GRID CORPN. OF ORISSA LTD.&ORS Vs EASTERN METALS & FERRO ALLOYS & ORS ETC.
Bench: R.V. RAVEENDRAN,H.L. GOKHALE, , ,
Case number: C.A. No.-005842-005889 / 1998
Diary number: 18300 / 1998
Advocates: RAJ KUMAR MEHTA Vs
SARLA CHANDRA
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.5842-5889 OF 1998
Grid Corporation of Orissa Ltd. & Ors. … Appellants
Vs.
Eastern Metals & Ferro Alloys & Ors. … Respondents
WITH
CA Nos. 3 to 8 of 1999, CA No.748 of 1999, CA No.7246 of 2010 (Arising out of SLP (C) No.4596 of 1999)
J U D G M E N T
R.V.RAVEENDRAN, J.
Leave granted in SLP(C) No.4596 of 1999.
These appeals involve the interpretation of a tariff provision in the
provisional supply and distribution Licence issued under the Orissa
Electricity Reform Act, 1995 (‘Act’ for short).
1
2. The State of Orissa enacted the said Act, to restructure and rationalize
the generation, transmission, distribution and supply of electricity in the
state.
2.1) Section 3 of the Act provided for the establishment of the Orissa
Electricity Regulatory Commission (‘Commission’ for short), to discharge
functions including the issue of licences in accordance with the Act and
determine the conditions of such licences.
2.2) Chapter VI of the Act deals with licensing of transmission and supply.
Section 14(iv) of the said Act authorized the State Government to grant
provisional licences for a period not exceeding twelve months, for carrying
on the business of transmission or supply of electricity, as a transitional
measure till the establishment of the Orissa Electricity Regulatory
Commission (‘Commission’ for short).
2.3) Section 13 of the Act provided that the Grid Corporation of India Ltd.
(‘GRIDCO’ for short, the appellant herein) incorporated with the main
object of engaging in the “business powers” of the state government under
section 12 of the Act, would be the principal company to undertake the
2
planning and co-ordination in regard to transmission and to determine the
electricity requirements in the state in co-ordination with various
stakeholders.
2.4 Chapter VIII of the Act dealt with tariffs. It contained two sections -
section 26 dealing with licencee’s revenues and tariffs and section 27
dealing with finances of licencees.
3. In exercise of the power under section 14(iv) of the Act, the State
Government, by notification dated 30.3.1996, issued three licences to the
appellant - the Provisional Orissa Transmission Licence 1996, Provisional
Orissa Supply Licence (Bulk Supply) 1966 and the Provisional Orissa
Supply Licence (Retail Supply and Distribution), 1996 -- authorising the
appellant to engage in the business of transmission, bulk supply and retail
supply and distribution of electrical energy within the State of Orissa, upon
the terms and conditions mentioned in those licences. In pursuance of such
licences, the appellant took over the transmission, distribution and supply of
electricity from the Orissa State Electricity Board (‘OSEB’ for short) with
effect from 1.4.1996. Part III of the Retail Supply and Distribution Licence
(similar provisions were contained in the Provisional Transmission Licence
3
and Provisional Bulk Supply Licence also) related to “Tariffs” and it is
extracted below :
“9. Basis of Charges
9.1 The charges made by the licensee shall not exceed on average 117% of those permitted under the interim tariffs issued by the State Government and in force on 1st April 1996.
9.2 The authority granted in clause 9.1 expires with the expiration of this license.”
The “interim tariffs in force as on 1.4.1996 issued by the state government”,
referred to in the said clause 9.1 were the tariffs which came into effect on
5.11.1995, contained in the Notification dated 28.10.1995 issued by the
Orissa State Electricity Board, predecessor of GRIDCO.
4. By notification dated 13.5.1996, the appellant revised/prescribed the
electricity charges for different categories of consumers of electricity in the
State as per the tariff schedule appended to the said notification with effect
from 21.5.1996, in supersession of the tariff rates prescribed in the OSEB
Notification dated 28.10.1995. The tariff schedule under the Notification
dated 13.5.1996, prescribed different tariff rates for (i) large industries, (ii)
medium industries, (iii) small industries, (iv) irrigation pumping and
agriculture, (v) public water works and sewerage pumping, (vi) commercial,
4
(vii) domestic, (viii) railway traction supply, (ix) street lighting, (x) direct
current service, (xi) power intensive industries, (xii) heavy industries, (xiii)
general purpose supply, (xiv) public institutions, (xv) mini-steel plants; and
(xvi) emergency power supply to captive power plants.
5. Several industries which were consumers of electricity and the Utkal
Chamber of Commerce, filed writ petitions before the High Court,
challenging (i) the validity of section 14(iv) of the Act; (ii) the validity of the
provisional Retail Supply and Distribution Licence issued by the State
Government under section 14(iv) of the Act to the appellant, in particular the
provision of the licence which enabled the appellant to increase the tariff not
exceeding on average 117% of those permitted under the interim tariff
issued by the State Government; and (iii) the tariff notification
dated 13.9.1996 issued by the appellant.
6. A Division Bench of the High Court disposed of the said writ petitions
by the impugned judgment dated 30.10.1998. The High Court upheld the
vires of section 14 (iv) of the Act and the Notification dated 30.3.1996 of the
State of Orissa granting the provisional licences in favour of the appellant. It
also upheld the power of the appellant to revise the tariff under the
5
provisional licence. It however held that the increase in tariff rates under the
tariff notification dated 13.5.1996 issued by the appellant was more than
17% (over the tariff rates contained in OSEB Notification dated 28.10.1995)
in regard to some categories of consumers and as such was in excess of the
power given to the appellant under clause 9.1 of the provisional supply &
distribution licence. The High Court held that while the appellant could
increase the tariff upto 17% in terms of the licence, there was no power or
authority to increase the tariff rates beyond 17% in respect of any particular
category of consumers; and as the appellant had increased the tariff rates by
different percentages in regard to different categories of consumers, in the
absence of a specific authorization for enhancement beyond 17% in regard
to any category of consumers, it was not competent for the appellant to
enhance the tariff rate beyond 17% in respect of any category of consumer.
The High Court negatived the contention of the appellant that it could
increase the tariff by more than 17% in regard to some categories, provided
the increase in respect of other categories was less than 17%, and the net
overall result by way of average did not exceed 17%. As a consequence, the
High Court quashed the tariff notification dated 13.5.1996 as also the
demands under the respective bills raised against the various writ petitioners.
The High Court directed the Commission to redetermine the tariff as per law
6
and further directed that any excess payments collected from the consumers
shall be adjusted towards future demand/s.
7. The said judgment is challenged in these appeals by special leave. The
appellant contends that Clause 9.1 of the Provisional Licence clearly
provided that the charges made by the licensee shall not exceed 17% on an
average, which implied that while the increase in case of some categories of
consumers could be more than 17%, it could be less than 17% in case of
other categories so that the total increase on an average does not exceed
17%. It is submitted that the interim tariffs permitted by the State
Government and which was in force on 1.4.1996 was an average 171.6 paisa
per unit. The revised tariff under the notification dated 13.5.1996 effective
from 21.5.1996 was estimated to yield a revenue of Rs.1241.12 crore by sale
of 629.1 crore units during the whole of the year 1996-97, which would
mean that the average tariff would be 200.15 paise per unit. During the year
1996-97, the interim tariffs were in force for the period 1.4.1996 to
20.5.1996 and the revised tariff under notification dated 13.5.1996 was in
force from 21.5.1996 to 31.3.1997. In view of it, the estimated yield of
revenue during the year 1996-97 worked out to Rs.1216.81 crore by sale of
620.1 crore units, and the average tariff for the full year 1996-97 worked out
7
to 195.228 paise per unit. Therefore it is contended that the average increase
in the tariff for the year 1996-97 over the interim tariff in force on 1.4.1996
was 14.35%, well within the permissible limits and did not violate the
provisions of clause 9.1 of the provisional supply and distribution licence.
8. This Court by interim order dated 3.4.2000 directed the Orissa
Electricity Regulatory Commission to determine the tariff by two methods,
that is by taking into account the observations made by the High Court in the
impugned judgment, and the second, without reference to the
observations/directions of the High Court.
9. In pursuance of the said direction, the Commission submitted a report
dated 24.11.2000 to this Court in regard to the tariff determination. The
Report stated :
“We have carefully examined the basic facts and figures on which the impugned tariff notification dated 13.05.96 was issued. The mandate for us is to redetermine tariff within the parameters stipulated in the provisional license that the charges shall not exceed 117% of those permitted under the interim tariffs in force. As per law, revised tariff can be proposed by licensee when it finds that its annual revenue requirement cannot be met by the charges fixed under prevailing tariff notification. As the estimated revenue fell short of annual revenue requirement, the licensee was authorized under the temporary licensee to increase the tariff, subject to the limit aforesaid. Gridco estimated its annual revenue requirement for 1996-97 at Rs.1413 crores which was at a substantially higher level than estimated realization of Rs.1033.94 crores on prevailing
8
interim tariff. Hence Gridco was entitled to revise tariff but within the parameters indicated at clause 9 of the Licence. The charges proposed under impugned notification dated 13.5.1996 would raise a total revenue of Rs.1241.22 Crores for a whole year and Rs.1212.83 Crores for the period upto 31.3.1997 when provisional license was to expire. Thus, Gridco’s notification authorized charges considerably short of its annual revenue requirements. Hence legitimacy of tariff increase cannot be assailed. We have come to this conclusion after taking into account objections raised before us during the redetermination proceeding. We do not consider it appropriate to burden this note with the facts, statements and views presented by the objectors during the proceeding. It may suffice to say that there has been no serious or reasonable challenge to the calculation of actual revenue requirement of Gridco even though objectors have challenged Gridco on various grounds such as lack of prudence in purchase of power, in expenditure, failure to restrict T & D Loss, unreasonableness of increase in tariff and lack of concern for affordability etc. In view of wide gap between revenue requirement and revenue realizable, Gridco was justified in increasing tariff. But what has to be ensured is whether the increase was hit by the ceiling imposed under clause 9 of provisional license.”
(emphasis supplied)
The report also noticed the submission of the appellant that as the average of
the interim tariff (as per OSEB Notification dated 28.10.1995) which was in
force till 20.5.1996 was 171.6 paise per unit and as it was empowered to
raise the average tariff to 117%, it had the mandate to raise the average tariff
to 200.772 paise per unit (that is 117% of 171.6 paise); that as the interim
tariff under OSEB notification dated 28.10.1995 was in operation till
20.5.1996 and the new tariff under GRIDCO notification dated 13.5.1996
was in operation from 21.5.1996 to 31.3.1997, the percentage of increase
over the interim tariff with reference to the revenue receipts for the said
9
period was only 200.166 paise, that is an increase of 16.65% and therefore,
was not hit by the ceiling of 117% imposed by the provisional lincence.
(For this purpose, the average tariff rate (200.166 paise) was arrived at by
dividing the Revenue for the period when the tariff was in force, by the total
consumption during that period). The Report did not find anything
unreasonable in the said contention of the appellant. But the commission
proceeded to opine that in the light of the definition of the word ‘tariff’ in
the Act and the clear difference between the words ‘tariff’ and ‘charges’,
clause 9 of the Provision Supply Licence by using the words “charges made
by the licencee”, conferred on the appellant only a limited power of raising
charges by a maximum of 17% for any category of consumer. It observed
that ‘tariff’ referred to the Schedule of standard prices/charges, and “charge”
referred to the rate to be charged for a particular category of customers and
therefore, ‘charges’ meant ‘prices’. Consequently the report rejected the
appellant’s method of calculating the ceiling with reference to overall rate of
tariff. The commission held that even if the observations of the High Court
were not taken into account, there would be a need to cut the charges in
respect of those categories of consumers where the increase was more than
17% as being in excess of appellant’s authorization. Consequently it held
that while the increase in charges for the category of “irrigation” and
1
category of “railway traction” will remain unchanged (as the increase therein
was less than 17%), there should be reduction in the tariff rates or charges
for all other categories of consumers (where the increase was more than
17%). The Commission in effect supported the decision of the High Court.
10. The appellant contended that the interpretation of clause 9.1, adopted
by the High Court and the Commission was erroneous. According to the
appellant, the High Court and the Commission while reading and
interpreting the words “charges made by the licensee shall not exceed on
average 117% …..” in clause 9.1, have ignored the significance of the
words ‘on average’ and rendered the said words redundant and otiose. The
appellant contended that they also overlooked the fact that clause 9.1 used
the words “charges made” and not the words “charges imposed” or “tariff
rates”. It was also pointed out that clause 9.1 neither referred to “consumers”
or “category of consumers”. The appellant submitted that the object of the
provision was not to bar category-wise revisions, but to provide for different
increases which on averaging increased the overall revenue by 17% over the
revenue that would have been derived with reference to pre-revision tariff
rates. The appellant contended that the use of the word ‘average’ was
intended to mean that the appellant was entitled to apply different rates to
1
different categories of consumers provided the aggregate of revenue on
account of the increases did not exceed 17% of the revenue with reference to
pre-revision tariff rates. The appellant contended that the provision did not
place a ceiling of 17% in regard to increase in the tariff rates for each of the
categories; that it was entitled to increase the tariff rates in respect of some
categories of consumers beyond 17% while restricting the increase in the
tariff rates for other categories to a lesser percentage, to ensure that the total
revenue for the electricity consumed during the relevant period, did not
exceed 17% over the revenue for such quantum based on the previous
interim tariff rates. It was therefore submitted that the tariff notification
dated 13.5.1996 was valid.
11. The respondents on the other hand contended that the word “charges”
in clauses 9.1 referred to the tariff rates. They relied upon the definition of
‘tariff’ in clause (b) of explanation to section 26 of the Act which reads as
under : “tariff” means a schedule of standard prices or charges for specified
services which are applicable to all such specified services provided to the
type or types of customers specified in the tariff”. They submitted that
“charges made” in clause 9.1 do not refer to the total revenue received by
appellant, but referred to the tariff rates prescribed by appellant. It was next
1
contended that even assuming that the words ‘charges made’ were capable
of being interpreted in more than one way, the interpretation that is
beneficial to the consumer should be adopted. They further contended that
where the opinion/ views of a technically competent body, that is the
Commission, was available in regard to the interpretation that should
normally be accepted unless it was shown to be arbitrary and unreasonable.
12. The report of the Commission discloses that in regard to consumers
falling under the category ‘irrigation’, the increase was only 8.33% and for
the Railways falling under the category ‘railway traction’, the increase was
only 10.09%. In regard to the domestic consumers, the increase was 17.47%.
In regard to all other categories of consumers, the increase was much more.
In particular, for small industries, the increase is said to be 27.59%, for
medium industries the increase is said to be 29.73% and for large industries
the increase is said to be 32.25%. The question is whether clause 9.1
authorized and permitted the appellant to increase the tariff rate in regard to
each category of consumers, by a percentage not exceeding 17% over the
pre-revision tariff rate, or whether the appellants had the discretion to
increase the tariff rate relating to different categories by different
percentages (that is even more than 17% in regard to some categories) so
1
long as the overall revenue on account of different increases, did not exceed
on the whole, 17% of the overall revenue calculated at the pre-revision tariff
rates. The entire question would thus revolve around the interpretation of the
words “shall not exceed on average 117%” in clause 9.1.
13. It is not disputed that clause 9.1 is capable of different interpretations.
The three possible interpretations are:
Interpretation (i) : There can be an increase in tariff rates, but the increase in
tariff rate in respect of any category of consumers, could not exceed 17% of
the interim tariff rates.
Interpretation (ii) : So long as the average of the different increases does not
exceed 17% of the interim tariff rates, the appellant had the discretion to
apply different rates of increases to different categories and some of them
can exceed 17%.
Interpretation (iii) : The increase in tariff rates for different categories of
consumers could be of different percentages, provided the average
realization per unit during the relevant period (arrived at by dividing the
estimated revenue during the period, by the estimated consumption during
that period) was not more than 17% of the average realization per unit
during the previous period when the interim tariff was in force.
1
The first interpretation has found favour with the High Court and the
Commission, having regard to the definition of ‘tariff’ in the Explanation to
section 26 of the Act.
14. This takes us to the correct interpretation of clause 9.1. The golden
rule of interpretation is that the words of a statute have to be read and
understood in their natural, ordinary and popular sense. Where however the
words used are capable of bearing two or more constructions, it is necessary
to adopt purposive construction, to identify the construction to be preferred,
by posing the following questions: (i) What is the purpose for which the
provision is made? (ii) What was the position before making the provision?
(iii) Whether any of the constructions proposed would lead to an absurd
result or would render any part of the provision redundant? (iv) Which of the
interpretations will advance the object of the provision? The answers to
these questions will enable the court to identify the purposive interpretation
to be preferred while excluding others. Such an exercise involving
ascertainment of the object of the provision and choosing the interpretation
that will advance the object of the provision can be undertaken, only where
the language of the provision is capable of more than one construction. (See
Bengal Immunity Co. v. State of Bihar – 1955 (2) SCR 603 and Kanailal Sur
1
v. Paramnidhi Sadhukhan – 1958 SCR 360 and generally Justice
G.P.Singh’s Principles of Statutory Interpretation, 12th Edition, published by
Lexis Nexis - Pages 124 to 131, dealing with the rule in Haydon’s case).
15. In this case, we have noticed above that clause 9.1 is reasonably
capable of more than one construction, that is at least three interpretations.
We may therefore attempt to ascertain the true meaning of the provision by
answering the four questions referred in the earlier para. On a careful
consideration, the answers to the four questions posed are : (i) The purpose
of clause 9.1 is to provide for an increase in revenue by revising the tariff
rates, by balancing the needs of the Licencee with the interests and needs of
different categories of electricity consumers. (ii) Clause 9.1 being a fresh
provision, the question of considering the position that existed before
making of the said provision does not arise. (iii) The interpretation
canvassed by the respondents, (that is interpretation (i) that increase in
respect of any category of consumers cannot exceed 17%) which found
favour with the High Court and the Commission, though may not lead to an
absurd result, would render the words ‘on average’ occurring in the clause,
redundant and otiose. (iv) The interpretation put forth by the appellant gives
1
meaning to every part of the clause and also achieves the object of the
clause. We will elaborate the reasons therefor.
Re: Interpretation (i)
16. The first interpretation of clause 9.1 is that it permits increase in tariff
rates but with a ceiling of 17% in regard to each and every category of
consumers, and therefore the increase in case of no category can exceed
17%, has found favour with the High Court and the Commission. The fact
that there can be different percentages of increases in tariff in regard to
different categories is an accepted procedure. For example a lesser tariff is
applied to agriculturists using electricity for irrigation purposes when
compared to consumers using electricity for commercial or industrial
purposes. Therefore, when there is a revision of tariff rates, the percentage of
increase will and can vary from category to category. If the aforesaid
interpretation is applied by holding that in no case, the increase can be more
than 17%, and if in regard to some categories, increases are to be nominal, it
will be impossible to achieve a 17% increase which is permitted and
contemplated under clause (9.1). Further, the words ‘on average’ would be
rendered meaningless if by average 17% increase cannot be achieved and if
the increases cannot exceed 17% in any case. This interpretation, if
1
accepted, would also prevent the licensee from creating or carving out any
new category of consumers and fix the tariff rate for such category.
Therefore this interpretation apart from rendering the words ‘on average’
redundant and meaningless, militates against the provisions of clause (9.1).
Re : Interpretation (ii)
17. The second interpretation is that so long as the average of the different
increases does not exceed 17% of the interim tariff rates, the appellant has
the discretion to apply different rates of increases to different categories and
increases with reference to some categories can exceed 17%. This
interpretation will also lead absurd result if put into effect. Let us illustrate
with reference to a hypothetical example (not with reference to actuals):
S.No. Category of Use Consumption share out of total quantity of electricity generated and distributed
Percentage in increase over the previous tariff rate
1. Industry 40% 60% 2. Domestic 30% 30% 3. Irrigation 10% 1% 4. Railway traction 10% 2% 5. Public Institutions 5% 3% 6. General purposes 5% 4%
The average of the percentages of increase in regard to six categories will be
only 16.66% which is less than 17%. But in terms of revenue realization, the
1
increase would exceed not only 17%, but even as much as 40% with
reference to revenue at the previous tariff rates. This obviously was not the
object. The average should ensure that there is no increase beyond 17% in
regard to the total revenue.
Re : Interpretation (iii)
18. The words used in clause (9.1) are “charges made by the licencee
shall not exceed on average 117% of those permitted under the interim
tariffs”. It is significant to note that the clause does not use the words “the
tariff rates prescribed by the licencee shall not exceed 17% of those
permitted under the interim tariffs.” The use of the words “charges” and
‘tariffs’ in the same clauses indicates that they were intended to signify
different meanings. As rightly noticed by the Commission, the word ‘tariffs’
referred to the schedule of rates. If the object of clause 9.1 was to refer to
‘tariff rates’ prescribed by the Licence, there was no need to use the words
“charges made”. The use of the words ‘on average’ while referring to 117%
has also some significance. If the words “charges made by the licencee” are
interpreted as “tariff rates fixed by the licencee”, then, the words ‘on
average’ would be rendered meaningless and becomes an useless appendage.
The use of the words ‘charges made by the licencee’ and use of the words
1
“shall not exceed on average 117%” necessarily indicates that the rates fixed
by the appellant should not result in an increase in realization or revenue in
excess of 17% of what it would have realized with reference to the tariff
rates that were earlier in force under the interim tariff. ‘Charges made by the
licensee’ therefore refers to the total revenue of appellant by sale of
electricity to the different categories of consumers.
19. The appellant, discharging the functions of the state government under
the Act, had to ensure that the burden of increase on the agriculturist –
consumers, that is those consuming electricity for “irrigation”, should be the
minimum. Similarly, increase in the tariff rate for electricity consumed by
railway traction had to be kept minimal in national economic interest.
Similarly, the increase in tariff for residential user should be comparatively
lesser than commercial user. At the same time, the appellant had to ensure an
increase in its revenue by 17%. If increase beyond 17% was not permissible
in regard to any category of consumers, and if some categories had to be
subjected to only small increases far below 17%, due to economic or social
justice criteria, the appellant would never be able to achieve the increase
anything in the range of 17%. Only by adopting the process of applying a
higher than 17% increase in the case of some categories of consumers, it can
2
offset the effect of small or marginal increase in the case of some other
categories like ‘irrigation’ and ‘railway traction”. Therefore, if appellant
chose to charge a lesser increase in percentage to some categories of
consumers and higher increases in regard to other categories of consumers, it
cannot be found fault with so long as its total revenue does not exceed 17%
over the corresponding revenue with reference to the old interim tariff rates.
If appellant would have realized ‘X’ amount as revenue at the interim tariff
rates which were in force before 21.5.1996, the object of the increase was to
provide an increase in revenue by 17% over ‘X’ after 21.5.1996. That is why
the word ‘on average’ is used in clause 9.1. This gives the discretion to
appellant to charge tariff rates with different increases depending upon the
category of consumers, so long as the overall increase in revenue, that is the
“charges made” by the licensee, does not exceed 17%. Any other
interpretation would render the words ‘on average’ otiose and have the effect
of substituting the words tariff rate for the word charges.
20. In fact, the Commission has accepted this contention of the appellant
to a large extent as is evident from the following observations in the report :
“As there will be considerable uncovered gap between revenue requirement and revenue expected. We do not find scope to bring down the charges in any category. But in the present environment of cross-
2
subsidy which is bound to continue for a number of years and in the absence of reliable data for calculating cost of supply and average tariff, we consider that the relative rates for different categories of consumers for the interim period as decided by GRIDCO is as good as any other alternative allocation of costs and charges………
It appears that it has not been brought to the notice of the Court that all along in the past varying charges for different categories of consumers has been determined in consideration of nature and purpose of use and affordability of different categories of consumers. The cost of supply, the quality of supply and affordability are widely different for different classes of consumers. Due to socio-political decision to cross-subsidize some categories, it has never been considered desirable or possible to levy uniform charges or to decide upon a uniform percentage of increase of charges…….
In the practice followed by electrical utilities in the country as well as abroad, the average “charges” for electricity tariff is calculated by considering the total revenue realizable during a period divided by number of units estimated to be sold during the period. Percentage of increase in charges or tariff, normally refers to percentage of increase of the average rate over the overall average rate of prevailing tariff calculated in this method. This has been the practice mainly due to the prevalence of cross- subsidy in the electricity tariff structure in India. Even when there is no cross-subsidy the rate of increase in tariff for various categories are different because the determination is with reference to cost of supply for a particular category of consumer. The concept of uniform rate of increase for all categories of consumers is unknown because every time there is a revision the interests of different categories are rebalanced in consideration of public policy, pattern of consumption, consumer composition and revenue requirements. Viewed in this light we find some justification in Gridco’s claim that ceiling of 117% was with reference to overall average of interim tariff and overall average rate of new tariff. This logic implies that there has been no clear distinction between ‘tariff’ and ‘charges’.”
21. The reliance upon clause (2) of Explanation to section 26 of the Act to
interpret the wording of clause 9.1 is misconceived. The explanation to
section 26 does not define the words ‘charges made’, but defines the word
2
‘tariffs’. Under the erroneous assumption that the word “charges” referred to
the actual tariff rates that were chargeable to different categories of
consumers, the Commission ignored its own conclusions and held that
clause 9.1 placed a ceiling of 17% in respect of increases in the tariff rates
applicable to different categories of consumers. It is true that the
interpretation by a technical body in regard to purely technical matters
deserves acceptance and will not be interfered, unless it is arbitrary or
unreasonable. But in this case, on technical issues, the Commission has
favoured the stand of the appellant. Having accepted the interpretation of the
appellant as being technically sound and correct, it reached a different
conclusion only because it thought that the word ‘charges’ had to be
interpreted as ‘tariff rates’. If that is found to be without basis or erroneous,
and therefore ignored, the opinion of the Commission fully favours the
appellant.
22. We are of the view that the High Court was not justified in holding
that the tariff rate in regard to none of the category of consumers can exceed
17% over the previous rates. We accept the explanation and interpretation of
the appellant. The Commission has found that the increase in revenue, on an
average, under the tariff notification dated 13.5.1996 was only 16.65% over
2
the revenue calculated with reference to the earlier interim tariff rates. We
therefore, allow these appeals, set aside the judgment of the High Court
dated 30.10.1998 and dismiss the writ petitions filed by the respondents
before the High Court and uphold the validity of the Tariff notification dated
13.5.1996.
…………………………..J. (R V Raveendran)
New Delhi; …………………………J. August 31, 2010. (H L Gokhale)
2