, thereby, there was no
question of the Receiver being in possession of the concerned property
or his giving the possession of the said property in favour of the
petitioners/appellants. The petitioners/appellants, undoubtedly, may
have purchased the other properties involved in the Suit, however,
insofar as this particular property was concerned, the learned Counsel
for the respondents insisted that the Receiver could not have been in
possession of the property, nor could he have granted the possession of
the properties to the petitioners/appellants. It is with that idea that the
learned Counsel rightly submit that there is absolutely no proof
anywhere that the petitioners/appellants were given the possession of
the concerned property.
18
16. On this backdrop when we see the history of the proceedings
under the Act, it is clear that Shri Keskar, who was the first Arbitrator
was followed later on by Shri P.G. Sirdesai, Shri J.B. Kamat, Shri K.S.
Keswani, Shri V.D. Kulkarni and it was Shri V.D. Kulkarni, who had
finalized the Scheme on 7.7.1998. The High Court had also noticed this
factor that the Appeal was decided by the Appellate Tribunal against the
Draft Scheme on 4.1.1982 and thereafter, Shri G.D. Karkare, who had
stepped into the shoes of Shri Kulkarni, had submitted the Scheme to
the State Government on 15.4.1983 after incorporating the decisions of
the Tribunal of Appeal and ultimately, it was this Scheme, which came to
be finalized and approved by Government of Maharashtra on 15.4.1996
by way of first variation. On the Backdrop of this, the learned Counsel
rightly contend that the claim of the petitioners/appellants to have
become owner of the property, cannot stand.
17. Mr. Shyam Divan, Learned Sr. Counsel, appearing on behalf of
the appellants very strenuously contended that apart from the certificate
of the Court Receiver, the petitioners/appellants was in fact, put in
possession on 13.12.1983 by the Court Receiver himself as per the
possession receipt. He also pointed out that in respect of other
properties, which were purchased, on Final Plot Nos. 7-A1 and 7-A3, the
petitioners/appellants had constructed a building called ‘Ghanshyam
Towers’. So also, in respect of a Final Plot No. 7B, there was some
dispute which was settled by the consent terms dt. 23.10.2002 before
19
this Court. The contention is attractive, but, meritless. It will be seen
that number of other properties, besides the concerned property were
purchased by the petitioners/appellants and there is nothing to
disbelieve that version that the petitioners/appellants were auctioned
purchasers. However, that does not mean that the
petitioners/appellants became the owner of the concerned properties in
Final Plot No. 22 and more particularly, Final Plot No.22B and 22C. The
prayer in civil suit related to Final Plot No.22B (Pt.) while the prayer in
writ petition is delightfully vague. It is only in respect of Letter of Intent
without mentioning specific plot number. It is obvious that the other
properties were not part of the TPS or at least, they have not been
shown as the part of the TPS. Even if it is accepted that the
petitioners/appellants had became the owner and dealt with those
properties that does not help the petitioners/appellants, insofar as the
present property is concerned, as it was already a part of the TPS and
the possession thereof was already taken under Section 83(3) by the
Arbitrator. Shri Divan urged that Section 83(3) did not apply. Section 83
is as under:-
“83. (1) Where a Planning Authority thinks that in the interest of the public, it is necessary to undertake forthwith any of the works included in a draft scheme for a public purpose, the Planning Authority shall make an application through the Arbitrator to the State Government to vest in it the land (without any building) shown in the draft scheme.
(2) The State Government may, if satisfied that it is urgently necessary in the public interest to empower the Planning Authority to enter on such land for the purpose of executing any of such works, direct the
20
Arbitrator, by notification in the official Gazette to take possession of the land, or may, after recording its reasons refuse to make any such direction.
Provided that, no such direction shall be made without the Arbitrator giving a hearing to any person or Planning Authority affected by such direction, and considering the report of the Arbitrator in that behalf.
(3) The Arbitrator shall then give a notice in the prescribed manner to the person interested in the land the possession of which is to be taken by Arbitrator requiring him to give possession of his land to the Arbitrator or any person authorized by him in this behalf within a period of one month from the date of service of notice and if no possession is delivered within the period specified in the notice, the Arbitrator shall take possession of the land and shall hand over the land to the Planning Authority. Such land shall thereupon, notwithstanding anything contained in this Act, vest absolutely in the Planning Authority free from all encumbrances.”
The contention was raised under sub-Section (3). The action of
taking the possession under Section 86(2) by the Arbitrator could be
done only when the Arbitrator gives a notice to the person interested in
the land. The learned Senior Counsel contended that the
petitioners/appellants were, undoubtedly, “person interested”, as the
petitioners/appellants came on the land via sale certificate in
September, 1981. This is clearly an incorrect argument, for the simple
reason that the petitioners/appellants merely purchased the properties
of Velkar Family in the auction in September, 1981, however, there is
nothing on record to suggest that the possession of those properties
was given by the Receiver. Indeed it could not have been given, for the
simple reason that the possession was already taken earlier in the year
21
1980 under the notice to Velkar family. Again the petitioners/appellants
were not anywhere in the picture, so as to insist upon a notice. It is
obvious that in the earlier proceedings under the Act, the
representatives of Velkar Family were properly heard and the Arbitrator
had proceeded perfectly in tune with the provisions of the Act. We do
not have any reason to dispute the claim on behalf of the Corporation,
as also the Arbitrator that the possession was taken in the year 1980
itself. If that is so, at that time, since the petitioners/appellants were not
on the picture, there was no question of giving any notice to them or
hearing them under Section 83(2). Shri Divan also, very heavily relied
on the property cards maintained by the City Survey Office, which were
amended by a mutation entry dt. 23.1.1986, which showed the name of
the petitioners/appellants as the holders in place of the Velkars. We
have no difficulty in accepting that the property cards were indeed
amended, but that by itself, will not give any benefit to the
petitioners/appellants, for the simple reason that a mere amendment in
the property cards of City Survey Office cannot and could not create a
title in favour of the petitioners/appellants. The entries may have a
presumptive value, however, that would not be sufficient. We have
already shown that the Velkar Family had lost the possession way back
in 1980 itself and the concerned plot was included in the Draft Scheme.
Under the circumstances, there was no question of the ownership
and/or possession being transferred to the petitioners/appellants by the
court receiver. If that is so, the amended property cards of City Survey
22
Office loose all the significance. It is needless to mention that this
contradiction stands explained by the affidavits of city survey
department and the Corporation and the officers of Corporation.
18. At this juncture, it will be better to consider some provisions
regarding the TPS and its legal implication. Under Section 59(1)(a), the
Planning Authority for the purpose of implementing the proposals in
Final Development Plan, prepares the TPS for the area in its jurisdiction
or any part thereof. Under Section 60, the Planning Authority declares
its intention to make a TPS and within 30 days, publishes the
declaration in the Official Gazette and a copy of the Plan is available for
inspection to the general public. Under Section 61, a Draft Scheme is
prepared. The limitation for it is 12 months. However, even if the
Scheme lapses because of the elapse of time of 12 months, that is no
bar for making fresh declaration. Section 65 provides for the power of
the Planning Authority to reconstitute the plots, while Section 68 speaks
about the power of the State Government to sanction the Draft Scheme.
Under sub-Section (2), though there is a limitation provided, Section 68
(2) gives power to the State Government to extend the time within which
the Draft Scheme can be sanctioned. Section 69 imposes restrictions
on use and development of land after declaration of TPS. Section 71
deals with the disputed claims as to the ownership of any land included
in the TPS or its declaration. Section 72 provides for the Arbitrator, who
is to be appointed immediately after the publication of the Draft Scheme.
23
Section 72(3) deals with the duties of such Arbitrators. Section 73 gives
finality to the decisions of the Arbitrator. We have already seen the
features of Section 83 under which the advance procedure can be
started for taking the possession. In the wake of all these provisions, we
have examined the records at the request of Shri Shyam Divan, Learned
Senior Counsel for the petitioners/appellants, including the possession
receipts. Shri Divan tried to criticize the proceedings before Arbitrator
and tried to show that the possession was not properly taken or given to
Corporation, however, it is obvious that the petitioners/appellants cannot
question all those claims because the petitioners/appellants were
nowhere in the picture at that time. We are satisfied with the
proceedings before the Arbitrator and we are also satisfied that the
Arbitrator had already taken the advance possession under Section 86
(2) and 83(3) and had also forwarded a draft Scheme.
19. Lastly, Shri Divan tried to argue that the State Government in this
case, had taken unduly long period of 13 years for sanctioning the
Scheme. He pointed out that if the Scheme was sent in 1983, it was
only sanctioned with effect from 15.4.1996, which was not possible. The
Counsel urged that though the State Government has power to extend
the period for sanctioning the Scheme, it could not be stretched to the
unreasonable period of 13 years. We appreciate the argument,
however, considering the fact that the area is from a very busy locality
like Borivali, Mumbai, the legal complications because of the pending
24
suits and the unduly long time taken in finalizing the Scheme, we hold,
that by itself, cannot invalidate the whole Scheme. In our opinion,
therefore, the petitioners/appellants have not been able to prime facie
prove the petitioners/appellants title or possession, vis-a-vis, the land in
question. Some minor contentions were raised by Shri Divan regarding
the breach of Section 82(2), as also, Rule 18 of the MRTP (Maharashtra
Regional and Town Planning) Rules. However, all those challenges
must fall in view of the fact that the petitioners/appellants had not been
able to prime facie establish his contentions regarding title and
possession. We do not mean to decide about the title of the
petitioners/appellants, however, all these enquiries and our observations
are only related to the Scheme and the claims made by the
petitioners/appellants, that the acquisition proceedings of the land in
question were bad, as they were not given any notice thereof. It is only
with that angle, that our observations should be read. It will be perfectly
open for the petitioners/appellants to establish their rights, if any, in
relation to the land in question in proper forums.
20. This takes us to a further question as to whether this Writ Petition
was tenable at all. It has been strenuously contended by Shri Savant,
Learned Senior Counsel, Shri Shishodia and Shri Kharde, Learned
Counsel, that the claims in Civil Suit and the Writ Petition were almost
identical and the Civil Suit was still pending, when the Writ Petition
came to be filed, after the injunction was refused to the
25
petitioners/appellants. The contention of the petitioners/appellants,
however, was that the frame of the Suit and the frame of the Writ
Petition are distinct. According to Shri Divan, Learned Senior Counsel
for the appellant, no reliefs in the Civil Suit were directed in the
proceedings under the Act, while the Writ Petition was in respect of the
illegalities, which vitiated the proceedings under the Act. According to
Shri Divan, the principal relief in the Writ Petition was directed against
the arbitral proceedings by the Arbitrator, culminating in the final
sanction of 1996 and since the directions dt. 18.4.2006 and the Survey
Notice dt. 21.8.2006 were consequential reliefs, they were included in
the petition. According to the Learned Counsel, the scope of the Suit
was primarily directed at the bogus and fraudulent Letter of Intent,
granted after inflating the number of occupants entitled to rehabilitation,
and since the petitioners/appellants as the owners, had not granted any
‘No Objection Certificate’, there was no scope for giving any Letter of
Intent to any other party for developing the plots. Shri Divan also
argued that under Section 149 of the Act, there is a bar to the
jurisdiction of the Civil Court and, therefore, the petitioners/appellants
were justified in filing the Writ Petition. We would not go to the extent of
saying that the Writ Petition was altogether barred, since the High Court
had entertained the Writ Petition and had chosen to dispose it of on
merits. We leave the question at that, as we have found that the High
Court was right in dismissing the Writ Petition on merits, more
particularly, holding that the petitioners/appellants could not assert their
26
entitlement to the notice, particularly, in view of the finalized proceedings
of Arbitration under the Act.
21. We must also take into consideration the argument on the part of
the respondents, that the petition was hopelessly belated. It cannot be
disputed that the Government had finalized the Scheme on 6.3.1996
and 7.3.1996. It is difficult for us to believe that the
petitioners/appellants asserting their title over the land and who are in
the construction business themselves as the builders, could not and did
not have the idea about the Scheme dt. 15.4.1996. It is also surprising
that the petitioners/appellants have come to know about the Scheme
etc. only when the Counter affidavit came in the Suit in reply to their
injunction application. It is also difficult to believe that the
petitioners/appellants had no idea, whatsoever, about the TPS, the Draft
of which was sanctioned as back as on 26.9.1962. We find that the
TPS was finalized on 7.7.1978 and right from 1972 to 1978, the
proceedings before the Arbitrator were in progress. If the
petitioners/appellants claimed to have come on the property by way of
an auction purchase in the year 1981, which included Final Plot No. 22,
it cannot be believed that the petitioners/appellants would have no idea
about the state of affairs regarding the Scheme, which was already
finalized in 1978. There is a clear reference to the Town Planning
Scheme II of Borivali in the Certificate dated 24.09.1981 which is a basic
document of the petitioners/appellants. It is again difficult to believe that
27
the petitioners/appellants did not have idea that the possession of this
plot was already taken by the Arbitrator in the year 1980 itself from
Velkars. At any rate, at that stage, when the possession was taken, if at
all anybody had any grievance, it was the Velkars and not the
petitioners/appellants, because the petitioners/appellants were nowhere
on the scene on that date. Therefore, it could not lie in the mouth of the
petitioners/appellants that the possession was illegally taken from
Velkars or was not taken at all. There are enough documents on record
to prove that the possession was actually taken and was thereafter
handed over to the Corporation. Even at the cost of repetition, we may
say that we have carefully seen the records regarding possession of the
plot being taken and being given to the Corporation. On the other hand,
there is nothing to suggest that the Court Receiver actually took the
physical or symbolic possession of Final Plot No. 22C. At any rate, the
appointment of the Court Receiver could not have affected the earlier
pending proceedings before the Arbitrator. It also does not lie in the
mouth of the petitioners/appellants, that there was no notification under
Section 83(2). In fact, the notification under Section 83(2) dt. 21.9.1979
was duly published in official gazette on 4.10.1979. In the wake of this
notification, if the petitioners/appellants came on the legal scene in the
year 1981, they were bound to enquire about the properties which they
had allegedly purchased in the Court auction. We are, therefore,
convinced that the petitioners/appellants maintained a sinister silence
right from 1983 till they ultimately filed the petition in the year 2006. We
28
are also surprised at the fact that though the petitioners/appellants
claimed to have got mutation in the year 1986 on CTS Survey, they did
not advert to the Corporation for mutation at any stage. All this brings
us to a conclusion that the petition was hopelessly belated. Even on
merits (presuming that the same could be considered), it is difficult to
appreciate the petitioners/appellants’ efforts to upset notification dt.
15.4.1996 by filing a Writ petition in 2006. We are, therefore, convinced
that the petition had no merits and was rightly dismissed.
22. However, the matters did not stand there, as at the end of the
arguments, Shri Divan also asserted that respondent No. 3 herein
Ashtavinayak Cooperative Housing Society Ltd. (proposed), as also
respondent No. 4 M/s. Siddhivinayak Developers did not have any locus
in the matter and could not be given the development rights for the
aforementioned plots. We have heard Shri Kharde, Learned Counsel
appearing on behalf of the SRA on that question.
23. In view of several slum dwellers in Mumbai City and Mumbai
Suburban Districts, since the slum dwellers had no basic amenities, the
Government of Maharashtra decided to redevelop the slums and framed
Development Control Regulation No. 33(10) (hereinafter called ‘DCR’).
The Maharashtra Government also amended the provisions of
Maharashtra Slum Area (I.C & R) Act, 1971 and inserted a chapter 1A
therein. SRA was established under Section 3A of the Slum Act for
29
implementation of the Slum Rehabilitation Projects in Mumbai City. At
the same time, Government of Maharashtra also amended the
provisions of Maharashtra Regional and Town Planning Act, 1960 (‘the
Act’ herein) and by these amendments, the powers of Planning Authority
were given to SRA for implementation of Slum Rehabilitation Projects.
This is how the SRA came into picture. The said Authority has issued
guidelines for implementation of the Schemes, under which the eligible
slum dwellers, i.e., 70% or more, have to form a society and appoint a
Chief Promoter. The said Chief Promoter has to collect all the
documents such as 7/12 extracts and PR Card of the plot on which the
slum is situated. Under the said Scheme, the Chief Promoter has to
submit an application in prescribed form Annexure 1, which describes
the details of the ownership of land, plot area, existing hutments,
amenities, Floor Space Index available and number of tenements to be
constructed. Annexure 2 to this application includes the details of the
plots, declaration of slum by the notification, structures on the plot,
details of slum dwellers, who have given consent in writing to the
proposed Slum Rehabilitation Scheme etc. The said Annexure 2 is
required to be certified by the land owning authority, in this case, the
Corporation. Annexure 3 prescribes the assessment of financial
capability of the Promoter. SRA scrutinizes the proposal submitted by
the Chief Promoter and Architect and then issues a Letter of Intent.
30
24. It is pointed out by the Learned Counsel for the SRA that in this
case, respondent Nos. 3 and 4 submitted the proposals for Final Plot
No. 22B in the year 2005. As the TPS was implemented for the said
area, it was apparent from the remarks obtained by the Architect that the
ownership of the plot was that of the Corporation. Accordingly, the
Corporation has issued Annexure 2 on 7.7.2005. It is asserted that the
SRA after scrutinizing the proposal issued the Letter of Intent on
18.4.2006, which was subsequently revised, and the revised Letter of
Intent was issued on 12.9.2006. It was pointed out by the Counsel that
respondent No. 4 developer had obtained all the necessary permissions
required under the Act and the Regulations and respondent No. 4 had
shifted the slum dwellers since 2006 to transit camps and the expenses
is borne by respondent No. 4. It was pointed out by the Counsel that it
was the right of the slum dwellers to choose their developer and appoint
him for the same by passing resolution in its meeting. In short, under
the Scheme, the Government or the land owners have no right to
impose a developer on the slum dwellers. The Learned Counsel was
also at pains to point out that under Section 14(1) of the Slum Act, if the
land owner was not prepared for allowing the development of the slums
on the encroached plot, the Slum Authority has the power to acquire the
property and proceed with the Scheme as per the wish of 70% of the
slum dwellers. It was pointed out by the Learned Counsel that only after
all these formalities, a Letter of Intent was issued in favour of
Ashtavinayak Cooperative Housing Society Ltd. (proposed) and M/s.
31
Siddhivinayak Developers, respondent Nos. 3 and 4 herein respectively,
who on their own expenses have arranged for the transit
accommodation of the slum dwellers in the said plot. Both Shri Savant,
as well as Shri Kharde, counsel for the respondents, pointed out that for
last two years, the slum dwellers are living at the expenditure of the 4th
respondent M/s Siddhivinayak Developers. This is apart from the fact
that the slum dwellers, who were uprooted from their tenements, were
now living at the far off place, suffering utmost on that account. Learned
Senior Counsel Shri Savant, urged that all these proceedings under the
Act would suggest that the Letter of Intent was issued properly. Shri
Savant also pointed out and referred to the provisions of Section 83(3)
of the Act, to point out that while M/s. Parag Construction, the appellant
herein, came on the scene on 24.9.1981 under the sale certificate dt.
21.9.1981, the Final Plot No. 22B had already vested in the Planning
Authority, i.e., the Corporation under Section 83(3) of the Act, the
possession of which was taken way back in 1980. He pointed out that
once the Arbitrator takes possession of the land and hands over the
land to the Planning Authority, such land vests absolutely in the
Planning Authority, free from all the encumbrances. The Learned
Senior Counsel rightly argued that the land which was handed over to
the Planning Authority, i.e., the Corporation, had vested in the Planning
Authority, free from all the encumbrances, including subsequent
encumbrances of the petitioners/appellants. We have already dealt with
this aspect earlier in the judgment and have already held that the land
32
had vested into the Planning Authority, particularly, after the sanction
under Section 86, as also under Section 88(a) of the Act.
25. The Learned Counsel also invited our attention to Section 88(b),
whereby, all rights in the original plots, which have been reconstituted,
are determined and the reconstituted plots became subject to the rights
settled by the Arbitrator. We have already approved the proceedings
before the Arbitrator. We have referred to all these contentions in order
to appreciate as to whether the appellants can find fault with the
proceedings under the SRA and more particularly, against the 3rd and 4th
respondent herein. We do not find any reason to interfere with any of
those proceedings.
26. As a desperate attempt, Shri Divan filed an affidavit on behalf of
the appellants that appellants should be permitted to develop the
specified land in the Letter of Intent dt. 18.4.2006 as per the terms and
conditions specified in the said Letter of Intent, for which the
petitioners/appellants shall deposit a sum of Rs.1 crore or such amount
as directed by this Court within 2 weeks from the date of the order with
the Chief Executive Officer (CEO) of respondent No. 5, SRA and that
the CEO may be permitted to utilize the aforesaid amount to the extent
required to compensate respondent No. 4 towards any expenses that
may have been incurred by them, pursuant to the Letter of Intent
towards rehabilitation of the slum dwellers, upon rendering of accounts
33
by the said respondent. We will not go into this aspect, particularly, at
this juncture, as we are concerned with the legality or otherwise of the
challenged judgment.
27. This is apart from the fact that the said affidavit has been met with
stiff opposition from M/s. Siddhivinayak Developers, who claimed that
they have already spent Rs.2.5 crores excluding the interest till date,
towards the expenses of formation of society, shifting of slum dwellers,
rental of slum dwellers, various security deposits and legal expenses in
defending present litigation and other expenses. It is asserted by the 4th
respondent that they have been working on this project for more than 3
years and under the circumstances, such an order should be made by
this Court. As has been stated earlier, we refuse to go into this
question. It will be for the parties to negotiate, if they want to, subject to
the approval of the SRA. With these observations, the appeal is
dismissed, but without any orders as to the costs.
………………………………..J. (Lokeshwar Singh Panta)
………………………………..J. (V.S. Sirpurkar)
New Delhi; November 19, 2008.
34