23 January 2009
Supreme Court
Download

M/S. ANSAL PROPERTIES & INDUSTRIES LTD. Vs STATE OF HARYANA

Bench: R.V. RAVEENDRAN,MUKUNDAKAM SHARMA, , ,
Case number: C.A. No.-008186-008186 / 2001
Diary number: 18202 / 1999
Advocates: Vs KAMAL MOHAN GUPTA


1

  REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 8186 OF 2001

M/s. Ansal Properties & Industries Ltd. ..Appellant

Versus State of Haryana & Anr. ..Respondents  

J U D G M E N T

DR. MUKUNDAKAM SHARMA, J

1. The issue that falls for our consideration in this appeal is in respect of a

demand of Rs. 61,000/- per gross acre, raised by the second respondent

towards  the  external  development  charges  but  actually  on  account  of

construction of internal community buildings, with a further stipulation

that no such charge would be realised from the plot holders.   

2. The appellant has challenged the said demand of the second respondent

as unlawful being contrary to the statutory provisions pertaining to the

construction  of  internal  community  buildings,  which  only  mandates

transfer of land free of cost to the Government, if the Government so

desires,  but  without  providing  for  any  amount  chargeable  from  the

2

licensee  to  the  Government  for  the  construction  of  these  internal

community buildings.    

3. These challenges are made by way of filing the present appeal which is

filed against the judgment and order of the Division Bench of the Punjab

and  Haryana  High  Court  dated  29.07.1999  whereby  the  writ  petition

filed by the appellant was dismissed.

4. Appellant is a public limited company registered and incorporated under

the  Companies  Act,  1956  and  is  into  the  business  of  real  estate

development  and  development  of  colonies.  Since  1983,  the  appellant

Company had been granted licenses by the Director, Town and Country

Planning (for short “Director”) being respondent No. 2 herein under the

provisions of Haryana Development and Regulation of Urban Areas Act,

1975 (for short the “Act”) and Haryana Development and Regulation of

Urban Areas Rules, 1976 (for short the “Rules”) for setting up colonies

in the District Gurgaon, Haryana.  For the said purpose, agreements were

entered  into  from  time  to  time  between  the  appellant  Company  and

respondent No. 2 in the prescribed form i.e. LC-IV,  under Rule 11 of the

Rules. The said licenses were renewed from time to time.

Page 2 of 32

3

5. As per clause 1 of the Licence Agreement,  the licensee is  required to

fulfil the conditions laid down in Rule 11 of the Rules.  However, before

we go into the various terms and conditions of the licence, we think it to

be useful to refer to and extract some of the relevant provisions of the

Act read with the Rules.  The said Act and Rules were framed to regulate

the use  of the  land,  in order to  prevent  ill  planned urbanization  in or

around the towns in the State of Haryana and the same inter alia governs

the  grant  of  licence  for  colonizing  upon  terms set  out  in  the  licence

agreement,  which  is  given in  the statutory form namely Form LC-IV.

The relevant provisions of the Act are quoted hereunder:-

“S.2.   Definition.  In  this  Act,  unless  the  context  otherwise requires:

…………………

(g)  “external  development  works”  include  sewerage,  drains, roads and electrical works which may have to executed in the periphery of, or outside, a colony for the joint benefit of two or more colonies:  

(i)    “internal development works” mean –  

metaling of roads and paving of footpaths;  

(ii) turfing and plantation with trees as open spaces;

(iii) street lighting;

(iv) adequate and wholesome water-supply;

Page 3 of 32

4

(v) sewers  and drains  both  for  storm and sullage water  and  necessary  provision  for  their treatment and disposal; and

(vi) any  other  work  that  the  Director  may  think necessary in the interest of proper development of a colony.

Section 3.  Application for licence. (1) Any owner desiring to convert  his  land into a colony, shall,  unless  exempted under section 9, make an application, to the Director, for the grant of a licence to develop a colony in the prescribed form and pay for it  such fee as  may be  prescribed.    The application  shall  be accompanied by an income-tax clearance certificate.

(2)……….

(3)    After the enquiry under sub-section (2), the Director by an order in writing, shall –  

(a) grant,  a  licence  in  the  prescribed  form,  after  the applicant  has  furnished  to  the  Director  a  bank  guarantee equal  to  twenty five  per  centum of  the  estimated  cost  of development  works  as  certified  by  the  Director  and  has undertaken--

(i) to enter into an agreement in the prescribed form for carrying  out  and  completion  of  development  works  in accordance with the licence granted:

(ii)……………………

(iii)…………...............

(iv) to construct at his own cost, or get constructed by an  other  institution  or  individual  at  its  cost,  schools, hospitals,  community  centres  and  other  community buildings on the lands set  apart  for this  purpose, or to transfer to the Government at any time, if so desired by the  Government,  free  of  cost  the  land  set  apart  for

Page 4 of 32

5

schools,  hospitals,  community  centres  and  community buildings,  in  which  case  the  Government  shall  be  at liberty to transfer such land to any person or institutions as it may deem fit;

(b)………

(4)  The licence so granted shall be valid for a period of two years and will be renewable from to time for a period of one year, on payment of prescribed fee.

(5) A separate licence shall be required for each colony.  

Section 5.  Cost of Development Works – (1) The colonizer shall deposit fifty per centum of the amount realised, from time to time, by him, from the plot-holders within a period of ten days of its realisation in a separate account to be maintained in a scheduled bank.  This amount shall only be utilized by him towards meeting the cost of internal development works in the colony.   After the internal development works of the colony have  been  completed  to  the  satisfaction  of  the  Director,  the colonizer shall  be at liberty to withdraw the balance amount. The  remaining  fifty  per  centum of  the  said  amount  shall  be deemed to  have  been retained by the colonizer,  inter-alia  to meet the cost of land and external development works.

(2) The colonizer shall maintain accounts of the amount kept in  the  scheduled  bank,  in  such  manner  as  may  be prescribed.

Sec. 8  Cancellation of license – (1)  A license granted under this Act, shall be liable to be cancelled by the Director if the colonizer contravenes any of the conditions of the license or the  provisions  of  the  Act  or  the  rules  made  thereunder, provided that  before such cancellation  the colonizer  shall  be given an opportunity of being heard.  

Page 5 of 32

6

(2)  After cancellation of the licence, the Director may himself, carry out or cause to be carried out, the development works in the colony and recover such charges as the Director may have to incur on the said development works from the colonizer and the  plot-holders  in  the  manner  prescribed  as  arrears  of  land revenue.

(3) The  liability  of  the  colonizer  for  payment  of  such charges shall not exceed the amount the colonizer has actually recovered from the plot-holders less the amount actually spent on such development works, and that of the plot-holders shall not  exceed  the  amount  which  he  would  have  to  pay  to  the colonizer towards the expenses of the said development works under the terms of the agreement of sale or transfer entered into between them;

Provided  that  the  Director  may, recover  from the  plot holders with their consent, an amount in excess of what may be admissible under the aforesaid terms of agreement of sale or transfer.

(4) Notwithstanding anything contained in this Act, after the colony  has  been  fully  developed  under  sub-section  (2),  the Director may, with a view to enabling the colonizer, to transfer the possession of and the title to the land to the plot-holders within a specified time, authorize the colonizer by an order to receive the balance amount, if any, due from the plot-holders, after adjustment of the amount which may have been recovered by the Director towards the cost of the development works and also transfer the possession of or the title to the land to the plot- holders within aforesaid time.  If the colonizer fails to do so, the  Director  shall  on  behalf  of  the  colonizer  transfer  the possession of  and the title  to the land to the plot-holders  on receipt of the amount which was due from them.

(5) After  meeting  the  expenses  on  developments  works under sub-section (2), the balance amount shall be payable to the colonizer.”  

Page 6 of 32

7

Some of the provisions of the Rules which require mention are extracted

herein below;

4. Percentage of area under of roads, open spaces etc. in layout plans section ; 3(4) and 24 :-  (1) In the layout plan of a colony other than an industrial colony, the land reserved  for  roads,  open  spaces,  schools,  public  and community buildings and other common uses shall  not be less than forty five percent  of the gross area of the land under the colony :

Provided  that  the  Director  may reduce  after  recording reasons therefor this percentage to a figure not  below thirty- five  where in  his  opinion  the planning requirements  and the size of the colony so justify.

(2) In the layout plan of an industrial colony, the land reserved for the purpose specified in sub– rule (1) shall not be less than thirty five percent of the gross area of the land under the colony :

Provided  that  the  Director  may reduce  after  recording reasons therefor this percentage to a figure not below twenty wherein his opinion the planning requirements and the size of the colony so justify.  

5. Development works to be provided in colony; section 3(3)  –  The   designs  and  specifications  of  the development  works  to  be  provided  in  a  colony  shall include:-

(a) metaling of roads and paving of footpaths ; (b) turfing and plantation with trees of open spaces ; (c) street lighting ; (d)adequate and wholesome water supply ;

(e) sewers and drains both for storm and sullage water   and necessary provision for their treatment and disposal ; and  

(f) any  other  works  that  the  Director  may  think  necessary  in  the interest of proper development of the colony.  

Page 7 of 32

8

11. Conditions  required  to  be  fulfilled  by  applicant, Section 3(3) - The applicant shall:-

(a) furnish to the Director a bank guarantee equal to twenty five per cent of the estimated cost of the development work as certified by the Director and enter into an agreement in form LC-IV  for  carrying  out  and  completion  of  development works in accordance with the licence finally granted;

(b)undertake  to  deposit  fifty  percent  of  the  amount  to  be released by him from the plot  holders,  from time to time, within ten days of its realisation in a separate account to be maintained in a scheduled bank and this amount shall only be utilized towards meeting the cost of internal development works in the colony;

(c) undertake to pay proportionate development charges if the main lines of roads, drainage, sewerage, water supply and electricity  are  to  be  laid  out  and  constructed  by  the Government or any other local authority.  The proportion in which and time within which such payment is to be made shall be determined by the Director.

(d) undertake responsibility for the maintenance and upkeep of all  roads,  open  spaces,  public  parks  and  public  health service for a period of five years from the date of issue of the  completion  certificate  under  rule  16  unless  earlier relieved of this responsibility and thereupon to transfer for all such roads, open spaces, public marks and public health service free of cost to the Government or the local authority as the case may be;

(e) undertake to construct at his own cost or get constructed by any  other  institution  or  individual  at  its  cost,  schools, hospitals,  community  centres  and  other  community buildings on the land set apart for this purpose, or undertake to transfer to the Government at any time if so desired by the Government free of cost, the land set apart for schools, hospitals, community centres and community buildings, in which  case the Government  shall  be  at  liberty to  transfer

Page 8 of 32

9

such  land  to  any  person  or  institution  including  a  local authority on such terms and conditions as it may deem fit; and  

(f) undertake  to  permit  the  Director  or  any  other  officer authorized by him to inspect the execution of the layout and the development  works in the colony and to  carry out  all directions issued by him for ensuring due compliance of the execution  of  the  layout  and  development  works  in accordance with the licence granted.

(2) If the  director,  having regard  to  the  amenities  which exist  or  are  proposed  to  be  provided  in  the  locality, decides that it  is not necessary or possible to provide such  amenity  or  amenities,  the  applicant  will  be informed thereof and clauses (c), (d) and (e) of sub-rule (1)  shall  be  deemed  to  have  been  modified  to  that extent.

12. Grant of Licence. Section 3(3) and (4) –  (1) After the applicant has fulfilled all the conditions laid down in  rule  11  of  the  satisfaction  of  the  Director,  the Director shall grant the licence in form LC-V.

(2) The licence granted under sub-rule (1) shall be valid for a period of two years from the date of its grant during which period  all  development  works  in  the  colony  shall  be completed and certificate of completion obtained from the Director as provided in rule 16.

Rule 14 of the Rules empowers the Director to renew the licence for a

period of one year provided he is satisfied that the delay in execution of the

development works was for the reasons beyond the control of the colonizer.

Rule 18 on the other hand provides that where the execution of the lay out

Page 9 of 32

10

plan  and  construction  of  other  work  is  not  proceeded  according  to  the

licence granted under Rule 12, or is below the specification or is in violation

of the provisions  of  any law or the Rules, the Director  by a notice shall

require the colonizer to remove various defects within the period specified

in the notice and if the colonizer fails to comply with the requirements, after

hearing the colonizer,  the Director may either cancel the licence or grant

him further time for complying with the requirement.

6. Form LC-III which is part of the Rules is the proforma of the letter to be

written by the Director to the colonizer referring to his application for

the grant of licence to set up a colony.  The said proforma requires the

Director to inform the colonizer that it was proposed to grant the licence

to him for setting up a colony and that he should fulfil the conditions laid

down in     Rule 11.   The said letter  is  to  be sent  by the Director  in

compliance with the provisions of Rule 10.  It is only after receipt of the

aforesaid  letter  that  a  colonizer  enters  into  an  agreement  with  the

Director  in  Form LC-IV.  The said  Form LC-IV which is  part  of the

statutory rule 11 is the format of the agreement which the owner of the

land intending to set up a colony enters into with the Director for and on

behalf of the Government of Haryana.

Page 10 of 32

11

7. A bare look of the said agreement which is a part of the record would

make it clear that many of the terms and conditions of the agreement are

extracts of the provisions of the Act and the Rules.  It is also provided in

the said agreement that colonizer would carry out all directions issued by

the  Director  for  due  compliance  of  the  execution  of  lay  out  and

development works in accordance with the licence granted.

8. It is also provided therein that without prejudice to anything contained in

the said agreement, all the provisions contained in the Act and the Rules

would  be  binding  on  the  owner.   In  order  to  better  appreciate  the

contention  raised  by  the  parties,  we  have  extracted  the  relevant

provisions of the Licence Agreement entered into between the appellant

and respondent      No. 2, herein.  

1. In consideration of the Director agreeing to grant licence to the owner to set up the said colony on the land mentioned in Annexure  hereto  on the fulfillment  of  all  the  conditions  laid down in Rule 11 by the Owner,   the owner hereby covenants as follows:

a) That  the  Owner  shall  be  responsible  for  the maintenance  and  upkeep  of  all  roads  open  spaces, public parks and public health services for a period of five years  from the date of  issue of  the  completion certificate  under rule  16  of  the  Rules  unless  earlier relieved of this responsibility, when the Owner shall transfer all such roads, open spaces, public parks and public health services free of cost to the Government or the Local Authority as the case may be.

Page 11 of 32

12

b) That  the Owner shall construct at his own cost or get constructed by any other institution or individual  at its  cost,  schools,  hospitals,  community  centres  and other  community building  on  the land set  apart  for this  purpose  or  undertake  to  transfer  to  the Government  at  any  time,  if  so  desired  by  the Government  free  of  cost,  the  land  set  apart  for schools,  hospitals,  community  centres  and  other community buildings, in which case the Government shall  be  at  the  liberty  to  transfer  such  land  to  any person  or  institution  including  Local  Authority  on such terms and conditions as if may lay down.

c) That  the  owner  shall  deposit  fifty  percent  of  the amount realized by him from plot holders, from time to time, in a separate account to be maintained in a Scheduled  Bank and that  this  amount  shall  only be utilized  by the  Owner  towards  meeting  the  cost  of internal development works in the colony.

d) That  the  Owner  shall  permit  the  Director  or  other Officer authorized by him in this behalf to inspect the execution of the layout and the development works in the  colony  and  the  Colonizer  shall  carry  out  all directions issued by him or ensuring due compliance of  the  execution  of  the  layout  plans  and  the development  works  in  accordance  with  the  licence granted.

e) That the Owner shall pay proportionate development charges as and when required and as determined by the  Director  in  respect  of  external  development charges.

f) That without prejudice of anything contained in this agreement all the provisions contained in the Act, and these rules shall be binding on the Owner.

2. Provided always and it is hereby agreed that if the Owner commit any breach of the terms and conditions of this

Page 12 of 32

13

agreement or violate any provisions of the Act or these rules, then and in any such case, and notwithstanding the waiver of any previous clause or right, the Director, may cancel the licence granted to him.

3. Upon cancellation of the licence under Clause 2 above the Govt. may acquire the area of the aforesaid colony under the Land Acquisition Act, 1894 and may develop the said area under any other law.   The Bank Guarantee in  that  events  shall  stand  forfeited  in  favour  of  the Director.

4. The stamp and registration charges on this deed shall be borne by the Owner.

5. The  expression  “the  Owner”  herein  before  used  shall include  his  heirs,  legal  representatives,  successors  and permitted assigns.  

The last clause (clause 6) provides that on completion and grant of

the completion certificate, the Director may release the bank guarantee on

the application filed by the appellant Company.

9. In  the  present  case,  the  respondent  No.  2  by  letter  dated  11.01.1988

informed the appellant Company that it was required to pay due amount

of  Rs.  3.72  lacs  per  gross  acre  on  account  of  external  development

charges.  It was also mentioned in the said letter that an amount of Rs.

3.72 lacs per gross acre, in fact includes Rs. 61,000/- per gross acre on

account of internal community buildings for which no recovery should

Page 13 of 32

14

be made from the plot holders.  It was also mentioned in the said letter

that credit would be given by Haryana Urban Development Authority for

the internal  community buildings already constructed by the colonizer

namely the appellant.  Again under letter dated 07.10.1993, the appellant

Company was informed that before its licence could be considered for

renewal, the appellant Company was required to pay the aforementioned

charges.  Subsequently on 04.05.1994, respondent No. 2 issued letter to

the  appellant  informing  that  the  licence  of  the  appellant  would  be

renewed only after the deposit of the aforesaid amount.   Aggrieved by

the aforesaid letter, the appellant Company made several representations

to respondent Nos. 1 and 2 contending inter alia that as per the licence

agreement and also as per the provisions of the Act and the Rules the

appellant Company was not liable to pay the amount of Rs. 61,000/- per

gross acre towards the construction of internal community buildings.  It

was also submitted in the said representations by the appellant that the

Director  had  wrongly  included  the  above  said  amount  and  the  said

demand was not only unjust  and arbitrary but  also contrary to licence

agreement  and  also  against  the  provisions  of  the  Act  and  the  Rules

framed thereunder.

Page 14 of 32

15

10. As its  aforesaid  representations  did  not  bear  any fruits,  the  appellant

Company filed a writ petition before the Punjab and Haryana High Court

challenging  the  demand  letters  dated  11.1.1988,  17.10.1993  and

4.5.1994 to the extent of demand for Rs. 61,000/- per acre (and interest

thereon) on account of internal community buildings, by including it in

the  external  development  charges.  The appellant  also  contended  inter

alia that as per provisions, the licensee was required to construct at his

own cost either itself or through an institution or individual, the schools,

hospitals,   community  centres  and  other  community  buildings  or  to

transfer  to  Government  free  of  cost  the  land  set  apart  for  schools,

hospitals, community centres and other community buildings.  

   

11. It  was  further  submitted  that  in  terms  of  the  aforesaid  provision,  the

appellant licensee was not required to pay for the development of those

buildings in case the land is transferred to the Government free of cost.

It was also pointed out by the appellant that in fact such a demand made

by the respondent No. 2 is beyond the competence of the Government as

any payment made for such development would not only be against the

provision of the Act and the Rules framed thereunder but would also be

against the principles of unjust enrichment.

Page 15 of 32

16

12. The  Punjab  and  Haryana  High  Court  considered  the  aforesaid  Writ

Petition  and  thereafter  by  the  impugned  judgment  and  order  dated

29.7.1999  rejected  the  contentions  of  the  appellant  holding  that  the

appellant had failed to develop the said buildings which it was obliged to

do and thus  the  Director  was  justified  in  demanding the said  amount

from  the  appellant  Company  which  would  be  invested  for  the

construction of these buildings only.  Aggrieved by the said judgment

and order, the present appeal is preferred by the appellant Company on

which we have heard the learned counsel appearing for the parties.

13. The  aforesaid  contentions  which  were  raised  by  the  appellant  in  the

various representations submitted were reiterated before us by Mr. Arun

Jaitley, the learned senior counsel appearing for the appellant.  It  was

further  submitted  by  him that  the  Director,  respondent  No.  2  herein,

while making the unlawful demand of Rs. 61,000/- per gross acre in the

name  of  construction  of  internal  community  buildings,  had  acted

arbitrarily, unfairly and unreasonably inasmuch as he had no power or

authority  to  include  the  cost  of  internal  community  buildings  in  the

external development charges.

14. Mr.  Anoop  G.  Chaudhary,  learned  senior  counsel  appearing  for

respondent No. 2, however, took up various pleas in order to support the

Page 16 of 32

17

demand made by the respondent No. 2.  It was submitted by him that the

entire transaction and the demand made is covered by the Act and the

Rules framed thereunder.   He submitted that the appeal is liable to be

dismissed as the writ petition itself was not maintainable, inasmuch as,

the contention  of  the  appellant  is  that  the impugned demand made is

outside the provisions of the Act and the Rules and therefore the actual

remedy that was available to the appellant to challenge said demand was

by way of filing a civil suit.

He also submitted that the present writ which is filed by the appellant

is in the nature of claim for rendition of accounts for which the writ is not a

proper remedy.  He submitted that on both the aforesaid counts, the writ

petition is  required to be dismissed.   He also submitted that  the demand

made is within the jurisdiction and parameters laid down in section 3(3)(a)

(iv) of the Act and therefore, the challenge made to the aforesaid demand is

unfair and unjustified.

He also advanced an alternative argument contending inter alia that if

the aforesaid  contentions  are  not  accepted,  even in  that  event,  the entire

amount for which demand was raised has since been paid by the appellant

and therefore, the principle of waiver and acquiescence will  apply to the

facts and circumstances of the present case.

Page 17 of 32

18

15. So  far  the  contentions  with  regard  to  the  maintainability  of  the  writ

petition  is  concerned,  we  are  not  impressed  and  persuaded  with  the

aforesaid  contentions  as  according  to  the  respondent  themselves,  the

aforesaid demand is being made within the parameter and ambit of the

provision  of section 3(3)(a)(iv).  That  being  the position,  the demand

made according to the respondent is  a statutory demand and therefore

challenge to such a demand could always be raised by the appellant by

filing  a writ  petition  as  such a demand is  sought  to  be protected  and

supported by way of statutory provision.

16. Even if the appellant has taken up the plea that such a demand is not

supported by the statutory provisions and is in fact in conflict with them,

even then the issue pertains as to whether or not such a demand could be

made and supported by the said provisions, in which case, a writ petition

is  competent  and  maintainable  and  the  plea  raised  by the  respondent

therefore with regard to the maintainability of the petition is only to be

rejected which we hereby do.

17. Section 3(3)(a)(iv) of the Act is the relevant provision and the merit of

the claim and repudiation thereof is  based on the interpretation of the

said provision.  It was pointed out on behalf of the appellant that 49 plots

Page 18 of 32

19

have  been  given  by  the  appellant  developer  to  the  Government  as

community sites.  Section 5 of the Act enumerates that colonizer would

deposit 50% of the amount realised from time to time by him from the

plot holders within the period of 10 days of its realization in a separate

account to be maintained in a scheduled bank.  It is also provided therein

that  the  aforesaid  50% amount  which  is  so  deposited  would  only  be

utilized towards meeting the cost of the internal development works in

the colony.   Further  stipulation  in  the  said  provision  is  that  after  the

internal development works of the colony have been completed to the

satisfaction of the Director, the colonizer would be at liberty to withdraw

the  balance  amount.    The  remaining  50%  of  the  amount  would  be

deemed to have been retained by the colonizer to meet the cost of the

land and external  development works.   Section 8 of the Act which is

extracted herein above also provides that the Director could cancel the

licence  given to  the  developer  colonizer  if  he contravenes  any of  the

conditions  of  the  licence  or  the  provision  of  Act  or  the  Rules  made

thereunder  and after  the  cancellation  of  the licence,  the  Director  may

himself carry out or cause to be carried out the development works in a

colony and recover such other charges as the Director may have to incur

on the said development work from the colonizer and the plot holders.

Page 19 of 32

20

18. Rules 4, 5 and 11 which are made part of the statutory rules give effect to

the aforesaid provision of Section 3(3).  The comparative reading of the

provisions of Section 3(3)(a)(iv) and sub-clause (b) of clause (1) of the

Licence  Agreement  would  clearly  show that  the  licensee-colonizer  is

required  to  construct  at  his  own  cost  schools,  hospitals,  community

centres and other community buildings or may get the same constructed

by any other institution or individual.  The developer also has the option

to  transfer  to  the  Government  at  any  time,  if  so  desired  by  the

Government,  free  of  cost  the  land  set  apart  for  schools,  hospitals,

community  centres  and  community  buildings  in  which  case  the

Government would be at liberty to transfer such land to any person or

institution including a local authority on such terms and conditions as it

may deem fit.

19.  The said  provision,  therefore,  gives  three options  for  construction  of

such community centres and facilities like schools, hospitals, community

centres  and  other  community  buildings.   Such  centres  and  buildings

could be constructed by the developer himself or he may get the same

constructed  by  any  other  institution  or  individual  whereby  such

individual would be able to utilize the said building. In  case  the

developer fails  to exercise either  of the aforesaid  two options,  a third

Page 20 of 32

21

option is also open to the developer under which he would transfer the

said land, where the community facilities are to be established, free of

cost  to  the  Government  in  which  case  such  schools,  hospitals,

community centres and community buildings could be constructed either

by the Government itself  or  the said  land could be transferred by the

Government to any person or institution including a local authority on

such  terms  and  conditions  as  the  Government  may  deem fit.    The

aforesaid provision is clear and explicit and there is no ambiguity in it.

The only question therefore, which arises herein is, in a case where the

land  is  transferred  to  the  Government  free  of  cost  and  when  such

schools, hospitals, community centres and community buildings are to be

constructed either by the Government or any agency appointed by the

Government  whether  the  charges  for  internal  community  buildings  is

also required to be paid by the developer.  

20. It was submitted by the counsel appearing for respondent No. 2 that the

demand  is  made  by  the  State  Government  as  external  development

charges  although  the  same is  actually  for  making  internal  community

buildings which was in the interest  of proper development of the said

colony.  The High Court upheld the said contention on the ground that a

colonizer  is  duty  bound  to  complete  the  development  works  in  the

Page 21 of 32

22

colony within a specified period and that the idea behind providing such

a  time  limit  was  only  to  safeguard  the  interest  of  various  plot

holders/residents of the colony so that they might not be left at the lurch

by the colonizer after selling plots to them.  It was further held that since

a complete control over the activities of the colonizer is envisaged under

the provisions  of the Act and the Rules,  the action of the Director  in

calling  upon  the  appellant  Company  to  pay  charges  for  some of  the

internal community buildings could not be termed as arbitrary.  

21. The said findings arrived at by the learned Division Bench of the High

Court appears to be in direct conflict and also in contradiction with the

provisions of Sections 3(3)(a)(iv) of the Act and also all the terms and

conditions  provided  in  sub-clause  (b)  of  clause  (1)  of  the  Licence

Agreement.   There  is  no  mention  at  all  of  any  requirement  for  the

licensee to provide for or to make payment for the cost of construction of

internal  community  buildings  when  the  land  is  transferred  to  the

Government free of cost.  No such statutory basis could be shown either

in the statute or in the licence agreement.  When a specific question was

put as to whether the amount was demanded towards internal community

buildings  or  external  development  charges,  the  learned  counsel,  was

constraint to admit that although the said amount was being demanded

Page 22 of 32

23

towards  external  development  works  but  in  fact  the  same was  being

demanded  from  the  appellant  towards  internal  community  buildings

which  were required to  be constructed  by the appellant.   There  is  no

dispute with regard to the fact that the developer of the colony, namely

the present appellant has carried out all the internal development works

as required to be done which is statutorily provided for.  A part of the

community centre has also been constructed by the developer themselves

but the entire community centre could not be developed by it or through

its  agencies  and  therefore  the  land  allocated  for  the  remaining

community  buildings/development  have  been  transferred  to  the

Government free of cost.

22. Since the land has been given free of cost, it is now open for the State

Government  to  get  the  remaining  community  buildings  constructed

either by themselves or through any agency or institution or individual at

its cost in terms of the provisions of the Act, in which case the terms and

conditions could be laid down by the Government for such community

buildings, to be constructed on the land which is transferred to it by the

appellant free of cost.  The Government cannot in law demand that the

buildings on the said lands which is to be transferred to them free of cost

should also be constructed by the appellant and then transfer the land to

Page 23 of 32

24

them free of cost along with the construction thereon and on failure to

construct to pay for the cost of construction.  That would in fact be a

case  of  an  illegal  and  unauthorised  demand  as  it  has  no  statutory

mandate. The respondent cannot demand transfer of the land free of cost

and also the construction cost of the facilities to be provided in the said

land.

23. When the  provisions  of  Section  3(3)(a)(iv)  are  analysed,  it  would  be

apparent that the word used in the said provision is  “land” and it  has

been  specifically  mentioned  therein  that  if  the  colonizer  does  not

construct the community buildings and facilities on its own or through

its agency or organization or individual, then the said licensee would be

required to transfer the said land set apart for the aforesaid purpose free

of cost to the Government.  

24. The  Government’s  claim  is  therefore  restricted  to  lands  which  the

developer has failed to develop as community centres.  In other words

only  that  land  which  the  developer  has  not  been  able  to  develop  as

community services facilities would stand transferred to the Government

free of cost and the said land could be utilized by the Government for the

aforesaid purpose either by itself or through its agency.  If the legislature

Page 24 of 32

25

had intended that the licensee is required to transfer the land and also to

construct the buildings on it or to make payment for such construction,

the legislature would have made specific provisions laying down such

conditions explicitly and in clear words in which event the provisions

would have been worded in altogether different words and terms.  It is

well settled principle in law that the court cannot read anything into a

statutory  provision  which  is  plain  and  unambiguous.    The  language

employed in a statute is determinative factor of legislative intent.  If the

language of the  enactment is  clear  and unambiguous,  it  would not  be

proper  for  the  courts  to  add  any  words  thereto  and  evolve  some

legislative intent, not found in the statue.

25. In Ganga Prasad Verma (Dr.) v. State of Bihar [1995 Supp. (1) SCC

192], it  has been held that where the language of the Act is clear and

explicit,  the  Court  must  give  effect  to  it,  whatever  may  be  the

consequences, for in that case the words of the statute speak the intention

of the legislature.  

26. Mr. Anoop G. Chaudhary, learned senior counsel wanted us to read the

provision of the Section 3(3)(a)(iv) of the Act by adding a few words to

it,  for according to him the latter part  of the aforesaid section i.e.  the

Page 25 of 32

26

obligation of the appellant to transfer to the Government at any time free

of cost the land, should be read by adding the provisions of the earlier

part of the section i.e. to construct at his own cost the community centres

and other community buildings on the lands set apart for this purpose.

27. The  aforesaid  contention  apparently  arises  out  of  the  complete

misreading  of  the  aforesaid  provision.   The  responsibility  regarding

construction of community centres and other community buildings could

be  discharged  by  adopting  any  of  the  three  options  as  mentioned

hereinbefore and each one of such options is an independent option and

one cannot be connected and related with the other.  We cannot read the

provision relating to construction at the own cost of the developer the

schools, hospitals, community centres and other community buildings on

the  land  set  apart  for  this  purpose,  into  an  independent  alternative

provision relating to transfer of such land to the Government free of cost.

The aforesaid option given to the developer to construct the community

centres and other community buildings at its own cost is when he can

utilize  himself  manage  it.   Therefore,  we  cannot  read  the  aforesaid

provision in the manner sought to be read by Mr. Chaudhary, for reading

by adding certain words in the aforesaid manner does not appear to be

the intention of the legislature while enacting the aforesaid legislation,

Page 26 of 32

27

for otherwise the legislature would have explicitly said so in the body of

the main part of the section itself.

28.Therefore,  we not  only reject  the  preliminary objections raised by the

respondent No. 2 in this matter, but we also reject his contention that the

aforesaid demand of Rs. 61,000/- per gross acre is permitted under the

provision of Section 3(3)(a)(iv) of the Act.

29. We, therefore, now come to the last submission of the counsel appearing

for respondent No. 2 which relates to issue of waiver and acquiescence

in view of the fact that payment was made by the appellant which was

demanded from him under the aforesaid letters.

30. The correspondences between the parties in respect of payment of the

aforesaid demand would clearly establish that respondent No. 2 made a

demand for  the  payment  of  the  aforesaid  amount  of  Rs.  61,000/-  per

gross acre failing which a threat was issued that the licence which was

issued to it would stand cancelled.  It is also pointed out on behalf of the

respondent   No. 2 that subsequently the respondent No. 2 has made it a

policy of including expressly the value of the community buildings in the

internal development works and ensuring that one fourth of the total cost

Page 27 of 32

28

of the internal development work could be secured by a bank guarantee.

It is needless to say that if the provision would have been the same at the

relevant time, in that event the situation would have been different but

no  such  provision  either  in  the  Act  or  in  the  Rules  or  in  any policy

framed by the Government could be brought to our attention.  Therefore,

what  we were required to consider  was only the  explicit  provision of

Section 3(3)(a)(iv) of the Act and the rules framed thereunder, which are

extracted herein before in terms of which we find no obligation on the

part of the appellant to pay for the construction of internal community

buildings  which  was  being  demanded  by  the  appellant  as  external

development charges.  Charges for construction of internal community

buildings can never be equated with the external development charges,

so  the  demand  itself  was  illegal.   The  view taken  by us  also  derive

support from the judgment of this Court in           DLF Qutab Enclave

Complex Educational Charitable Trust v.  State of Haryana, [(2003)

5 SCC 622] wherein it was held that construction of schools, hospitals

and community centres and other community buildings does not come

within the purview of the term “development works” as the same come

within the purview of the term “amenities”.  The Court in Para 33 held as

under:  

Page 28 of 32

29

“Construction of schools, hospitals and community centres and other community buildings do not come within the purview of the term “development works”. They come within the purview of the term “amenities”. Only in relation to the development works the colonizer is bound to pay the development charges, carry out  and complete  development  works.  He has  also  the responsibility to maintain the same for a period of five years from  the  date  of  issue  of  the  completion  certification whereafter,  the  same  is  required  to  be  handed  over  to  the Government or the local authority as the case may be, free of cost.”

31. Since the respondent No. 2 sought to justify the demand made on the

ground that such demand is justified as internal community building, we

have no other option but to hold that such demand could not have been

made  even  as  internal  community  buildings  for  no  such  power  and

jurisdiction was vested in the Government to make such a demand for

the simple reason that there was neither any statutory support nor any

policy decision in support of the same.  Even in the Licence Agreement,

nothing was contemplated to the effect that in addition to the liability to

transfer the land set apart for the said buildings to the Government free

of  cost,  on the  contingency mentioned in  the statue  and relied  in  the

Licence  Agreement,  the  licensee  is  also  required  to  pay  for  the

construction of said buildings.  

Page 29 of 32

30

32. So far the issue with regard to the waiver and acquiescence is concerned,

we  find  that  such  contention  that  the  principles  of  waiver  and

acquiescence is attracted to the facts of the case is also not tenable.  In

the  letter  dated  08.02.1988  which  was  written  by  the  appellant  in

response  to  the  letter  of  respondent  No.  2  dated  11.01.1988  on  the

subject of payment of external development charges, it was clearly stated

that the revised rates which is since determined by the Director in their

communication dated 18.9.1987 and its further revision are not covered

by  the  clause  of  the  agreements  being  referred  in  the  recent

communications.   In  paragraph  2 of  the said  letter  it  was  specifically

stated that the respondent No. 2 had included an amount of Rs. 61,000/-

per  gross  acre  on  account  of  community  buildings  in  the  external

development  charges,  which  is  not  payable,  as  according  to  the

requirements of the Act and licence the appellant  was required to pay

external development charges only and there was no mention of charges

towards construction of internal community buildings in case the land set

apart for the said purpose is transferred to the Government free of cost.

Therefore there was a protest  and demur on the part  of the  petitioner

against the aforesaid demand.

Page 30 of 32

31

33. In the case of  Municipal Corpn. of Greater Bombay v.  Hakimwadi

Tenants' Assn., [1988 Supp SCC 55],  it was held by this Court that  in

order  to  constitute  waiver,  there  must  be  voluntary  and  intentional

relinquishment of a right.  The essence of a waiver is an estoppel and

where there is no estoppel, there is no waiver.  Estoppel and waiver are

questions of conduct and must necessarily be determined on the facts of

each case.  

34. It is thus established that the appellant on receipt of the demand issued

by respondent No. 2 raised this objection regarding the charge and the

demand made and the payment which was made by the appellant was

due  to  the  threat  issued  by  respondent  No.  2  that  on  failure  of  the

appellant  to  pay  the  same  its  licence  would  stand  cancelled.   Such

demand  was  made  by  the  appellant  under  protest  as  aforesaid.

Therefore,  the  principle  of  waiver  and  acquiescence  will  have  no

application in the present case and therefore we reject the said contention

of the learned counsel appearing for respondent No. 2.

35. The appeal, therefore, stands allowed and we hold that respondent   No.

2 was not authorized or justified in raising the aforesaid demand of Rs.

61,000/- per gross acre.   Whatever payment is  made in respect  of the

Page 31 of 32

32

aforesaid demand was not payable by the appellant to the respondent No.

2 as the said demand is held to be illegal, unjustified and unreasonable.

The  counsel  for  the  appellant  during  the  course  of  his  arguments

however submitted that the said amount now payable by the respondent

No. 2 be adjusted towards the dues of the appellant.   Accordingly we

direct such adjustment of the amount in accordance with law.

36.We  accordingly,  dispose  of  this  appeal  in  the  light  of  the  aforesaid

directions and observations.  

……………………… …...J.

    (R.V. Raveendran)  

   ……………………………J. (Dr. Mukundakam Sharma)

New Delhi; January  23, 2009

Page 32 of 32