M.D.,M/S.RAMAKRISHNA POULTRY P.LTD. Vs R.CHELLAPPAN .
Case number: C.A. No.-003413-003413 / 2009
Diary number: 28569 / 2008
Advocates: K. V. BHARATHI UPADHYAYA Vs
PAREKH & CO.
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. OF 2009 (Arising out of SLP(C)No.24713/2008)
M.D., M/s. Ramakrishna Poultry P. Ltd. …Appellant Vs.
R. Chellappan & Ors. …Respondents
J U D G M E N T
ALTAMAS KABIR, J.
1. Leave granted.
2. The appellant is a Private Limited Company
engaged in the business of poultry farming which is
confined to the production of eggs. It has
constructed three separate sheds on Survey
Nos.242/2 and 249/3 in Nanniyur Pudur Village in
Karur District in the State of Tamil Nadu for
1
accommodating about 1.25 lakh layer birds. It is
the case of the appellant that it had invested a
sum of about Rs.6 crores in acquiring the lands,
erecting the sheds thereupon and acquiring the
birds for the purpose of starting the poultry farm.
3. At this juncture, it may be noted that the
lands on which the poultry farm was started by the
appellant, had been acquired in two stages. About
11 acres of land were acquired by the appellant-
Company on 23rd June, 2004 and about 4 acres were
acquired on 19th November, 2004.
5. At about the same time, the 3rd respondent, The
Power Grid Corporation of India Ltd. (hereinafter
referred to as ‘the Corporation’) took up the work
of construction of a 400 KV Perambalur – Pugalur
D/C Line as part of the Neyveli Thermal Station
Expansion Project for evacuation of electricity
generated therein. In the process, transmission
towers were required to be installed in various
2
locations, some of which were private lands,
including the Patta lands of the appellant, where
its poultry farm is situated.
6. On 8th October, 2006, the appellant sought an
opinion from the Assistant Director, Department of
Animal Husbandry, regarding the effect on the layer
birds on account of emission of electro magnetic
fields from the High Voltage Transmission Lines
passing over the poultry sheds. According to the
said authority, the passing of High Voltage
Electricity Current Transmission Wires over the
poultry sheds would adversely affect the
performance and health of the birds in the long
run.
7. The appellant thereupon filed Writ Petition
No.6850/06 before the High Court, seeking a re-
alignment of the transmission lines so that either
the appellant’s poultry sheds could be avoided or
the height of the tower/pylon could be raised.
3
Relying on an earlier order dated 18th January,
2007, passed by a learned Single Judge of the
Madras High court in Writ Petition No.49172/06, the
learned Single Judge of the Madras High Court by
his judgment and order dated 31st January, 2007,
disposed of the said Writ Petition, along with
other connected writ petitions, with liberty to the
writ petitioners to submit their objections, if
any, to the District Magistrate concerned, within a
period of two weeks from the date of the order. The
District Magistrate was directed to consider the
same in the light of the order passed by the Court
and pass an order on merits and in accordance with
law, after affording an opportunity to the
petitioners, as well as the respondents, to make
out their respective cases, within a period of six
weeks thereafter.
8. Pursuant to the aforesaid order, the District
Magistrate issued notice to the appellant and the
Corporation to file objections, if any. The
4
appellant filed its objections indicating the
damage that would be caused to the poultry farm, if
the transmission line was not shifted to avoid the
poultry sheds. The appellant asked for a small
deviation of the route of the power line in the
eastward direction, within his lands, so that
minimum damage was effected to the poultry farm.
On the other hand, the Corporation submitted that
no deviation of the transmission line from the
approved route of alignment was feasible. After a
spot inspection, the District Magistrate upon being
satisfied as to the damage that was likely to be
caused to the appellant’s poultry farm, was of the
view that a slight shift in the alignment of the
power line from location No.145 to location No.144,
either westward or eastward, might not cause
extensive damage to the coconut trees or the temple
indicated by the respondents, while, at the same
time, it would not affect the health of the birds
in the poultry farm. Accordingly, by his order
5
dated 30th April, 2007, passed under Section 17(3)
of the Indian Telegraph Act, 1885 (hereinafter
referred to as the ‘Telegraph Act’), the District
Magistrate directed the Corporation to realign the
transmission power line in such a way that it did
not pass above the poultry sheds of the appellant.
9. Inasmuch as, the proposed realignment entailed
that the transmission lines would pass over a
portion of the adjacent plot belonging to the first
respondent, R. Chellappan, he challenged the said
order of the District Magistrate in Writ Petition
No.10259/07 on 19th November, 2007, and the same was
dismissed upon holding that the order of the
District Magistrate did not suffer from any
infirmity or arbitrariness. Aggrieved by the order
of the learned Single Judge, the first respondent
filed Writ Appeal No.522/08 which was allowed by
the Division Bench on consideration of the
provisions of Section 16 of the Telegraph Act and
holding that under the said provisions, the
6
District Collector had no power to direct change of
alignment.
10. Aggrieved by the said order, the appellant has
filed the present appeal.
11. The main thrust of challenge is with regard to
the jurisdiction of the District Magistrate to
direct change of alignment of a transmission line
under Section 16 of the Telegraph Act, which, under
the provisions of Section 51 of The Indian
Electricity Act, 1910, which is equivalent to the
provisions of Section 164 of the Electricity Act,
2003, empowers the appropriate Government to confer
on any Authority or person engaged in the business
of supplying electricity under the Act, any of the
powers which the Telegraph Authority possesses
under the Telegraph Act with respect to the placing
of telephonic lines or posts for the purpose of a
telephone established or maintained by the
Government or to be so established or maintained.
7
On behalf of the appellant it was submitted that
the Division Bench was wrong in holding that under
Section 16 of the Telegraph Act, the District
Magistrate had no power to change the alignment and
that the Division Bench had failed to notice that
the order of the District Magistrate was not under
Section 16, but under Section 17(3) of the said
Act.
12. Another ground of challenge was that the
impugned order of the Division Bench was contrary
to the earlier order dated 31st January, 2007,
directing the Corporation to approach the District
Magistrate concerned in each case for permission to
deal with the objections raised by the petitioners
with the further direction that the said District
Magistrate would consider the objections and pass
orders in accordance with the provisions which have
been indicated in the said order. It was also
urged that since the same had become final between
the parties, there was no scope for a contrary
8
order to be passed, as has been done in terms of
the impugned order of the Division Bench in Writ
Appeal No.522/08, holding that under Section 16 of
the Telegraph Act the District Collector was not
empowered to change the alignment.
13. The last ground of challenge was that the
Division Bench had lost sight of the fact that the
Corporation had, in fact, accepted the order passed
by the District Magistrate and has even acted
thereupon, as it had stated in its Counter
Affidavit filed in response to the writ petition
filed by R. Chellappan.
14. Mr. S. Ganesh, learned Senior counsel appearing
for the appellant, submitted that Sections 10 and
17 of the Telegraph Act have to be read
pragmatically to meet a situation where the
transmission line had already been erected and even
if the alternative prayer made by the appellant in
its writ petition was to be granted, the same would
9
not lessen the danger of the Electromagnetic Waves
created by the high power transmission lines
damaging the health of the birds in the poultry
farm and adversely affecting their egg-laying
capacity. Mr. Ganesh urged that such a prayer had
been made without the assistance of the opinion of
an expert, who has subsequently indicated in no
uncertain terms that even if the height of the
transmission lines was raised to double the height
to which it had been raised, it would still
adversely affect the egg-laying capacity of the
birds.
15. Mr. Ganesh vehemently submitted that the
application of the appellant being under Section 17
of the Telegraph Act, it was within the power and
jurisdiction of the District Magistrate to direct a
small deviation of the transmission line over the
appellant’s own lands, the expenses wherefor would
be borne by the appellant, so as to avoid its
passing directly over the poultry sheds. Mr.
10
Ganesh also submitted that since the Corporation
was ready and willing to make a deviation over the
adjoining land belonging to Respondent No.1, except
for the alleged damage as may be caused to the
coconut trees and the temple on its revised route,
there was no reason why the same could not be
adopted in order to save the huge investment which
the appellant had already made in the poultry farm,
the loss whereof would completely cripple the
appellant’s business, particularly, when the
poultry farm was already in operation before the
evacuation project from the Neyveli dam had even
been contemplated or started.
16. Learned counsel appearing for the Respondent
No.1 supported the order of the District Collector
but contended that since the interest of the public
at large relating to supply of electricity was
involved, it was necessary for the dispute to be
set at rest so that the transmission line could be
commissioned at the earliest opportunity.
11
17. On behalf of the Corporation, Mr. Parag
Tripathi, learned Additional Solicitor General
contended that the order of the District Magistrate
directing change in alignment of the transmission
line did not take into consideration various
factors, namely, that the transmission line which
would pass over the contiguous plot belonged to the
Respondent No.1 and bordered the plot of the
appellant.
18. Mr. Tripathi submitted that the electricity to
be generated by the Neyveli Thermal-II Expansion in
the State of Tamil Nadu has to be distributed by
the construction of a 400 KV D/C transmission line
from Neyveli to Pugalur comprising of 576 towers
with a length of 198 kms. connecting the Neyveli
Thermal Power Station II to Pugalur 400 KV Sub-
station. The estimated cost of the project was set
at Rs.691.83 crores. He also submitted that on 24th
December, 2003, the Government of India had, in
12
exercise of its powers conferred under Section 164
of the Electricity Act of 2003, passed an order
authorizing the Corporation to exercise all the
powers vested in the Telegraph Authority under
Part III of the Indian Telegraph Act, 1885 in
respect of the electrical lines and electrical
plants established or maintained, or to be so
established or maintained for transmission of
electricity or for the purpose of telephonic or
telegraphic communication necessary for the proper
coordination of work. Further more, M/s. Shyama
Power (India) Private Ltd. had already been issued
the Works Order for detailed survey on 9th June,
2004 and such work had been completed in the year
2004 itself. He submitted that the local public
was taken into confidence during the consultation
programmes organized by the Corporation on 2nd
October, 2004 and only thereafter, on completion of
the survey works, the route alignment was marked
along with vital landmarks, including the crossing
13
of the Cauveri river and the locations on which the
towers were to be erected. Mr. Tripathi contended
that despite having knowledge that the area was
marked for an overhead transmission line over
Survey Nos.249/1 to 249/11 and 242 of Nanniyur
Village, the petitioner went on to purchase the
lands on which the poultry farm was established on
23rd June, 2004 and 19th November, 2004. The learned
Additional Solicitor General also submitted that
the work of the project had advanced to a stage
where out of the total number of 576 locations, the
foundation work for erection of towers had been
completed in respect of 568 locations and towers
had already been erected at 553 locations.
Furthermore, out of the length of 198 kms., the
stringing work of the transmission lines had been
completed upto 171 kms. and, although, the
transmission line should have been commissioned on
or before the month of October, 2007, the same had
been delayed due to the present litigation. The
14
learned Additional Solicitor General also submitted
that the representation made by the appellant-
Company had been disposed of by the Corporation on
7th May, 2005 on the ground that at the time of the
survey work, there was no poultry farm in existence
and that it was not techno-economically feasible to
realign the transmission line at the advanced stage
of implementation. Mr. Tripathi urged that the
fact that the Managing Director of the appellant-
Company was a local man would also be evident from
the fact that the Certificate of Incorporation of
the appellant-Company indicates the plots in
question to be the address of the Company and it is
difficult to accept that the Managing Director of
the Company did not have any knowledge of the
ongoing project, which included large scale survey
work for finalizing the alignment and the route to
be taken, including the construction of
towers/pylons for carrying the transmission lines.
15
19. It was also submitted that the alternate prayer
made on behalf of the appellant-Company had been
duly considered and acted upon and the height of
the transmission towers in question had been raised
from 46.5 meters to 52 meters so that the gap
between the highest point of the construction and
the lowest point of the sag in the transmission
line was 30 ft. The same having been done, the
appellant should not have any further cause for
complaint.
20. Mr. Tripathi submitted that while passing the
order, purporting to be an order under Section 17
of the Telegraph Act, the District Magistrate had
failed to take into consideration that an order
under Section 17 could only be passed after the
erection of the towers and that too for altering
the alignment within the same land. Further more,
the alternate plea of raising the height of the
towers, as also the technical feasibility regarding
the crossing of the transmission lines at the
16
Highway crossing and also the river Cauveri,
together with the higher cost provision for
realignment and the ecological aspect had not been
taken into consideration by the District Collector,
who passed the order on 30th April, 2007 in a purely
mechanical manner without giving any thought to the
various consequences that such order was bound to
give rise to.
21. Mr. Tripathi referred to the Full Bench
decision of the Kerala High Court in Mammoo Vs.
State of Kerala & Anr. [AIR 1980 Kerala 18], where
it was held that while Section 16(1) of the
Telegraph Act vested the District Magistrate with
certain authority which he would be entitled to
exercise in his discretion, such functions were
only of an administrative or executive nature. In
effect, it was held that the District Magistrate,
while exercising power under Section 16(1) of the
above Act, did not act as a Court, but in a purely
administrative capacity.
17
22. Reference was also made to the decision of the
Kerala High Court in Moidu alias Kunnippa Vs. The
District Magistrate and District Collector,
Malappuram and Ors. [MANU/KE/0410/1998], in support
of the submission that in order to attract Section
17 of the aforesaid Act, the telegraph line or post
in question would have had to be installed and
would have had to be shifted from one portion to
another portion of the same property.
23. Mr. Tripathi submitted that having regard to
the prayers made by the appellant in its Writ
Petition (MD) No.6850/06 before the Madurai Bench
of the Madras High Court, the alternate prayer for
raising the height of the tower has been acted upon
by the Corporation and the appellant could not,
therefore, have any further grievance against the
Corporation with regard to the carriage of the
transmission lines over the appellant’s property.
18
24. Appearing for R. Chellappan, the Respondent
No.1, Mr. A.T.M. Ranga Ramanujam, learned Senior
counsel adopted Mr. Tipathi’s submissions and
submitted that if the order of the District
Collector was accepted as having been passed under
Section 17 of the Indian Telegraph Act, then any
realignment of the transmission line would have to
be effected within the plot of the person at whose
instance such realignment is sought. The proposed
alternate alignment through the land of the
Respondent No.1 was not, therefore, permissible and
such proposed alternate alignment was liable to be
rejected.
25. On the other hand, Mr. R. Nedumaran, learned
counsel appearing for the State of Tamil Nadu,
while supporting the order passed by the District
Collector, urged that the erection of the towers
for carrying the transmission lines was for the
benefit of the public at large who stood to
benefit from the energising of the target area for
19
the improvement of the lot of the people of the
area. Mr. Nedumaran, however, also pointed out
that from the order of the District Magistrate and
Collector dated 30th April, 2007, it would be more
or less evident that the poultry sheds had been
constructed before the proposed route alignment.
From the order of the District Collector, Mr.
Nedumaran also pointed out that while the appellant
had no objection to the power transmission line
being taken over its lands, the District Collector
had taken into consideration the limited request
made on behalf of the Appellant-Company that the
route of the power line be diverted in the eastward
direction within the limits of its lands instead of
passing through the middle of the said lands which
would cause extensive damage to its poultry farm.
Mr. Nedumaran submitted that the Collector, by
invoking his powers under Section 17(3) of the
Indian Telegraph Act, 1885, directed the Appellant-
Company to realign the transmission lines in such a
20
way that they did not pass directly above the
poultry sheds of the Respondent No.1 situated at
S.F. Nos.242/2 and 249/3, Nanniyur Village, Karur
Taluk.
26. On consideration of the rival submissions made
on behalf of the respective parties, it is obvious
that a balance will have to be achieved between the
appellant’s grievance and both the technical as
well as techno ecological feasibility of altering
the route of the transmission lines in keeping with
the directions given by the District Collector.
The simplest and the most ideal solution would have
been to alter the route of the transmission lines
so that they did not directly pass over the
appellant’s poultry sheds, particularly when the
appellant is ready and willing to bear the expenses
of such alteration. However, since, according to
the Power Grid Corporation and its experts, that
would entail a deviation over the lands of the
Respondent No.1, R. Chellappan, the same gave rise
21
to the objections raised by R. Chellappan. Keeping
aside the technical aspect of the matter as to
whether the order passed by the District Collector
was one under Sections 16 or 17 of the Indian
Telegraph Act, 1885, in order to arrive at a
practical solution to the problem, the Power Grid
Corporation accepted the alternate suggestion made
on behalf of the Appellant-Company and raised the
height of the lowest point of sag of the
transmission lines between the two towers on either
side of the poultry sheds of the Appellant-company
from 46.5 meters To 52 meters, which in practical
terms means a clearance of 30 ft. between the
lowest point of the sag and the highest point of
the poultry shed. Of course, it has been contended
by Mr. Ganesh that according to the report of the
expert, even if the height of the tower was raised
to a 100 meters, the electro-magnetic field created
by the transmission of high voltage electricity
would still encompass the poultry sheds and
22
adversely affect the reproductive system not only
of the chickens but of all living things within
that zone.
27. However, what goes against the case of the
Appellant-Company is the fact that the purchases of
the land for starting the poultry business and the
erection of the poultry sheds were effected at a
point of time when the process of identifying the
route of the transmission lines was already in
progress and survey work was being undertaken. We
find it difficult to accept that the Appellant-
company did not have knowledge of the ongoing
project, which is for the benefit of a large number
of people of the area as against the interest of a
single individual. In view of the objections on
behalf of the Power Grid Corporation that the
deviation in the transmission lines, as suggested
on behalf of the Appellant-company, could not be
practically achieved, we are left with the next
best solution, i.e., to increase the clearance
23
between the lowest point of the sag of the
transmission cable and the top most portion of the
appellant’s poultry sheds. It should not also be
forgotten that from the point of the sag on both
sides the cable moves upwards and the clearance
becomes even greater on both sides of the lowest
spot. During the hearing we had asked Mr. Tripathi
to confirm with the Engineers of the Power Grid
Corporation to explore the possibility of raising
the height of the towers even further to lessen the
damage, if any, that may be caused to the egg
laying capacity of the layers in the appellant’s
poultry farm.
28. Although, the response appears to be equivocal,
we set aside the order of the Division Bench of the
Madras High Court impugned in this appeal and
direct the Power Grid Corporation to increase the
clearance indicated above from 52 meters to 56
meters so that the clearance between the lowest
24
point of the sag of the cable and the top most
portion of the poultry shed is not less than 40 ft.
29. The Appellant-Company will be entitled to such
compensation to which it may be entitled for use of
its lands or the damage caused thereto on account
of the erection of the tower/pylon for carrying the
transmission lines over the appellant’s plant, in
accordance with the provisions of Section 10(d) of
the Indian Telegraph Act, 1885.
30. The appeal is accordingly allowed to the extent
indicated hereinabove.
________________J. (ALTAMAS KABIR)
________________J. (CYRIAC JOSEPH)
New Delhi Dated: 08.05.2009
25