M/S.GOAN REAL ESTATES & CONSTR.LTD. Vs PEOPLE'S MOVEMENT FOR CIVIC ACTION
Bench: K.G. BALAKRISHNAN,J.M. PANCHAL, , ,
Case number: C.A. No.-005281-005281 / 2008
Diary number: 19650 / 2008
Advocates: E. C. AGRAWALA Vs
ANITHA SHENOY
Non-Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5281 OF 2008 (Arising out of S.L.P. (C) NO. 16728 OF 2008)
Goan Real Estate & Construction Ltd. and another ... Appellants
Versus
People’s Movement for Civic Action And others ... Respondents
O R D E R
1. Leave granted.
2. This Court has heard the learned counsel for the
parties regarding relief claimed by the appellants.
3. The appeal is directed against order dated July 10,
2008, rendered by the High Court of Bombay at Goa in
Miscellaneous Civil Application No. 866 of 2007,
which was filed in Writ Petition No. 403 of 2007 by
which the parties have been directed to maintain
status quo in respect of construction within 50 to 100
meters of High Tide Line on survey Nos. 12/1 and
99/2 situated near river Zuari at Goa till the matter is
finally heard by the Court.
4. The record would indicate that after purchase of the
lands in question the appellants applied to the
Panchayat for sanction of plans for construction of
hotel. The permission was granted by the village
Panchayat on November 26, 1993. The Ministry of
Environment and Forests had issued a notification
called Coastal Regulation Zone for regulating the
development of areas within 500 meters of the coast.
The said notification was amended on August 16,
1994 reducing the “No Development Zone” to 50
meters from 100 meters. The appellant No. 1 had
submitted amended plans seeking permission to put
up construction leaving 50 meters “No Development
Zone”. The Village Panchayat had granted the
2
permission sought for. In Indian Council for Enviro-
Legal Action vs. Union of India (1996) 5 SCC 281, this
Court held that the amendment reducing the No
Development Zone from 100 meters to 50 meters was
illegal. The case of the appellants is that in view of
financial constraints and depressed market
conditions, the construction was not actively
progressed but building plans were revalidated by the
Panchayat from time to time and the respondent No. 4
has granted extension for a period of three years from
September 17, 2005. It may be mentioned that the
Ministry of Environment and Forests had clarified on
January 24, 2007 that the construction activities in
the zone between 50 to 100 meters would attract the
provisions of CRZ Notification from the date of
judgment of the Supreme Court. Though the
appellants had commenced construction prior to the
date of pronouncement of judgment by the Supreme
Court, the Additional Collector had not vacated the
stop work order passed on December 22, 2006. The
3
respondent No. 1 has filed Public Interest Litigation for
quashing the revalidating and grant of extension for a
period of 3 years to enable the appellants to put up
the construction of the plans granted to the
appellants. Similarly, the appellants have filed
petition challenging the validity of order by which they
were directed to stop construction work. The Bombay
High Court at Goa had recorded the statement of
Additional Solicitor General, appearing for MOEF,
Union of India in the petition filed by the appellants to
the effect that the project of the appellant No. 1 was
treated by MOEF as an ongoing project. In view of the
said statement, the learned Advocate General,
appearing for the State, had withdrawn the impugned
orders by which the appellants were directed to stop
the construction work.
5. It may be mentioned here that in the Public Interest
Litigation MOEF has filed reply confirming its stand
taken in the petition filed by the appellants and,
4
therefore, the High Court rejected the application
made in PIL for interim relief on September 12, 2007.
The High Court declined to grant interim relief noting
that the Central Government had itself referred the
matter to National Coastal Zone Management
Authority. The Court, while declining to grant interim
relief, directed the said Authority to consider the
matter after giving personal hearing to all parties. The
record shows that the said Authority gave hearing to
all the parties and has treated the project of the
appellants as an ongoing project. By the impugned
order the High Court has directed the parties to
maintain status quo regarding construction because
according to the High Court it was admitted by one of
the directors of the appellants that from 1997 to 2005
there was no construction activity and the Apex Court
has struck down amendment restricting the NDZ to 50
meters only.
5
6. As noted earlier, the project of the appellants is
treated to be an ongoing project. The decision dated
October 30, 2007 rendered by the National Coastal
Zone Management Authority is in favour of the
appellants, which is now challenged by the
respondents in PIL by amending the petition. Without
considering the validity of the same the impugned
interim direction should not have been granted, more
particularly, when interim relief was earlier refused to
the respondent. Grant of stay of construction activity
would result into considerable loss to the appellants
who have invested huge amount in the project. On
the facts and in the circumstances of the case this
Court is of the opinion that interest of justice would be
served if the appellants are permitted to complete
incomplete construction at their own risk and cost.
7. For the foregoing reasons the appeal partly succeeds.
The impugned order is set aside. During the
pendency of the petition before the High Court, the
6
appellants are permitted to complete the incomplete
construction work done by them at their own risk and
cost. The High Court is requested to dispose of the
matter on merits without being inhibited by this order
granting interim relief to the appellants as early as
possible and without any avoidable delay.
8. No costs.
………………………....…CJI. (K.G. BALAKRISHNAN)
…………………………....…J. (J.M. PANCHAL)
New Delhi; August 28, 2008.
7