M/S B.S.N.JOSHI & SONS LTD. Vs AJOY MEHTA
Bench: S.B. SINHA,CYRIAC JOSEPH, , ,
Case number: CONMT.PET.(C) No.-000245-000245 / 2007
Diary number: 13022 / 2007
Advocates: Vs
A. S. BHASME
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CONTEMPT PETITION NO. 245 OF 2007 IN
CIVIL APPEAL NO. 4613 OF 2006
M/s. B.S.N. Joshi & Sons Ltd. …Petitioner
Versus
Ajoy Mehta & Anr. …Respondents
J U D G M E N T
S.B. SINHA, J :
1. This contempt proceeding has been initiated against respondent Nos.
1 and 2 for alleged wilful disobedience of this Court’s order dated
31.10.2006, the operative portion whereof reads as under:
“…We, therefore, intend to give another opportunity to MAHAGENCO. It shall consider the offer of Appellant upon consideration of the matter afresh, as to whether it even now fulfils the essential tender conditions. If it satisfies the terms
of the tender conditions, the contract may be awarded in its favour for a period of one year; but such contract shall take effect after one month from the date of the said agreement so as to enable the private Respondents herein to wind up their business. This order is being passed in the interest of MAHAGENCO as also the private Respondents herein.”
2. The Maharashtra State Power Generation Co. Ltd. (for short
“MAHAGENCO”) issued a notice inviting tender, inter alia, for coal
liaisoning, quality and quantity supervision of its thermal power station.
One of the conditions laid down therefor is as under:
“(ii) The Bidder should have executed the work of total minimum quantity of 5 (Five) Million Metric Tons per year for preceding 5 years. Besides this bidder should have executed the work of total quantity of 10 (ten) Million MT’s in any of the preceding 5 (Five) years. Above execution of work should be on behalf of State Electricity Board and/or NTPC and/or other State or Central Undertaking and/or the private Power Generating Companies as their liaison agent/coal agent, with regard to receipt and supply of the coal including supervision on dispatch, loading, movement of the coal upto destination by Railway only.”
The term “year” occurring therein is said to be the financial year.
Petitioner along with various others submitted its tender, inter alia, on the
2
premise that the petitioner did not fulfill the essential conditions of having
transported the quantity of minimum five lakh tonnes of coal for the
preceding five years, its offer was not accepted.
3. A writ petition was filed before the Madhya Pradesh High Court,
which having been dismissed, Civil Appeal bearing No. 4613 of 2006 was
preferred by the petitioner upon obtaining special leave.
One of the questions which arose for consideration before this Court
was as to whether MAHAGENCO committed a serious error in not taking
into account the quantity of coal supplied by the petitioner to the Andhra
Pradesh Power Generation Corporation Limited; as it appears from its letter
dated 15.06.2005 that the petitioner had supplied the following quantity of
coal:
“S. No.
Period Name of Colliery Quantity in MT
01. 11.09.2003 to March 2004
M/s MCL Talcher 3172750.00
02. 01.10.2003 to 31.03.2004
M/s MCL, Ibvalley Area
316930.00 ----------------- 3489680.00 ----------------
3
03. 01.04.2004 to 10.09.2004
M/s MCL Talcher 2774455.00
04. 01.04.2004 To 30.09.2004
M/s MCL Ibvalley Area
389732.00 ---------------- 3164187.00 ----------------”
By a judgment and order dated 31.10.2006, this Court held:
“It is, therefore, evident that total quantity of 62,64,135 metric tones of coal had been handled by Appellant for them.
The intention of introduction of the said clause becomes self-evident from the aforementioned note. It may be true, as was observed by the High Court, that the Respondents in the tender documents did not categorically state that the block of 365 days in respect of handling of coal by the tenderes shall be taken into consideration. It is also true that the Corporation must be held to be aware as to what was the true intent and purport of the said term.”
4. It was, however, found that other tenderers, viz., M/s. Nair Coal
Services Ltd., Nagpur, M/s. Nareshkumar & Co. Ltd., Nagpur and M/s.
Karamchand Thapar & Brs. Ltd., Mumbai had formed a cartel.
4
Alleged contemnor Shri Ajoy Mehta, Managing Director of
MAHAGENCO (Respondent No. 1 herein) in a note dated 19.08.2005
stated as under:
“On perusal of rates of M/s Nair Coal Services Ltd., Nagpur, M/s Nareshkumar & Co Ltd., Nagpur and M/s Karamchand Thapar & Brs. Ltd., Mumbai, it is apparent that they have formed a cartel. The rates quoted by these firms are nearly 51 crs. to 52 crs. more than that quoted by LT. As a goodwill gesture the above parties were called for negotiations. However, they have refused to match the L1 rates.
In view of above it is in public interest and in the interest of MAHAGENCO a Govt. owned, public utility that the work is allocated to the lowest qualified bidder namely M/s B.S.N. Joshi & Co.”
Ultimately, however, the said proposal was not accepted.
5. Despite the fact that a cartel was formed, the contract was awarded to
the members thereof. In the aforementioned context, this Court observed:
“While saying so, however, we would like to observe that that having regard to the fact that a huge public money is involved, a public sector undertaking in view of the principles of good corporate governance may accept such tender which is economically beneficial to it. It may be true that essential terms of the contract were
5
required to be fulfilled. If a party failed and/or neglected to comply with the requisite conditions which were essential for consideration of its case by the employer, it cannot supply the details at a later stage or quote a lower rate upon ascertaining the rate quoted by others. Whether an employer has power of relaxation must be found out not only from the terms of the notice inviting tender but also the general practice prevailing in India. For the said purpose, the court may consider the practice prevailing in the past. Keeping in view a particular object, if in effect and substance it is found that the offer made by one of the bidders substantially satisfies the requirements of the conditions of notice inviting tender, the employer may be said to have a general power of relaxation in that behalf. Once such a power is exercised, one of the questions which would arise for consideration by the superior courts would be as to whether exercise of such power was fair, reasonable and bona fide. If the answer thereto is not in the negative, save and except for sufficient and cogent reasons, the writ courts would be well advised to refrain themselves in exercise of their discretionary jurisdiction.”
It was on the aforementioned premise, the Civil Appeal was allowed
by this Court.
6. Mr. Vikas Mehta, learned counsel appearing on behalf of the
petitioner, in support of the contempt petition, would argue:
6
(i) Alleged contemnors had from the very beginning gave a twist to
the said order insofar as it proceeded on the basis that the five
years period should be calculated from the date of the order of this
Courts.
(ii) MAHAGENCO refused to grant a contract in favour of the
petitioner relying on or on the basis of the interim order passed by
this Court.
(iii) A different stand is being taken now that the petitioner should not
be allotted any contract in view of a subsequent event, viz., the
letter dated 20.02.2007 issued by the Sanjay Gandhi Thermal
Power Station.
On the aforementioned premise, the learned counsel would submit
that the alleged contemnors must be held to have committed gross contempt
of this Court.
7. Mr. Altaf Ahmed, learned senior counsel appearing on behalf of the
alleged contemnors, on the other hand, would contend that:
7
(i) the alleged contemnors might have committed a mistake in
properly understanding the order of the court, but the same would
not mean that they have committed contempt of the court.
(ii) The term “year” having been found by this Court to mean a
financial year, even if the figures supplied by the petitioner are
taken into consideration, it cannot be said to have satisfied the
essential conditions for grant of contract of transportation of coal.
In any event, the learned Senior Counsel would submit that the
alleged contemnors are ready and willing to abide by any direction which
may be issued by this Court.
8. Supply of coal and that too good quality of coal is essential for
running of a thermal power station. It was with that intent in mind that this
Court, either at the interim stage or final stage, did not intend to pass any
order which would hamper transportation of coal resulting in stoppage of
the functioning of the thermal power station.
9. The alleged contemnors, in our opinion, misconstrued the order of
this Court for which there was no basis that they were bound by the interim
8
order passed by this Court. For the sake of clarity, we may notice the
interim order dated 27.03.2006 which reads as under:
“Learned counsel for the petitioner submits that the main petition is coming up for final hearing on 17th April 2006. Learned counsel appearing for respondent Nos. 2 & 3 submits that for purposes of generating power, coal supplies have to be continued to the respondents failing which the entire generation of electricity shall come to a standstill. Keeping in view this fact, the respondents are permitted to go ahead with their tender process including award of contract. They are free to make whatever arrangement they want to make in this behalf to ensure continued supply of coal to them. It is, however, made clear that whatever arrangement is made by the respondents the same will be subject to the final decision of this Special Leave Petition.”
[Underlining is ours for emphasis]
10. We, therefore, fail to understand as to how a fresh tender was floated
to allot the work of liaisoning of coal and the same companies who had
formed a cartel were allowed to carry on the contract job. We may,
however, place on record that the contracts were awarded on the condition
that the same would be subject to the final outcome and decision of this
Court.
9
11. Our attention has been drawn to the fact that the petitioner was asked
to file additional documents in support of its contention that it fulfilled the
essential conditions of contract, if it so intended to do. It was, however,
wholly unnecessary as only a fresh look was required to be given in regard
to the eligibility of the petition for the purpose of awarding the contract
wherefor the Scrutiny Committee was required to form an opinion as to
whether the petitioner had substantially complied with the tender
conditions, subject, of course, to the fulfillment of essential conditions.
12. Alleged contemnors, in our opinion, committed a serious error in
calculating the quantity of coal transported for preceding five financial
years from the date of the judgment. The date of the judgment was not at all
relevant for the aforementioned purpose. The alleged contemnors did not
explain how they have understood the order of this Court wrongly as they
had also proceeded on the basis that the five financial years should be
counted from the date of calling for the tender and the date of the judgment
separately. If they had any difficulty in understanding the direction of the
court, they should have approached this Court for clarification but could not
have arrived at such an absurd conclusion that what was necessary to be
10
considered is handling of coal by the petitioner for the preceding five years
from the date of passing of the judgment by this Court.
13. What was necessary for them to consider was implementation of the
directions issued by this Court in the backdrop of the events noticed by this
Court. This Court in its judgment had not only taken into consideration the
contentions raised by MAHAGENCO in regard to non-fulfillment of the
essential conditions on the part of the petitioner but also implications
thereof at some details.
They furthermore sought to take into consideration a purported
subsequent event, viz, the letter dated 20.02.2007 issued by the Sanjay
Gandhi Thermal Power Station, which was neither relevant nor decisive.
14. The alleged contemnors, therefore, in our opinion, did not read the
directions of the court in their proper perspective.
We say so:
(i) because they could not have considered the directions contained in
the interim order passed by this Court. The interim order merged
into the final order. In any event, even the said interim order was
11
subject to the decision of the court and, thus, we fail to understand
as to how the interim order was found to be continuing despite
passing of the final order.
(ii) As the matter was required to be considered afresh, the purpose of
considering the eligibility of the petitioner is concerned, they
committed a serious error insofar as the eligibility criteria were
applied from the date of the judgment.
(iii) They furthermore could not have ignored the note of the alleged
Contemnor No. 1 that the other respondents in the Civil Appeal
had formed a cartel. They furthermore did not notice that having
regard to the overall situation and particularly in view of the
opinion of the Scrutiny Committee that the petitioner had
substantially complied with the conditions and, thus, the general
power of relaxation should have been used.
15. It is, therefore, not a case where two interpretations of the judgment
of this Court were possible.
16. Before us an additional affidavit has been filed by Shri Ajoy Mehta,
Contemnor No. 1, stating:
12
“17. I, therefore, respectfully submit that we have not flouted the orders passed by the Hon’ble Court and we shall abide by all directions given by this Hon’ble Court including awarding of the contract to M/s BSN Joshi & Sons Ltd., Petitioner herein, if this Hon’ble Court so directs.”
Keeping in view the aforementioned statement made before us, we
accept the apology tendered by the alleged contemnors for the time being
and direct that the contract for a period of one year be granted to the
petitioner in terms of our judgment dated 31.10.2006.
17. We are distressed to see that MAHAGENCO had been encouraging
formation of a cartel and, thus, allowing the rate of transportation of coal to
go high up. Unless a power generating company takes all measures to cut
down such malpractices, the generation cost of electricity is bound to go
higher and ultimately the same would be passed on to the consumers of
electricity. We hope a public sector undertaking would take adequate and
appropriate measures to meet the said contingency in future.
18. The contempt petition is disposed of with the aforementioned
directions.
13
………………………….J. [S.B. Sinha]
..…………………………J. [Cyriac Joseph]
New Delhi. December 19, 2008
14