24 April 1990
Supreme Court
Download

HIND BUILDERS ETC. Vs UNION OF INDIA AND VICE-VERSA

Bench: RANGNATHAN,S.
Case number: Appeal Civil 1280 of 1988


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 15  

PETITIONER: HIND BUILDERS ETC.

       Vs.

RESPONDENT: UNION OF INDIA AND VICE-VERSA

DATE OF JUDGMENT24/04/1990

BENCH: RANGNATHAN, S. BENCH: RANGNATHAN, S. AHMADI, A.M. (J)

CITATION:  1990 AIR 1340            1990 SCR  (2) 638  1990 SCC  (3) 338        JT 1990 (2)   186  1990 SCALE  (1)788

ACT:     Arbitration:   Award--Error   on   the   face   of   the award--Clause in the contract open to two equally  plausible interpretations--Legitimate for Arbitrators to accept one or the  other of the available interpretations and even if  the court may think that the other view is preferable, the court will not and should not interfere.     Award--Error on the face of award  Annexure setting  out the award as against various items of claim--Mere fact  that statement  of claim refers to various items in the  schedule to the contract does not result in the contract itself being incorporated  in  the award--No error can be  found  in  the award.     Pendente  Lite Interest: Power of Arbitrator--Not  enti- tled  to  grant pendente lite interest unless  reference  is made in the course of a suit--Same powers to grant  interest pendente  lite as the courts when matter is referred by  the Court.

HEADNOTE:     Certain  disputes  having arisen between  the  Union  of India and the Contractors in respect of the Contract awarded to  the  letter  for the execution of  certain  civil  works pertaining  to  the Metro Railway Project in  Calcutta,  the same were referred for decision to two Arbitrators appointed by  the High Court of Calcutta. The Contractors filed  their itemised  claim  before the Arbitrators for a total  sum  of Rs.2,05,67,554.   The   Arbitrators   awarded   a   sum   of Rs.57.47,198 to the contractors in full and final settlement of  all their claims which included a sum of Rs.6.76,540  as interest  vide item (1). They directed that the award  shall be complied with within sixty days of its publication  fail- ing  which  simple  interest @ 11 percent  per  annum  shall accrue  thereon (excluding interest amount  of  Rs.6.76,540) till the date of payment or decree upon award which ever  is earlier. On an application being made to the High Court  for making  the  Award a rule of the Court. the  learned  single judge  confirmed  the award except that  the  principal  sum awarded  was reduced by Rs.5,20,000 with the direction  that the  amount so awarded will carry interest @ 11%  per  annum from the date of reference till the date of the award.

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 15  

639     The  Union of India preferred an appeal to the  Division Bench, which  reduced the amount awarded under item (c)(xii) from Rs.23.96.000 to Rs.2.39,000. Thus the principal  amount to  be  awarded  to  the  contractors  was  finally  put  at Rs.30.70,798 and this amount was directed to carry  interest @ 11% per annum from the date of the reference till the date of the award.     Aggrieved  by the order of the Division  Bench  reducing the amount awarded under item (c)(xii) from Rs.23,96,000  to 239,600  the contractors preferred an appeal to this  Court. The  Union  of Indian on the other hand preferred  a  cross- appeal  praying (i) that interest should not be  payable  on the amount of Rs.30,70,798 fixed by the High Court but  only on Rs.23,94,258 left after deducting therefrom the amount of Rs.6,76,540  awarded by the Arbitrators in respect  of  item No.  (L)  and  (ii) that. though the  arbitrators  had  also awarded  interest  on  the principal sum till  the  date  of payment  or  decree on award in case payment  was  not  done within  sixty  days  of the publication of  the  award.  the contractors  should  be held entitled to interest  upto  the date  of the award only and not beyond it because  both  the learned single judge and the Division Bench have held so and the contractors have preferred no appeal therefrom.     Taking up the contractor’s appeal first, this Court came to  the conclusion that the Division Bench had exceeded  its jurisdiction in interfering with this part of the award  and restored  the amount awarded by the arbitrators  under  item (c)(xii).     Dealing with the appeal of the Union of India this Court ruled  that there was really no dispute left about Union  of India’s  first contention as to what was the correct  amount on  which interest was payable to the contractors after  its findings in the contractor’s appeal and placed the figure at Rs.45,50,658.     Dealing  with the second contention as to what  was  the period with reference to which interest would be payable  to the contractors on the above amount it was noticed that  the arbitrators  had  allowed  interest from  5.10.82  (date  of termination  of contract) to 26.3.84 (date of  award)  under item (L) and had also allowed interest from the date of  the award till the date of payment or decree whichever is earli- er.The learned single judge had deleted the interest for the period  5.10.82 to 6.5.83 (date of reference) but held  that the arbitrators had jurisdiction to award interest from  the date of the reference till the date of award and also  post- award interest. As the objection of the Union of India 640 before  the  Division Bench in the LPA on  the  question  of interest was only that the arbitrators had erred in awarding interest  from 6.5.1983 to 26.3.1984 the High Court had  not decided  that the contractors were not entitled to  interest beyond  the date of award and therefore this  contention  of the Union of India failed and was rejected. The Court.     HELD:  The  grant  of pendente lite  interest  would  be justified only when reference to arbitration is made in  the course  of a suit. The principle indicated is that  since  a court has. under S. 34 of power to grant pendente lite interest in a suit. an arbitra- tor to Whom a reference to arbitration is made in the course of  the  suit would be clothed with all the  powers  of  the court including one to grant such interest. Generally speak- ing.  it would only seem reasonable that the power to  grant interest pendente lite should be treated as ancillary to the award of damages or compensation which. but for the delay in

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 15  

the litigation (Whether in court or by way of  arbitration). the  claimant  should have received much  earlier.  However. though pendente interest  has been made available in court proceedings.  its extension  to arbitration law appears to have acquired  some technical  limitations resulting in denial of pendente  lite interest  in most arbitration cases. Pendent  lite  interest cannot  still be awarded by an Arbitrator appointed  by  the parties under a private agreement for which there may be  no justification  in  equity.  Anomalies  have  arisen  because formerly  an Arbitrator could not be treated as a  court  to which  the code of civil procedure applied and  because  now the Interest act, 1978, while including arbitration proceed- ings within its ambit, has, apart from a reference to S.  34 omitted to provide specifically for pendente lite  interest. This has been clearly brought out by Chinnappa Reddy, J., in Abhaduta Jena which outline the principle the learned  judge had  in mind for permitting pendente lite interest by  arbi- trator. Abhaduta Jena has been followed in later cases  also and  its scope has been recently explained in Sharma’s  Case (1988-4 SCC 353), and the Gujarat Water Supply case  (1989-1 SCC  532)  where pendente lite interest was  denied.  [655H; 656A-F]     Gujarat Water Supply & Sewage Board v. Unique  Erectors, [1989]  1 S.C.C. 532; Firm Madan Lal Roshan Lal  Mahajan  v. Hukumchand  Mills Ltd., lndore, [1967] 1 S.C.R.  105;  Allen Berry & Co. Pvt. Ltd v. Union of India, [1971] 3 S.C.R. 287; N. Chellappan v. Secretary, Kerala State Electricity Board & Anr.,  [1975]  1 S.C.C. 289; Hindustan Tea Co.  v.K.  Shashi Kant  Co. & Anr., [1986] Suppl. S.C.C. 506; Hindustan  Steel Works  Construction  Ltd.  v. C. Rajasekhar  Rao,  [1987]  4 S.C.C.  93; Sudarsan Trading Co. v. Government off Kerala  & Anr.. [1989] 2 S.C.C. 38: M/s. Alppi Prashad & Sons, Ltd. v. 641 Union  of India, [1960] 2 S.C.R. 793; Bhagat Trading Co.  v. Union of India, AIR 1984 Delhi 358; Union of India v. Bakshi Ram,  [1957] LIX P.L.R. 572; Executive Engineer v.  Abhaduta Jena, [1988] 1 S.C.C. 418; Nachiappa v. Subramaniam,  [1960] 2 S.C.R. 290; Satinder v. Amrao, [1961] 3 S.C.R. 676;  Union v. Bungo Steel Furniture P. Ltd., [1967] 1 S.C.R. 324; Ashok Construction Co. Ltd. v. Union, [1971] 3 S.C.C. 66; State v. Saith & Skelton P. Ltd., [1972] 3 S.C.R. 233; Food  Corpora- tion of India v. Surendra, Devendra & Mohendra Tansport Co., [1988] 1 S.C.C. 547 and State of Rajasthan v. Sharma &  Co., [1988] 4 S.C.C. 353, referred to.

JUDGMENT:     CIVIL  APPELLATE JURISDICTION: Civil Appeal No.  1280  & 1281 of 1988.     From  the  Judgment  and Order dated  21.4.1987  of  the Calcutta High Court in Appeal from Original Order No. 128 of 1985, Award Case No. 151 of 1987.     A.K. Sen, Dr. Shankar Ghosh, Ajay K. Jain, Praveen Kumar and Pramod Dayal for the Appellant. M.K. Banerjee and G.S. Chatterjee for the Respondent. The Judgment of the Court was delivered by     RANGANATHAN,  J.  These are cross appeals by  M/s.  Hind Builders (hereinafter referred to as ’the contractors’)  and the  Union of India. from an order of Division Bench of  the Calcutta High Court in an arbitration matter.     The  contractors  had been awarded a  contract  for  the execution  of  certain civil works in  connection  with  the Metro  Railway Project in Calcutta. Certain  disputes  arose

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 15  

between  the Union and the contractors. These disputes  were referred  for decision to two arbitrators appointed  by  the High  Court  of Calcutta. The arbitrators entered  upon  the reference  on 27th June. 1983. The contractors had  filed  a claim before the arbitrators for a sum of Rs.2,05,67,554. On 26.3.1984  the arbitrators awarded a sum of Rs.57,47,198  to the contractors.     The  claim of the contractors filed before the  arbitra- tors  was an itemised claim in respect of various  items  of works  executed by them. The body of the award made  by  the arbitrators reads as follows:      "We .....  make and publish our Award, as below: 642       (i) That the Respondent  ..........  shall pay   ..... the    Contractors    a   sum   of    Rs.57,47,198     ..... only  in full and final settlement of all their  claims  and dues under the above mentioned contract agreement. In  addi- tion,  the  three  Bank Guarantees   ..........   issued  by Vijaya  Bank,  Cuttack,  on behalf of  the  contractors,  in favour  of Metro Railway, Cuttack, shall be released by  the Respondent  Railway,  as detailed in the  Annexure  to  this Award. XXX                                                      XXX XXX The Award shall be complied with within 60 (Sixty) days from the date of publication of this Award, failing which  simple interest @ 11 per cent per annum on the amount of the  Award (excluding  interest  vide  item (1) of  the  Annexure  i.e. Rs.6,76,540) shall accrue till the date of payment or decree upon Award whichever is earlier." In the annexure to the award, the arbitrators tabulated  the various  items of the claim before them, the amount  claimed against each item and the amount awarded against each  item. Under item (1) in the annexure, the arbitrators had  awarded an  interest  of Rs.6,76,540 and that is why  the  direction regarding  interest by the arbitrators excluded this  amount from  the  principal amount which was to bear  interest.  As stated earlier, the total amount awarded was Rs.57,47,198 in respect  of  items (a) to (q) of the award  as  against  the claim of Rs.2,05,67,554 made by the contractors.     On  an application being made to the High Court of  Cal- cutta  on the Original Side for making the award a  rule  of court, the learned single Judge sitting on the Original Side confirmed  the  award except to the extent  of  Rs.5,20,000. This  is  no longer in issue. The  learned  Judge.  however, concluded his judgment with the following words: "The principal sum awarded stands reduced by Rs.5,20,000  as mentioned above. The respondent will be entitled to interest at the rate of 11 per cent per annum from the date of refer- ence till the date of the award."     The Union of India preferred an appeal from the order of the  learned  single Judge. The Division Bench  was  of  the opinion that the arbitrators were not justified in  awarding a sum of Rs.23,96,000 to the contractors (as against a claim of  Rs.42,65,957 made by them) in respect of  item  (c)(xii) viz.  "cost  towards consolidation of earth by  ramming  and rolling" and that they could have awarded under the 643 contract only a sum of Rs.2,39,600 in respect of this  item. The  amount  awarded  to the contractors  was  thus  further reduced  by  the  Division Bench by a  sum  of  Rs.21,56,400 (Rs.23,96,000--Rs.2.39,600).  The Bench then  observed  that the principal sum to be awarded to the contractors would now stand  at  Rs.30,70,798  and directed  that  the  respondent contractor should be entitled to interest at the rate of  11

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 15  

per  cent per annum on the said amount from the date of  the reference till the date of the award.     The  contractors  have appealed from the  order  of  the Division  Bench  being  aggrieved by the  reduction  of  the amount  awarded  under  item (c)(xii)  to  Rs.2,39,600  from Rs.23,96,000.  The  Union of India has preferred  an  appeal contending  principally that, since the principal amount  on which  the arbitrator awarded interest was not  Rs.57,47,198 but only Rs.50,70,658 (i.e. Rs.57,47,198--Rs.6,76,540),  the contractors  would be entitled to interest, after the  judg- ment  of the Division Bench, not on Rs.30,70,798 as held  by the Division Bench but only on Rs.23,94,258. In addition, at the tune of the hearing before us, counsel for the Union  of India raised two further points:        (1) that the Division Bench erred in awarding  inter- est  to the contractors from the date of the reference  till the date of the award.        (2)  That  though the arbitrators  had  also  awarded interest on the principal sum till the date of payment,  the contractors  should  now be held entitled to  interest  only upto the date of the award because the learned single  Judge and the Division Bench have held so and the contractors have preferred no appeal therefrom.     Taking  up  the  contractor’s appeal  first,  the  point raised  falls within a very narrow compass and turns on  the interpretation  of  item  No. -.09 of the  annexure  to  the contract  containing the schedule of rates. This item  reads as follows. Item Brief description         Approx-  Unit of  Rate of No.  of work                   imate    payment  payment in                                Qty.              "words" &                                                  "figures"                                                     Rs. P. 1         2                       3         4         5 644 4.09 (a)Earthwork in open excava  235000    10      Rs.180       tion for forming garbage    cubic     cubic  (Rupees       tanks in all kinds and      metres    metres  one       conditions of soils upto                      hundred       depth varying from 0 to 3                     eighty       3 metres from the existing                    only)       ground level and disposing       of the spoils so as to       raise land required for       piling work, to fill up the       existing low lying areas       and ponds, to form embank-       ments for roads, etc of the       Car Depot complex includ-       ing spreading in layers,       breaking clods, levelling,       dressing, all lifts/descents       and all leads etc. complete       Note:       No  extra  payments will be       made  if wet excavation is       met  with or for baling/       pumping out of water of all       sorts including rain water.  (b) Extra over item (a) above,   135000  10      Rs.20      for consolidation of the     Cubic   Cubic   (Rupees      filled up areas or some of   metres  metres  Twenty      the top layers of the filled                 only).      up areas or road embank-      ment portions by watering

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 15  

    and ramming/rolling as      directed. In  respect of these items the statement of claim  filed  on behalf of the contractor was in the following terms: (b)  Earthwork in excavation measured but not paid in  full: That under agreement item No. 4.09 (a) the claimants as  per instructions, specifications and agreement excavated 645 earthwork  in open excavation for forming garbage  tanks  in all kinds of soil for a quantity of 2, 15,000 Cum and there- after  the  contract  was rescinded  against  which  reduced quantity  has been measured provisionally upto 17th CC  bill for  2,09,523  Cum measured on 24.5.82 and as per  the  said measurements the claimants are yet to be paid for a quantity of  5,477 Cum over and above the payments already made  upto 17th CC. The claimants claim payment for 5,477 Cum of  exca- vation @ Rs. 18 per each Cum. amounting to Rs.98,586.00.                              CLAIM AMOUNT... Rs. 98,586.00 (c)(xii) Cost towards consolidation of earth by ramming  and rolling: That  as  per agreement item No. 4.09(b) the  claimants  are required  to fill up the low lying areas etc., as  specified under  General Conditions of the Contract at para 3.05  with the excavated spoils obtained out of earthwork in excavation under agreement item No. 4.09(a). The payment for  earthwork in  open excavation for work executed under  agreement  item No.  4.09(a) is to be made on sectional measurements  calcu- lated  by level sections. The excavated earth obtained  from garbage  excavation,  a  quantity of 2, 15,000  Cum  as  per provisions  made in agreement item No. 4.09(b) was  consoli- dated  in different areas as per instructions  and  approved plan.  The  claimants  claim payment for  this  quantity  of consolidation  at Rs.20 per Cum i.e. Rs.2 extra over Rs.  18 per  Cum as specified in agreement item No. 4.09(a)  &  (b), amounting to Rs.43,00,000.00 against which payment has  been made  in  CC  bills  for  reduced  quantity  and  amount  of Rs.34,043.00.  The  claimants   claim   payment   for    the balance  amount  of Rs.42,65,957.00 not paid for.                              CLAIM AMOUNT Rs.42,65,957.00 In other words, the contractors claimed payment at the  rate of  Rs.18 per cubic metre in respect of the excavation  work done by them under item No. 409(a). Again, in respect of the same  quantity.  of 2,15,000 cubic metres,  the  contractors made a claim at Rs.20 per cubic metre as the amount  payable to them in respect of the consolidation of 646 excavated  earth by ramming and rolling. The Division  Bench was of the view that under item No. 4.09(b), the contractors were  entitled to an additional payment of Rs.2 only,  since the  contractors had already been paid at the rate of  Rs.18 per  cubic metre in respect of the excavation done by  them. The extra charges for ramming and rolling were payable  only at  the  rate of Rs.2 per cubic metre instead of  Rs.20  per cubic metre. The Division Bench accordingly scaled down  the amount awarded by the arbitrator in this regard to 1/10th of the amount awarded by him.     It  is submitted on behalf of the contractors  that  the rate payable for the work under item 4.09(b) of the contract was not at all in dispute between the parties at any  stage. The  Union  had not raised any plea in this  regard  in  its reply  to the contractors’ claim, in the objections  to  the award filed in the High Court or in the arguments before the learned Single Judge. Clearly, the Division Bench  travelled beyond  the limits permissible for the interference with  an award  by a court of law in reducing the amount  awarded  on

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 15  

this  account. It is pointed out that the award itself is  a non-speaking award. The award does not refer to the terms of the  contract or incorporate the details of the claims  made by  the contractors. Though it is true that the  arbitrators awarded  a sum of Rs.23,96,000 against item  (c)(xii),  they have  not given reasons therefore. The award  neither  shows that the amount has been worked out at the rate of Rs.20 per cubic  metre  nor does it show the quantity  in  respect  of which the amount has been worked out. There is no  reference to the terms of the contract or to item No. 4.09, clause (a) or  (b). No reasons have been given by the  arbitrators  for determining that a sum of Rs.23,96,000 has to be paid to the contractors  under item (c)(xii). It is therefore  submitted that there was no error apparent on the face of the  record. Learned counsel vehemently contended that it is now  settled law  that an award cannot be said to suffer from a  manifest error  unless the error appears on the face of the award  or of  some  document incorporated in the award.  Reference  is made to the decisions of this Court in the following  cases: Firm  Madanlal Roshanlal Mahajan v. Hukumchand  Mills  Ltd., Indore,  [1967]  1 SCR 105; Allen Berry & Co. Pvt.  Ltd.  v. Union  oflndia, [1971] 3 SCR287;N. Chellappan v.  Secretary, Kerala  State  Electricity Board & Anr., [1975] 1  SCC  289; Hindustan  Tea  Co.  v. K. Shashi Kant Co.  &  Ant.,  [1986] Suppl. SCC 506; Hindustan Steel Works Construction Ltd. v.C. Rajasekhar Rao, [1987] 4 SCC 93 and Sudarsan Trading Co.  v. Government  of Kerala & Anr., [1989] 2 SCC 38. According  to the contractors, what the Division Bench has done is to give its  own  interpretation to item Nos. 4.09(a) & (b)  of  the contract, to read an erroneous interpretation 647 of the said item into the award made by the arbitrators  and to substitute its opinion in the place of that given by  the arbitrators.  Thus, it is submitted, runs quite contrary  to the principles enunciated in the above decisions and should, therefore, be set aside.     On the other hand, Shri Milon Banerjee, learned  counsel for the Union of India submitted that the award is really  a speaking  award  in  so far as it does  specify  the  amount granted in respect of each item of claim. He submitted  that the  present case falls within the principle  enunciated  in M/s  Alopi Prashad & Sons, Ltd. v. Union of India, [1960]  2 S.C.R. 793, which has been taken note of in the case of  M/S Sudarsan Trading Co. v. Government of Kerala & Anr.,  [1989] 2  SCC 38 at p. 54 that an award which overlooks or  ignores the  terms of the contract is bad. He also made a  reference to  the decision of the Delhi High Court in  Bhagat  Trading Co.  v. Union, AIR 1984 Delhi 358 in this context.  He  also referred to a decision of the Punjab High Court in Union  of India  v.  Bakshi Ram, [1957] LIX P.L.R. 572,  holding  that "when  there  are pleadings in an arbitration and  they  are specifically  referred to in the award so that it cannot  be understood  without reference to them, then those  pleadings are  incorporated in the award and they must be included  in the consideration whether there is any error apparent on the face of the award" and that "if a lump sum is awarded by  an arbitrator  and  it appears on the face of the award  or  is proved  by extrinsic evidence that in arriving at  the  lump sum matters were taken into account which the arbitrator had no jurisdiction to consider, the award is bad." The  conten- tion  of  Shri Banerjee is that the annexure  to  the  award clearly  incorporates  the statement of claim  made  by  the contractors. Since in turn the statement of claim refers  to the  clauses of the contract, the contract should also  have been treated as incorporated in the award. It is also appar-

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 15  

ent on the face of the award, insofar as it relates to  item (c)(xii), that the arbitrators have awarded payment at Rs.20 per cubic metres under item 4.09(b) whereas it must obvious- ly  be  at Rs.2 per cubic metre. According  to  the  learned counsel, the decisions relied upon by him clearly show  that an  award which ignores or overlooks the express terms of  a contract  suffers from an error apparent on the face of  the record and can be set aside by this Court. He submitted that the award, read with the annexure, brings out the  reasoning of  the arbitrators and that an error therein can be  recti- fied  by the court. The arbitrators had no power  to  travel beyond the authority of the contract and, in order to deter- mine whether they had exceeded their authority, the contract can be looked into by the court. In support of this  conten- tion,  the learned counsel also referred to a passage at  p. 42 1 in the Law of Arbitration by Bachawat (Second Edition). 648     We  have  considered the respective contentions  of  the parties  and we are of the opinion that the  Division  Bench erred in setting aside the award insofar as it relate to the sum of Rs.25,96,000. Though the annexure sets out the  award of  the arbitrators as against various items of claims,  the mere enumeration of the heads of claims cannot be equated to an  incorporation of the statement of claim by the  contrac- tors into the award. At any rate, the award does not  relate the  claims to the various clauses of the contract  and  the mere  fact  that the statement of claim  refers  to  various items in the schedule to the contract does not result in the contract itself being incorporated as part of the award.  No error  can  be found in the award unless one reads  into  it first  the statement of claim and then the relevant  clauses of the contract. But this cannot be done unless these  docu- ments are treated as incorporated in the award. This  cannot be  done. That apart even if the contract can be  read  into the award, we doubt whether this case can be treated as  one of an error on the face of the award. All that the award has stated  is that for the extra work involved in  ramming  and rolling,   the  contractors  were  to  be  paid  a  sum   of Rs.23,96,000. The award does not mention how this amount  is arrived  at. There is no mention of the quantity in  respect of  which this is awarded nor the rate at which the  payment has  been calculated. It is, however, pointed out that  con- tractors had claimed payment at the rate of Rs.20 per  cubic metres in respect of 2,15,000 cubic metres and that, even if it is assumed that the ramming and rolling had been done  in respect  of the entire volume of 2,15,000 cubic metres,  the contractors  could  have, on a proper  construction  of  the contract, been awarded only a sum of Rs.4,30,000 and nothing more. Obviously, the award is calculated at Rs.20 per  cubic metres in respect of 1,19,800 cubic metre. It is clear, says counsel for the Union, that the volume of the item for which payment has to be made has been cut down but the amount  has been  calculated at Rs.20 per cubic metre which exceeds  the amount of Rs.2 stipulated in the contract and this is  erro- neous on the face of it.     We are afraid that, in putting forward this  contention, the respondents are really trying to analyse the reasons  of the arbitrator for making the award under this head when  no such  reasons  have been stated in this award. In  fact,  it does  not necessarily follow that the payment has  been  di- rected at the rate of Rs.20 per cubic metre in respect of 1, 19,800 cubic metre. Theoretically, it could have been award- ed,  in  respect  of the entire volume of  2,  15,000  cubic metre, at the rate of Rs.11 and odd per cubic metre. It  is, however,  clear that the payment has been granted at a  rate

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 15  

in  excess of Rs.2 per cubic metre. We shall, however,  take it that the arbitrators have awarded at the rate 649 of  Rs.20  per cubic metre in respect of this item  of  work for,  as  pointed out by Dr. Ghosh, the Union of  India  had never  put forward the case either before the arbitrator  or before  the learned single Judge that the  contractors  were not entitled to payment at the rate of Rs.20 per cubic metre as  claimed  and it was before the Division  Bench  for  the first  time that a question arose that the payment  for  the item should be at Rs.2 and not Rs.20 per cubic metre. Wheth- er the payment should be made at the rate of Rs.20 per cubic metre  or at Rs.2 per cubic metre will depend upon a  proper interpretation  of the contract. It is argued that the  main item  of work viz. excavation and distribution of the  exca- vated work has been paid for under item No. 4.09(a) and that item  4.09(b)  envisages an additional payment of  Rs.2  per cubic metre if the excavated soil, instead of being  loosely distributed, is rammed and rolled by applying some pressure. This  seems,  prima  facie, a  plausible  interpretation  of clause 4.09(b). But we cannot assume, in the absence of  any evidence  or expert knowledge, that the ramming and  rolling was  not an independent, heavy or cumbersome piece  of  work and merely involved a minor addition to the work under  item 4.09(a).  On the other hand, in the grounds of appeal  filed by the contractors it is contended: "The  High  Court failed to appreciate that the  process  of ramming and rolling is a very expensive specialised  process as it has to be done layer by layer not exceeding six inches at  a time and requires watering, breaking of clods and  use of specialised road rollers, bulldozers and other equipment. The work of ramming and rolling is much more expensive  than that of earth excavation provided for in item 4.09 (a).  The High Court further failed to appreciate that in its reply to the statement of claim of the petitioner, the respondent No. 1 had not disputed that the rate applicable for ramming  and rolling was Rs.20 per cubic metre. The respondent No. 1  had only  raised  a dispute with regard to the quantity  of  the ramming  and rolling done by the petitioner. The High  Court misinterpreted the contract and erred in reducing the  award for ramming and rolling by erroneously applying the rate  of Rs.2 per cubic metre." This  may  be fight or wrong but this is  also  a  plausible view. Unfortunately, this was an aspect not urged before, or considered by, the arbitrators. There was no evidence before the  arbitrators or material adduced before the Court as  to the  nature of these operations. It is difficult to say,  by merely reading the terms of contract that the 650 arbitrators  have erroneously interpreted the terms  of  the contract. It is not without significance that the departmen- tal officers did not dispute the rate of the claim. Equally, the  arbitrators  were experienced engineers and  would  not have  passed,  what is now said to be, an  astounding  claim without  thought. It is difficult to assume that  all  these persons have overlooked that the contractor had already been paid  at Rs.18 under item 4.09(a) especially when it  is  so stated  on the face of the claim. This, therefore. is not  a case  where tile arbitrators can be said to have ignored  or overlooked  a  term of the contract; on the  contrary,  they have  acted  upon  a particular  interpretation  of  certain clauses  of  the contract on which two views  are  possible. This  case certainly cannot be brought under  the  principle that the arbitrators have ex facie exceeded the authority or jurisdiction  conferred on them by the Contract.  At  worst,

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 15  

what can be said is that they may have committed an error in deciding  the  issue referred to them but the error  is  not apparent  on the face of the award even if the  contract  is read  as  part of it both because the arbitrators  have  not given their reasoning and because the view taken by them  of the  relevant  terms of the contract cannot be  said  to  be clearly erroneous. In a matter on which the contract is open to  two equally plausible interpretations, it is  legitimate for  the  arbitrators  to accept’ one or the  other  of  the available  interpretations and, even if the Court may  think that  the other view is preferable, the Court will  not  and should not interfere. This view is too well settled to  need any reference to any precedent other than Sudershan  Trading Co’s  case  referred to earlier. That is why we  think  that this case does not fall within the principle referred to  by Shri Banerjee and that Dr. Ghosh is right in his  submission that the Division Bench exceeded its jurisdiction in  inter- fering with this part of the award.     Turning  now to the appeal of the Union of India,  there is  really no dispute about the first  contention  regarding the amount on which interest is payable to the  contractors. The correct computation should stand as follows in the light of our findings in the contractors’ appeal:      Compensation awarded       57,47,198      by arbitrator      Less: Interest element      therein [item (1)]           6,76,540      Net principal amount      awarded                      50,70,658 651       Less:Amount deleted       by learned Single Judge      5,20,000                                 ---------------                                   45,50,650                                 ---------------                                 --------------- The contractors will be entitled to interest on this amount.     What  is  the period with reference  to  which  interest would  be payable on the above amount? The  arbitrators  had allowed interest on the amount awarded by them from  5.10.82 to 26.3.84 under item (1) and had also allowed interest from the  date of the award till the date of payment  or  decree, whichever is earlier. Of this, the learned Single Judge  had deleted  the interest for the period 5.10.82 to  6.5.83  and what  remains is the award of interest from 6.5.83 till  the date  of  payment. There are two disputes as  to  this.  The first  objection raised on behalf of the Union is  that  the contractors  will  not be entitled to any interest  for  the period from the date of reference to arbitration  (6.5.1983) till  the  date of the award (26.3.1984). On behalf  of  the contractors,  Dr  Ghosh refutes this contention.  He  relies upon  the  decision of this Court in Executive  Engineer  v. Abhaduta  Jena. [1988] 1 SCC 418 and contends that,  in  all cases  where, as in this case, arbitrators are appointed  by Court  and disputes referred to them for  arbitration,  pen- dente  lite interest can and should be awarded by the  arbi- trator. He points out that, though initially in Seth Thawar- das’ case [1955] 2 SCR 48 some doubts were raised about  the competence  of the arbitrator to award interest, this  Court has subsequently consistently held that an arbitrator can do this:  vide,  Nachiappa v. Subramaniam, [1960]  2  SCR  209; Satinder  v.  Arnrao,  [1961] 3 SCR 676;  Firm  Madanlal  v. Hukamchand  Mills  Ltd., [1967] 1 SCR 105;  Union  v.  Bungo Steel  Furniture P. Ltd., [1967] 1 SCR 324; Ashok  Construc- tion Co. Ltd. v. Union, [1971] 3 SCC 66 and State v. Saith &

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 15  

Skelton P. Ltd., [1972] 3 SCR 233. After referring to  these and  other  cases,  Chinnappa Reddy, J.  in  Abhaduta  Jena, (supra) summed up the position thus: "15. As a result of the discussion of the various cases,  we see that Bengal Nagpur Railway Co. Ltd. v. Ruttanji  Ranjit, 65 IA 66; Union of India v. West Punjab Factories, [1966]  1 SCR 580 and Union of India v. Watkins & Co., AIR 1966 SC 275 were cases of award of interest not by an arbitrator, but by the court. It was laid down in those three cases that 652 interest  could not be awarded for the period prior  to  the suit  in  the  absence of an agreement for  the  payment  of interest  or any usage of trade having the force of  law  or any provision of the substantive law entitling the plaintiff to  recover interest. Interest could-also be awarded by  the court under the Interest Act if the amount claimed was a sum certain  payable  at a certain time by virtue of  a  written instrument. In regard to pendente lite interest, the  provi- sions of the Civil Procedure Code governed the same. 16.  The question of award of interest by an arbitrator  was considered in the remaining cases to which we have  referred earlier. Nachiappa Chettiar v. Subramaniam Chettiar,  [1960] 2 SCR 209; Satinder Singh v. Amrao Singh, [1961] 3 SCR  676; Firm  Madanlal Roshanlal Mahajan v. Hukumchand  Mills  Ltd., [1967]  1 SCR 105; Union of India v. Bungo  Steel  Furniture Pvt. Ltd., [1967] I SCR 324; Ashok Construction Co. v. Union of India, [1971] 3 S.C.C. 66 and State of Madhya Pradesh  v. M/s.  Saith & Skelton Pvt. Ltd., [1972] 3 SCR 233  were  all cases in which the reference to arbitration was made by  the court, of all the disputes in the suit. It was held that the arbitrator  must be assumed in those circumstances  to  have the  same  power to award interest as the court. It  was  on that basis that the award of pendente lite interest was made on  the  principle  of Section 34 Civil  Procedure  Code  in Nachiappa Chettiar v. Subramaniam Mills Ltd., (supra);  Firm Madanlal   Roshanlal  Mahajan  v.  Hukumchand  Mills   Ltd., (supra);  Union  of  India v.  Bungo  Furniture  Pvt.  Ltd., (supra)  and State of Madhya Pradesh v. M/s Saith &  Skelton Pvt. Ltd., (supra). In regard to interest prior to the suit, it  was  held in these cases that since  the  Interest  Act, 1839, was not applicable, interest could be awarded if there was an agreement to pay interest or a usage of trade  having the  force of law or any other provision of substantive  law entitling the claimant to recover interest. Illustrations of the provisions of substantive law under which the arbitrator could  award interest were also given in some of the  cases. It  was said, for instance, where an owner was  deprived  of his  property, the right to receive interest took the  place of the right to retain possession, and the owner of  immova- ble  property  who  lost possession of  it  was,  therefore, entitled  to claim interest in the place of right to  retain possession. It was further said 653 that it would be so whether possession of immovable property was  taken away by private treaty or by compulsory  acquisi- tion.  Another instance where interest could be awarded  was under Section 61(2) of the Sale of Goods Act which  provided for the award of interest to the seller or the buyer, as the case  may  be,  under the circumstances  specified  in  that section. XXX                                                      XXX XXX 18. While this is the position in cases which arose prior to the  coming into force of the Interest Act, 1978,  in  cases arising after the coming into force of the Act, the position

12

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 15  

now  is that though the award of pendente lite  interest  is still governed by the same principles, the award of interest prior to the suit is now governed by the Interest Act, 1978. Under  the Interest Act, 1978, an arbitrator is  by  defini- tion,  a court and may now award interest. in all the  cases to which the Interest Act applies."     Sri  Milon Banerjee, appearing for the Union  of  India, however,  contends  that the above principle  is  applicable only in cases where an arbitrator is appointed on  interven- tion of count as contemplated in Chapter IV of the  Arbitra- tion  Act.  It is only in these cases that  the  arbitration proceedings  can be considered to be a continuation  of  the court proceedings, empowering the arbitrator to do all  that the  court  could do. For, even in cases arising  after  the Interest Act, 1978, the award of pendente lite interest  can only  be in terms of the provisions of s. 34 of the Code  of Civil  Procedure  and  this cannot be invoked  in  cases  of arbitration except in cases falling under Chapter IV  merely on the ground that the appointment of the arbitrator is made under  S. 8, 12 or 20 of the said Act. Counsel submits  that Chinnappa Reddy, J. has pointed out in Abhadhuta Jena’s case [  [1988]  1  SCC at pp. 434-5] that in  all  cases  whether arising  before  or after the Interest  Act,  the  claimants would not be entitled to interest from the date of reference to  the  date of the award for the simple reason  that  "the arbitrator  is not a court nor were the references to  arbi- tration  made in the course of suits". It is this  principle that  has  been reiterated in Food Corporation of  India  v. Surendra,  Devendra & Mohendra Transport Co., [1988]  1  SCC 547  (at pp. 554 et seq) and Gujarat Water Supply  &  Sewage Board v. Unique Erectors, [1989] 1 SCC 532. There  is  force in the contention urged  by  Sri  Banerjee. There are 654 passages  in Abhaduta Jena which indicate that the grant  of pendente  lite  interest would be justified  only  when  the reference  to arbitration is made in the course of  a  suit: vide, the last sentence on p. 428, the first sentence on  p. 429,  the emphasis added in the extracts from earlier  judg- ments  on pp. 430-1, and the summings up at p. 433 and  435. The principle indicated in these passages apparently is that since  a  Court has, under s. 34, of the  C.P.C.,  power  to grant  pendente  lite interest in a suit, an  arbitrator  to whom a reference to arbitration is made in the course of the suit  would  be  clothed with all the powers  of  the  Court including  the one to grant such interest. This is how  this Court has also looked at the matter in a subsequent case. In State  of Rajasthan v. Sharrna & Co., [1988] 4 SCC 353,  the parties had entered into a compromise in certain proceedings in  Court agreeing that their disputes would be  settled  by arbitration but the arbitrators were appointed  subsequently by  the parties themselves and a reference made to  them.  A Bench  of this Court (of which one of us was a  member)  re- viewed  the  earlier  cases and explained  the  decision  in Abhaduta Jena thus: "12.  This was awarding interest pendente lite. This  is  in violation  of  the principles enunciated by  this  Court  in Executive Engineer (Irrigation), Balimela v. Abhaduta  Jena. Our  attention was drawn by Shri Soli J.  Sorabjee,  counsel for  the respondent, to the decision of this Court  in  Food Corporation  of India v. M/s Surendra, Devendra  &  Mohendra Transport  Co.,  where at pages 555-556 of the  report,  the Court  referred  to  certain decisions  cited  by  Chinnappa Reddy, J. in Executive Engineer (Irrigation) in which he had expressed the view that those were cases in which the refer-

13

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 15  

ences  to  arbitration were made by the court  or  in  court proceedings of the disputes in the suit. In that context  it was  held  in those cases that the arbitrator had  power  to grant  interest. It was contended before us that this was  a similar  case.  There was a court proceeding  in  this  case regarding the appointment of the arbitrator and, as such, on the  same analogy it should be treated that  the  arbitrator had power to grant interest. We are unable to accept this. 13. What Mr. Justice O. Chinnappa Reddy meant to say by  the latter  judgment  in Executive Engineer  (Irrigation)  case, referred  to  in  Food Corporation of India  was  where  the disputes regarding the merit of the case were pending in the court and such disputes instead of being decided by the 655 court,  adjudication had been referred to an  arbitrator  by the  court,  in such cases the arbitrators deciding  in  the place of court, would have the same powers to grant interest pendente  lite  as the courts have under Section 34  of  the Civil   Procedure   Code.  Instant  case  is  not   such   a proceeding." This  principle  would logically be applicable,  as  rightly contended  by Shri Banerjee, only to cases where the  refer- ence to arbitration arises in the course of a suit.     Dr.  Ghosh, however, submits that, except for  Nachiappa v.  Subramaniam,  [1960]  2 SCR 209  and  Hukumchand  Mills, [1967]  1 SCR 105, the other cases referred to by  Chinnappa Reddy,  J.  were all only cases in which an  arbitrator  had been appointed under s. 8 or 20 of the Arbitration Act.  The principle  enunciated,  he submits, was  actually  a  little wider  than that contended for by Shri Banerjee. It is  this that  where  an arbitrator is appointed by the Court  and  a reference  is  made  to him, he has all the  powers  of  the Court.  He invites attention to the observations  in  Hukum- chand  Mills,  case  [1967] 1 SCR 105,  reiterated  (in  the context of post-award interest) in Union v. Bungo  Furniture Co., [1967] 1 SCR 324 at p. 329) that it is "an implied term of the reference that the arbitrator will decide the dispute according  to law and would give such relief with regard  to pendente  lite interest as a Court could give if it  decided the dispute". He urges that Abhaduta Jena related to a batch of cases, arising out of references made prior to, and later than, the commencement of the Interest Act, 1978, but by the parties themselves under the terms of the contract,  without reference  to  court and so it was held that  pendente  lite interest  could  not be granted. But that is not so  in  the present case. He says that this decision was simply followed in  State v. Construction India, [1987] Suppl. SCC  708,  in the  Food Corporation case [1988] 1 SCC 547 and in State  v. Sharma  and Co., [1988] 4 SCC 353. The Gujarat Water  Supply case   [1989]  ISCC 532 was, he urges, also a  similar  case (see  para 5) though in that case there appear to have  been some  proceedings in Court earlier. In short,  he  virtually submits  that  Abhaduta Jena and Sharma’s case  have  unduly restricted  the grant of pendente lite interest and  require reconsideration  and that pendente lite interest  should  be awarded  in  all cases where the intervention  of  Court  is sought  for  the  appointment of  arbitrators,  directly  or indirectly, at any stage.     Generally  speaking, it would only seem reasonable  that the power to grant interest pendente lite should be  treated as ancillary to the award of damages or compensation  which, but for the delay in the 656 litigation (whether in Court or by way of arbitration),  the claimant should have received much earlier. However,  though

14

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 15  

pendente  lite  interest has been made  available  in  Court proceedings,  its  extension to arbitration law  appears  to have acquired some technical limitations resulting in denial of pendente lite interest in most cases of arbitration. Even if  we  accept the contention of Dr.  Ghosh,  pendente  lite interest cannot still be awarded by an arbitrator  appointed by the parties under a private agreement for which there may be  no justification in equity. These anomalies have  arisen because  formerly  an arbitrator could not be treated  as  a Court  to  which  the Code of Civil  Procedure  applied  and because now the Interest Act, 1978, while including arbitra- tion proceedings within its ambit, has, apart from a  refer- ence to s. 34, omitted to provide specifically for  pendente lite interest. This has been clearly brought out by Chinnap- pa  Reddy,  J.  We have earlier referred  to  passages  from Abhaduta Jena which outline the principle the learned  Judge had  in  mind for permitting pendente lite  interest  by  an arbitrator.  It is interesting, in fact, to notice that  the present  contentions of Dr. Ghosh (based on certain  earlier decisions of this Court) appear to have been advanced by him in  the Food Corporation case [1988] 1 SCC 547 to support  a wider  contention  that  pendente lite  interest  should  be awarded  even in an arbitration by private agreement (as  in that case) so long as the terms of the arbitration agreement did not exclude the jurisdiction of the arbitrator to enter- tain such a claim. But the Court did not accept the  conten- tion  and  followed Abhaduta Jena. Abhaduta  Jena  has  been followed in later cases also and its scope has been recently explained  in Sharma’s case [1988] 4 SCC 353. We  may  point out  that  in the latter case, a specific point  was  raised that since the Court had been concerned with the appointment of  the arbitrator at some stage it should be treated  as  a reference  to arbitration by court warranting the  grant  of pendente lite interest but this contention was negatived and the  principle confined only to cases where a  reference  to arbitration is made in the course of suits. The position was similar  in the Gujarat Water Supply case [1989] 1  SCC  532 but  pendente lite interest was denied. In view of  Abhaduta Jena  and the clarification specifically set out in para  13 of Shartna’s case, we are unable to accede to the contention of Dr. Ghosh, attractive as it is an equitable proposition.     The Division Bench of the High Court had no occasion  to consider  the  above recent pronouncements  of  this  Court. Further,  it  is seen that, before the Division  Bench,  the Union  took  an  objection that under clause  16(2)  of  the general conditions of contract, the contractors could  claim no interest on the amounts that may be determined as 657 payable  to them. The Division Bench met this contention  by relying  on  a circular issued by the  Government  of  India making  the claim for interest entertainable in  arbitration "if   notice  had  been  issued  in  this  behalf   by   the arbitrator".  There is, however, no finding and  nothing  on record  brought  to  our notice to show  that  any  specific notice, claiming interest, had been given as contemplated by the contract. Having regard to all these considerations,  we are unable to uphold the order of the Division Bench on this issue.     This takes us to the second point urged on behalf of the Union  in  regard to interest. The contention  is  that  the learned  Single Judge had restricted it to the date  of  the award,  and  that this has become final as  the  contractors have  preferred no appeal therefrom. The grounds  of  appeal before  us by the Union are confined only to the mistake  in not  taking into account the sum of Rs.6,76,540 and  do  not

15

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 15  

raise  any  question regarding post-award interest.  It  is, therefore, not open to Shri Banerjee to raise this question. That apart, on merits also the contention raised that  post- award  interest has been declined by the High Court  is  not correct.  The contention overlooks the course  of  pleadings between the parties. The arbitrators had, in the annexure to the  award, computed interest from 5.10.82 to  26.3.84  i.e. from  the date of the termination of the contract  till  the date of the award and in the award, had granted interest  on the  amount awarded from the date of award till the date  of decree  or payment. A point had been raised before the  High Court  in  the memo of objections that the  arbitrators  had erred  in awarding interest in the manner mentioned  in  the award  but  the  objection urged by  the  Union  before  the learned  Single  Judge  was a different one  viz.  that  the arbitrators  ought  not  to have granted  interest  for  the period prior to the date of reference without any  agreement or  right in law to claim such interest. It is this  conten- tion  that  was  accepted by the learned  Single  Judge  who deleted  the interest award prior to the date of the  refer- ence and held that the arbitrators had jurisdiction to award interest from the date of the reference till the date of the award. This did not affect the arbitrator’s direction in the main  part  of the award, that interest will accrue  on  the amount of the award (if the said amount was not paid  within 60  days) till the date of payment or decree,  whichever  is earlier. This part of the award was not questioned. In fact, the  decree  drawn  up in consequence of the  order  of  the learned  Single Judge, specifically directs (a) interest  on the  awarded  amount  from 6.5.83  (date  of  reference)  to 26.3.84  (date of the award ); (b) "thereafter, interest  on the  amount’ awarded at 11% from 27.3.84 to 11.12.84"  (date of the decree); and (c) interest thereafter at 658 9%  per annum. The objection of the Union in the LPA on  the question of interest was only that the arbitrators had erred in awarding interest from 6.5.1983 to 26.3.1984. It is  this contention that was accepted by the Division Bench. The High Court had, therefore, not decided that the contractors  were not entitled to interest beyond the date of the award.  This contention of the Union, therefore, fails and is rejected.     In the result C.A. 1280/88 is allowed and C.A. 128  1/88 is allowed in part. There will be no order as to costs. R.N.J.                                               Appeals allowed. 659