26 July 1999
Supreme Court
Download

M.I.BUILDERS PVT.LTD Vs RADHEY SHYAM SAHU

Bench: S.B.MAJMUDAR,D.P.WADHWA
Case number: C.A. No.-009323-009325 / 1994
Diary number: 15170 / 1994


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 53  

PETITIONER: M.I. BUILDERS PVT. LTD.

       Vs.

RESPONDENT: RADHEY SHYAM SAHU AND OTHERS

DATE OF JUDGMENT:       26/07/1999

BENCH: S.B.Majmudar, D.P.Wadhwa

JUDGMENT:

D.P. Wadhwa, J.

     These  appeals are directed against the judgment dated August  23,  1994 of a Division Bench of the High  Court  of Judicature  at  Allahabad,  (Lucknow Bench).   By  a  common judgment  in  three  writ  petitions,  High  Court  speaking through  Shobha  Dixit,  J.  held that the decision  of  the Lucknow  Nagar Mahapalika (’Mahapalika’ for short), also now called Nagar Nigam or Corporation, permitting M.I.  Builders Pvt.   Ltd.  (the appellant herein) to construct underground shopping  complex  in  the Jhandewala Park  (also  known  as Aminuddaula  Park) situated at Aminabad Market, Lucknow, was illegal,  arbitrary  and unconstitutional.  High  Court  set aside and quashed the relevant resolutions of the Mahapalika permitting  such  construction and also the agreement  dated November 4, 1993 entered into between the Mahapalika and the appellant  for the purpose.  Writ of mandamus was issued  to the  Mahapalika  to  restore back the park in  its  original position  within  a period of three months from the date  of the judgment and till that was done, to take adequate safety measures  and to provide necessary safeguard and  protection to  the  public, users of the park.  High Court had  noticed that the fact that the park was of historical importance was not  denied  by  the  Mahapalika  and  also  the  fact  that perseverance  or maintenance of the park was necessary  from the environmental angle and that the only reason advanced by the   Mahapalika  for  construction   of   the   underground commercial complex was to ease the congestion in area.  High Court,  however,  took  judicial notice  of  the  conditions prevailing  at  the  Aminabad  market.  It said  it  was  so crowded   that  it  was  bursting   from  all   its   seams. Construction of the underground shopping complex in question would  only  complicate the situation and that  the  present scheme  would  further congest the area.  It said  that  the public   purpose,  which  is  alleged   to  be   served   by construction  of the underground commercial complex,  seemed totally illusory.

     Aggrieved  by the impugned judgment of the High Court, appellant  has  come  to this Court.  Mahapalika  also  felt aggrieved  and filed appeals (Civil Appeal Nos.  9326-28  of 1994)  but these appeals by the Mahapalika were subsequently allowed  to  be withdrawn by order dated February  6,  1997. There  is  controversy  as to how the Mahapalika  which  had

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 53  

earlier  justified its action later turned round and  sought to  withdraw the appeals.  The order allowing withdrawal  of the appeals by the Mahapalika is as under:  -

     "I.A.  Nos.  10 TO 12 IN

     CIVIL APPEAL NOS.  9326-28 OF 1994

     Nagar Mahapalika Appellants

     Versus

     Radhey Shyam Sahu & others Respondents

     O R D E R

     Taken on board.

     The  learned counsel for the appellant seeks leave  to withdraw  the  appeals and states that Mr.  S.V.   Deshpande who  appears  for  the other side has no  objection  to  the withdrawal.   The appeals will, therefore, stand disposed of as withdrawn with no order as to costs.

     Sd/- .......CJI

     New Delhi, Sd/- February 6, 1997 ......,J."

     Mahapalika  also  cancelled the building plans.   This action  of the Mahapalika was subject matter of criticism by the  appellant  as  to how a duly sanctioned plan  could  be revoked  without  any notice to the appellant.  We  may,  at this  stage,  itself reproduce the relevant portion  of  the resolution  dated  August  6,  1996 of  the  Mahapalika  for withdrawal of its appeals which is as under:-

     "The  Lucknow Bench of Hon’ble High Court of Allahabad has  declared the agreement dated 4.11.1993 executed between the  Nagar  Mahapalika, Lucknow and M.I.  Builders,  Karamat Market  Lucknow  in respect of construction  of  underground Palika  Bazar  and Multistoreyal parking on Jhandewala  Park Aminabad,  Lucknow as invalid and not in the public interest vide their judgment dated 23.8.1994.

     The  Hon’ble  High  Court   rendered  the  above  said Judgment  by  accepting  the  writ  petitions  preferred  by several  elected  sabhasad of the then Nagar Mahapalika  and the citizens.

     On  the  directions  of the then  Nagar  Pramukh  Shri Akhilesh  Das,  who  wanted to cause undue  profit  to  M.I. Builders  against the interest of Nagar Mahapalika now Nagar Nigam  Lucknow,  the  citizens of Lucknow, the  Nagar  Nigam Lucknow  filed Special Leave Petition No.  17223-25 of  1994 in  the  Hon’ble Supreme Court against the Judgment  of  the Hon’ble High Court.

     It  is proposed that in the interest of the citizen of Lucknow  and  the  Lucknow Nagar Nigam and  pending  Special Leave  Petition No.  17223-25 of 1994 in the Hon’ble Supreme Court  be  withdrawn and the Nagar Nigam Lucknow be  further directed  to oppose the Special Leave Petition filed by M/s. M.I.   Builders  in  the Hon’ble Supreme Court  against  the

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 53  

Judgment  dated  23.8.1994 of Lucknow Bench of Hon’ble  High Court of Allahabad.

     Unanimously  decided that the aforesaid resolution  be passed and accordingly the action may be taken."

     The  letter revoking the sanctioned building plans  is dated April 17, 1997 and is as under:-

     "To

     M/s   M.I.   Builders  (P)   Ltd.    Karamat   Market, Nishatganj, Lucknow

     Sir,

     Vide  this  office  letter No.   223/Sa.Sa.A./95  dtd. 23.1.1995 the building plans for construction of underground shopping  and parking complex at Jhandewala Park,  Ameenabad were sanctioned.

     After taking legal advice by the Hon’ble Nagar Pramukh from  the  standing  counsel  of the Nagar  Nigam  and  Add. Advocate  General the earlier sanctioned building plans  has been  revoked vide order dated 17.4.97.  As such these  have no legal sanctity.

     Please be informed.

     Yours  faithfully,  Sd/-  S.K.    Gupta  Mukhya  Nagar Adhikari  17.4.97  Copy  to:   The  Vice  Chairman,  Lucknow Development Authority, for information.

     Sd/- S.K.  Gupta Mukhya Nagar Adhikari"

     There  were three writ petitions before the High Court and  during  the course of hearing of those  petitions  High Court had directed maintenance of status quo.  At that time, it  would  appear only digging in some part of the park  had been  done  and there was no construction.  When the  matter came before this Court, by order dated December 14, 1994 the Court passed the following order:-

     "Exemption   from  filing   official  translation   is allowed.

     Liberty to add the omitted parties in the cause title.

     Leave granted.

     We  have  heard  counsel on the question of  grant  of interim relief.

     Printing dispensed with.

     The  operation of the impugned order of the High Court is stayed on the following conditions:

     Taking   all   the  facts   and   circumstances   into consideration  and having regard to the fact that it may not be possible for this Court to hear the appeal within a short time  having regard to the pressure of work and pendency  of old  cases, we direct that the appellant shall be  permitted

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 53  

to construct an under ground shopping complex by raising its own  funds  without  collecting any  additional  funds  from individuals  or concerns to whom the promise of allotment of shop  is made.  To clarify the matter, we say that the funds can  be  raised from agencies other than those to  whom  the shops are ultimately allotted.  It will be made clear to the agencies  from whom the funds are raised that they will  not be  entitled  to  allotment of shops.   The  appellant  will maintain  accounts  and  file an undertaking  to  the  above effect  in  this  Court  within two weeks  from  today.   In addition  the  undertaking will contain a statement  to  the effect  that  in the event the appeals fail,  the  appellant will  not raise questions as to equity or the ground on  its having  invested a huge amount and will be totally  amenable to  such  directions and orders that this Court may make  in regard  to  the  maintenance or otherwise  of  the  shopping complex.   In  other words, if the Court directs removal  of the shopping complex in the event of failure of the appeals, the  shopping  complex  will  have  to  be  removed  at  the appellant’s  cost without claiming anything in return.   The construction will be so carried out that the open space will remain  available for the public and the entire complex will be  so constructed that it will be an underground one except for  the  ingress and egress portions to the  complex.   The total  area  to  be constructed on the surface of  the  plot shall not exceed 10% of the plot.

     SLP (C) Nos.  17223-25/94

     Exemption from filing official translation is allowed.

     Leave granted.

     Tag  on  with  appeals arising from S.L.P.   (C)  Nos. 16907-09  of 1994 in which interim orders have already  been made."

     It  is  contended  by  the appellant  that  after  the aforesaid  interim  order, it got necessary  building  plans sanctioned  by  the  Mahapalika  and  started  construction. Respondents,  however, filed an application complaining that construction  was in violation of the building plans and was also  against the provisions of the U.P.  Urban Planning and Development  Act,  1973 (for short, the ’Development  Act’). To ascertain the nature of construction being carried out at that  time this Court appointed a Local Commissioner.  These applications  were then disposed of by passing the following order:-

     "I.A.  Nos.  10-12

     The Commissioner, Mr.  Justice Loomba, a retired Judge of the High Court of Allahabad, has pursuant to this Court’s order,  submitted  his Report dated February 15,  1996.   In paragraph  3 of the Report he identifies the points on which the  Report  was required and then proceeds to indicate  the actual  physical condition in regard to the construction  of the  market  and  states  that the entire  market  is  being constructed  underground  and not above the ground and  that the  total area on the surface of the market for the ingress and  egress  (with Chabutras) and light purposes etc.   does not  exceed  10 per cent of the plot and is about  9.74  per cent  of the area in which the market is being  constructed. He,  however,  notes  that  the level of  the  park  at  the

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 53  

periphery  appears  to be higher than the estimated  average level  of the original park by about 3.21 feet = 3 feet  2.5 inches as worked out on the basis of available old signs and that  the same does not appear to be in any manner offensive and  is of no consequence.  He also points out that the park made  on  the market area is and will be available  for  the public  in the form of park less the structures made on  the surface,  which  as pointed out above;  does not exceed  the permissible limit of 10 per cent of the total plot area.  He also  states  that the Chabutras constructed on the back  of the  structures will also be available to the public and may serve  as benches in the park.  In view of this Report which precisely  indicates the actual physical condition  existing on  the  date  of the Report and the plan  appended  thereto which  shows  beyond  any manner of doubt  that  the  entire construction is underground, the total surface area does not exceed  the permissible limit of 10 per cent and the raising of  the height on the periphery is of no consequence because it  does  not  in any manner affect the surface  area.   We, therefore, accept the Report of the learned Judge and see no merit in these I.As."

     The  Court,  however,  did not go  into  other  issues raised in the applications.  By a subsequent order dated May 7, 1997 the Court stopped further construction.

     Before we consider the details of the case we may note in brief the contentions of the parties.

     Petitioners   (now  the  respondents)   in  the   writ petitions  submitted  that  the park was not only  of  great historical  significance  but its maintenance was  necessary from  the  environmental point of view as mandated  by  law. Admittedly,  the park is the only open space in the Aminabad market,  which is an over-crowded commercial and residential area of the city.  Possession of the park was handed over to the   appellant  (M.I.   Builders)  in  violation   of   the provisions  of  law  to construct  an  underground  shopping complex  and underground parking with the ostensible purpose of  decongesting  the area.  It is not that the  encroachers would be removed from the area as the underground shops were not  allotted  to any one of them.  They would  nevertheless remain  at  the places occupied by them.  Challenge  to  the action  of  Mahapalika in allowing construction was  on  the grounds:  -

     1.   It was against the public purpose to construct an underground  market in the garb of the decongesting area  of the  encroachers to destroy a park of historical  importance and  of  environmental necessity.  It would be in breach  of Articles 21, 49, 51-A(g) of the Constitution as the existing park  which is the only open space in the busiest commercial area  in  the heart of the city of Lucknow can be  destroyed and  the  citizens  particularly the residents of  the  area would  be deprived of the quality of life to which they  are entitled under the law and to maintain ecology of the area.

     2.   It is in violation of the statutory provisions as contained in the U.P.  Nagar Mahapalika Adhiniyam, 1959 (now called Uttar Pradesh Municipal Corporation Adhiniyam, 1959 - by  Amending  Act  12  of 1994) (for short  the  Act),  U.P. Regulation  of Buildings Operations Act, 1958 (for short the ’Building   Act’),   Uttar  Pradesh   Urban   Planning   and Development  Act, 1973 (for short the ’Development Act’) and

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 53  

also  Uttar  Pradesh  Parks,  Playgrounds  and  Open  Spaces (Preservation  and  Regulation)  Act, 1975  (for  short  the ’Parks Act’).

     3.   No tenders were invited by the Mahapalika  before entering  into  the  agreement with the builder.   This  was against   the  established  procedure   and  thus  it  acted arbitrarily  in the matter of disposing and dealing with its immovable   property  which  was  of  immense  value.    The agreement  is wholly one sided and gives undue advantage  to the builder at the cost of the Mahapalika.

     4.   The agreement between Mahapalika and the  builder smacks of arbitrariness, is unfair and gives undue favour to the  builder  and  this was done with mala fide  motives  of personal   gain  by  the   authorities  of  the   Mahapalika particularly  the  Mukhya  Nagar Adhikari  (Chief  Executive Officer) and the Adhyaksh (the Mayor).

     5.   The resolution of the Mahapalika by which it  has agreed  to  enter  into the agreement with the  builder  was against the provisions of the Act which were mandatory.

     6.   The  whole action of the Mahapalika  was  against public  interest.  Lucknow Development Authority (for  short LDA) which was constituted under the Development Act and was responsible  for  development in the area which  would  mean construction  of  the  underground   shopping  complex   and underground  parking lot was side-lined and no sanction  was obtained  from  the  Vice Chairman in  accordance  with  the provisions of the Development Act.

     The  builder  as  well as the Mahapalika  filed  their respective counter affidavits in the High Court opposing the writ  petitions.   No counter affidavit was filed either  by the  State  or by LDA though they were parties in  the  writ petitions.   Chief  Executive  Officer and  the  Mayor  were impleaded  by name as respondents in the writ petitions  and allegations  of mala fides and favourtism made against  them but  none  of  them  choose to file  any  counter  affidavit controverting  those allegations.  In the High Court a  very strange  scenario emerged and that was that though the stand of  Mahapalika and LDA as spelled out from documents was  at variation  with each other, yet both were represented by one counsel.  Builder was represented by the Advocate General of the  State  while  State  was represented  by  its  standing counsel.   Before us though Mahapalika earlier supported the builder  as  noted above and also filed appeals against  the impugned  judgment  but subsequently it reversed its  stand, withdrew  its appeals and filed an affidavit supporting  the impugned  judgment of the High Court.  The State  Government and  the  LDA  also filed their  affidavits  supporting  the judgment  of the High Court with full vigour though as  seen earlier   before  the  High  Court   they  were  just   mute spectators.   We  may  also  note   that  in  reply  to  the applications IA Nos.  10 and 11 in this Court the Mahapalika lent  its  support  to  the builder.   This  action  of  the Mahapalika  changing  its stand midstream was  subjected  to severe  criticism  by the appellant and it was  stated  that there  was estoppel by deed in the case and Mahapalika could not go back on its earlier stand.

     The  impugned  judgment  has been  challenged  by  the builder on the following grounds:  -

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 53  

     a) There was no disposal of the property by Mahapalika in favour of the builder and therefore provisions of Section 128  of the Act were inapplicable.  Even assuming it was so, provisions  of  Sections  129  and  132  of  the  Act  stood complied.

     b)  There  was  no arbitrariness  or  unreasonableness vitiating  the agreement between Mahapalika and the  builder particularly  in  view  of the express finding of  the  High Court  that there was no lack of bona fides and that it  was not  disputed that the builder was competent to execute  the job.   This  was  having regard to special features  of  the construction  and  further  on account of the fact  that  no party  had come forward at any time to execute the  project. In  such  a situation omission to invite tenders  would  not vitiate  the  agreement particularly when the  proposal  for construction of the project by the builder was widely known.

     c)  In view of its stand before the High Court and  in the  Special  Leave  Petition  of the builder  and  its  own appeals  filed in this Court it is not open to Mahapalika to advance  any contention or take a stand contrary to what had been taken earlier.

     d)  High Court exceeded its jurisdiction as it did not apply  correct parameters of its power of judicial review as laid  by  this  Court in Tata Cellular vs.  Union  of  India (1994  (6) SCC 651) and other cases and the High Court  went wrong in going into the question of expediency and wisdom of the proposed project.

     e)  Mahapalika  could  not revoke  the  building  plan without  notice to the builder and without hearing it in the matter.

     This  last submission we need not go into the question if  cancellation  of  the sanctioned building plans  by  the Mahapalika  was  valid as that was not the issue before  the High Court.

     Mahapalika  is a body corporate constituted under  the Act.   The  Act  provides  for   various  functions  of  the Mahapalika  and how these are to be performed.  Its  various authorities are described in Section 5 which is as under:  -

     "5.    Corporation  Authorities.-    The   Corporation authorities charged with carrying out the provisions of this Act for each city shall be -

     (a)  the Corporation;  (aa) the Ward Committees;   (b) an  Executive Committee of the Corporation;  (bb) the  Nagar Pramukh;   (c)  a Development Committee of the  Corporation; (d)  A  Mukhya  Nagar  Adhikari and an  Apar  Mukhya  Nagar Adhikari appointed for the Corporation under this Act;  and (e)  in  the  event  of   the  corporation  establishing  or acquiring electricity supply or public transport undertaking or  other  public utility services, such other committee  or committees  of  the Corporation as the Corporation may  with the previous sanction of the State Government establish with respect thereto."

     Chapter  II  provides  for   constitution  of  various committees   and   Chapter  III   for  proceedings  of   the Mahapalika,  Executive Committee, Development Committee  and

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 53  

other  Committees.   In  view of the  applicability  of  the Development Act, 1973, the Executive Committee of Mahapalika has ceased to be in operation to that extent.  Under Section 91  falling  in this Chapter, a list of the business  to  be transacted  at  every meeting except an  adjourned  meeting, shall  be sent to each member of the Mahapalika or of  other Committees  at  least  ninety-six  hours in the  case  of  a meeting  of  the Corporation before the date fixed  for  the meeting  and  seventy two hours in the case of a meeting  of any  such Committee and "no business, except as provided  in sub-  section  (2),  shall be brought or transacted  at  any meeting  other  than  a business of which  notice  has  been given".  Sub-section (2) is as under:  -

     "(2)  Any member of the Corporation or of a  Committee referred  to  in sub- section (1), as the case may  be,  may send  or deliver to the Mukhya Nagar Adhikari notice of  any resolution  with a copy thereof proposed to be moved by  him at  any  meeting  of  which   notice  has  been  sent  under sub-section  (1).  The notice shall be sent or delivered  at least  forty-eight  hours  in the case of a meeting  of  the Corporation  and twenty four hours in the case of a  meeting of  any committee before the date fixed for the meeting  and thereupon  the Mukhya Nagar Adhikari shall with all possible despatch  cause  to be circulated such resolution  to  every member  in such manner as he may think fit.  Any  resolution so  circulated may, unless the meeting otherwise decides, be considered and disposed of thereat."

     Under  Section 95 of the Act, the Mahapalika may  from time  to  time  by special resolution constitute  a  special committee  to  enquire  into  and  report  upon  any  matter connected  with its powers, duties or functions.  Every such special  committee shall conform to any instruction that may be given to it by the Mahapalika.  The report of the special committee  shall,  as  soon as may be practicable,  be  laid before  the Mahapalika which may thereupon take such  action as it thinks fit or may refer back the matter to the special committee  for  such further investigation and report as  it may  direct.   Section  97   provides  for  constitution  of sub-committees  by the Executive Committee or any  committee appointed  under  clause (e) of Section 5 and any such  sub- committee  shall possess such powers and perform such duties and  functions as the committee appointing it may from  time to time delegate or confer.  Section 105 of the Act provides that no act done or proceeding taken under this Act shall be called  in question in any court on the ground merely of any defect  or  irregularity  in  procedure  not  affecting  the substance.   Under  Section  119 of the  Act  falling  under Chapter  V  which  prescribes  duties   and  powers  of  the Mahapalika  and  its  authorities, there  is  provision  for delegation  of  functions  which we reproduce,  in  relevant part, as under:  -

     "119.   Delegation of functions, - (1) Subject to  the other  provisions  of this Act and the rules thereunder  and subject  to  such  conditions  and restrictions  as  may  be specified by the Corporation -

     (a)  the  Corporation  may delegate to  the  Executive Committee  or  to  the  Mukhya Nagar  Adhikari  any  of  its functions  under this Act other than those specified in Part A of Schedule I."

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 53  

     It  is not necessary to refer to Part A of Schedule  I mentioned  in  Section  119  as none  of  the  functions  of Corporation   on  which  there  is  prohibition   has   been delegated.   Under Section 119, reproduced above, delegation can  only  be  to the Executive Committee or to  the  Mukhya Nagar  Adhikari  and  to  no other person  or  authority  or Committee.   Sections  421,  422  and 423 of  the  Act  were referred  to  contend  that it is only  for  the  Mahapalika itself to establish private markets.  These sections fall in Chapter   XVI   dealing   with    regulation   of   markets, slaughter-houses, certain trades and acts, etc.

     Chapter  VI  of  the  Act   deals  with  property  and contracts.   Under  Section  125 falling  in  this  Chapter, Mahapalika  has  power  to  acquire,  hold  and  dispose  of property  or any interest therein whether within or  without the  limits  of the city.  Under sub-section (3) of  Section 125  any immovable property which may be transferred to  the Corporation  by the Government shall be held by it,  subject to such conditions including resumption by the Government on the occurrence of a specified contingency and shall apply to such  purpose as the Government may impose or specify  while making  the  transfer.  Section 128 deals with power of  the Mahapalika  to dispose of the property.  As to what are  the provisions   governing  disposal  of   property  these   are mentioned in Section 129.  Sections 128 and 129, in relevant part, are as under:  -

     "128.   Power  to  dispose  of property.   -  (1)  The Corporation  shall, for the purpose of this Act, and subject to  the  provisions thereof and rules made thereunder,  have power to sell, let on hire, lease, exchange, mortgage, grant or otherwise dispose of any property or any interest therein acquired by or vested in the Corporation under this Act.

     Provided   that  no  property   transferred   to   the Corporation  by  the Government shall be sold, let on  hire, exchange  or  mortgaged or otherwise conveyed in any  manner contrary  to the terms of the transfer except with the prior sanction of the State Government.

     129.   Provision  governing disposal of  property.   - With  respect  to the disposal of property belonging to  the Corporation  the  following  provisions shall  have  effect, namely:

     (1)  Every  disposal  of  property  belonging  to  the Corporation  shall  be made by the Mukhya Nagar Adhikari  on behalf of the Corporation.

     (2) XXX XXX XXX

     (3) The Mukhya Nagar Adhikari may with the sanction of the  Executive Committee dispose of by sale, letting out  on hire  or  otherwise  any movable property belonging  to  the Corporation,  of  which  the  value  does  not  exceed  five thousand  rupees;   and may with the like sanction  grant  a lease   of   any  immovable   property  belonging   to   the Corporation,  including any such right as aforesaid, for any period  exceeding  one  year  or sell or grant  a  lease  in perpetuity  of  any  immovable  property  belonging  to  the Corporation  the  value of premium whereof does  not  exceed fifty  thousand rupees or the annual rental whereof does not exceed three thousand rupees.

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 53  

     (4) the Mukhya Nagar Adhikari may with the sanction of the  Corporation  lease, sell, let out on hire or  otherwise convey  any property, movable or immovable, belonging to the Corporation.

     (5) xxx xxx xxx

     (6)  the sanction of the Executive Committee or of the Corporation  under sub-section (3) or sub-section (4) may be given either generally or any in class of cases or specially in any particular case.

     (7)  the aforesaid provisions of this section and  the provisions  of  the rules shall apply to every  disposal  of property  belonging to the Corporation made under or for any purposes of this Act."

     Sections 131, 132 (in relevant part) and 133 prescribe the  manner of execution of Contract and these are as under: -

     "131.    Powers  of  Corporation  to  the  making   of contracts.     Subject to the provisions of this  Act,  the Corporation  shall have power to enter into contracts  which may  be necessary or expedient under or for any purposes  of this Act.

     "132.  Certain provisions relating to the execution of the  contracts.   (1) All contracts referred to in  Section 131  including  contracts  relating to the  acquisition  and disposal  of immovable property or any interest therein made in connection with the affairs of the Corporation under this Act, shall be expressed to be made, for and on behalf of the Corporation,  and  all such contracts and all assurances  of property  made in exercise of that power shall be  executed, for  and  on behalf of the Corporation, by the Mukhya  Nagar Adhikari  or by such other officer of the Corporation as may be authorised in writing by the Mukhya Nagar Adhikari either generally or for any particular case or class of cases.

     (2) ............

     (3) ............

     (4)  No  contract involving an  expenditure  exceeding five  lakh  rupees  shall be made by Mukhya  Nagar  Adhikari unless it has been sanctioned by the Corporation."

     "133.   Manner  of  execution.  - (1)  Every  contract entered  into by the Mukhya Nagar Adhikari on behalf of  the Corporation shall be entered into in such manner and form as would  bind him if it were made on his own behalf and may in like manner and form be varied or discharged :

     Provided that :  -

     (a)  the  common  seal  of the  Corporation  shall  be affixed  to  every contract which, if made  between  private persons, would require to be under seal, and

     (b)  every  contract for the execution of any work  or the  supply of any materials or goods which will involve  an expenditure  exceeding two thousand and five hundred  rupees

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 53  

shall  be  in writing, shall be sealed with the seal of  the Corporation and shall specify-

     (i)  the work to be done or the materials or goods  to be supplied as the case may be;

     (ii)  the price to be paid for such work, materials or goods;  and

     (iii)the  time  or times within which the contract  or specified portion thereof shall be carried out.

     (2) The common seal of the Corporation shall remain in the  custody  of the Mukhya Nagar Adhikari and shall not  be affixed  to  any contract or other instrument except in  the presence  of  a Sabhasad, who shall attach his signature  to the contract or instrument in token that the same was sealed in his presence.

     (3)  The  signature  of  the said  Sabhasad  shall  be distinct  from the signature of any witness to the execution of such contract or instrument.

     (4) No contract executed otherwise than as provided in the section shall be binding on the Corporation."

     Relevant  part of Section 136 on which some  arguments addressed, is reproduced hereunder:  -

     "136.  Estimates exceeding rupees fifty thousand - (1) Where  a project is framed for the execution of any work  or series  of works the entire estimated cost of which  exceeds fifty thousand rupees-

     (a)  the Mukhya Nagar Adhikari shall cause a  detailed report  to be prepared including such estimates and drawings as  may  be requisite and forward the same to the  Executive Committee  who  shall submit the same before the  Mahapalika with its suggestions, if any;

     (b)  the Mahapalika shall consider the report and  the suggestions  and  may reject the project or may  approve  it either in its entirety or subject to modifications."

     (By  the amending Act 12 of 1994 w.e.f.  30.5.1994 the amounts  in sub-sections (1) and (2) of Section 136 are  now respectively 5 lakhs and 10 lakhs of rupees.)

     Part  IX  of  the  Constitution was  inserted  by  the Constitution (74th) Amendment Act, 1992.  Article 243W under this   part   prescribes  the    powers,   authorities   and responsibilities  of  Municipalities etc.  It  provides,  in relevant  part, that the legislature of a State may, by law, endow  the  Committee  or the Municipality such  powers  and authority  with respect to performance of functions and  the implementation  of  schemes  as  may   be  entrusted  to  it including  those matters listed in the Twelfth Schedule.  If we refer to the Twelfth Schedule, Entries 8, 12 and 17 would be relevant and are as under:  -

     "8.  Urban forestry, protection of the environment and promotion of ecological aspects.

12

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 53  

     12.   Provision of urban amenities and facilities such as parks, gardens, play-grounds.

     17.   Public  amenities   including  street  lighting, parking lots, bus stops and public conveniences."

     Keeping  this aspect in view, the Act was amended  and some  of  the  relevant  duties  of  Mahapalika,  which  are obligatory as given in Section 114, are as under:

     "114.Obligatory  duties of the Corporation.- It  shall be  incumbent  on  the Corporation to  make  reasonable  and adequate  provision,  by any means or measures which  it  is lawfully  competent to it to use or to take, for each of the following matters, namely:  -

     (viii)  guarding  from pollution water used for  human consumption  and  preventing  polluted water from  being  so used;

     (ix)  the  lighting  of  public  streets,  Corporation markets  and public buildings and other public places vested in the Corporation;

     (ix-a)  the  construction and maintenance  of  parking lots, bus stops and public conveniences;

     (xxx) planting and maintaining trees on road sides and other public places.

     (xxxiii-a)  promoting  urban forestry  and  ecological aspects and protection of the environment;

     (xli) providing urban amenities and facilities such as parks, gardens and play-grounds."

     The Development Act is in force and it is not disputed that  whole  of  the city of Lucknow has  been  declared  as development  area  within the meaning of Section 3  of  this Act.  "Development" is defined in clause (e) of Section 2 of the Act and it is as under:-

     "(e)  "development", with its grammatical  variations, means  the carrying out of building, engineering, mining  or other  operations in, on, over or under land, or the  making of any material change in any building or land, and includes re-development."

     Lucknow   Development   Authority   (LDA)   has   been constituted under Section 4 of the Development Act.  Chapter III  of  the  Development Act provides  for  preparation  of Master  Plan and zonal development plan for the  development area.   Section 13 provides for the procedure for  amendment of  the  Master Plan or zonal development plan.  Section  14 provides  for  development of land in development  area  and this section is as under:-

     "14.   Development  of land in the developed area.   - (1)  After  the declaration of any area as development  area under  Section 3, no development of land shall be undertaken or  carried  out or continued in that area by any person  or body   (including  a  department   of   Government)   unless

13

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 53  

permission for such development has been obtained in writing from  the Vice-Chairman in accordance with the provisions of this Act.

     (2)  After  the  coming into operation of any  of  the plans  in  any  development  area no  development  shall  be undertaken  or carried out or continued in that area  unless such development is also in accordance with such plans.

     (3) Notwithstanding anything contained in sub-sections (1)  and  (2),  the  following  provisions  shall  apply  in relation  to  development of land by any department  of  any State  Government  or  the Central Government or  any  local authority --

     (a)  when  any  such  department  or  local  authority intends to carry out any development of land it shall inform the  Vice  Chairman  in writing of its intention to  do  so, giving  full  particulars thereof, including any  plans  and documents,   at  least  30   days  before  undertaking  such development;

     (b)  in  the  case  of  a  department  of  any   State Government  or the Central Government, if the  Vice-Chairman has  no  objection it should inform such department  of  the same within three weeks from the date of receipt by it under clause  (a)  of the department’s intention, and if the  Vice Chairman  does not make any objection within the said period the  department  shall  be free to carry  out  the  proposed development;

     (c)  where  the Vice Chairman raises any objection  to the  proposed development on the ground that the development is  not  in  conformity  with   any  Master  Plan  or  zonal development  plan prepared or intended to be prepared by it, or  on  any  other  ground, such  department  or  the  local authority, as the case may be, shall -

     (i)  either  make  necessary   modifications  in   the proposal  for  development to meet the objections raised  by the Vice- Chairman;  or

     (ii)  submit  the proposals for  development  together with  the  objections  raised by the Vice- Chairman  to  the State Government for decision under clause (d);

     (d)  the State Government, on receipt of proposals for development  together  with  the  objections  of  the  Vice- Chairman,  may either approve the proposals with or  without modifications   or  direct  the   department  or  the  local authority, as the case may be, to make such modifications as proposed  by  the Government and the decision of  the  State Government shall be final;

     (e)  the  development  of any land begun by  any  such department or subject to the provisions of Section 59 by any such  local authority before the declaration referred to  in sub-  section  (1)  may be completed by that  department  or local  authority  with  compliance with the  requirement  of sub-sections (1) and (2)."

     The  Development  Act  also   contains  provision  for penalties  and power of the LDA to demolish buildings and to stop  development in case of contravention of the provisions

14

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 53  

of this Act.  When the Development Act is in operation, then under  Section 59 of this Act, certain functions of the U.P. Municipal  Corporation Adhiniyam, 1959 become inoperative so far as these are relevant for the purpose :

     "59.    Repeal  etc.,  and   Savings.   -  (1)(a)  The operation  of  clause (c) of Section 5, Sections 54, 55  and 56,  clause  (xxxiii)  of Section 114, sub- section  (3)  of Section  117,  clause  (c)  of sub-section  (1)  of  Section 119..."

     The  provisions  of the U.P.  Regulation of  Buildings Operation  Act,  1958 also become inoperative by  virtue  of Section 59 of the Development Act.

     The Parks Act provides for preservation and regulation of parks, play-grounds and open spaces in the State of Uttar Pradesh.  The Parks Act applies to an area included in every Nagar  Mahapalika  under the Uttar Pradesh Nagar  Mahapalika Adhiniyam, 1959.  It is not disputed that this Act is now in force  (w.e.f.  February 1, 1995).  Park has been defined in clause  (b) of Section 2 of the Act to mean a piece of  land on  which  there are no buildings or of which not more  than one-twentieth  part is covered with buildings, and the whole or  the  remainder  of which is laid out as  a  garden  with trees, plants or flower-beds or as a lawn or as a meadow and maintained  as  a  place for the resort of  the  public  for recreation,  air or light.  The Act provides for maintenance of parks and prohibits construction of building, except with the  previous sanction of the concerned authority, which  is likely to affect the utility of the park.

     As  to  how the impugned agreement dated  November  4, 1993  came  to  be executed between the Mahapalika  and  the builder  we now consider the proceedings of the  Mahapalika, the  Executive  Committee and its sub- committee called  the High Power Committee.

     On  July 6, 1993 notice was issued for meeting of  the Mahapalika for July 12, 1993 with following agenda:

     "1.Discussions on the accepted proposals passed by the Executive Committee on 27.5.1993, and 27.6.1993.

     2.  Discussions on the various proposals.

     3.   Other  subjects,  subject to  the  permission  of Presiding Officer."

     There  were  no details regarding agenda item No.   3, which,  it  is said, pertained to Palika Bazaar,  i.e.,  the underground  shopping  complex.   On   that  day   following resolution  constituting  the  High   Power  Committee   for disposal  of  the  properties of the Mahapalika  was  passed under aforesaid agenda item No.3:-

     "The  full  details, maps, conditions of allotment  in respect  of  Shri Rafi Ahmad Kidwai Nagar Yojna  and  Rajaji Puram Vistar Yojna may be prepared at the earliest.  And for this   act  a  committee  may   be  constituted  under   the chairmanship  of  the  Nagar Pramukh in  which  two  Honble Sabhasad  and  three officers be appointed.  For  nominating the  members,  the  Nagar Pramukh may  be  authorised.   The

15

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 53  

powers  of  disposing  of  the entire  land,  allotment  and transfer  in respect of both the schemes shall be vested  in the above committee.

     It  was  also decided that the  Committee  constituted under  the Chairmanship of the Nagar Pramukh shall have  the rights  of  disposing  of  all  the  properties,  allotment, transfer  etc.   situated  within the limits  of  the  Nagar Mahapalika  and the above committee shall have the right  to give  the  final  shape to the conditions of  allotment  and agreement  etc.   In  this  manner  this  sub  Committee  is authorised  to  exercise  the aforementioned rights  of  the Mahapalika  conditions  of allotment and agreement etc.   In this manner this Sub Committee is authorised to exercise the aforementioned rights of the Mahapalika."

     Meeting  of  the High Power Committee  so  constituted under  the aforesaid resolution of the Mahapalika, was  held on  October 13, 1993 and was adjourned to October 19,  1993. In  the meeting of the High Power Committee held on  October 19,  1993, presided over by Mr.  Akhilesh Das, Nagar Pramukh as  Chairman, there is discussion regarding construction  of the  underground  air conditioned Palika Bazar  at  Aminabad Jhandewala  Park on the lines of Palika Bazar in New  Delhi. It  was recorded that the Vice-Chairman, Lucknow Development Authority  by his letter No.279/Architect dated October  16, 1993  intimated that as per the Master Plan, the land use of the  Aminabad, Jhandewala park is commercial.  The draft  of the  contract to be entered into between the Mahapalika  and the  MI  Builders was approved.  The minutes ended with  the recording  as  under:   "Amended  and  final  draft  of  the contract  was  read by the Advocate before the Committee  on this,  the  opinion  of  the members was asked  for  by  the Chairman  on  which all the members were unanimous that  all the  members  after  discussing  over  the  suggestions  and conditions  set  out  by the Mahapalika Advocate  took  this decision  that  the prescribed project may got  executed  by M.I.   Builders  Pvt.  Ltd.  And the Mukhya  Nagar  Adhikari should  be  authorised  for conducting all  the  forthcoming actions and formalities.

     The  Honble  Chairman also directed that  the  entire proceedings  may be presented for information in the meeting of the Executive Committee dated 20.10.93 and meeting of the Mahapalika house held on 21.10.93.

     Sd/-  Sd/-  B.K.   Singh yadav Sushil  Dubey  Sabhasad Member.  Mukhya Nagar Adhikari Member.

     Sd/-  G.C.   Goyal  Architect Sd/-D.K.   Doal,  Member Member, UP Nagar Adhikari.

     Sd/-  Akhilesh  Dass Sd/- Laxmi Narain  Nagar  Pramukh Sabhasad, Chairman of the Committee Member."

     In  view of the directions of the High Power Committee the  matter  was  placed before the Executive  Committee  on October 20, 1993 which passed the following resolution:  -

     "Resolution No.  (85) As per the decision taken in the meeting  dated  12.7.1993 of the Mahapalika, Sub-  Committee constituted  under  the  Chairmanship of the  Honble  Nagar Pramukh was entrusted with the powers of developing, leasing and  to  transfer the immovable property of the  Mahapalika.

16

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 53  

In  exercise of these powers, the Sub- Committee, keeping in view  the  grave  problem  of encroachment  and  parking  in Aminabad  Submitted  the  proposal of  the  Honble  Members namely  Sh.   Kalraj Mishra (President Bhartiya Janta  Party U.P.)   and  Shri  Ejaj  Rijvi,   Ex.   Minister   for   the construction  of an Air Conditioned Palika Bazar and parking place  in the Jandewala park (Aminabad Park) on the  pattern of  the  Delhi  Bazar, with a parking place for  about  1000 vehicles  through M/s.  M.I.  Builders Pvt.  Ltd.  Presented before  the  Executive Committee for information  which  was welcomed by all and the proposal was approved."

     Thereafter,  the  matter came to be placed before  the Mahapalika  in  its meeting dated October 21, 1993  and  the following minutes were recorded:  -

     "In view of the decision taken by the General House of Mahapalika   dated   12.07.93,  a  subcommittee  under   the Chairmanship  of Mayor was entrusted to transfer, to develop and  to give on lease of immovable properties of Mahapalika. In  exercise of these powers, the Sub-Committee, keeping  in view  the  grave  problem  of encroachment  and  parking  in Aminabad  submitted  the  proposal  of  Sh.   Kalraj   Misra (President)  Bhartiya Janta Party U.P.  and Sh.  Eagaz Risvi (Ex-Minister)  for construction of an air-conditioned Palika Bazar  and parking place in the Jhandewala Park (Aminuddaula Park) on the pattern of Delhi (Air-conditioned) Palika Bazar and  a  parking  in which there should be  a  provision  for parking  of about 1000 vehicles through M.I.  Builders  Pvt. Ltd.   presented before the House for information which  was welcomed and a unanimous resolution was passed and the Nagar Pramukh was congratulated for this important work."

     It  will  be  advantageous to reproduce  the  impugned agreement  dated November 4, 1993, which is executed between the Mahapalika and the builder:  -

     "WHEREAS,  the party No.1 is an absolute owner of  the plot  of  land  situated  at  Aminabad  popularly  known  as Jhandewala Park measuring about 2,45,000 sq.ft.  and bounded as below :

     NORTH Chhedilal Dharamshala Road

     SOUTH Ganga Prasad Road

     EAST Road locating Central Bank of India

     WEST Road locating Hyder Husain building.

     More specifically mentioned in the site- plan attached herewith.

     WHEREAS,  the  party No.1 is a body constituted  under the  UP  Nagar Mahapalika Adhiniyam (Act II 1959),  managing the parks, roads street lights and other such maintenance of amenities in the city.

     WHEREAS,  owing  to high increase in urban  population (according to 1991 Census, Lucknow Urban agglomeration has a population  of 16,69,204) because of the migratory character of  Rural  Population to Urban Areas which is too  congested due  to overflow of population, the city is also being faced

17

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 53  

overwhelmingly  with  day  to day  problem  of  encroachment causing  much  of  acrimony  perpetrating  high  guilts  and discrete errors.

     WHEREAS,  the  party No.1 remained ever  conscious  to keep  the  city  hygienically sound free  from  all  adverse effects  but  the problem of encroachment is no less than  a headache  for the Lucknow Nagar Mahapalika which has emerged like  a  growing nightmare and becoming unmanageable by  the Lucknow  Nagar  Mahapalika owing to its limited  and  scanty resources  and flow of supplementary income.  The  eagerness of Nagar Mahapalika to maintain proper road, construction of new  roads  with street lighting and the cleanliness  derive during  monsoon for removing sand and silt from the  nallahs is too often inadequately met by the Local Bodies Department of  the  Government  as  the Schedule  of  New  Demands  for providing  requisite funds are not available timely as  well as  sufficiently.   This is one of the major  hindrances  in keeping  the functioning of the Lucknow Nagar Mahapalika  at low ebb.

     WHEREAS,  considering  the  above  points  M/s.   M.I. Builders   Private  Limited  had   prepared  a  viable   and constructive  proposal  keeping  in  view  the  interest  of Lucknow  Nagar Mahapalika in all respects and, the same  was submitted   to   Lucknow  Nagar   Mahapalika  as  it   dealt exhaustively  the  benefits that will be oriented after  its implementation to the Lucknow Nagar Mahapalika as well as to the  Lucknow Populace.  The proposal was found beneficial to the  Nagar  Mahapalika  Lucknow as well as  to  the  general public.  The proposal which will be known as PALIKA BAZAR if given  affect  will be a source of control over the  traffic and will reduce the congestion in the vicinity.

     WHEREAS,  the  aforesaid proposal was accepted by  the Lucknow  Nagar Mahapalika in its Meeting thereby procuring a No  Objection  Certificate  from   the  Lucknow  Development authority  under  Section 14 of Urban Building Planning  and Development  Act, 1973 for constructing the PALIKA BAZAR  on the land mentioned above 279/vastuvid dated 16.10.1993.

     NOW this agreement witnesseth as under :-

     1.   That  party no.2 shall construct the said  PALIKA BAZAR according to the plan (attached herewith) with respect to which No Objection Certificate has been obtained by party no.1 from the prescribed authority.

     2.   That  the  PALIKA BAZAR shall be  constructed  by party  no.2 at his own cost and party no.2 shall be entitled to  realise the cost of construction with reasonable  profit which in any case shall not be more than 10% with respect to each shop as may fixed by party no.2 in lieu of construction and  when the project of Palika Bazar is completed and  cost of  construction has been realised the PALIKA BAZAR  shall be handed over to the Lucknow Nagar Mahapalika as its owner.

     3.    That   the  party   no.2  shall   also   provide air-conditioning  facility  in the PALIKA BAZAR at  his  own cost   as  well  as  the   installation  of  the  plant  and construction of the infrastructure in this regard.

     4.   That  the party no.2 shall have the right to  fix the  amount  of cost of construction while the rent  of  the shops  shall be at the rate of Rs.2.50 p.  only per sq.  ft.

18

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 53  

and  50  p.  will be charged as lease rent as 1/5th  of  the rent  of covered area and Rs.300/- per shop for  maintenance subject  to  enhancement  of  the  air  Conditioning  plant, maintenance of the complex as well as the electric charges.

     5.   That party no.2 shall be at liberty to lease  out the shops as per its own terms and conditions to the persons of  their  choice  on behalf of party no.1  which  shall  be binding  on  party no.1 but the conditions as  mentioned  in para  4 as aforesaid in this agreement regarding rent  shall remain in force.

     6.   That the party no.2 shall also have the right  to sign  the agreement if necessary on behalf of party no.1  as person  authorised by party no.1 on the terms and conditions which the party no.2 may deem fit and proper and the copy of the  agreement  shall  be  given to  party  no.1  after  its execution  and  the terms of the deed shall be binding  upon both  the  parties  of  this deed provided  the  party  no.2 executes  only that much of agreement which number of  shops are  available  in  Palika Bazar and in any case  shall  not exceed  the same but the rent of the shops shall remain  the same as mentioned above.

     7.   That the construction of PALIKA BAZAR shall start within  three  months from the date of registration of  this agreement  and,  shall be completed within three years  from the date of its start.

     8.   That party no.2 shall have the right to publicise the  project  and take advances from the buyers and to  give them proper allotment receipts.

     9.  That party no.1 shall co-operate in all manners in the  constructional work activities of party no.2 and  shall extend  all its co-operation and help as and when needed  by party no.2 from time to time.

     10.   That the party no.1 shall be responsible to help and  assist  party no.2 in completing the project and  party no.1  shall also be exclusively responsible for getting  the electric   sewer  and  water   connection   from   concerned department for the above project at the cost of party no.2.

     11.   That  party  no.1 shall help the party  no.2  in getting  the Project completed and meeting all the needs and requirements in completing the project.

     12.   That  in case there is in any  obstruction  from Mahapalika  or  legal  proceedings  resulting  in  the  non- completion  or  carrying out the constructional work of  the project  resulting  in  the non-completion stoppage  of  the work, the party no.1 shall be responsible for all the losses and damages that may accrue to party no.2.

     13.   That  party  no.2 shall not allot the  5%  shops before  completion  of  parking and other  services  of  the complex to ensure the proper compliance of the agreement and further ensure the quality of construction.

     14.   That party no.2 shall give the bank guarantee of Rs.25,00,000/-  (Rs.  twenty five lacs) for its  performance within  3  months  from  the date of  registration  of  this agreement  but  this  clause  is subject  to  all  necessary co-operation of party no.1.

19

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 53  

     15.   That party no.1 shall charge Rs.5,000/- per shop for every second and subsequent transfer of the shops.

     16.   That  after  the completion of the  project  the party  no.2 shall hand over the entire documents in original to the party no.1 for keeping the final records.

     17.   That  in  case of any  disputes  or  differences arising  out  of  the  project between the  parties  to  the agreement, the same shall be referred for arbitration to the mutually  appointed arbitrator who shall in all cases be the retired  justice of Honble High Court or its equivalent and his award shall be binding upon both the parties.

     18.  That the agreement between the party no.2 and the shop  keeper shall be duly approved by the Nagar  Mahapalika Lucknow and the party no.2 has made that agreement available to  the party no.1 and the party no.1 has approved the  said agreement.

     19.   That  all the legal expenses in  executing  this agreement shall be borne only by the party no.2.

     IN  WITNESS  WHEREOF,  the parties of this  deed  have signed  the  deed on the day and the year  mentioned  herein below  in presence of the following witnesses and the  terms of  this  agreement shall be binding upon the  legal  heirs, successors,  assignees  and   legal  representatives.   Sd/- Lucknow  :   dated  Party No.1 November 4, 1993.   For  M.I. Builders Pvt.  Ltd.

     WITNESSES Sd/- Managing Director Party No.  2 1.  Sd/- Drafted  by:  Sd/- 2.  Sd/- (Arvind Razdan) Advocate.  Civil Court, Lucknow"

     Mr.   Soli Sorabjee, learned counsel for the  builder, submitted that the agreement was not against public interest and  could not have been revoked by the Mahapalika.  He said the  petitioners in the writ petitions did not bring forward any contractor who could say that he was more competent than M.I.   Builders  to execute the job and at a cost less  than that  to be incurred by M.I.  Builders.  He said case of the builder  was  covered  by a judgment of this Court  in  M/s. Kasturi Lal Lakshmi Reddy and others vs.  State of Jammu and Kashmir  and  another  (1980 (4) SCC 1).  In this  case  the State  of J & K awarded a contract to the second  respondent for tapping of 10 to 12 lakhs blazes annually for extraction of resin from the inaccessible chir forests in the State for a  period  of  10 years.  This was in  accordance  with  the policy of the State Government and it was agreed upon that a part  of resin so extracted would be delivered to the  State for  running the State-owned industry and the rest would  be retained  by  the  second respondent  for  establishing  and running  its  own factory in the State.  The petitioners  in the writ petition assailed the order of the State Government on the following main three grounds:-

     "(A) That the order is arbitrary, mala fide and not in public  interest,  inasmuch  as  a  huge  benefit  has  been conferred on the 2nd respondents at the cost of the State.

     (B)  The  order creates monopoly in favour of the  2nd respondents   who  are  a   private  party  and  constitutes

20

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 53  

unreasonable  restriction on the right of the petitioners to carry on tapping contract business under Article 19(1)(g) of the Constitution.

     (C)  The State has acted arbitrarily in selecting  the 2nd  respondents  for  awarding  tapping  contract,  without affording   any  opportunity  to   others  to  complete  for obtaining  such contract and this action of the State is not based  on  any  rational  or   relevant  principle  and  is, therefore,  violative  of Article 14 of the Constitution  as also  of  the  rule  of administrative  law  which  inhibits arbitrary action by the State."

     This  Court,  after examining the whole facts  of  the case  and  applying  the parameters laid in  Ramana  Dayaram Shetty  vs.  International Airport Authority of India  (1979 (3)  SCC  489)  negatived  all   the  pleas  raised  by  the petitioners.    Referring  to  its   earlier   decision   in International Airport Authority of India case this Court had observed that there are two limitations imposed by law which structure  and  control the discretion of the Government  in giving  largess.   The  first is in regard to the  terms  on which  largess may be granted and the other in regard to the persons  who  may be recipients of such largess.   Then  the Court said as under:  -

     "So far as the first limitation is concerned, it flows directly  from the thesis that, unlike a private individual, the  State cannot act as it pleases in the matter of  giving largess.   Though  ordinarily a private individual would  be guided by economic considerations of self-gain in any action taken  by him, it is always open to him under the law to act contrary  to  his  self-interest  or to  oblige  another  in entering  into a contract or dealing with his property.  But the  government  is not free to act as it likes in  granting largess  such  as awarding a contract or selling or  leasing out  its property.  Whatever be its activity, the government is  still  the  government  and is,  subject  to  restraints inherent  in  its  position in a  democratic  society.   The constitutional  power conferred on the government cannot  be exercised  by  it  arbitrarily  or  capriciously  or  in  an unprincipled  manner;  it has to be exercised for the public good.  Every activity of the government has a public element in  it  and it must therefore, be informed with  reason  and guided  by  public  interest.   Every action  taken  by  the government  must  be  in public  interest;   the  government cannot  act  arbitrarily and without reason and if it  does, its  action  would  be  liable to be  invalidated.   If  the government  awards  a  contract or leases out  or  otherwise deals  with  its  property or grants any other  largess,  it would  be  liable  to  be tested for  its  validity  on  the touchstone  of reasonableness and public interest and if  it fails  to satisfy either test, it would be  unconstitutional and invalid."

     The Court said that the State of J & K, in view of its policy  of industrialization, was interested in the  setting up  of  the factory by the second respondents,  particularly since   the  second  respondents   had  two  factories   for manufacture  of resin, turpentine oil and other  derivatives and  they  possessed large experience in the  processing  of resin  and  reprocessing of resin, turpentine oil and  other derivatives.   The  Court  considered   the  nature  of  the

21

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 53  

contract  and observed that it was obvious that, in view  of the  policy  of  the  State Government, no  resin  would  be auctioned in the open market and in this situation, it would be  totally irrelevant to import the concept of market price with reference to which the adequacy of the price charged by the State to the second respondents could be judged.  If the State  were  simply selling resin, there could be  no  doubt that  the  State must endeavour to obtain the highest  price subject,  of course, to any other overriding  considerations of  public interest and in that event, its action in  giving resin  to  a private individual at a lesser price  would  be arbitrary  and contrary to public interest.  But, where  the State  has, as a matter of policy, stopped selling resin  to outsiders  and decided to allot it only to industries set up within   the   State   for   the  purpose   of   encouraging industrialization,  there  could be no scope  for  complaint that  the State was giving resin at a lesser price than that which  could be obtained in the open market.  The  yardstick of price in the open market would be wholly inept because in view  of the State policy, there would be no question of any resin being sold in the open market.

     After  examining  this  judgment it  is  difficult  to appreciate  the  argument  of Mr.  Sorabjee as  to  how  the principles  laid  in  this  case can be  applicable  to  the present case.

     To  substantiate his argument that there was "estoppel by  pleading" against the Mahapalika Mr.  Sorabjee  referred to  the  stand  of  the   Mahapalika  as  reflected  in  the proceedings  before the High Court as well as in this Court. It  was also pointed out that in the counter affidavit filed by  the State Government in the High Court it supported  the builder.   There  was  no  disposal  of  property  by  the Mahapalika  within  the meaning of Section 128 of  the  Act. Resolution  of  Mahapalika to enter into the agreement  with the  builder  was  validly  passed.   The  project  was  the brainchild  of  M.I.   Builders  and   the  nature  of   the transaction was such that it was unconventional and there is no  universal  rule  that tender be invited in  every  case. There  was  no  secrecy.  Everything was done  in  open  and discussed  freely at various stages.  In the affidavit dated January 8, 1994 of Mr.  B.K.  Singh, Chief Executive Officer of  the Mahapalika filed in the High Court he had  explained why  it was necessary to have the project executed in  order to  avoid  congestion in Aminabad commercial area.   In  the affidavit  dated  October  19,  1995 of  Mr.   T.K.   Doval, Upnagar  Adhikari which was filed in answer to IAs 10-12/95, complaining  breach of this Court’s order dated December 14, 1994, again the earlier stand of Mahapalika was re-affirmed. Mr.   Sorabjee  criticised the action of the  Mahapalika  in withdrawing its appeals in this Court on February 6, 1997 on mere  mentioning in the Court.  He said plan, which had been sanctioned  by  order  dated January 23, 1995,  was  revoked illegally  on  April  17,  1997 without any  notice  to  the builder.   There  is, however, resolution of the  Mahapalika dated August 6, 1996 filed by Mr.  S.K.  Gupta, Mukhya Nagar Adhikari  of the Mahapalika opposing the present appeals  by the  builder.   Mahapalika  took a summersault  and  gave  a complete  go- bye to its earlier stand.  That there could be estoppel  by  pleadings reference was made to a decision  of this  Court in Union of India vs.  M/s Indo-Afghan  Agencies Ltd.   (1968 (2) SCR 366) approving the earlier decision  of the Calcutta High Court in The Ganges Manufacturing Co.  vs. Sourujmull  and others (1880 ILR Calcutta 669 at 678).   Mr.

22

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 53  

Sorabjee  said a party could not change its stand even if it was legally wrong in its earlier stand as otherwise it could be a negation of everything.

     In  the  Ganges Manufacturing Co.  vs.   Sourujmull  & Ors.   [(1880)  5  ILR  Cal 669] a  Division  Bench  of  the Calcutta  High  Court held that "a man may be  estopped  not only from giving particular evidence, but from doing any act or relying upon any particular argument or contention, which the  rules  of equity and good conscience prevent  him  from using as against his opponent".

     In  Union  of India and others vs.  M/s.   Indo-Afghan Agencies Ltd.  [(1968) 2 SCR 366] in a certain scheme called the  Export Promotion Scheme incentives were provided to the exporters  for  woolen goods.  M/s.  Indo-  Afghan  Agencies Ltd.   Exported woolen goods to Afghanistan of F.O.B.  value of  over Rs.5 crores.  The Deputy Director in the office  of the  Textile Commissioner, Bombay, issued to them an  Import Entitlement  Certificate  for about Rs.2 crores only.   When the  representations  made  to the Government for  grant  of Import  Entitlement  Certificate for full F.O.B.  value,  it produced  no response and writ petition under Article 226 of the  Constitution  was filed in the High Court.  High  Court allowed  the writ petition.  In the appeal filed by Union of India  to this Court various contentions were raised.   This Court said:  -

     "Under  our jurisprudence the Government is not exempt from liability to carry out the representation made by it as to  its  future conduct and it cannot on some undefined  and undisclosed  ground of necessity or expediency fail to carry out  the  promise solemnly made by it, nor claim to  be  the judge  of  its own obligation to the citizen on an ex  parte appraisement  of  the circumstances in which the  obligation has arisen."

     And further:  -

     "The  defence  of executive necessity was  not  relied upon in the present case in the affidavit filed on behalf of the  Union  of  India.   It was also not  pleaded  that  the representation  in the Scheme was subject to an implied term that  the  Union  of India will not be bound  to  grant  the import  certificate for the full value of the goods exported if  they  deem it inexpedient to grant the certificate.   We are  unable  to accede to the contention that the  executive necessity  releases the Government from honouring its solemn promises  relying  on  which citizens have  acted  to  their detriment.  Under our constitutional set-up no person may be deprived of his right or liberty except in due course of and by  authority of law:  if a member of the executive seeks to deprive  a citizen of his right or liberty otherwise than in exercise  of power derived from the law -- common or statute -- the Courts will be competent to and indeed would be bound to, protect the rights of the aggrieved citizen."

     It was also held:  -

     "We  hold  that  the  claim   of  the  respondents  is appropriately  founded upon the equity which arises in their

23

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 53  

favour  as a result of the representation made on behalf  of the  Union of India in the Export Promotion Scheme, and  the action   taken   by  the   respondents  acting   upon   that representation  under  the belief that the Government  would carry  out  the  representation made by it.   On  the  facts proved in this case, no ground has been suggested before the Court  for exempting the Government from the equity  arising out  of  the acts done by the exporters to  their  prejudice relying upon the representation."

     Mr.   Sorabjee then referred to Section 128 of the Act and  to  the  expression  "disposal" and  also  to  Sections 129(4),  131 and 132 of the Act.  According to him there was no  disposal of any property and no interest in the land had been  transferred by the Mahapalika to the builder.  In this connection  reference  was  made  to  the  agreement   dated November  4,  1993.  Reference was also made to the  counter affidavit  filed  earlier by Mr.  B.K.  Singh, Mukhya  Nagar Adhikari,  wherein he had stated that the property vested in Mahapalika and that there was no disposal or transfer of any interest  in  the  property to the builder.  As to  what  is meant  by the expression "disposed of" reference was made to another  decision  of this Court in Deputy  Commissioner  of Sales  Tax  (Law), Board of Revenue (Taxes),  Ernakulam  vs. M/s.   Thomas  Stephen and Co.  Ltd.  (1988 (2) SCC  264  at 266).   This  judgment was of course in context of  sale  of goods.   Reference  was also made to a decision of House  of Lords  (1959 (1) WLR 465 at 472) to contend that  "disposal" means disposal absolutely.

     If  it was necessary to call tender reference was made to  a decision of this Court in G.B.  Mahajan and others vs. Jalgaon Municipal Council and others (1991 (3) SCC 91) where tender  was invited to construct the building but  authority was  given  to the developer to grant occupancy rights.   In this  case,  this  Court considered the  scope  of  judicial review in the case of contractual transaction of Government, its  policy  decision  and right of the  Government  on  its instrumentality  to  evolve any method for execution of  the project.  In this case respondent Jalagaon Municipal Council entered into a contract with a private developer/builder for construction   of  a  commercial   complex.    The   project contemplated   its   execution   by    the   developer    on self-financing   basis   subject  to    handing   over   the administrative  building  of  the complex to  the  Municipal Council  free  of cost and allotting some shops at  a  fixed rate/free  of cost to certain specified persons while having right  to dispose of the remaining accommodation at its  own discretion  and  to  retain the premia received  by  way  of reimbursement  of  its financial outlays plus profits.   The execution  of the project was challenged on the ground  that it  was unconventional and thus untenable.  This Court  said that  the Government or its instrumentality policy option to adopt  any method or technique for management of the project provided  the  same is within the constitutional  and  legal limits.   This  Court  held that the project was  not  ultra vires  the  powers of Municipal Council and such a case  was not open to judicial review.  The following main contentions were raised apprising the project:  -

     "a)  That  the scheme of financing of the project  was unconventional  and  was  not one that was, as a  matter  of policy,  open  and permissible to a governmental  authority. The  municipal  authority  could  either  have  put  up  the

24

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 53  

construction  itself departmentally or awarded the execution of  the whole project to a building contractor.  The  method of  financing  and execution of the project are ultra  vires the powers of the Municipal authority under the Act.

     b)  That the terms of the agreement with the developer that  the  latter be at liberty to dispose of the  occupancy rights  in the commercial complex in such manner and on such terms  as  it  may choose would amount to  an  impermissible delegation  of  the  statutory functions  of  the  Municipal Council under Section 272 of the Act to the developer.

     c)  That  the  project,  in effect,  amounted  to  and involved the disposal of municipal property by way of a long term  lease  with  rights of sub-letting in  favour  of  the developer violative of Section 92 of the ’Act’.

     d)  That the scheme is arbitrary and unreasonable  and is violative of Article 14 of the Constitution.  The project is  patently one intended to and does provide for an  unjust enrichment of respondent 6 at public expense."

     This  Court negatived all these contentions.  It  said that  the project, otherwise legal, does not become any  the less  permissible by reason alone that the local  authority, instead of executing the project itself, had entered into an agreement  with a developer for its financing and execution. This  Court did not find any violation of any provisions  of the  Maharashtra  Municipalities  Act,  1965  governing  the Municipal  Council.  On the question of reasonableness  this Court  said  that a thing is not unreasonable in  the  legal sense  merely  because the court thinks it is unwise.   Then this Court said:  -

     "The  contention regarding impermissible delegation is not  tenable.  The developer to the extent he is  authorised to induct occupiers in respect of the area earmarked for him merely exercises, with the consent of the Municipal Council, a power to substitute an occupier in his own place.  This is not impermissible when it is with the express consent of the Municipal  Council.   It would be unduly restrictive of  the statutory  powers  of  the local authority  if  a  provision enabling  the  establishment  of  markets  and  disposal  of occupancy  rights therein are hedged in by restrictions  not found in the statute."

     Reference was then made to a decision of this Court in Tata  Cellular vs.  Union of India (1994 (6) SCC 651)  where this  Court  considered  the scope of  judicial  review  and adduced the following principles:  -

     "(1)  The modern trend points to judicial restraint in administrative action.

     (2)  The  court does not sit as a court of appeal  but merely reviews the manner in which the decision was made.

     (3)  The court does not have the expertise to  correct the   administrative   decision.   If  a   review   of   the administrative decision is permitted it will be substituting its  own  decision,  without the necessary  expertise  which itself may be fallible.

     (4)  The  terms of the invitation to tender cannot  be

25

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 53  

open  to judicial scrutiny because the invitation to  tender is  in  the  realm  of  contract.   Normally  speaking,  the decision  to  accept  the tender or award  the  contract  is reached  by  process of negotiations through several  tiers. More  often than not, such decisions are made  qualitatively by experts.

     (5)  The Government must have freedom of contract.  In other  words,  a  fair  play in the joints  is  a  necessary concomitant  for  an administrative body functioning  in  an administrative   sphere  or   quasi-administrative   sphere. However,  the  decision  must  not only  be  tested  by  the application   of  Wednesbury   principle  of  reasonableness (including  its  other facts pointed out above) but must  be free  from arbitrariness not affected by bias or actuated by mala fides.

     (6) Quashing decisions may impose heavy administrative burden  on  the  administration and lead  to  increased  and unbudgeted expenditure."

     Lastly,  Mr.   Sorabjee  said that  after  this  Court allowed  builder to construct, in upholding the judgment  of the  High  Court,  equities would have to be  balanced.   Of course,  it would be different matter if the appeals were to be allowed, he said.

     Fifty prospective allottees of the shops, who had made payment to M.I.  Builders for allotment of shops before High Court  granted  order of stay, filed an application in  this Court  seeking permission to intervene in these appeals.  We heard  Mr.  Salve, learned senior counsel, who appeared  for them.  We record his submissions as under:  -

     1.   It  is  not in public interest to  dismantle  the shops  if  the court ultimately upholds the judgment of  the High Court.

     2.   Advertisement was made by the builder on December 24,  1993  offering to allot the shops and required each  of the prospective allottee to pay Rs.25,000/- with application for  allotment.  500 such applications were received out  of which  380  applications  were accompanied  with  cheque  of Rs.25,000/-  each.   Remaining   120  prospective  allottees deposited  the  amount of Rs.25,000/- each by mean of  cash. When, however, possession of the area was handed over to the builder  it  was  found that it was less  than  that  agreed earlier and that the total number of shops to be constructed would  be now in 263 in number.  Shops were of two sizes  of 10 x 15 ft.  and 10 x 20 ft.

     3.   Question  raised  now  is:    if  by  putting  in possession any interest in land was created in favour of the builder?   Could it be said that there was charge created in favour of the builder on the property including the land and the  structure  built upon it till the builder got whole  of the  amount  invested by it plus 10% of the profit over  and above  that?  No interest in the land was created in  favour of  the builder.  The agreement was something like a lien on a  property  of  an unpaid creditor as  understood  in  law. Builder  in  that situation would have right  to  possession till it was paid its dues.  As per the terms of the contract builder would retain the property by way of security till it was  paid but it could not claim to have any interest in the

26

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 53  

property.   It  is like an unpaid creditor.  When  the  term "disposed  of"  is used it means that full title had  passed but  when we say any interest in the property is passed then we mean a slice of that title has passed.

     4.  Agreement though is silent as to what is the legal right  of the builder on the land, it grants merely a  right to  the builder to enter upon the land and to build upon  as per its terms.  Provisions of Section 128 of the Act are not attracted.

     5.   It  is  a  moot point if  in  a  Public  Interest Litigation  the petitioner can tell the court to consider  a document  whether it is favourable or not.  Court cannot use a  magnified  glass  to see whether any  interest  had  been created  and  then  to  strike   down  the  agreement  being violative  of  Section 128 of the Act.  Ultimately it  boils down  to  the intention of the parties otherwise it will  be straining the point too far which is not permissible.

     6.   If  this Court decides to uphold the judgment  of the  High Court the applicants would request that the relief be  moulded.  In Public Law relief can be moulded even where the  court found irregularity or illegality to deny  relief. That  can  be  done under Article 142 of  the  Constitution. After  all  what  the  High Court has  found  was  that  the resolution  was  not properly considered before passing  the same;   that requirements of the provisions of Sections  128 and  129  of the Act were not adhered to;  and that  tenders were not invited in order to favour the builder.

     7.   It  is not the case of the writ petitioners  that any  extraordinary advantage was conferred on the builder or that  funds  of the taxpayers have been drained out.  If  it was  a  hospital or an industry or a dangerous  building  it would  be  imperative that the building be pulled  down  but here  construction is underground made to remove  congestion and  the only complaint of the petitioners was that it would create  more congestion.  Therefore, a mere irregularity  or even   illegality  would  not   result  in  destroying   the construction,  particularly, when there is no clear  finding of  any  mala  fide by the High Court.  It is not  that  any other  builder  has  been  aggrieved by the  action  of  the Mahapalika and had come forward to complain.  In fact one of the persons who himself is a party to the resolution was one of  the petitioners.  In the Administrative Law there is  an authority  that  relief  could  be  moulded.   There  is  no affidavit of the Lucknow Development Authority that building was  in any way dangerous.  Shopping complex and the parking lot,  which  has been built upon, is for public good and  an order of demolition would not be in general public interest. Discretion  should  be  used  not to  invalidate  the  whole process  even  if  provision of Sections 128  and  129  were violated.   Some  mechanism  could be evolved so  that  fair price  for the shops and use of parking lot is fixed and the case  of every prospective allottee could be examined and so also  perhaps the terms of the agreement between the builder and  the Mahapalika.  It would be an extraordinary order  if demolition is ordered.

     Reference  was made to Wade on Administrative Law, 7th Edition,  page  720  and to De Smith on Judicial  Review  of Administrative  Action, 5th Edition, page 271 to support the contention  that relief could be moulded in law.  In  Wade’s treatise the following part is relevant:  -

27

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 27 of 53  

     "The  freedom  with  which  the   court  can  use  its discretion  to mould its remedies to suit special situations is  shown by two decisions already encountered.  One was the case  where the House of Lords refused mandamus to a  police probationer  wrongly induced to resign, although he made out a  good  case  for that remedy, in order not  to  usurp  the powers  of  the chief constable, and instead granted him  an unusual  form  of  declaration  to the effect  that  he  was entitled  to  the remedies of unlawful removal  from  office except  for  reinstatement.  The other was the case  of  the Take-over Panel, where in fact no relief was granted but the Court  of  Appeal explained the novel way in which  remedies should  be  employed in future cases, with the  emphasis  on declaration  rather than certiorari and on ’historic  rather than  contemporaneous’  relief.  The same freedom  to  mould remedies  exists  in  European   Community  law,  where  the European Court of Justice may declare non-retroactivity when holding some act or regulation to be void."

     In De Smith it is as under:  -

     "The  principle  that  failure to  observe  formal  or procedural rules in the administrative process may be venial if  no  substantial  prejudice  has  been  caused  to  those immediately  affected  now appears in a number of  statutory contexts, but it is too early to say that it has established itself  as a general principle of law in contexts where  the enabling  Act  is  silent on the point, though some  of  the cases  on  the effect of disregarding statutory time  limits point vaguely in this direction.

     Administrative inconvenience

     Is  administrative  inconvenience a proper reason  for rebutting  the presumption that a decision which violates  a statutory  provision  is  unlawful (and therefore  that  the provision  is,  in  the   circumstances  not   "mandatory")? Administrative  inconvenience  is an accepted  criterion  in relation  to  remedies  provided by the courts  in  judicial review.    For  example,  where  a  series   of   commercial transactions  have  been  undertaken in  reliance  upon  the impugned  decision the court may, in its discretion, fail to quash that decision in view of the administrative chaos that would  result  from such a remedy.  Judicial  discretion  is employed  here to balance fairness to the individual against the general public interest.  The task, however, of deciding the force of a statutory provision does not involve judicial discretion.   It  involves the faithful construction of  the objects  and purposes of an act of Parliament in the context of  the  particular  decision.  Although aspects  of  public policy  may play a part in this exercise, it would be  wrong of  the  courts  to  impute  any  general  implication  that Parliament may intend administrative inconvenience to excuse in  advance  the  violation  of   its  statutes.   Such   an implication invites careless administration and assumes that the  legislature  would  too easily excuse a breach  of  its statutes.   It is suggested, therefore, that  administrative inconvenience  is  not normally a proper criterion to  guide the   question   of  whether  a   statutory   provision   is "mandatory"."

     Mr.   Sorabjee  and  Mr.   Salve  were  opposed  by  a

28

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 28 of 53  

formidable  cohort of lawyers.  Mr.  N.M.  Ghatate  appeared for  the  corporators  who filed writ petition in  the  High Court  and  were present themselves in the meetings  of  the Mahapalika on July 12, 1993 and October 21, 1993;  Mr.  G.L. Sanghi  appeared  for the Mahapalika;  Mr.  Adarsh Goel  for the  State of U.P.;  Mr.  Arun Jaitley for the LDA;  and Mr. Dushyant  Dave for Amrit Puri, who had separately filed  the writ  petition.   Their  submissions can  be  summarised  as under:  -

     1.   There was no proper convening of the meetings  of the  Executive  Committee and the Mahapalika, which  granted approval  to  the  construction   of  underground   shopping complex.   There  was also no such agenda in the meeting  of the Mahapalika.  Constitution of the High Power Committee by the  Mahapalika was itself not legal.  Regulations had  been framed  under  the Act for conduct of the  meetings.   Under Section  91  of the Act the requirement is four days  notice for  the  general body meeting of the Mahapalika  and  three days  notice  for  the meeting of the  Executive  Committee. Regulation  7  prescribes  as  to how the  business  of  the meeting  is to be conducted, as to which item is to be taken up  first  and rest in seriatim.  Regulation  7(f)  requires that  resolution  of  the   Executive  Committee  should  be separately  circulated  to  the  members  and  the  business respecting that should not be transacted in the heading "any other  business  with  permission  of  the  chair".    Under Regulation  30 it is necessary for a resolution to be  valid that there should be a proposer and a seconder.

     2.  The impugned agreement was not executed as per the requirement of Section 133 of the Act and on that account it is  not binding on the Mahapalika.  Reliance was placed on a decision  of this Court in Dr.  H.S.  Rikhy & Ors.  vs.  The New  Delhi  Municipal Committee [AIR 1962 SC 554].  In  this case  the  question for consideration before this Court  was whether  the provisions of Section 8 of the Delhi and  Ajmer Rent  Control  Act,  1952  (the Rent  Act)  applied  to  the transactions  between  the  appellants  and  the  New  Delhi Municipal  Committee  (the Committee) constituted under  the Punjab Municipal Act, 1911.  The Committee had constructed a market  and allotted the shops and flats by inviting tenders in  pursuance to an advertisement.  On an application  filed under Section 8 of the Rent Act by an allottee, an objection was  raised by the Committee that there was no  relationship of landlord and tenant between the parties.  High Court held that  there  was  no  relationship of  landlord  and  tenant between  the  parties  inasmuch as there was  no  ’letting’, there  being  no properly executed lease.  In coming to  the conclusion  that  there  was  no  valid  lease  between  the parties, High Court relied upon the provisions of Section 47 of  the  Punjab  Municipal Act.  High  Court  negatived  the contention  that the Committee was estopped from questioning the  status  of the applicants as tenants, having all  along admittedly  accepted  rent from them.  On an appeal  against the  judgment  of the High Court to this Court, it was  held that  use  of the term ’rent’ cannot preclude  the  landlord from pleading that there was no relationship of landlord and tenant.   The question must, therefore, depend upon  whether or  not  there was a relationship of landlord and tenant  in the  sense  that  there was a transfer of  interest  by  the landlord  in favour of the tenant.  This Court said that  in its  opinion  the  Rent  Act applied only  that  species  of ’letting’  by which the relationship of landlord and  tenant is  created,  that  is to say, by which an interest  in  the

29

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 29 of 53  

property,  however,  limited in duration is  created.   This Court referred to the provisions of Section 47 of the Punjab Municipal Act which is as under :

     "47.   (1) Every contract made by or on behalf of  the Committee of any municipality of the first class whereof the value  or amount exceeds one hundred rupees, and made by  or on behalf of the Committee of any municipality of the second and  third  class whereof the value or amount exceeds  fifty rupees  shall  be  in  writing, and must be  signed  by  two members,  of whom the president or a vice-president shall be one, and countersigned by the secretary :

     Provided  that,  when the power of entering  into  any contract on behalf of the committee has been delegated under the  last foregoing section, the signature or signatures  of the  member or members to whom the power has been  delegated shall be sufficient.

     (2)  Every transfer of immovable property belonging to any  committee  must  be made by an instrument  in  writing, executed  by the president or vice-president and by at least two  other  members  of committee, whose  execution  thereof shall be attested by the secretary.

     (3)  No  contract  or   transfer  of  the  description mentioned  in  this  section   executed  otherwise  than  in conformity  with  the  provisions of this section  shall  be binding on the committee."

     This Court said that in order that the transfer of the property  in question should be binding on the Committee, it was essential that it should have been made by an instrument in  writing, executed by the President or the Vice-President and  at  least two other members of the Committee,  and  the execution by them should have been attested by the Secretary and  If these conditions are not fulfilled, the contract  of transfer  shall  not  be binding on the Committee.   It  was observed  that provisions of Section 47(3) are mandatory and not merely directory.  Finally considering the argument that the  Committee  is estopped by its conduct from  challenging the enforceability of the contract this Court said :

     "The  answer  to the argument is that where a  statute makes  a specific provision that a body corporate has to act in  a particular manner, and in no other, that provision  of law  being  mandatory and not directory, has to be  strictly followed."

     3.   It  was  the  appellant,  the  builder,  who  was building  the  underground  shopping complex.   It  was  not undertaking  the construction as an agent of the Mahapalika. In this connection reference was made to a decisions of this Court in Akadasi Padhan vs.  State of Orissa (1963 (2) Supp. SCR  691  at  722).  It was, therefore, mandatory  that  the building plan be approved by the LDA.

     In  Akadast  Padhan vs.  State of Orissa  (1963  Supp. (2)  SCR 691) the State of Orissa acquired a monopoly in the trade of Kendu leaves.  Prior to this the petitioner used to carry  on  extensive trade in the sale of Kendu leaves.   He filed  a  petition  under  Article 32  of  the  Constitution complaining  restrictions put on his fundamental rights.  In the course of discussion this Court said:-

30

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 30 of 53  

     "When  the  State  carries on any trade,  business  or industry   it   must   inevitably   carry   it   on   either departmentally  or  through its officers appointed for  that purpose.   In  the very nature of things, the  State  cannot function  without the help of its servants or employees  and that inevitably introduces the concept of agency in a narrow and  limited sense.  There are some trades or businesses  in which  it may be inexpedient to undertake the work of  trade or  business departmentally or with the assistance of  State servants.   In such cases, it is open to the State to employ the  services of agents, provided the agents work on  behalf of the State and not for themselves."

     The Court then said:  -

     "It is true that an agent is entitled to commission in commercial  transactions,  and  so, the fact that  a  person earns commission in transactions carried on by him on behalf of  another  would not destroy his character as  that  other persons  agent.  Cases of Delcredere agents are not unknown to  commercial  law.   But we must not forget  that  we  are dealing  with agency which is permissible under Art.   19(6) (ii),  and as we have already observed, agency which can  be legitimately  allowed under Art.  19(6)(ii) is agency in the strict  and  narrow  sense of the term;   it  includes  only agents  who  can be said to carry on the monopoly  at  every stage  on  behalf of the State for its benefit and  not  for their  own  benefit at all.  All that such agents  would  be entitled  to would be remuneration for their work as agents. That being so, the extended meaning of the word agent in a commercial  sense  on  which  the  learned  Attorney-General relies  is  wholly  inapplicable  in  the  context  of  Art. 19(6)(ii)."

     4.   Mahapalika had disposed of the land in favour  of the  builder in contravention of the provisions relating  to disposal  of property under Sections 128 and 129 of the Act. If the substance of the impugned agreement is looked into it is the transfer of interest in land by the Mahapalika to the builder.

     5.   Even Section 128 of the Act was not applicable as the  land  was  a park which could not be  disposed  by  the Mahapalika.   As a matter of fact Mahapalika was the trustee of  the  park  and the doctrine of public trust,  which  was applicable in India as held by this Court in M.C.  Mehta vs. Kamal  Nath  and others (known as Span case) (1997  (1)  SCC 388),  was applicable to the park in question.   Mahapalika, therefore, could only manage the park and could not alienate it  or  convert it something different from the park.   Park was  held  by  the Mahapalika on trust for the  citizens  of Lucknow.

     In  M.C.   Mehta vs.  Kamal Nath and others (1997  (1) SCC  388)  the  case, which is also known as that  of  ’Span Resorts  case’, owned by Span Motels Pvt.  Ltd., this  Court observed,  that  public trust doctrine, as discussed in  the judgment,  is  a  part of the law of land.  The  Court  gave various  directions  even  cancelling the lease  granted  in favour  of  the  Motel  and   directing  the  Motel  to  pay compensation  by  way  of  cost   for  restitution  of   the

31

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 31 of 53  

environment and ecology of the area.  The judgment was cited to  reaffirm the argument for preservation of ecology, which is an important factor in preserving the Jhandewala Park.

     6.   Section  114 of the Act provides  for  obligatory duties  of the Mahapalika and one such obligatory  functions is  to  maintain  public places, parks and to  plant  trees. This  cannot  now  be  done as the park  has  been  dug  and construction  made  underground.   By  allowing  underground construction   Mahapalika  has  deprived   itself   to   its obligatory  duties which cannot be permitted.   Irreversible changes  have  been made.  Qualitatively it may still  be  a park  but it is a park of different nature inasmuch as trees cannot  be planted.  Now it is like a terrace park.   Though the  Park  Act came into operation w.e.f.  February 1,  1995 and the construction of the underground shopping complex had started  in  January, 1995 after the interim order  of  this Court  but  since the construction was made subject  to  the final  order  of this Court the provisions of the  Park  Act will have to be considered while deciding the matter.

     7.   Contract of such a magnitude could not have  been awarded  to the builder without calling for tenders.   There was no ground to depart from the settled norms.  Decision of this  Court in Sachidanand Pandey & Anr.  vs.  State of West Bengal  and  others (1987 (2) SCC 295), is no authority  for the proposition that it was not necessary to invite tenders. That  was a case relating to development of tourism industry in  the State of West Bengal.  The case did not lay any rule but  was  an  exception thereto.  In that case a  lease  was granted  by the State Government to Taj Group of Hotels  for construction  of a Five Star Hotel.  This was challenged  on various grounds in a writ petition filed under the banner of PIL.   The writ petition was dismissed by the learned single judge  of  the  High Court.  On appeal, the  Division  Bench confirmed  the  judgment of the learned single  Judge.   The matter  then  came  to this Court under Article 136  of  the Constitution  and  leave was granted.  One of the  questions raised  was  that  lease  which was  granted  by  the  State Government  without  inviting  tenders or holding  a  public auction.   This Court posed the question if in pursuing  the socio-economic  objective,  the  State is  bound  to  invite tenders  or  hold a public auction.  The Court  referred  to various  judgments  of  this Court in Rashbihari  Panda  vs. State  of  orissa  [(1969)  1 SCC  414;   R.D.   Shetty  vs. International  Airport Authority of India & Ors.  [(1979)  3 SCC  489];  Kasturi Lal Lakshmi Reddy vs.  State of J.  & K. [(1980)  4 SCC 1];  State of Haryana vs.  Jage Ram [(1983) 4 SCC  556];  Ram and Shyam Co.  vs.  State of Haryana &  Ors. [(1985)  3  SCC  267];  and Chenchu Rami Reddy &  Anr.   vs. Government  of A.P.  & Ors.  [(1986) 3 SCC 391].  Then  this Court observed as under :

     "On a consideration of the relevant cases cited at the bar  the  following  propositions  may   be  taken  as  well established:   State-owned or public- owned property is  not to  be  dealt  with  at   the  absolute  discretion  of  the executive.   Certain  precepts  and principles  have  to  be observed.   Public interest is the paramount  consideration. One  of the methods of securing the public interest, when it is considered necessary to dispose of a property, is to sell the  property  by  public auction or  by  inviting  tenders. Though  that  is the ordinary rule, it is not an  invariable rule.   There  may be situations where there are  compelling reasons  necessitating departure from the rule but then  the

32

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 32 of 53  

reasons for the departure must be rational and should not be suggestive  of discrimination.  Appearance of public justice is  as  important as doing justice.  Nothing should be  done which gives an appearance of bias, jobbery or nepotism.

     Applying these tests, we find it is impossible to hold that  the Government of West Bengal did not act with probity in  not inviting tenders or in not holding a public  auction but  negotiating  straightway at arms length with  the  Taj Group of Hotels."

     This  Court  also  found that on  the  commercial  and financial  aspect  of the lease even on a prima facie  view, there  appears  to be nothing wrong or objectionable in  the ’net sales’ method.  The ’net sales’ method is a fairly well known method adopted in similar situations.  It is a profit- oriented  and  appears  to be in the best  interest  of  the Government of West Bengal.

     8.   There was collusion among certain members of  the Mahapalika,  its officers and the builder.  Even the conduct of  the  lawyer  of  the   Mahapalika  was  commented   upon adversely.   It was not necessary for the Mahapalika to file a  separate appeal against the impugned judgment of the High Court.   These members of the Mahapalika equated  themselves with  the builder.  The lawyer of the Mahapalika drafted the agreement  dated November 4, 1993 between the Mahapalika and the  builder.   He  also filed special  leave  petitions  on behalf  of  the Mahapalika which had since  been  withdrawn. All  the fees of the lawyer of the Mahapalika for  attending the  meetings  of  the Mahapalika, drafting  the  agreement, preparing  special  leave petitions, etc.  were paid by  the builder  though that was shown to be done at the instance of the  Mahapalika.  There is on the record of the Mahapalika a letter  of the builder that there was a collusion among  the Mahapalika,  builder,  the lawyers and the officers  of  the Mahapalika,  the  architect of the Mahapalika, who  approved the  lay out plan, was also the architect of the LDA.  After the  lay out plan was submitted to the LDA the architect  of the  Mahapalika himself okays the lay out plan as  architect of  the LDA, which is then approved by the Vice-Chairman  of the LDA.

     9.  A body corporate cannot be made to remain bound by its  earlier  decision  if  that decision  is  found  to  be contrary  to  law.  There could not be any estoppel  against the  statute particularly when the whole project is  against public interest.  The State Government was right in changing its stand.  State Government considered the whole matter and on  the representations received from the public decided  to accept the judgment of the High Court.

     10.   The  agreement  is a fraud on the power  of  the Mahapalika.   Prime land has been given to the builder for a song.   The  fact that the scheme was so lucrative could  be seen  that  all shops to be constructed less 5% were  booked within  six days of the advertisement appearing in December, 1993.   Public  interest  and  public  exchequer  have  been sacrificed.   Mahapalika divested itself of its control over the  project.   The agreement is wholly one sided  favouring the builder.  It is unjust, unreasonable and irrational.

     11.   Builder  had already collected Rs.25,000/-  from each   of  the  prospective  allottees   at  the   time   of

33

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 33 of 53  

registration when it was originally planned to construct 500 shops.    There   were  no   building  plan  in   existence. Collecting   of  this  amount  by   the  builder  is  of  no consequence  in  deciding  the present appeals.  It  is  now stated  that  263  shops  had been  constructed  though  the builder  collected earnest money for 500 shops.  In spite of the  judgment of the High Court the builder did not care  to refund the earnest money so collected.  Its conduct does not entitle  it  to  any  consideration.  No  proper  study  was undertaken  before  the Mahapalika granted its approval  for construction  of  the underground shopping  complex.   There were no building plans when the agreement was entered into.

     12.   Narrow consideration that a few crores of rupees have  been  spent  on  the  construction  cannot  come  into consideration when the construction is in clear violation of the  Act,  the  Development  Act   and  Article  21  of  the Constitution.   That crores of rupees have been spent is  an argument   which  is  advanced  in   every  other  case   of unauthorised construction.

     13.  There is no alternative to the construction which is  unauthorised  and illegal to be dismantled.   The  whole structure built is in contravention of the provisions of law as  contained in the Development Act.  The decision to award contract  and  the agreement itself was  unreasonable.   The construction of the underground shopping complex, if allowed to  stand, would perpetuate an illegality.  Mahapalika could not  be allowed to benefit from the illegality.  A  decision of  this  Court  in Seth Badri Prasad and others  vs.   Seth Nagarmal  and  others (1959 (1) Supp.  SCR 769 at  774)  was referred  to,  to contend that the court could  not  exclude from  its  consideration  a  public statute  and  since  the construction  of the underground shopping complex was wholly illegal  it had to be dismantled.  No question of moulding a relief  can  arise as the builder made construction  on  the basis  of  the  interim order of this Court and at  its  own risk.   Various decisions of this Court in support of  these contentions  where  demolition of unauthorised  construction was  ordered,  were referred to, these being (1) K.   Ramdas Shenoy  vs.   The  Chief Officers, Town  Municipal  Council, Udipi  and  others (1975 (1) SCR 680 at 685),  (2)  Virender Gaur  and others vs.  State of Haryana and others (1995  (2) SCC  577  at 582), (3) Pleasant Stay Hotel and  another  vs. Palani  Hills Conservation Council and others (1995 (6)  SCC 127  at 139), (4) Cantonment Board, Jabalpur and others  vs. S.N.   Awasthi and others (1995 Supp.  (4) SCC 595 at  596), (5)  Pratibha Cooperative Housing Society Ltd.  And  another vs.  State of Maharashtra and others (1991 (3) SCC 341), (6) Dr.   G.N.   Khajuria  and  others  vs.   Delhi  Development Authority  and  others (1995 (5) SCC 762), (7)  Mrs.   Manju Bhatia  and  another  vs.  New Delhi Municipal  Council  and another  (JT 1997 (5) SC 574) and (8) an unreported decision of  this  Court  in Ram Awatar Agarwal vs.   Corporation  of Calcutta  (Civil Appeal 6416 of 1981) decided on August  20, 1996.

     In  K.   Ramadas Shenoy vs.  The Chief Officers,  Town Municipal  Council,  Udipi  and others (1975  (1)  SCR  680) respondent  was  granted  by  resolution  of  the  Municipal Committee  to  construct a cinema theatre at a  place  where earlier  respondent was granted licence for the construction of  Kalyan  Mantap-cum-Lecture  Hall.  In a  petition  under Article 226 of the Constitution the High Court held that the cinema  theatre  could not be constructed in a  place  other

34

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 34 of 53  

than  specified localities without proper sanction but since the  third respondent had spent a large sum of money it  did not   quash  the  impeached   resolution  of  the  Municipal Committee.   The appellant contended before this Court  that the  Town Planning Scheme forbade in cinema building at  the place  asked  for  and,  therefore, the  resolution  of  the Municipal  Committee  was invalid.  This Court  observed  as under:  -

     "An   illegal  construction  of   a  cinema   building materially affects the right to or enjoyment of the property by  persons residing in the residential area.  The Municipal Authorities  owe a duty and obligation under the statute  to see  that the residential area is not spoilt by unauthorised construction.   The  scheme  is  for   the  benefit  of  the residents  of the locality.  The Municipality acts in aid of the  schemed.   The rights of the residents in the area  are invaded by an illegal construction of a cinema building.  It has  to  be remembered that a scheme in a  residential  area means   planned   orderliness  in    accordance   with   the requirements  of the residents.  If the scheme is  nullified by  arbitrary acts in excess and derogation of the powers of the  Municipality  the  courts will quash orders  passed  by Municipalities in such cases.

     The  Court enforces the performance of statutory  duty by  public  bodies as obligation to rate payers who  have  a legal  right to demand compliance by a local authority  with its duty to observe statutory rights alone.  The scheme here is for the benefit of the public.  There is special interest in  the  performance of the duty.  All the residents in  the area  have their personal interest in the performance of the duty.  The special and substantial interest of the residents in the area is injured by the illegal construction."

     In  Virender Gaur and others vs.  State of Haryana and others   (1995  (2)  SCC   577),  the  Municipal  Committee, Thanesar,  District  Kurukshetra  in the  State  of  Haryana framed  Town  Planning Scheme, which was sanctioned  by  the Government.   In  the  Scheme  certain land  vested  in  the municipality.  State Government sanctioned allotment of that land  to  Punjab  Samaj Sabha on payment of a price  at  the rates  specified therein.  When the Punjab Samaj Sabha after getting  sanction started construction the appellants  filed writ  petition  in the Punjab and Haryana High Court,  which was, however, dismissed.  It was submitted before this Court that  the  purpose of the Scheme was to reserve the land  in question   for  open  spaces   for  the  better  sanitation, environment  and the recreational purposes of the  residents in  the  locality  and that the Government had no  power  to lease  out  the land to Punjab Samaj Sabha.   Reversing  the judgment  of  the High Court this Court said that after  the writ petition was filed by the appellants Punjab Samaj Sabha instead  of  awaiting the decision on merits proceeded  with the construction in post-haste and expended the money on the construction.   Therefore, the Court said, "we do not  think that it would be a case to validate the actions deliberately chosen,  as a premium, in not granting the necessary relief. It  was open to the Punjab Samaj Sabha to await the decision and  then  proceed  with the construction.  Since  the  writ petition  was  pending, it was not open to them  to  proceed with  the  construction  and then to plead equity  in  their favour.  Under these circumstances, we will not be justified in  upholding  the  action of the State  Government  or  the

35

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 35 of 53  

Municipality  in allotting the land to Punjab Samaj Sabha to the  detriment  of the people in the locality and  in  gross violation  of requirements of the Scheme.  Any  construction made by Punjab Samaj Sabha should be pulled down and it must be  brought back to the condition in which it existed  prior to allotment.  The Municipality is directed to pull down the construction  within  four  weeks from today.   They  should place  the report on the file of the Registry of the  action taken in the matter."

     In  Pleasant  Stay Hotel and another etc.   etc.   vs. Palani  Hills Conservation Council and others (1995 (6)  SCC 127) the question was whether the impugned Government Orders were  lawfully  and  validly made and, if so,  whether  they could  regularise the unauthorized construction.  High Court quashed  the  impugned Government orders and issued  certain directions.   This Court observed as under and then referred the matter to the High Court for certain clarifications:  -

     "In  our  considered  opinion the  most  eloquent  and patent  fact  that  must tilt the scale in this  dispute  in favour  of the Council is that the Hotel has admittedly made a residential construction of seven floors even though their sanctioned  plan was only for two floors.  That  necessarily means that five floors of the building have been constructed illegally   and  unauthorisedly.   It   is  not   surprising therefore  that the entire endeavour of the Hotel now is  to protect  the two floors constructed above the road level and to  yield  to any workable formula.  It is in  that  context that  the  Hotel,  without  prejudice   to  its  rights  and contentions,  had  suggested  that the entire  structure  of seven  floors  might  be  allowed to remain  and,  for  that purpose  it  was prepared to give an undertaking  that  they would  not use the five floors below the road level for  any residential purpose but utilise it only the for keeping air- conditioning  plant and other attendant purposes for running the  Hotel  on  the two floors above the  road  level.   The Council, however, vehemently opposed the above suggestion on the  ground  that  acceptance   thereof  would  mean  giving judicial   imprimatur  to  utter   and  flagrant  breach  of statutory provisions to which the Hotel resorted to in spite of  repeated  opportunities  given and reminders  issued  to retrace  their  steps  and any sympathy shown to  the  Hotel would  be wholly misplaced.  We need not, However, dilate on this  aspect of the matter as it appears to us that there is some  confusion  as  to  the   nature  of  the  above-quoted direction,  given  by the High Court and it requires  to  be clarified."

     In  Cantonment  Board, Jabalpur and others  vs.   S.N. Avasthi  and  others  (1995 Supp.  (4) SCC 595)  this  Court observed  that  construction  made in contravention  of  law would  not be a premium to extend equity so as to facilitate violation  of  the mandatory requirements of law.  Here  the Cantonment  Board had granted permission for construction of a building which was later on cancelled as the resolution of the   Board  granting  permission   was  suspended  by   the GOC-in-Chief.

     In  Pratibha  Cooperative  Housing Society  Ltd.   And another  vs.  State of Maharashtra and others (1991 (3)  SCC 341)  this  Court came down heavily on the  housing  society which  made construction in violation of Floor Space  Index. This  Court said that such unlawful construction was made by

36

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 36 of 53  

the  Housing  Board  in  clear and  flagrant  violation  and disregard of FSI and upheld the order of demolition of eight floors  as  ordered  by the  Bombay  Municipal  Corporation. While  dismissing  the  special leave  petition  this  Court observed as under:  -

     "Before parting with the case we would like to observe that  this case should be a pointer to all the builders that making  of  unauthorised  constructions never  pays  and  is against  the  interest of the society at large.  The  rules, regulations  and  by-laws  are made by the  Corporations  or development  authorities  taking in view the  larger  public interest  of  the society and it is the bounden duty of  the citizens  to  obey and follow such rules which are made  for their own benefits."

     In   Dr.   G.N.   Khajuria   and  others  vs.    Delhi Development  Authority  and  others   (1995  (5)  SCC  762), appellants  were  some  of  the residents  of  Sarita  Vihar colony,  developed by the Delhi Development Authority (DDA). It  was contended that the DDA permitted a nursery school to be  opened  in a certain park in complete violation  of  the provisions  of  the  Delhi  Development  Act,  1957.   After considering  the  provisions  of the Delhi  Development  Act Master  and Zonal Development Plans this Court said that the site  at  which  the school was allowed to be opened  was  a park.   It  further held that it was not open to the DDA  to carve  out  any space meant for park for a  nursery  school. This  Court said that the allotment for opening the  nursery school  was misuse of power and it cancelled the  allotment. This  Court  observed  that the construction put up  by  the allottee,  even though permanent, was of no relevance as the same  has  been  done on a plot of land allotted  to  it  in contravention of law.  As to the submission that dislocation from  the  present site would cause difficulty to  the  tiny tots,  this Court said that the same has been advanced  only to  get  sympathy from the court inasmuch as  children,  for whom  the nursery school is meant, would travel to any other nearby  place  where  such a school would be set up  by  the allottee  or  by  any  other person.  Six  months  time  was granted  to the allottee to make alternative arrangements as it  thinks fit to shift the school so that the children  are not  put to any disadvantageous position.  Then, this  Court observed as under:-

     "Before  parting, we have an observation to make.  The same  is  that  a  feeling is gathering  ground  that  where unauthorised  constructions  are demolished on the force  of the  order  of courts, the illegality is not taken  care  of fully  inasmuch as the officer of the statutory body who had allowed  the  unauthorised construction to be made  or  make illegal  allotments go scot free.  This should not, however, have  happened  for two reasons.  First, it is  the  illegal action/order  of  the officer which lies at the root of  the unlawful  act of the citizen concerned, because of which the officer  is  more  to be blamed than the  recipient  of  the illegal  benefit.   It is thus imperative, according to  us, that  while  undoing  the mischief which would  require  the demolition  of the unauthorised construction, the delinquent officer  has  also  to be punished in accordance  with  law. This,  however,  seldom happens.  Secondly, to take care  of the  injustice  completely, the officer who had misused  his power  has  also to be properly punished.   Otherwise,  what happens  is that the officer, who made the hay when the  sun shined, retains the hay, which tempts others to do the same.

37

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 37 of 53  

This  really gives fillip to the commission of tainted acts, whereas the aim should be opposite."

     In  Mrs.   Manju  Bhatia and another  vs.   New  Delhi Municipal  Committee  and another (JT 1997 (5) SC 574),  the builder,  after  obtaining  requisite sanction  to  build  8 floors,  constructed  more floors, sold the flats  and  gave possession  to  the respective buyers.  Subsequently it  was found that the builder constructed the building in violation of  the  building regulations and consequently flats on  the top  four  floors  were  ordered   to  be  demolished.   The demolition was challenged in the High Court by way of a writ petition,  which was dismissed.  Special leave to appeal  to this  Court  was also dismissed.  The question  before  this Court  was  whether  the appellants, who had  purchased  the flats  without  the  builder informing them of  the  illegal construction, should be compensated for the loss suffered by them.   High  Court  in the impugned judgment  directed  the return  of the amount plus the escalation charges.  All this was on a suit brought by the appellants.  This Court noticed that  the  escalated price as on the date was around  Rs.1.5 crores  per flat.  Taking into consideration the totality of the  circumstances  this Court directed the builder  to  pay Rs.60 lacs including the amount paid by the allottees.

     In  an unreported decision of this Court in Ram Awatar Agarwal  &  ors.   Vs.  The Corporation of Calcutta  &  ors. [C.A.   No.   6416 of 1981] decided on August 20,  1996,  an unauthorised  construction  in  the  city  of  Calcutta  was allowed to be demolished by the Corporation of Calcutta.  It was a multistory building.  The Court observed as under:-

     "We  share  the feeling of the Deputy  City  Architect when he states in paragraph 18 of his affidavit that this is a  case  in which an unscrupulous builder took advantage  of the  courts order upto a point of time and after he  failed in the legal process upto this court the tenants were set up to  delay  the  inevitable  and  thus  in  this  matter  the unauthorised  structure  hazardous and unsafe has stood  all these  years.   We have, therefore, no manner of doubt  that this is a case in which exemplary costs should be awarded."

     At  the  conclusion of the arguments and in  order  to decide the matter fully and finally but without prejudice to the respective contentions of the parties, we wanted to know the  nature of construction so far as carried out;  the cost thereof;    the   area  meant   for  shopping  and   parking separately;   and  if the plans were in accordance with  the Development Act and Rules.  This was particularly so when by an  interim  order  of this Court construction  was  allowed though with certain clear stipulations.

     Prof.   T.S.  Narayanaswami, Ex-Head of Department  of Building  Engineering and Management, School of Planning and Management,  New  Delhi was appointed as Local  Commissioner for  the  purpose.  He was asked to report on the  following aspects of the construction :

     "1.   What is the extent of construction put up by the appellant under ground the aforesaid part?

     2.  What is the nature of said construction?

38

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 38 of 53  

     3.  What cost can be said to have been incurred by the appellant in the construction uptil now?

     4.   What  further costs, if any, are required  to  be incurred   for  completion  of   the  project  with  parking provisions?

     5.  What will be the extent of the cost required to be incurred  if the structures existing on spot are required to be demolished and the land is to be restored to its original position?

     6.   Whether the present structures are put up by  the appellant  in accordance with the building plans  sanctioned by the Nagar Nigam?

     7.   Whether  the present structures comply  with  the building  requirements  as per the provisions governing  the Lucknow Development Authority?

     8.   Whether the structures existing on spot are  safe and  sound  and not likely to create any health  hazard,  if they are allowed to be retained on spot?

     9.   Whether  the  existing structures  with  suitable alterations  can be used for parking of vehicles and/or  for putting up other amenities like public convenience etc?

     10.  If the land earmarked for parking in the building plans  submitted  to the Nagar Nigam by the  appellant,  and which land is dug up at present, if restored to its original position,  is it feasible to use the existing structures for parking of vehicles and for putting up other amenities?

     11.   What are the existing general conditions of  the locality and the area around the park?"

     It is not necessary to examine the report of the Local Commissioner in detail except to note that :

     1.  extent of work carried out is approximately 80% of the  civil  and structural work, about 30% of the  finishing work and 20% of the services support work;

     2.  it is a First Class permanent construction;

     3.   cost of construction of the work so far  executed is approximately Rs.3.52 crore and the cost of work still to be done is approximately 2.97 crore;

     4.   dismantling  of the construction so far made  and restoration  of  the  park would  cost  Rs.98,10,181/-  less Rs.22,19,550/- salvage value;

     5.    though   there  is  a  letter  of  approval   of confirmation  having  been  given, there are  no  sanctioned drawings  (Chief  Architect  of  the  Mahapalika  said  that sanctioned drawings were "missing" from his files).

     6.   Lucknow Development Authority (LDA) did not  play any  role in sanctioning the project except the Layout Plan. (Layout Plan was forwarded to the LDA by the Chief Architect of  the  Mahapalika  who  was   also  officiating  as  Chief Architect of LDA at that time.  In other words, the approval

39

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 39 of 53  

of  the Layout at the LDA level was recommended by the  same person who forwarded it from the Mahapalika);

     7.  Master Plan could not have envisaged the park as a site  available  for  commercial   exploitation,  given  the density and congestion of the surrounding area;

     8.   structure as designed is safe from the structural engineering view point;

     9.   air  pollution  levels  of   the  park  and   the surrounding  areas  would go up by substantial amount  as  a result of underground shopping complex-cum-parking;  and

     10.  there is a lot of crowding during day hours (9.00 a.m  to  6.00  p.m.) leading to generally slow  movement  of traffic  and  occasional traffic hold ups.  A  high  decibel level  thanks to vehicles and moving people and vendors.   A lot  of  solid  waste collection at the end of the  day  and generally high level of pollution as a result.

     By  and  large the Report of Prof.  Narayanaswamy  has found acceptance by all the parties.

     Mr.   M.L.   Verma,  learned   senior  advocate,   who appeared  for  M.I.   Builders  after the  report  of  Prof. Narayanaswamy,  submitted  that  the  Report  of  the  Local Commissioner  insofar  as  it  gives cost  incurred  on  the constructions  is not correct and so also the cost  required to  be incurred for completion of the project.  His argument was that cost so far incurred was in fact more than what the Local   Commissioner  said  and   that  cost  required   for completion  of the project was less than that arrived at  by the  Local Commissioner.  We, however, do not find merit  in his  submission  as we find that the Local Commissioner  has applied  the  same principles while arriving at the cost  so far  incurred and the cost to be incurred for completion  of the  project.  We, therefore, accept the Report of the Local Commissioner  in its entirety.  But to what effect we  shall presently see.

     Jhandewala  Park,  the park in question, has  been  in existence  for  a great number of years.  It is situated  in the   heart   of  Aminabad,   a   bustling   commercial-cum- residential locality in the city of Lucknow.  The park is of historical  importance.   Because  of  the  construction  of underground  shopping complex and parking it may still  have the  appearance of a park with grass grown and path laid but it  has  lost  the  ingredients of a  park  inasmuch  as  no plantation  now  can be grown.  Trees cannot be planted  and rather while making underground construction many trees have been   cut.    Now  it  is   more  like  a   terrace   park. Qualitatively  it may still be a park but it is certainly  a park  of  different nature.  By construction of  underground shopping  complex  irreversible changes have been made.   It was  submitted  that  the  park was acquired  by  the  State Government  in the year 1913 and was given to the Mahapalika for  its management.  This has not been controverted.  Under Section  114  of  the Act it is the obligatory duty  of  the Mahapalika to maintain public places, parks and plant trees. By allowing underground construction Mahapalika has deprived itself  of its obligatory duties to maintain the park  which cannot  be  permitted.   But  then  one  of  the  obligatory functions  of  the Mahapalika under Section 114 is  also  to construct  and  maintain parking lots.  To that extent  some

40

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 40 of 53  

area  of  the  park  could  be   used  for  the  purpose  of constructing  underground parking lot.  But that can only be done  after  proper  study has been made  of  the  locality, including  density of the population living in the area, the floating    population   and     other   certain    relevant considerations.   This study was never done.  Mahapalika  is the  trustee  for the proper management of the  park.   When true  nature  of  the park, as it existed, is  destroyed  it would  be  violative  of  the doctrine of  public  trust  as expounded  by  this Court in Span Resort Case (1997 (1)  SCC 388).  Public Trust doctrine is part of Indian law.  In that case  the respondent who had constructed a motel located  at the  bank of river Beas interfered with the natural flow  of the river.  This Court said that the issue presented in that case illustrated "the classic struggle between those members of  the public who would preserve our rivers, forests, parks and  open  lands in their pristine purity and those  charged with   administrative   responsibilities   who,  under   the pressures  of the changing needs of an increasingly  complex society,  find it necessary to encroach to some extent  upon open lands heretofore considered inviolate to change".

     In  the  treatise  "Environmental  Law  and  Policy  : Nature,   Law,  and  Society"  by  Plater  Abrams   Goldfarb (American  Casebook  series  - 1992) under  the  Chapter  on Fundamental  Environmental Rights, in Section 1 (The  Modern Rediscovery  of  the  Public  Trust Doctrine)  it  has  been noticed  that  "long ago there developed in the law  of  the Roman  Empire  a legal theory known as the Doctrine of  the public trust." In America Public Trust doctrine was applied to  public properties, such as shore-lands and parks.  As to how  doctrine works it was stated:  "The scattered evidence, taken  together,  suggests  that  the   idea  of  a   public trusteeship  rests  upon three related  principles.   First, that  certain  interests - like the air and the sea  -  have such importance to the citizenry as a whole that it would be unwise  to  make  them  the subject  of  private  ownership. Second,  that they partake so much of the bounty of  nature, rather  than  of individual enterprise, that they should  be made freely available to the entire citizenry without regard to  economic  status.  And, finally, that it is a  principle purpose  of  government  to  promote the  interests  of  the general public rather than to redistribute public goods from broad  public  uses to restricted private  benefit...  With reference to a decision in Illinois Central Railroad Company v.  Illinois (146 U.S.  387 [1892]), it was stated that the court articulated in that case the principle that has become the  central substantive thought in public trust litigation. When  a  state holds a resource which is available  for  the free  use  of  the general public, a court  will  look  with considerable  skepticism upon any governmental conduct which is  calculated  either  to reallocate the resource  to  more restricted   uses  or  to  subject   public  uses   to   the self-interest  of  private  parties.    This  public  trust doctrine  in  our country, it would appear, has  grown  from Article 21 of the Constitution.

     Thus  by allowing construction of underground shopping complex in the park Mahapalika has violated not only Section 114 of the Act but also the public trust doctrine.

     If  we now refer to the provisions of law relating  to notice  of  meetings and business of the Mahapalika and  its committees  it  is apparent that these provisions  were  not adhered  to.   There is no authority with the Mahapalika  to

41

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 41 of 53  

constitute   High  Power  Committee   and  to  delegate  its functions to that High Power Committee.  There was no agenda at  any  time in any of the meetings of the  Mahapalika  for consideration  of  the underground shopping complex.   There were  no  proposals,  no documents, no plan,  no  study,  no project  report or feasibility report on the basis of  which Mahapalika  could have given a green signal for construction of   the  underground  shopping   complex.   There  was   no discussion  and no informed decision.  Mahapalika completely abdicated its functions.  Mahapalika delegated its functions to  the  High Power Committee in contravention of  the  Act. Constitution  of the High Power Committee itself was  wholly illegal.   High  Power Committee took decision to hand  over the  park to the builder for construction of the underground shopping  complex  and  also  approved   the  terms  of  the agreement  dated  November  4, 1993.  Decision of  the  High Power  Committee was put before the Executive Committee  and the  general  body  of  the Mahapalika for  the  purpose  of "information  and both these bodies stamped their approval. As  noted  above  there was no agenda for  consideration  of these   resolutions  of  the   Executive  Committee  of  the Mahapalika.   Corporators had no time to apply their  minds. Such  an important matter, where the cost of the project was likely  to  run  in crores of rupees, could  not  have  been considered  under the topic "other subjects, subject to  the permission  of  the Presiding Officer".  Section 105 of  the Act  protects any act done or proceeding taken on account of any  defect  or irregularity in procedure not affecting  the substance.   In the present case it is not mere irregularity or  defect  in the procedure but the whole procedure  is  in clear  breach  of Sections 91 and 119 of the Act  which  are mandatory.

     The  law mandates that not only the notice of the date and  the time of the meeting but the notice of the  business to  be transacted at such meeting should be given at least 4 clear days before the date of the meeting for the Mahapalika and 3 days for the Executive Committee.  When the agenda did not  include  the  subject of  construction  of  underground shopping  complex nor was there any material to support  the discussion  the  subject  of   construction  of  underground shopping  complex  it could not have been considered in  the meetings of the Mahapalika and the Executive Committee.

     In  Myurdhwaj  Cooperative Group Housing Society  Ltd. vs.   Presiding Officer, Delhi Cooperative Tribunal and Ors. [(1998)  6 SCC 39), the appellant was a Housing Co-operative Society  registered under the Delhi Co- operative  Societies Act,  1972 and Delhi Co-operative Societies Rules, 1973.  In the  meeting  of  the general body of the  society,  it  was decided  that  only those who have deposited minimum  amount specified by the general meeting would be allotted flats and others  would be accommodated on the flats to be constructed on the additional land in Phase-II construction.  Respondent No.3  who  was  one of the original members of  the  society challenged  the decision of the general meeting.  One of the contention  raised  was  that decision of the  general  body which  relegated her and other such members to Phase-II  was not  on  the  agenda.  This Court said a  general  body  can always  with the approval of the house in the meeting of its members  take up any other matter not covered by the  agenda on  that  account, no illegality could be held.  This  Court also  observed  that  Section 28 of the  Delhi  Co-operative Societies  Act,  1972 vests final authority in  the  general body of a cooperative society.  It has wide powers including

42

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 42 of 53  

residuary  power  except  those not delegated to  any  other authority  under  the Act, the rules and its  bye-laws.   In other  words,  its power, if any, is only restricted by  the Act,  the rules, the bye-laws and any order having force  of law.  This decision is of no help to the appellant as in the present case we are considering the statutory provisions for holding  of the meetings of the Mahapalika and the Executive Committee which have been violated.

     Agreement dated November 4, 1993 has not been executed as required under Section 133 of the Act.  Resolution of the High Power Committee, which was placed before the Mahapalika and  the Executive Committee for information, required  that the  prescribed  project  may  be   got  executed  by  M.I. Builders Pvt.  Ltd.  and the Mukhya Nagar Adhikari should be authorised  for  conducting all the forthcoming actions  and formalities".   Now,  Mahapalika  has power  to  enter  into contracts  (Sec.131).  Under sub-section (1) of Section  132 contract shall be expressed to be made, for and on behalf of Mahapalika and shall be so executed for and on behalf of the Mahapalika.  Under sub-section (4), no contract involving an expenditure  exceeding  five  lakh rupees shall be  made  by Mukhya  Nagar  Adhikari (Chief Executive Officer) unless  it has  been  sanctioned  by the Mahapalika.   Proviso  (a)  to Section  133(1) requires common seal of the Mahapalika to be affixed on every contract.  The common seal shall be affixed only  in  the presence of a corporator (Sabhasad) who  shall attach his signatures to the contract in token that the same was sealed in his presence.  The signature of the corporator shall  be distinct from the signature of any witness to  the execution  of such contract (sub-sections 2 and 3 of Section 133).   Under  sub-section  4  of Section  133  no  contract executed  otherwise than as provided in the section shall be binding  on the Mahapalika.  The impugned agreement is  thus not  executed  in accordance with the requirements  of  law. Further,  under  sub- section (2) of Section 136  where  the Mahapalika  approves  the project and the  entire  estimated cost  exceeds rupees ten lakhs, the project report shall  be submitted  to  the State Government and it is for the  State Government to reject or sanction the project with or without modifications.   Till  that  is  done   no  work  shall   be commenced.   No  such sanction of the State  Government  was obtained  in  the present case.  It was submitted that  this provision  would  apply only if the project cost was  to  be incurred  by the Mahapalika.  We do not think it is so.   It is  the cost of the project that matters and not who  incurs the cost in the first instance.  Agreement dated November 4, 1993  is, therefore, not a valid contract and not binding on the  Mahapalika.  As held in H.S.  Rikhys case (AIR 1962 SC 554)  where a statute makes a specific provision that a body corporate has to act in a particular manner and in no other, that  provision of law being mandatory and not directory has to  be strictly followed.  This principle will apply both as regards  holding of meeting of the Mahapalika and  execution of  contract on its behalf.  This judgment is also authority for  the  preposition  that there is no estoppel  against  a statute.

     We  may now examine some of the terms of the agreement dated  November  4,  1993.  There are six  recitals  to  the agreements  which cannot be co-related to any discussion  in any  of  the  meetings  of  the  Mahapalika,  the  Executive Committee  or the High Power Committee.  Under clause (2) of the  agreement it is for the builder to make construction at its  own  cost and then to realise the cost with profit  not

43

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 43 of 53  

exceeding more than 10% of the investment in respect of each shop.   Nobody knows how much cost the builder is likely  to incur  and how long it will continue to be in possession  of the  shopping  complex.  Full freedom has been given to  the builder  to  lease  out the shops as per its own  terms  and conditions  to  persons  of  its choice  on  behalf  of  the Mahapalika  and Mahapalika shall be bound by these terms and conditions.   Builder has also been given the right to  sign the  agreement on behalf of the Mahapalika on the terms  and conditions  which  the  builder  may deem  fit  and  proper. Builder  is only required to give a copy of the agreement to the  Mahapalika after its execution and both the  Mahapalika and  the  builder  shall remain bound by the terms  of  that agreement.   Since  there is no project report nobody  knows how  many  shops  the builder would construct  and  of  what sizes.   Mahapalika is allowed to charge Rs.5,000/- per shop for  every  second and subsequent transfer of shops  by  the builder  but  what  amount is to be charged  for  the  first transfer  or  subsequent  transfers  is  left  to  the  sole discretion  of  the builder.  A bare glance at the terms  of agreement  shows  that  not  only that the  clauses  of  the agreement  are unreasonable for the Mahapalika but they  are atrocious.   No person of ordinary prudence shall ever enter into such an agreement.  A trustee, which the Mahapalika is, has  to  be  more cautious in dealing with  its  properties. Valuable  land  in  the heart of commercial  area  has  been handed  on a platter to the builder for it to exploit and to make run away profits.  As a matter of fact on examining the terms  of  the  agreement we find that Mahapalika  has  been completely  ousted from the underground shopping complex for an  indefinite  period.   It has  completely  abdicated  its functions.

     To  repeat,  the  agreement is  completely  one  sided favouring  the builder.  The land of immense value has  been handed  over to it to construct underground shopping complex in  violation  of the public trust doctrine and  the  Master Plan  for  the city of Lucknow.  Mahapalika has no right  to step in even if there is any violation by the builder of the terms  of  the agreement or otherwise.   Mahapalika,  though considered to be the owner of the land, is completely ousted and  divested of the land for a period which is not definite and  which depends wholly on the discretion of the  builder. On  the question of reasonableness reference may be made  to Wade  on  Administrative  Law, 7th Edition, page  399.   The learned author observed that "The court must strive to apply an objective standard which leaves to the deciding authority the  full range of choices which the legislature is presumed to  have  intended.   Decisions  which  are  extravagant  or capricious  cannot be legitimate".  Quoting Lord Hailsham LC in  Re  W.  (an infant) ([1971] AC 682) where he said,  "two reasonable persons can perfectly reasonably come to opposite conclusions  on  the  same set of facts  without  forfeiting their  title  to be regarded as reasonable".  The  following passage from the treatise would be relevant:-

     "This is not therefore the standard of the man on the Clapham  omnibus.   It is the standard indicated by a  true construction of the Act which distinguishes between what the statutory  authority may or may not be authorised to do.  It distinguishes  between  proper  use and  improper  abuse  of power.  It is often expressed by saying that the decision is unlawful if it is one to which no reasonable authority could have  come.   This  is the essence of what is  now  commonly called  ’Wednesbury unreasonableness, after the now  famous

44

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 44 of 53  

case in which Lord Greene MR expounded it as follows.

     It   is  true  that   discretion  must  be   exercised reasonably.  Now what does that mean?  Lawyers familiar with the  phraseology  used in relation to exercise of  statutory discretions  often  use the word unreasonable in a  rather comprehensive  sense.   It has frequently been used  and  is frequently  used as a general description of the things that must  not be done.  For instance, a person entrusted with  a discretion  must,  so to speak, direct himself  properly  in law.  He must call his own attention to the matters which he is   bound   to  consider.   He   must  exclude   from   his consideration matters which are irrelevant to what he has to consider.   If he does not obey those rules, he may truly be said,  and  often  is  said, to  be  acting  unreasonably. Similarly, there may be something so absurd that no sensible person could ever dream that it lay within the powers of the authority.   Warrington  LJ in Short v.   Poole  Corporation [1926] Ch.  66.  Gave the example of the red-haired teacher, dismissed because she had red hair.  This is unreasonable in one  sense.   In  another it is  taking  into  consideration extraneous  matters.   It is so unreasonable that  it  might almost  be  described as being done in bad faith;   and,  in fact, all these things run into one another.

     This  has  become  the most frequently  cited  passage (though  most  commonly  cited  only  by  its  nickname)  in administrative  law.  It explains how unreasonableness, in its  classic formulation, covers a multitude of sins.  These various   errors  commonly  result   from  paying  too  much attention to the mere words of the Act and too little to its general  scheme  and  purpose,  and from  the  fallacy  that unrestricted   language    naturally    confers   unfettered discretion.

     Unreasonableness  has thus become a generalised rubric covering  not  only sheer absurdity or caprice, but  merging into  illegitimate motives and purposes, a wide category  or errors  commonly  described as irrelevant  considerations, and  mistakes and misunderstandings which can be classed  as self-misdirection,  or  addressing  oneself   to  the  wrong question.   But  the language used in the cases shows  that, while  the abuse of discretion has this variety of differing legal  facets,  in practice the courts often treat  them  as distinct.  When several of them will fit the case, the court is  often  inclined to invoke them all.  The  one  principle that  unites them is that powers must be confined within the true scope and policy of the Act.

     Taken  by itself, the standard of unreasonableness  is nominally  pitched  very high:  so absurd that no  sensible person could ever dream that it lay within the powers of the authority  (Lord Greene MR);  so wrong that no  reasonable person  could  sensibly take that view (Lord  Denning  MR); so outrageous in its defiance of logic or of accepted moral standards  that no sensible person who had applied his  mind to  the  question  to be decided could have arrived  at  it (Lord  Diplock).  It might seem from such language that  the deliberate  decisions  of  ministers and  other  responsible public  authorities  could  almost never be  found  wanting. But,  as  may  be  seen in the following  pages,  there  are abundant  instances  of legally unreasonable  decisions  and actions  at  all levels.  This is not because ministers  and public  authorities take leave of their senses, but  because the  courts in deciding cases tend to lower the threshold of

45

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 45 of 53  

unreasonableness  to  fit  their   more  exacting  ideas  of administrative good behaviour."

     When we keep in view the principles laid by this Court in its various judgments and which we have noticed above, it has  to be held that the agreement dated November 4, 1993 is not  a  valid  one.   The agreement  defies  logic.   It  is outrageous.    It  crosses  all   limits   of   rationality. Mahapalika has certainly acted in fatuous manner in entering into  such an agreement.  It is a case where the High  Court rightly  interfered  in exercise of its powers  of  judicial review  keeping in view the principles laid by this Court in Tata Cellular vs.  Union of India (1994 (6) SCC 651).  Every decision  of  the authority except the judicial decision  is amenable  to  judicial  review and reviewability of  such  a decision  cannot  now  be questioned.  However,  a  judicial review  is permissible if the impugned action is against law or   in  violation  of  the   prescribed  procedure  or   is unreasonable,  irrational or mala fide.  On the principle of good governance reference was made to a decision of Division Bench  of Bombay High Court in State of Bombay vs.  Laxmidas Ranchhoddas  and another (AIR 1952 Bombay 468 at 475)  (Para 12).   It  was  submitted  that bad governance  sets  a  bad example.  That is what exactly happened in the present case.

     In  State  of Bombay vs.  Laxmidas Ranchhoddas &  Anr. [1952  AIR Bom.  468] a Division bench of the High Court was considering  the  argument that the writ of  mandamus  being discretionary,  the Court should consider whether it  should not  put a limitation upon its own powers and  jurisdiction. It  was  submitted that it was impossible for any  State  to function  if  there was a constant interference by the  High Court in the executive acts performed by the officers of the State.  Chagla, CJ, speaking for the Court, said :

     "It  may  be that interference by the High  Court  may result  in  inconvenience or difficulty  in  administration. But  what  we have to guard against is a much greater  evil. When  we  find in the modern State wide powers entrusted  to Government,  powers which affect the property and person  of the  citizen, it is the duty of the Courts to see that those wide  powers  are  exercised  in conformity  with  what  the Legislature  has  prescribed.  We are not oblivious  of  the fact that in order that the modern State should function the Government  must  be armed with very large powers.  But  the High  Court  does not interfere with the exercise  of  those powers.   The High Court only interferes when it finds  that those  powers  are  not  exercised in  accordance  with  the mandate of the Legislature.  Therefore, far from interfering with  the good governance of the State, the Court helps  the good  governance by constantly reminding Government and  its officers that they should act within the four corners of the statute  and not contravene any of the conditions laid  down as   a  limitation  upon   their  undoubtedly  wide  powers. Therefore,  even  from a practical point of view, even  from the  point  of view of the good governance of the State,  we think  that the High Court should not be reluctant to  issue its  prerogative  writ whenever it finds that the  sovereign Legislature has not been obeyed and powers have been assumed which the Legislature never conferred upon the executive."

     It  cannot  be  said  that  the  construction  of  the underground  shopping complex is by the builder as an  agent

46

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 46 of 53  

of  the Mahapalika.  Concept of agency is totally missing in the  present  case.   Rather the deal is from  principal  to principal.   Reference  may be made to the decision of  this Court  in  Akadasi  Padhans case [1963  Supp.(2)  SCR  691] quoted  above.   When  the "development" is by  the  builder provisions of Section 14 of the Development Act would apply. There is no sanction of the building plan of the underground shopping  complex  by the LDA.  Construction is,  therefore, per  se illegal.  Even after the interim order of this Court allowing  construction,  plans were not got sanctioned  from the LDA, which would be authority under the Development Act. Sanction  of  the  building plan by  the  Mahapalika  would, therefore,  be  meaningless.   Even   then,  there  were  no sanctioned  drawings.  It has been pointed out that  process of  sanction  appeared  to  be ad hoc  and  skeletal.   When construction  started LDA issued a show cause notice to  the Mahapalika  but  then in view of the interim order  made  by this Court show cause notice was subsequently withdrawn.  It was stated that against the order withdrawing the show cause a  revision was filed by Mr.  Amrit Puri, a writ  petitioner to  the  State  Government,  which was stated  to  be  still pending.

     It  is  not  disputed  that there  is  a  Master  Plan applicable to city of Lucknow.  This Master Plan is prepared under  the Development Act.  It was submitted by the builder that  the park could be exploited for commercial purposes as Aminabad  has been shown to be a commercial area.  No  doubt Aminabad  is  a commercial area but that does not mean  that the  park  can be utilised for commercial purposes.   Rather using  the park for commercial purposes would be against the Master  Plan.  However, in letter dated October 16, 1993  by Vice-Chairman, LDA to the Mahapalika did say :

     "I  am to inform you in this regard that the land  use of  the  Jhandewala park situated in Aminabad is  commercial one  as  per  the  Master  Plan.   This  department  has  no objection on the layout plan submitted accordingly."

     How  this letter came to be written one may notice the sequence.   High  Power Committee meets on October 13,  1993 and  is adjourned to October 19, 1993.  Mr.  G.C.  Goyal  is the Architect of Mahapalika and he forwarded the layout plan to LDA.  Mr.  Goyal is also officiating as Architect of LDA. Approval  of  the  layout plan by LDA is dated  October  16, 1993, which is 3 days before the next meet of the High Power Committee.   This  approval  of  the   layout  at  LDA   was recommended  by  the same person who forwarded it  from  the Mahapalika and in a great hurry.  In the Master Plan for the city of Lucknow, it is Aminabad area which is commercial and that  would not mean that Park can be put to commercial use. By  letter  dated  November 23, 1993, LDA  objected  to  the construction  being undertaken in the Park without obtaining permission/No   objection   from  it    and   required   the construction to stop.  Mahapalika in turn by its letter sent on  the  following  day to the builder informed  it  of  the objection  raised  by  LDA  and  that  before  starting  any construction  the permission/No objection of LDA as required under  Sections  14  and  15  of  the  Development  Act  was necessary.  It does appear to us that the Master Plan of the city of Lucknow could not have envisaged the Jhandewala Park as  a site available for commercial exploitation considering the density and congestion in the area.

47

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 47 of 53  

     The  reason  for  the   construction  of   underground shopping  complex  given  was  that   it  would  remove  the congestion  in  the  area.   We have  report  of  the  Local Commissioner,  which says that it would rather lead to  more congestion.   We think Mr.  Dave is right in his  submission that a decision to construct underground shopping complex by M.I.   Builders  had already been taken and that  the  whole process  was  gone  into  to confer undue  benefit  to  M.I. Builders  and  the  bogie of congestion  was  introduced  to justify  the action of the Mahapalika.  It is wholly illegal and   smacks   of    arbitrariness,   unreasonableness   and irrationality.

     We  may also note the argument of Mr.  Adarsh Goel who said  that Jhandewala Park was acquired by the State in  the year  1913  and was given to Mahapalika for its  management. He  said  under Section 41 of the Development Act read  with Section 5 of the U.P.  Regulation of Building Operations Act a  Government  order  was issued on August 18, 1986  by  the State  Government whereby the use of park for any other  use was  prohibited.  This direction of the State Government was incorporated  in the Master Plan for the city of Lucknow and of  course violated by allowing construction of  underground shopping complex.

     Action   of   the  Mahapalika  in  agreeing   to   the construction    of   underground     shopping   complex   in contravention of the provisions of the Act and then entering into an agreement with the builder against settled norms was wholly illegal and has been held to be so by the High Court. No  doubt  Mahapalika  is a continuing body and it  will  be estopped  from  changing its stand in the given  case.   But when  Mahapalika  finds that its action was contrary to  the provisions  of  law by which it was constituted there  could certainly  be no impediment in its way to change its  stand. There   cannot  be  any   estoppel  operating  against   the Mahapalika.   Principles  laid in Union of India  vs.   M/s. Indo-Afgan Agencies Ltd.  (1968 (2) SCR 366) and of Calcutta High  Court in The Ganges Manufacturing Co.  vs.  Sourujmull and others (1880 ILR Calcutta 669) cannot apply to the facts of the present case.

     Section  128  of  the  Act   confers  powers  on   the Mahapalika to sell, let of, hire, lease, exchange, mortgage, grant  otherwise  dispose  of any property or  any  interest therein  acquired by or vested in the Mahapalika.  Appellant and  the intervenors said that there was no disposal of  any property and no interest in the land had been transferred by the  Mahapalika to the builder.  Respondent, as noted above, contended to the contrary.  Under Section 54 of the Transfer of  Property Act, 1882 agreement to sell does not create any interest in land.  We are not concerned with this provision. Reference  may, however, be made to Sections 60(b) and 62(f) of the Easement Act, 1882.  Though the licence under Section 60(b)  is  irrevocable  but  it can  be  revoked  after  the happening  of  certain event which is when the  builder  has recovered  whole  of his investment plus 10% of the  profit. Reference  may  be  made  to a decisions of  this  Court  in Chawalier  I.I.   Iyappan and another vs.   The  Dharmodayam Company  [(1963)  1 SCR 85].  In this case an  argument  was raised  by the appellant that he had been granted a  licence and  acting  upon  the  licence he had executed  a  work  of permanent  character and incurred expenses in the  execution thereof and, thereafter, under Section 60(b) of the Easement Act, 1882 the licence was irrevocable.  This Court said:-

48

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 48 of 53  

     "In  our opinion no case of licence really arises  but if  it does what is the license which the appellant obtained and  what is the licence, which he is seeking to plead as  a bar.  The licence, if it was a licence, was to construct the building and hand it over to the respondent company as trust property.   There  was no licence to create another kind  of trust  which the appellant has sought to create.  It  cannot be  said  therefore  that there was an  irrevocable  license which falls under s.  60(b) of the Act.  Even such a license is  deemed  to be revoked under s.  62(f) of that Act  where the  licence  is  granted  for a specific  purpose  and  the purpose  is attained or abandoned or becomes  impracticable. In  the  present case the purpose for which the license  was granted   has   either   been   abandoned  or   has   become impracticable because of the action of the appellant."

     [The  Indian  Easement  Act, 1882:  Sections  52,  53, 60(b0 and 62(f) :-

     52.   Where  one  person grants to another,  or  to  a definite number of other persons, a right to do, or continue to  do,  in or upon the immovable property of  the  grantor, something  which  would,  in the absence of such  right,  be unlawful,  and such right does not amount to an easement  or an interest in the property, the right is called a license.

     53.   A  license  may  be granted by any  one  in  the circumstances  and  to  the extent in and to  which  he  may transfer  his  interests  in the property  affected  by  the license.

     60.  A license may be revoked by the grantor, unless:-

     (a)..........

     (b)  the  licensee,  acting   upon  the  license,  has executed  a  work  of  a permanent  character  and  incurred expenses in the execution.

     62.  A license is deemed to be revoked -

     (a) to (e) ...........

     (f)  where  the  license is granted  for  a  specified purpose  and  the  purpose  is attained,  or  abandoned,  or becomes impracticable;]

     We  find force in the submissions of respondents  that by  granting licence to the builder to construct underground shopping  complex of permanent nature and to hold on to  the same  for a period which is not definite and then under  the impugned  agreement builder having been authorised to  lease out  the shops on behalf of the Mahapalika, it is a  dubious method adopted to subvert the provision of Section 128 which apply  as well in the case of lease and thus the transaction will also be covered by the expression "otherwise dispose of any  interest in the property".  It is, therefore, difficult to  accept  the argument of the builder that transaction  is outside Section 128 of the Act.  Now, first licence has been granted to the builder to enter upon the park and to execute a  work  of  permanent character and incur expenses  in  the execution  of the work, thus making the licence irrevocable.

49

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 49 of 53  

However,  the  licence  is deemed to be  revoked  after  the licensee  has  recovered his full cost on  the  construction plus  10% of the profit on the investment made by him.  When this purpose is achieved by the licensee is anybodys guess. Not only that licensee, i.e., the builder is then authorised to  lease  out  the shops so constructed on  behalf  of  the Mahapalika.   The  result  would  be  that  to  the  builder provisions  of  Section 129 of the Act, cannot be thus  made applicable.   In such a situation for the builder to contend that  the  transaction  is not covered by Section  128  and, therefore,   Section  129  will   not  apply  is   certainly incredulous.   Provision  of  Section 129 of  the  Act  has, therefore,  been flouted.  Impugned agreement dated November 4, 1993 is bad having been executed also in contravention of the requirement of Section 129 of the Act.

     The  facts  and circumstances when examined  point  to only  one  conclusion that the purpose of  constructing  the underground  shopping  complex  was a mere pretext  and  the dominant  purpose  was to favour the M.I.  Builders to  earn huge profits.  In depriving the citizens of Lucknow of their amenity  of an old historical park in the congested area  on the  spacious  plea of decongesting the area Mahapalika  and its  officers  forgot  their duty towards the  citizens  and acted in a most brazen manner.

     Proposition  of  construction of underground  shopping complex  was  so  lucrative and the land  so  valuable  that Mahapalika  itself could have done it by collecting  earnest money from the prospective allottees.  But then nobody cared to  examine  this aspect and a plea was also  advanced  that Mahapalika  had no finance to undertake the project.  If one refers  to the agreement the builder itself devised a  self- financing  scheme and it had not to spend anything from  its own  pocket.   On  mere booking of the shops  builder  could collect  rupees  one crore twenty five lakhs and would  have collected  more money with the progress of the  construction at  various stages.  A public body would not sequester  away its property by devising new methods.

     Thus  there are two distinct areas of challenge in the present  case  - (1) the agreement is fraud on power,  prime land  has been given for a song by the Mahapalika.  The fact that  the scheme is so lucrative could be seen from the fact that  all  shops less 5% were booked within six days of  the advertisement  appearing in December, 1993.  Public interest and  public  exchequer have been sacrificed.  Mahapalika  is divested  of its control over the project though  notionally not for ever but the builder, on the other hand, has control over  the project for all times to come and (2) construction is in contravention of the provisions of law as contained in Development  Act.   The  project has been entrusted  to  the builder  in  violation  of the provisions of the  Act.   The decision  taken  by  the  Mahapalika   was  not  on   proper consideration  and  was not an informed objective  decision. Judicial  review  is permissible if the impugned  action  is against  law or in violation of the prescribed procedure  or is  unreasonable, irrational or mala fide.  As said  earlier High Court rightly exercised its power of judicial review in the  present case.  It has examined the manner in which  the decision  was made by the Mahapalika.  Second principle laid in  Tata  Cellular’s case [(1994) 6 SCC 651] applies in  all respects.   High Court held that the maintenance of the park because  of  its  historical  importance  and  environmental necessity was in itself a public purpose and, therefore, the

50

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 50 of 53  

construction  of  an  underground  market  in  the  garb  of decongesting the area was wholly contrary and prejudicial to the public purpose.  By allowing the construction Mahapalika had  deprived its residents as also others of the quality of life  to which they were entitled to under the  Constitution and  the  Act.   The   agreement  smacks  of  arbitrariness, unfairness  and  favourtism.  The agreement was  opposed  to public  policy.   It  was  not in  public  interest.   Whole process  of  law was subverted to benefit the  builder.   We agree with the findings and conclusions of the High Court.

     High  Court  in its impugned judgment has not  doubted the  capacity of M.I.  Builders to undertake the project but then  that is not the issue.  The question is why it was not necessary  to invite tenders for the project of such a  high cost.   Why  it  was  thought  that it  was  only  the  M.I. Builders  in  the country who could undertake the job?   Why project  report  was  not obtained to know the cost  of  the project?   Why  could it not be thought that there could  be any  other  person who could undertake the job at  a  lesser cost  and in equally competent manner?  Public interest  has certainly  been given a go bye.  There was some undercurrent flowing to award the contract to M.I.  Builders.  High Court said  "lest we are taken amiss we wish to make it clear that we  do not doubt either the bona fides of the authorities or the  competence  of the respondents M/s.  M.I.  Builders  to enter  into  the impugned agreement but we are of  the  view ..." The competence of M/s.  M.I.  Builders to undertake the project  is  not  doubted when now it is  seen  that  proper construction  has  been made but before taking  decision  to award  the  contract to it nobody knew its credentials.   No attempt  made whatsoever to consider if there was any  other person  more competent for the job or if of equal competence could  offer  better terms.  In these circumstances,  dictum contained  in  the  case of Kasturi Lal  Lakshmi  Reddy  vs. State  of  J & K [(1980) 4 SCC 1] becomes inapplicable.   No advantage  can be drawn by the builder from the decision  of this Court in G.B.  Mahajans case [(1991) 3 SCC 91] as here the whole process of awarding contract to M.I.  Builders has been  gone  through in an unabashed manner and  in  flagrant violation of law with the sole purpose of conferring benefit on  it.   All  said  and  done we  fail  to  understand  the certificate  given by the High Court about the bona fides of the  authorities  in  awarding the contract  to  M/s.   M.I. Builders.    The  officers  of   the  Mahapalika,  who  were impleaded  as respondents by name, did not file any  replies to  contradict the allegations made against them.  Rather it appears  that it was a fit case where High Court should have directed an inquiry to be made as to how the project came to be  awarded  to M.I.  Builders including the conduct of  the lawyers.

     High  Court  has  directed dismantling  of  the  whole project  and  for  restoration of the park to  its  original condition.   This Court in numerous decisions has held  that no consideration should be shown to the builder or any other person  where  construction is unauthorised.  This dicta  is now  almost  bordering rule of law.  Stress was laid by  the appellant  and  the  prospective allottees of the  shops  to exercise  judicial discretion in moulding the relief.   Such discretion  cannot be exercised which encourages  illegality or perpetuates an illegality.  Unauthorised construction, if it   is  illegal  and  cannot  be  compounded,  has  to   be demolished.   There  is  no way  out.   Judicial  discretion cannot  be  guided by expediency.  Courts are not free  from

51

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 51 of 53  

statutory  fetters.  Justice is to be rendered in accordance with  law.   Judges are not entitled to exercise  discretion wearing  robes of judicial discretion and pass orders  based solely   on  their  personal   predilections  and   peculiar dispositions.   Judicial discretion wherever it is  required to  be  exercised has to be in accordance with law  and  set legal principles.  As will be seen in moulding the relief in the  present  case and allowing one of the blocks meant  for parking  to  stand  we have been guided  by  the  obligatory duties  of the Mahapalika to construct and maintain  parking lots.

     In  the  present case we find that the builder got  an interim  order  from this Court and on the strength of  that order  got  sanction of the plan from the Mahapalika and  no objection   from  the  LDA.   It   has  no  doubt   invested considerable  amount  on  the   construction  which  is  80% complete  and by any standard is a first class construction. Why  should  the builder take such a risk when  the  interim order  was specific that the builder will make  construction at  its  own  risk  and will not claim  any  equity  if  the decision  in  the appeal goes against it?  When the  interim order  was  made  by  this Court Mahapalika  and  the  State Government  were favouring the builder.  As a matter of fact Mahapalika  itself  filed  appeals   against  the   impugned judgment  of the High Court.  Perhaps that gave hope to  the builder  to  go ahead with the construction and to take  the risk  of  getting the construction demolished and  restoring the  park  to its original condition at its own  cost.   The builder  did not foresee the change in stand not only of the Mahapalika but also of the State Government.  It also, as it would  appear,  over-rated its capacity to manage  with  the State  Government  to  change  the land  use  of  the  park. Builder is not an innocent player in this murky deal when it was  able  to get the resolutions of the Mahapalika  in  its favour   and   the  impugned   agreement   executed.    Now, construction of shops will bring in more congestion and with that  the  area  will  get more  polluted.   Any  commercial activity  now  in  this unauthorised construction  will  put additional  burden on the locality.  Primary concern of  the Court  is  to eliminate the negative impact the  underground shopping  complex will have on environment conditions in the area  and  the congestion that will aggravate on account  of increased traffic and people visiting the complex.  There is no  alternative  to  this  except  to  dismantle  the  whole structure  and  restore the park to its  original  condition leaving  a  portion constructed for parking.  We  are  aware that it may not be possible to restore the park fully to its original  condition as many trees have been chopped off  and it  will take years for the trees now to be planted to grow. But beginning has to be made.

     There  are  four blocks under construction.   Services like air-conditioning, fire-fighting, water supply, sanitary installation,  necessary  pumps for drainage  and  sewerage, etc.  are yet to be installed and completed.

     In  block  No.  1 there are shops at the  level  minus 9’6".  These shops are divided by partition walls.  There is a  big hall with pillars below these shops at level of minus 19’6".

     In block 2 there are shops on the upper basement level 9’6".  There is no lower basement level.

52

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 52 of 53  

     Third block is currently designed to have shops at the upper  basement  level  and parking at  the  lower  basement level.   The  upper basement level can be converted to  have parking at that level too since the structural configuration will permit the same.  Flooring on the lower basement is yet to  be  laid.  There can thus be parking both on  the  upper basement  and  the lower basement.  This parking  place  for vehicles would lead to decongestion of the roads surrounding the park which are otherwise choked with the parked vehicles in its entire periphery.

     Fourth  block is only partially developed with just  a separate  ramp going down to the first basement level and  a few  columns with their foundations standing from the  lower basement  level.   This fourth block, is currently  dug  up. However,  to facilitate the movement of the vehicles to  the two levels of parking in the third block a new ramp shall be constructed adjacent to and contiguous to the third block.

     We  have  noted  above  that under  clause  (ix-a)  of Section 114 of the Act, it is incumbent on the Mahapalika to make  reasonable  and  adequate provision by  any  means  or measures  which it is lawfully competent to it to use or  to take  for the construction and maintenance of parking  lots, bus stops and public convenience.

     Number  of  cases  coming to this  Court  pointing  to unauthorised  constructions  taking place at many places  in the   country   by   builders   in   connivance   with   the Corporation/Municipal  officials.   In the series of  cases, this   Court  has  directed   demolition   of   unauthorised constructions.   This  does not appear to have any  salutary effect  in cases of unauthorised construction coming to this Court.    While   directing   demolition   of   unauthorised construction, court should also direct inquiry as to how the unauthorised  construction  came  about  and  to  bring  the offenders to book.  It is not enough to direct demolition of unauthorised  construction, where there is clear defiance of law.   In  the present case, but for the observation of  the High  Court, we would certainly have directed an inquiry  to be  made  as  to how the project was conceived and  how  the agreement dated November 4, 1993 came to be executed.

     We direct as under :

     1.   Block  1,  2 and 4 of  the  underground  shopping complex  shall  be  dismantled and demolished and  on  these places park shall be restored to its original shape.

     2.   In  Block  3  partition walls  and  if  necessary columns  in  the  upper basement shall be removed  and  this upper   basement  shall  be   converted  into  parking  lot. Flooring should be laid at the lower basement level built to be  used as parking lot.  Ramp shall be constructed adjacent to  Block 3 to go to upper and lower basement levels for the purpose  of  parking of vehicles.  Further to make  block  3 functional  as  a separate unit walls shall  be  constructed between block 2 and block 3 and also block 3 and block 4.

     3  Dismantling and demolishing of these structures  in Blocks  1,  2 and 4 and putting Block 3 into  operation  for parking  shall  be done by the Mahapalika at its  own  cost. Necessary  services  like sanitation, electricity  etc.   in Block 3 shall be provided by the Mahapalika.

53

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 53 of 53  

     4.   Mahapalika  shall be responsible for  maintaining the  park and the Block 3 for parking purposes in proper and efficient manner.

     5.   M.I.   Builders  Pvt.  Ltd.,  the  appellant,  is divested  of  any right, title or interest in the  structure built  by it under or over the park.  It shall have no claim whatsoever against Mahapalika or against any other person or authority

     6.   Block  3 shall vest in Mahapalika free  from  all encumbrances.   Licence of M.I.  Builders to enter into  the park  and the structure built therein is cancelled of  which possession  is  restored  to the Mahapalika  with  immediate effect.   No obstruction or hindrance shall be caused to the Mahapalika  by  any  one in discharge of  its  functions  as directed by this order.

     7.   Restoration of the park and operation of Block  3 for parking purposes shall be completed by Mahapalika within a  period  of 12 months from today and report filed  in  the registry of this Court.

     With  the  directions  aforesaid,   the  appeals   are dismissed with costs.