M/S JOY AUTO WORKS Vs SUMER BUILDERS (P) LTD.
Case number: C.A. No.-002131-002131 / 2009
Diary number: 2099 / 2008
Advocates: MANIK KARANJAWALA Vs
RAJINDER MATHUR
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2131_______OF 2009 (Arising out of S.L.P.(C)NO.1868 of 2008)
M/s Joy Auto Works & Ors. ... Appellants
Vs.
Sumer Builders (P) Ltd. & Anr. ... Respondents
J U D G M E N T
ALTAMAS KABIR, J.
1. Leave granted.
2. One Khatau Bhanji (hereinafter referred to
as ‘Bhanji’) was said to be the owner of
Original Plot No.227 measuring 4874.95 sq.
yards within the city of Mumbai. The
Arbitrator appointed under the Maharashtra
1
Regional and Town Planning Act, 1966
(hereinafter referred to as the ‘1966 Act’)
passed an Award on 24.2.1962 in respect of
the said plot and Original Plot No.231 owned
by one Javle. In terms of the Award, Javle
lost all his rights to Original Plot No.231
while Original Plot No. 227 was divided into
plot No. 878 (1000 sq. yards), plot No.879
(3647 sq. yds.) and plot No. 877. By virtue
of the said Award, Bhanji was given Final
Plot No. 879 measuring 3647 square yards in
lieu of Original Plot No.227, while Javle
was given plot No.878 measuring 1000 square
yards in lieu of Original Plot No.231, and
Plot No.877 was earmarked for the
construction of a 40 feet Development Plan
Road (hereinafter referred to as ‘DP Road’).
3. The appellants herein claimed that they had
been granted lease of 1305 sq. yards. out of
plot No.879 on 20.10.1962 by Bhanji, which
was contiguous to plot No.878, which was
2
also under the occupation of the appellants.
The appellant No.1 claims to have been
running an automobile garage and carrying on
other connected activities on the said
properties since 1979 and in connection with
the business it had two motorable accesses
to plot No.878 through the portion of plot
No.879 demised in favour of the appellant by
Bhanji, for egress and ingress to and from
the public road. According to the
appellants there was no other motorable
access either to plot No.878 or the portion
of the plot No.879 under the occupation of
the appellants.
4. According to the appellants in an attempt to
have them evicted from plot No.878 Javle
complained to the Bombay Municipal
Corporation that the said plot was being
used by the appellants for commercial
purposes although in the Development Plan
the same had been earmarked for residential
3
purposes. On such complaint notices were
issued for removal of the structures in
which such commercial activities were being
carried out. Ultimately, however, plot
No.878 was purchased by the appellants from
Javle and no further steps were taken by the
Bombay Municipal Corporation pursuant to the
said notices.
5. In the meantime, the respondent No.1
acquired Bhanji’s interest in the remaining
portion of plot No.879 and began obstructing
the use of the motorable access from the
public road to plot Nos.879 and 878.
Accordingly, on 11.6.2005 the appellants
wrote to the respondent No.1 informing it of
their right in Final Plot No.878 and the
portion of Final Plot No.879 under their
occupation together with the two access
roads. Since despite the said letter the
respondent No.1 brought two iron gates and
building-material to block the entrance to
4
plot Nos.878 and 879 from the public road,
the appellant No.2 and the original
plaintiff-Mulji Shah were compelled to file
L.C. Suit No.5570 of 2005 in the City Civil
Court at Bombay for perpetual injunction and
by Notice of Motion prayed for an injunction
to restrain the respondent from obstructing
or interfering with the use, occupation and
possession of plot No.878 and plot No.879 to
the extent of 1305 sq. yards together with
the structures thereupon with motorable
access to and from the public road through
plot No.879. The appellants prayed for an
injunction to restrain the respondents from
constructing or placing any gates upon plot
No.879, pending the hearing and final
disposal of the suit and also to restrain
the defendant No.2, the Bombay Municipal
Corporation, from approving any plans for
construction of a boundary wall or gates on
plot No.879, which would obstruct the free
5
and full use of the two accesses by the
appellants from the public road.
6. Considering the facts indicated hereinabove
the Trial Court initially granted an ad-
interim injunction against the respondent
No.1 on 23.12.2005. Upon notices being
served the respondents contested the claim
and respondent No.1 contended that he had
acquired the ownership of Final Plot No. 879
measuring 3043.50 sq. yards by a Deed of
Conveyance executed in his favour on
20.12.2004.
7. When the Notice of Motion was taken up for
hearing the Respondent No.1 contended that
in terms of the Town Planning Scheme–IV
(TPS-IV) there is a 40 feet wide D.P. Road
abutting plot No.878 through which the
appellants have a right of passage.
According to the respondents the appellants
have a right of passage from plot No.878
6
only from the D.P. Road and at no point of
time had they enjoyed any right of passage
through the property of the respondent No.1,
nor have they established any prescriptive
right or an easementary right of necessity
so as to attract the provisions of Sections
13, 19 and 41 of the Indian Easement Act,
1882.
8. After hearing the parties on the Notice of
Motion the Trial Court rejected the claim of
the appellants regarding the two access
points through plot No.879 but allowed the
appellants to use one of the two access
passages, referred to as Access No.2, to
reach their plot from the public road. Such
access was, however, denied for the use of
vehicles.
9. While passing the aforesaid order, the Trial
Court took note of the fact that Mr. Javle,
the vendor of Appellant No.2 had by Writ
7
Petition No.1667 of 1984 sought a direction
upon the Bombay Municipal Corporation to
remove the hutments on the land abutting
Final Plot No. 878 which had been set aside
for a 40 feet wide D.P. Road and to
construct the said road expeditiously. The
said writ petition was withdrawn on 7.8.1984
purportedly in view of the statement made by
the Bombay Municipal Corporation that action
would immediately be taken under the 1966
Act and that the demolition of
encroachments, which was preventing the
construction of the road, would be carried
out in accordance with law. A Notice issued
by the Bombay Municipal Corporation on
8.8.1984 to that effect, was challenged by
one Arun Sales, a licensee of the Appellant
No.1, who filed L.C. Suit No. 5822 of 1984
against the Bombay Municipal Corporation
challenging the said notice. Ultimately, the
Notice of Motion taken out in the suit was
dismissed and the suit itself came to be
8
disposed of in view of a settlement between
the appellants and some members of the Javle
family whereby the appellant No.2 acquired
Final Plot No.878 from the Javle family.
10. In the appeal preferred by the appellants
herein the appeal Court accepted the
position that the Original Plot No.227 had
been divided into Final Plot No.879
measuring 3043.50 sq. yards and Final Plot
No.878 which belong to appellant No.2 in
respect whereof there is no dispute.
However, the appeal Court also came to a
finding that there was no material on record
to show that the appellants had ever
exercised any right of access through Final
Plot No.879 belonging to the respondent No.1
and when the appellant No.2 purchased Final
Plot No.878 under TPS-IV it was clearly
understood that in order to approach the
said plot she would have a right of passage
through the proposed 40 feet wide D.P. Road
9
provided under the Scheme. As a result, the
appellant No.2 could claim a right of
passage to and from plot No. 878 against the
Bombay Municipal Corporation only through
the proposed D.P. Road. Furthermore, the
Appellant No.1 being the husband of the
Appellant No.2 and since the structure on
Final Plot No.879 was contiguous to Final
Plot No.878, he could also claim right of
passage from the said D.P. Road. The appeal
Court held that merely because the Bombay
Municipal Corporation had failed to
discharge its duties in providing a road and
passage to the appellants the appellants
could not claim such a right through
property belonging to others and thereby
create obstructions in their use of the
property. The appeal Court, accordingly
chose not to interfere with the limited
relief granted by the trial Court and
dismissed the appeal.
10
11. It is the said order of the Appeal Court
dated 12.12.2007 which is the subject matter
of challenge in the present appeal.
12. Appearing in support of the appeal Mr. C.A.
Sundaram, learned Senior Counsel emphasized
the fact that in the absence of any other
access to Final plot No.878 or the portion
of plot No. 879 the only means of access for
over 35 years had been through plot No.879
which formed part of the Original Plot
No.227 which was sub-divided into plot
Nos.878, 879 and 877. Mr. Sundaram also
submitted that the 40 feet wide D.P. Road,
indicated in the Development Plan under TPS-
IV, was only in contemplation when the Award
was passed by the Arbitrator under the 1966
Act and on account of the various
encroachments and obstructions the said road
has never been constructed. This, in fact,
had prompted Javle to file a Writ Petition
for a direction upon the Bombay Municipal
11
Corporation to remove the said encroachments
and constructions and to take up the
construction of the road immediately. Mr.
Sundaram submitted that in the absence of
any actual road adjacent to plot No.878, the
owner thereof had access to her land only
through plot No.879. Mr. Sundaram contended
that only after the respondent No.1 had
acquired the ownership of plot No.879 in
2004 that such right was attempted to be
disturbed by the Respondent No.1 by
threatening to put up a boundary wall and an
iron gate to prevent the use of such passage
which was being used for more than 35 years.
13. Mr. Sundaram submitted that though the
Special Leave Petition had been filed
against an interim order it had become
necessary to do so since the only means of
egress and ingress to and from plot No.878
and the portion of plot No.879 under the
possession of appellant No.1 would be
12
completely obstructed, if the respondents
were not restrained from obstructing the
motorable access to the said plots which the
appellants had been enjoying for over 35
years. Mr. Sundaram urged that the Courts
below had wrongly relied on only a proposal
for the construction of a 40 feet wide D.P.
Road adjacent to plot No. 878 in passing a
limited interim order without ascertaining
whether such road had actually been
constructed and was in existence. Mr.
Sundaram also submitted that both the Courts
below had lost sight of the fact that plot
No.878 and the portion of plot No.879 under
the occupation of the appellants was
completely land-locked since the
construction of the 40 feet wide D.P. Road
next to plot No.878 was still in the realm
of planning and had not yet been executed.
In other words, the appellants had no access
to their portion of the plots under their
occupation except through plot No. 879.
13
14. Mr. Sundaram’s submissions were strongly
opposed by Mr. Dushyant Dave, learned Senior
Counsel appearing for respondent No.1. He
strenuously urged that the appellants never
had any right of passage through plot No.879
and their access to plot No.878 and the
portion of plot No.879 under their
occupation was from the 40 feet wide D.P.
Road which was adjacent to plot No.878. Mr.
Dave also urged at the outset that the
Special Leave Petition was not maintainable
since it was directed against the orders
passed in an interlocutory application in
which concurrent findings of fact had been
arrived at.
15. Mr. Dave then contended that, in any event,
since plot No. 878 and the portion of plot
No.879 under the occupation of the
appellants had been earmarked in the Master
Plan for residential purposes under no
circumstances could the appellants be
14
permitted under the provisions of the 1966
Act to continue with commercial activities
thereupon.
16. Mr. Dave also contended that it is for the
very same reason that a complaint had been
made by Javle and notices had been issued
thereupon by the Bombay Municipal
Corporation to the appellants to remove the
structures which were being used for such
commercial purposes.
17. From the site plan which had been made Exh.
‘A’ in the suit, Mr. Dave pointed out that
the claim of the appellants to a right of
motorable access through plot No.879 renders
the said plot unfit for any use by the
respondent No.1 and that in the earlier
suits the appellants have never asserted
such right.
15
18. Mr. Dave submitted that while disposing of
the Notice of Motion dated 11.9.1975, the
learned Trial Court noticed the fact that
after obtaining an ad-interim order of
injunction, the appellants had tried to
convert the temporary structures on the
plots in question into a permanent ones. Mr.
Dave also submitted that while dismissing
the Notice of Motion, the High Court also
took into consideration the Town Planning
Scheme No.IV, Mahim, which came into force
on 15th August, 1963, whereunder the Final
Plot allotted to Bhanji and Javle could not
be used for commercial purposes and that
accordingly the appellants were not entitled
to an order of injunction which would have
the effect of altering the said Scheme and
the use of the plots earmarked for
particular purposes.
19. On behalf of the Bombay Municipal
Corporation it was submitted by Mr. Shekhar
16
Naphade, learned Senior Counsel, that in the
Development Scheme conceived by the Planning
Authority different plots had been earmarked
for different purposes. Mr. Naphade urged
that under the TPS-IV Scheme certain Final
Plots which had been identified for
industrial purposes could be used for such
purposes only. Similarly, except the plots
which had been allotted for ‘public
purposes’ the remaining plots could be used
for residential purposes and Final Plot Nos.
878 and 879 fell within the ambit of
paragraph 1(n) of TPS-IV and could be used
for residential purposes only. Mr. Naphade
submitted that the appellants had been
offered an alternative plot of land
measuring 500 sq. yards at Powell Land
Industrial Estate, Kondivili, Bombay, but
such offer had been turned down by the
appellants.
17
20. Ultimately, on the complaint made by Javle,
the appellants were issued notices under
Sections 89 and 90 of the 1966 Act to remove
the structures from the plots in question
and also for the eviction of the appellants
therefrom.
21. Mr. Naphade submitted that upon service of
the said notices, the appellants filed Suit
No.6544 of 1975 in the City Civil Court at
Bombay, inter alia, for a declaration that
the Final Scheme viz. TPS-IV was not binding
on the appellants and that the said notices
under Sections 89 and 90 of the said Act
were illegal and void and had no effect in
law. In the said suit, the appellants took
out a Notice of Motion for an ad-interim
order of injunction to restrain the Bombay
Municipal Corporation from demolishing the
structures which had been put up in Final
Plot No.878 and a part of Final Plot No.879.
Ultimately, as indicated hereinabove, the
18
Notice of Motion was dismissed and the
appeal taken against the said order was
withdrawn by Mulji Shah on 1st August, 1977.
Subsequently, on 29th September, 1977, Mulji
Shah filed another suit in the City Civil
Court in Bombay, being Suit No.7540 of 1977,
in which an ex-parte ad-interim order was
passed restraining the Bombay Municipal
Corporation from removing him from the Final
Plot No.878 and a part of Final Plot No.879
and from removing the structures thereupon
in any manner. The said Notice of Motion
came up for hearing in 1979 and was
dismissed for default and the ad-interim
injunction was vacated.
22. Mr. Naphade also submitted that thereafter
Dr. K.V. Javle filed Writ Petition No.1667
of 1984 and prayed for a Mandamus upon the
Bombay Municipal Corporation and its
officers to carry out their statutory
obligations under the 1966 Act and the rules
19
framed thereunder and in particular to give
effect to the TPS-IV, Mahim, by directing
the said authorities to remove all the
structures, temporary or otherwise, from
Final Plot No.878 and to direct the
authorities of the Bombay Municipal
Corporation to hand over and deliver vacant
possession of the said plot measuring 1000
sq. yards and for a further direction on the
said respondents to construct the DP road
adjoining Final Plot No.878. Mr. Naphade
pointed out that on the assurance given on
behalf of the Bombay Municipal Corporation
and its authorities that notice for
demolition would be issued under Sections 89
and 90 of the 1966 Act and served within two
weeks and demolition will be carried out as
prescribed in law, the writ petition was
allowed to be withdrawn by order dated 7th
August, 1984.
20
23. Mr. Naphade submitted that in 1984 a fresh
notice was given to the appellants for
removal of the structures on the plots in
question. Thereafter, as mentioned
hereinabove, Arun Sales, a licensee of the
Appellant No.1, filed L.C. Suit No.5822 of
1984 against the Bombay Municipal
Corporation challenging the notice dated 8th
August, 1984, and obtained interim orders
which were subsequently vacated.
24. Mr. Naphade contended that the structures
raised by the appellants were not in
conformity with the Town Planning Scheme
though in the suit filed by the appellants
an attempt has been made to make out a case
that since the 40 feet wide DP Road had not
yet been constructed by the Corporation, it
should not permit any new construction on
Final Plot No.879 so as to block the only
access available over the said plot to Plot
No.878. Mr. Naphade submitted that such a
21
case was against the provisions of the Town
Planning Scheme and taking advantage of an
order of injunction, the appellants could
not be allowed to continue to use plot
No.878 and the portion of plot No.879 in
their occupation for commercial purposes.
25. Mr. Naphade submitted that the learned Trial
Judge had, while denying motorable access
through plot No.879, allowed access
otherwise to the appellants from the main
road to the premises under their occupation.
26. Since the appellants have come up against
the refusal of the High Court to grant their
interim prayer to have motorable access to
plot No.878 and a portion of plot No.879
under their possession from the main road
through plot No.879 during the pendency of
the suit, we can only consider the case of
the parties on a prima facie basis, inasmuch
as, the suit is yet to be decided on merits.
22
The case being argued on behalf of the
appellants, may not ultimately be dependent
upon whether the appellants run any
commercial venture on plot No.878 and the
portion of plot No.879 under their
possession, but the question of such a right
of passage may ultimately be relevant if it
is established that there is no other access
to the said premises. Accordingly, having
regard to Exh.A in the suit, which is a site
plan which has been referred to as Exh.C in
the paper book at page 120, some provision
has to be made even at the interim stage to
preserve a motorable access from the main
road to the premises under the occupation of
the appellants so that upon development of
plot No.879 such a right is not totally
extinguished. While the Trial Court has
allowed access on foot from the main road to
the said premises, in our view, a motorable
access should be preserved at least till the
40 feet wide DP road adjacent to plot No.878
23
is available to the appellants for egress
and ingress from their portion of the
premises, which is otherwise land-locked, on
till the disposal of the suit.
27. It would not be appropriate on our part to
make any observation on the merits of the
case of the parties since the same is yet to
be decided. We are only required to ensure
the balance of convenience and inconvenience
and the equities between the parties at this
stage. We are also required to consider if
any of the parties will suffer irreparable
loss and injury unless an interim order, as
prayed for by the appellants, is allowed or
denied. This is not one of those cases where
the appellants may be suitably compensated
by damages in case their suit succeeds.
28. Having considered the submissions advanced
on behalf of the respective parties,
including that of the Bombay Municipal
24
Corporation, we are of the view that ad-
interim protection, as prayed for by the
appellants, should be given in the facts and
circumstances of the case.
29. We, therefore, direct that the appellants/
plaintiffs will be entitled to a motorable
access from the main road to Plot No.878
through Plot No.879 and the portion of Plot
No.879 in their possession either till the
disposal of the suit or till the
construction of the 40 feet wide D.P. Road
running adjacent to Final Plot No.878 by the
Bombay Municipal Corporation in terms of the
assurance given by it on 7th August, 1984, in
Writ Petition No.1667 of 1984 and also in
terms of the directions given in Writ
Petition No.2443 of 2006 filed by the
Respondent No.1 before the Bombay High
Court, whichever is earlier. However, once
the said 40 feet wide D.P. Road is
constructed by the Bombay Municipal
25
Corporation, giving clear motorable access
to Plot No.878, the Respondent No.1 should
no longer be deprived of the full enjoyment
of its property and will be entitled to move
the Trial Court to get the right of way
through Plot No.879 granted by this order
revoked and this order will not stand in the
way of such an order being passed by the
Trial Court, if it is satisfied that
sufficient motorable access is available to
the appellants on account of construction of
the 40 feet wide D.P. Road. We also make it
clear that the right of motorable access to
Plot No.878 through Plot No.879 granted by
this order to the appellants will not
preclude the Bombay Municipal Corporation
from taking any action as it may be entitled
to under the 1966 Act or other relevant
enactments in relation to the Town Planning
Scheme No.IV, Mahim. Furthermore, subject
to any order to the contrary that may have
been passed in any other proceeding, the
26
Bombay Municipal Corporation must implement
the assurance given by it on 7th August,
1984, when the Writ Petition No.1667 of 1984
was permitted to be withdrawn, regarding
construction of the 40 feet wide D.P. Road
adjacent to Final Plot No.878, with utmost
expedition.
30. We, therefore, allow the appeal to the
extent indicated hereinabove.
31. There will be no order as to costs.
________________J. (ALTAMAS KABIR)
________________J. (MUKUNDAKAM SHARMA)
New Delhi Dated:2.4.2009
27