GREAT OFFSHORE LTD. Vs IRANIAN OFFSHORE ENG&CONSTN. CO.
Bench: DALVEER BHANDARI, , , ,
Case number: ARBIT.CASE(C) No.-000010-000010 / 2006
Diary number: 11248 / 2006
Advocates: Vs
SHRISH KUMAR MISRA
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO.10 OF 2006
Great Offshore Ltd. … Petitioner/Applicant
Versus
Iranian Offshore Engineering & Construction Company …Respondent
J U D G M E N T
Dalveer Bhandari, J.
1. Great Offshore Limited has filed a petition under section
11(5)((6)(9) and (12) of the Arbitration and Conciliation Act,
1996 whereby the applicant seeks the appointment of a sole
arbitrator. The applicant, Great Offshore Ltd., submits that it
has entered into a charter party agreement with the
respondent, Iranian Offshore Engineering & Construction
Company. The charter party agreement (“CPA”) contains an
arbitration clause. Relying on this clause, the applicant has
asked this Court to appoint an arbitrator to resolve the
dispute. The respondent, however, contends that the two
parties had not progressed beyond the stage of negotiation
and that there is no concluded contract between them.
Therefore, it is argued that there is no question of referring the
dispute to arbitration.
2. Brief facts which are relevant to dispose of this
arbitration petition are recapitulated below.
3. The charter party agreement in dispute marks the
second time the parties have done business with each other.
The first time was in 2004. In March of that year, the
respondent entered into a contract with the Oil and Natural
Gas Corporation Limited (“ONGC”) to carry out construction
work on ONGC’s installations at Bombay High. On 26th
October, 2004, the applicant and the respondent entered into
a charter party agreement. Under this prior agreement, the
respondent hired a vessel combination from the applicant. The
respondent required a specialized offshore construction barge
known as a “Gal Constructor.” It also required an anchor
handling tug, named “AHT Malaviya Five.” The AHT Malaviya
2
is used in combination with the Gal Constructor. I shall refer
to the Gal Constructor and the AHT Malaviya as the “vessel
combination.”
4. The respondent needed this combination to execute
offshore work for ONGC. This work was part of ONGC’s
RSPPM project, Phase I. The first phase was completed in
November 2004.
5. In this case, the controversy is confined to the alleged
agreement relating to the second phase of ONGC’s project.
6. In this arbitration petition, I need to decide whether the
parties have entered into a valid contract containing an
arbitration clause. To this end, it has become imperative to
review the relevant correspondence between them. Only then
will I be able to arrive at a conclusion as to whether there was
a concluded contract or whether the parties had never
progressed beyond the stage of negotiation.
7. After the parties expressed mutual interest in resuming
business for Phase II, the respondent faxed a letter to the
3
applicant. The letter is dated June 20th, 2005. In this letter,
the respondent expressed its intention to use the applicant’s
vessel combination for 170 days pursuant to the same terms
as the preceding agreement. A few amendments, however,
were to be made to that agreement.
8. The applicant responded vide email the next day and
stated that it would like to “come to an agreement.” After
meeting the respondent on 22nd June, the applicant faxed an
offer to the respondent on June 23rd, 2005.
9. In turn, the respondent faxed a letter of intent on June
23rd, 2005. The letter stated that it was “…a firm and
unconditional letter of intent (for short LIO) for award of
contract for charter hire of your barge Gal Constructor and
Malviya 5”. Nevertheless, the very same letter contained a
contingency clause:
“ This Agreement is subject to IOEC [respondent] providing a suitable barge and AHT acceptable to GE Shipping [applicant] for a period of 45-55 days on mutually agreed rates for commencement between 25th October and 10th November 05 for BHN MOL project works.”
4
10. On July 1st, 2005, the respondent’s minutes of meeting
indicate that the barge (vessel) was to be available for visual
examination “…until 25th of July after which the barge will
leave AJMAN port in UAE for the project in PG”.
11. On August 4th, 2005, the applicant explained that it no
longer wanted the respondent to provide a barge for 45-55
days, as mentioned in the respondent’s June 23rd letter of
intent. Because the parties could not agree on the rate for
this service, the applicant said that it would make alternate
arrangements.
12. On August 11th, the respondent sent a letter in regard to
modifying the Barge Gal Constructor so that it could function
as a riser installation barge. Based on its engineering
analysis, it sought to install “…5 davits in the port or STBD
side at the barge” as well as a “… working platform as an
extension to main deck in the aft quarter over one of the
anchor rests”.
13. In response to a meeting on August 8th and the above
letters, the respondent faxed a letter to the respondent on
5
August 13th, 2005. The letter suggested that additional
provisions be incorporated in a new draft of the contract. The
respondent requested the right to modify the Gal Constructor,
thereby enabling it to perform a riser installation. The
respondent further asked the applicant to pay the outstanding
amount (USD 188,500) from the preceding contract. In
conclusion, the respondent stated that it would be willing to
finalize the contract before the 30th of August.
14. On 16th August, the parties met to discuss the proposed
changes. The applicant formally responded to the
respondent’s suggestions in a letter dated August 22nd, noting
that the parties had come to the following agreement
regarding a number of outstanding issues:
S. No. Clause Agreement 1 Modifications for Riser
Installation Clause on the basis of Addendum 3 to Charter Party dated 26th Oct 04 to be incorporated
2 Early Termination Clause
It was mutually agreed not to include the clause suggested
3 Employment of vessel Clause as per Charter Party dated 26th Oct 04 to be incorporated
4 Sublet Clause Clause 17 of the charter party to be referred in additional clause pertaining to sublet
5 Credit note issue Addressed hereunder
6
… we confirm our acceptance of the credit note amounting to US$186,618 … for subject vessel combination for charter party dated 26th Oct 2004. …”
15. Before proceeding with the correspondence, it is
pertinent to note that the faxed charter party agreement
(“faxed CPA”) is dated August 22nd. After having settled a
number of outstanding issues vide the above letter, the
applicant allegedly sent the faxed CPA to the respondent on
the same day.
16. The faxed CPA officially entitled the “Charter Party for
Offshore Service Vessels Code Name ‘Supplytime 89’” dated
August 22nd, 2005 is reproduced, in relevant part. The
“charterer” is the respondent, and the applicant is the
“owner”:
1. Place & Date. Mumbai, India. 22nd August 2005. …
9. Period of Hire. 204 days firm / minimum …
14. Early termination of charter (state amount of hire payable) (Cl. 26(a)) Not Applicable.
18. Employment of Vessel restricted to (state nature of service(s))
(Cl 5a)) Hook up, commissioning, accommodation and offshore Installation work such as I-Tube installation and Riser Installation and all other activities of RSPPM Project, within Vessel’s natural Capabilities and safe practices/
7
operations.
19. Charter Hire (state rate & currency) (Cl 10(a) & (d))
USD 31,000 … PDPR …
22. Payments …
Payments shall be made against acceptable, unconditional, revolving and irrevocable Letter of Credit issued at sight by the Charterer’s bank for USD 6,500,000 …
These L/C(s) to be opened, latest by 15th September 2005. However draft of L/C(s) should be provided to the Owners by 1st September 2005.
33. Law and arbitration (state Cl 31(a) or 31(b) or 31(c), as agreed, If 31c agreed also state place of arbitration) (Cl.31)
Clause 31(c) – Indian Arbitration and Conciliation Act, 1996 at Mumbai
…. . ”
17. I must provide some background before dealing with
other documents, as the faxed CPA sits at the center of this
dispute.
18. It appears that both parties signed the faxed CPA, and it
bears the applicant’s seal. However, it does not bear the
respondent’s seal. The applicant contends that it had sent the
original to the respondent on August 22nd. The respondent
did not return the original. Instead, on September 8th, the
8
respondent’s head office faxed a copy of the CPA to its local
office. [The top of the said fax shows the date and time as well
as the place from and to which it was sent; it reads “08-SEP-
2005 13:52 FROM IOEC HEAD OFFICE TO ALLAHVERDI”].
This faxed copy is signed by the respondent’s Project Director,
Mr. M. Sabbaghi.
19. The respondent’s Mr. Ali Rahmati provided the applicant
the faxed CPA on October 12th, according to the applicant’s
letter dated October 21st. In a letter dated October 26, the
respondent originally asserted that it never signed the faxed
CPA and that the document was forged.
20. Between the date on which the applicant sent the faxed
CPA – 22nd August – and the date on which the respondent
reportedly returned it to the applicant – 12th September,
ONGC had advised the respondent to get the vessel
combination certified before proceeding with a Riser
installation. ONGC’s letter dated 30th August stated that the
vessel did not have any past track record with riser
installations.
9
21. The applicant later expressed concern that the
respondent’s failure to return the original contract, i.e.,
charter party agreement, could result in undue delay. In an
email sent at 9:03 a.m. on 14th September, the applicant
stated, in relevant part, that:-
“... You would appreciate that it is imperative for us to have the charter party with us in order to initiate actions from various departments such as operations, fleet personnel, accounts etc to prepare for the said contract and in absence of this document we are not in a position to push for same. This will result in last minute hassles and delays. …”
22. The respondent’s email rejoinder came at 4:31 p.m. on
the same day. The relevant part reads as under:-
“…
The CPA of Gal Constructor and Malavya 5 is ready in our office and will be hand over to you.
…”
23. On September 15th, 2005, the applicant sent the
following email to the respondent. It reads in relevant part as
under:-
“1. Understand that charter party is ready in your office. However, we are yet to receive the same and
10
urgently require it to be circulated among the concerned departments so that they are prepared for the next contract. Will get in touch with your office again today for the same. …”
24. The respondent faxed a letter dated September 23rd,
2005 to the applicant. The letter asks the applicant to issue a
cheque for the outstanding amount due from the parties’
Phase I work. It further demands that the applicant grant the
respondent the sole and absolute right to sublet the vessel to
its subcontractor(s) at the agreed charter party rate. It
concludes by saying that the respondent “… can not conclude
the charter party agreement until the above issue are settled.”
25. On September 24th, the respondent met with Likpin
Engineers to discuss whether the applicant’s vessel could be
converted to perform a riser installation. Likpin surveyed the
vessel on 23rd September 2005 and, in the following minutes,
concluded that:-
“Taking into account the number of problems associated with the vessel, it is the conclusion of Likpin and IOEC that the Gal Constructor is not suitable as a riser installation. … the vessel size combined with the limited crane reach cannot be corrected or overcome and hence the vessel should not be chartered for riser installation operations.”
11
26. In a letter dated September 27th, 2005, the respondent
again asked the applicant to issue a cheque or remit
$186,618. It once again demanded that it be granted the right
to sublet the vessel and that until those issues were settled, it
could not conclude the CPA.
27. In a letter dated September 29th, 2005, the respondent
reiterated its demands, namely, that the applicant remit
$186,618 and that it provide the respondent with the sole and
absolute right to sublet the vessel combination. It admitted
that this payment had nothing to do with Phase II of the
project and thus “… has no connection with the current
negotiations and should be closed out immediately, so that
Phase II can begin on a clean slate.” It further stated that:
“… the sole and absolute right to sublet the vessel to IOEC subcontractors … is an essential element in IOEC work plan for Phase II. … Lack of, or delay in, the ability to exercise the sublet option will impact on IOEC work plan and also affect the cost schedule of RSPPM project and is not acceptable to IOEC. Please note that time is running short and in absence of GESCO’s immediate compliance with above two requirements IOEC may be compelled to take recourse to other options. …”
12
28. The applicant responded to the above with the following
letter dated 30th September 2005. The relevant part reads as
under:-
“… We are in the process of arranging funds to be remitted to you against the said amount and will confirm remittance as soon as possible. 2) Your request for sole and absolute right to sublet the vessel is not acceptable to us. The LOI for the contract has been issued by you on 23rd June 2005 after we mutually agreed on the terms and conditions of charter party. Thereafter, on your request, we have provided with you with signed originals of the charter party on 22nd August 2005 for your signatures. You have accepted the same and conformed to us vide your letter communique dated 14 September that he charter party has been signed and is ready in your office and will be handed over to us. Previous to that, you have also sent us letter saying that you confirm that the charter party will be finalized by 30 August 2005. While we have been provided a photocopy of the signed charter party by your office, it is now 30 September and rather than keeping your commitment and returning the original and issuing the L/C as promised, you are deliberately delaying the same.
29. The letter goes on to demand that the respondent
immediately issue the signed, stamped original charter party
agreement as well as the irrevocable line of credit. The
applicant further demanded that both tasks be completed by
1st October at 1200 hours.
13
30. Vide letter dated 10th October, the applicant informed the
respondent that the applicant’s vessel combination arrived at
P & V Channel, Mumbai on October 6th. Because it had yet to
receive the line of credit, it informed the respondent that it
could not proceed further with the mobilization of the vessel
combination. The applicant provided the respondent with an
invoice for mobilizing its vessel combination. It gave the
respondent another chance to comply with the purported
contract: “please note that contractual hire will begin as and
from 0000 hours of the 11th October 2005. We on our party
stand ready and willing to comply with all our obligations.”
31. In its October 10th letter, the respondent reiterated that
the terms of the agreement were still under negotiation and
that no contracted had been concluded. It objected to the
absence of a provision that provided the respondent with the
absolute right to sublet the vessel.
32. It also argued that the applicant’s vessel combination
was not fit for the agreed purpose. This issue is beyond the
scope of this decision, which limits itself to deciding whether
14
or not a contract containing an arbitration clause was formed.
While I have made mention of some of the other issues, such
as whether the vessel was fit for the agreed purpose, I need
not rehash each and every one. All matters, save for whether
the alleged contract/arbitration clause was formed, would be
more appropriately addressed by an Arbitral Tribunal.
33. The letter goes on to state that it would still consider
hiring the applicant’s vessel combination if it received the
right to sublet and also if the crane were made fit for the
purpose for which the respondent intended. On 18th October,
the respondent sent a letter in which it stated that it would
have to look for a vessel from an alternative provider. The
respondent said that it would treat the matter with the
applicant as “closed.” It concluded by asking the applicant to
pay the amount due for Phase I. It sent a letter on 20th
October reiterating the same.
34. On 21st October, the applicant sent a letter detailing the
sequence of events that had occurred between the parties.
Para 5 of the said letter is reproduced as under:-
15
“The Charter Party Agreements, two originals duly signed and stamped by us, were submitted to your office on 22nd August 2005 requesting you to forward us one original after execution of the same from your side. You never returned one original for our records. However, your Mr. Ali Rahmati had handed over to us a fax copy of the formal Charter Party document signed by your Mr.M. Sabbaghi when we had a meeting with him on 12 th September 2005. A copy of the same is enclosed herewith for your perusal.”
35. In its 26th October 26th, the respondent once again
claimed that the charter party remained unconcluded. It
alleged that the faxed copy of the charter party agreement was
“forged and the story of delivery false and concocted.”
Moreover, it stated that “since we have found the vessel
completely unfit for riser installation as the said vessel with
the present condition of the crane is not suitable at all,
therefore we thought fit to withdraw from the negotiation….”
It claimed that the applicant had misrepresented its vessel’s
ability to perform a riser installation. Thus, it thought this
misrepresentation had vitiated the negotiations. At this point,
it appeared that their relationship had officially soured.
36. In its letter dated 16th November, the respondent
reiterated much of what is already provided above. Of interest,
16
it stated that:-
“You are aware that initially, we intended to hire the vessel combination for only 170 days. However, since you agreed to take barge and AHT from us for 45-55 days, we agreed to extend the intended hire period from 170 days to 200 days and accordingly in this background the said LOI was issued. However, since thereafter you unilaterally declined to take our barge and AHT on the ground of difference in rate levels offered by us, we, in view of the said condition and in the light of your refusal to accept our barge and AHT, asked you for absolute subletting right of the said vessels to compensate us/minimize our expenses for risk of additional days than the originally intended 170 days. The correspondences which were exchanged between us make it aptly clear that negotiations and change in terms and conditions from your side continued even after issuance of LOI and therefore the question of concluding the CPA in respect of RSPPM project phase-II does not arise at all.”
37. In its December 2nd, 2005 letter, the respondent called
upon the applicant to arrange for a third party inspection of
the applicant’s vessel, in order to determine whether or not it
was suitable for riser installation.
38. In response, on 23rd January 2006, the applicant served
the respondent with a notice of arbitration. On 2nd February
2006, the respondent replied to the same.
17
39. With the relevant correspondence outlined above, I turn
to the parties’ main submissions. The applicant contends,
inter alia, that the faxed copy of the charter party agreement
(“faxed CPA”) dated 22nd August is a binding, concluded
contract. The applicant gives four reasons for this assertion.
40. First, the faxed CPA is signed by both parties. Second,
the applicant’s statement to this effect was not denied in the
pleadings [See the last page of the respondent’s
supplementary written submission of May 13th, 2005: (“…it
was not signed properly and but for the last page, the said fax
communication, did not bear signature on other page.”)
41. Third, the respondent admitted in its letter dated 14th
September that the original CPA “… is ready in our office and
will be hand to you.” The applicant argues that because the
applicant had already signed the original CPA, there was
nothing left for the respondent to do but sign. Hence, by
saying it was “ready”, I may infer that it was signed.
42. Fourth, the respondent’s letter of 10th October did not
18
deny the fact that the original CPA was signed by the
respondent and was waiting in the respondent’s office, even
though the applicant had asserted as much in its letter dated
30th August. It was not until 26th October that the respondent
deemed it necessary to deny this fact.
43. The respondent contends that because the original
signed copy was never given to the applicant, the parties were
in negotiations at all times. With respect to the faxed CPA, it
points to the fact that the respondent did not sign every page.
It gives further weight to the fact that the faxed copy was not
sent vide fax from the respondent to the applicant; rather, it
was first sent vide fax from the respondent’s main office to its
local branch.
44. Learned counsel for the respondent states in its written
submission that “…the respondent failed to even sign the
formal contract document that the applicant had sent to it for
its signature.” It argues that because the original CPA was
not signed by the respondent, the Court will have to find a
contract, if any, in the correspondence. According to Mulla:-
19
“In construing whether or not a particular agreement does or does not amount to a contract, the court would look for the intention of the parties, the nature of the transaction, the language employed in the informal agreement and other relevant circumstances. None of these is conclusive in itself. … The fact that the parties contemplate that the letters or an informal agreement would be superceded by a more formal one, does not prevent it from taking effect as a contract. If the letter of intent is acted upon, especially for a length of time, the court is likely to hold the parties bound by the contract.” [See Mulla, Indian Contract and Specific Relief Acts, 13th Edition at pages 317-318].
45. In Dresser Rand S.A. v. M/s. Bindal Agro Chemical
Ltd. & Another, AIR 2006 SC 871 at page 884 at para 34, a
two-Judge Bench of this Court emphasized that whether
letters of intent rise to the level of being a contract hinges on
the terms of the letter itself. It observed as under:-
“It is no double true that a Letter of Intent may be construed as a letter of acceptance if such intention is evident from its terms. It is not uncommon in contracts involving detailed procedure, in order to save time, to issue a letter of intent communicating the acceptance of the offer and asking the contractor to start the work with a stipulation that the detailed contract would be drawn up later. If such a letter is issued to the contractor, though it may be termed as a Letter of Intent, it may amount to acceptance of the offer resulting in a concluded contract … . But the question whether the letter of intent is merely an expression of intention to place an order in future or whether is a final acceptance of the offer thereby leading to a contract, is a matter
20
that has to be decided by reference to the terms of the letter.”
[Emphasis added].
46. The respondent’s main submission is that it never
actually concluded a contract and that, if anything, the
applicant mistakenly thought that the respondent’s LOI of 23rd
June was an offer. Why else would the applicant have sent its
acceptance on 4th? Its attack against the LOI as a contract is
two-fold. First, it argues that the parties cannot leave a major
piece of the contract open for future negotiation. Second, it
contends that the parties were not eye-to-eye, or ad idem on
the points.
47. According to the respondent, the applicant’s assumption
that the respondent’s 23rd June LOI read with the applicant’s
4th August letter is misplaced. The LOI of 23rd June read with
the applicant’s letter of 4th August does not form a contract
because a contract cannot leave a major part of its terms open
to future negotiation. The respondent relies on May &
Butcher Limited v. The King (1934) 2 KB 17, for the
proposition that an agreement in which some critical part of
21
the contract matter is left undetermined is no contract at all.
48. In its assertion that the applicant’s LOI of 23rd June was
conditional, it points to the following language from the same
LOI: “this agreement is subject to IOEC providing a suitable
barge and AHT acceptable to GE Shipping for a period of 45-
55 days on mutually agreed rates for commencement between
25th October and 10th November 05 for BHN MOL project
works.” The respondent’s supplying the barge to the applicant
for 45-55 days went unmet when the applicant said it would
not need this barge.
49. In addition, the respondent argues that this condition
was material to the contract, as evidenced by the fact that the
respondent only agreed to increase the duration of the work
from 170 to 200 days if it got paid for supplying the barge. By
doing so, the respondent was attempting to offset the costs it
would incur by having the applicant’s vessel combination for
an extra 30 days.
50. Furthermore, the respondent claims that no contract
could arise from its LOI of 23rd June because the parties were
22
not ad idem, i.e., in agreement on each point. Along these
lines, Chitty on Contracts [29th Edn. Vol.1 at page 134] has
observed:-
“When parties carry on lengthy negotiations, it may be difficult to say when and whether a contract has been concluded. The court must then look at the whole correspondence and decide, whether on its true construction, the parties had agreed to the same terms.”
51. In M/s. Rickmers Verwaltung Gimb H v. Indian Oil
Corporation Ltd., AIR 1999 SC 504 at page 509 para 12,
this Court reiterated this stand: “Unless from the
correspondence it can unequivocally and clearly emerge that
the parties were ad idem to the terms, it cannot be said that
an agreement had come into existence between them through
correspondence.” [See also: Dresser Rand S.A. v. M/s.
Bindal Agro Chemical Ltd. & Another, AIR 2006 SC 871 at
page 879 para 21 (affirming the same)]
52. The respondent argues that they were still negotiating
the terms and conditions. It cites to its letter of 13th August
and the applicant’s letter of 22nd August as evidence of
continued negotiations. In the respondent’s letter dated 13th
23
August, it suggests that a number of changes be made to the
“new draft contract.” [emphasis added]. “Draft” suggests that
nothing had been finalized. Moreover, the letter lists a
number of issues that were still open to negotiation. The
applicant’s letter of 22nd August, however, addressed the
proposed changes.
53. The respondent concedes that while it said it would sign
and finalize the contract by 30th August, it changed its mind
on 27th August and conveyed the message that it would not
enter the agreement until all outstanding issues were
resolved.
54. Like the applicant’s counsel, the respondent also makes
use of the fact that the applicant did not object to the
respondent’s letter dated 13th August. The applicant should
have said that there was no question of finalizing the contract
when it had already been finalized. I note that this argument
seems unfair because the applicant could not have gotten the
faxed CPA from the respondent until 8th September at the
earliest, as that is the date that appears on the fax. According
24
to the applicant, it received the faxed copy on 12th September.
55. Of course, all of the respondent’s arguments become
moot if the faxed CPA dated 22nd is valid. In the instant case,
the burden to prove that a valid contract containing an
arbitration clause existed first rested on the applicant, as it
was the applicant that was moving this Court. However, upon
producing the faxed CPA that, on its face, appears legitimate,
the onus shifted to the respondent to prove that it was forged.
It appears, prima facie, to be legitimate because it bears the
heading “08-SEP-2005 13:52 FROM IOEC HEAD OFFICE TO
ALLAHVERDI” (hereinafter the “fax header”). This is an
important piece of evidence that makes its genuineness more
probable than not. Hypothetically, the applicant could have
fabricated the fax header. But that is highly unlikely and
presumes much more than what is expected in normal human
conduct especially when that conduct concerns the forgery of
an executive officer’s signature. It should not be forgotten
that this case is between sophisticated companies, not warring
family members that dispute the authenticity of a will.
25
56. The respondent could argue that it handed over an
unsigned copy of the faxed CPA and that the applicant forged
it after the fact. Such an assumption is equally dubious. Why
would the respondent go through the trouble of returning the
applicant’s August 22nd CPA unsigned, when it had been
routed vide fax through its Head Office?
57. There is no evidence to suggest that the faxed CPA was
forged. To the contrary, the evidence we do have is the faxed
CPA bearing the parties’ signatures coupled with
correspondence between the parties. The correspondence, as
it is more than just a pleading, adds additional weight to the
applicant’s story. The applicant’s letter of 21st October
corroborates the allegation that Ali Rahmati delivered the
faxed CPA to the applicant on 12th September. The date of
delivery of 12th September fits the timeline provided on the fax
header, as the respondent could only have delivered the faxed
CPA after 8th September. Moreover, it appears that having
received the faxed CPA on 12th September, the applicant was
prompted to ask for the original vide email on 14th September.
Once again, the dates match up.
26
58. The fax header, on its face, suggests that the document
is genuine. This conclusion is bolstered by the above-
mentioned correspondence. Thus, I find that the applicant
had discharged its initial burden of sufficiently proving that
the faxed CPA was not forged. The onus shifted to the
respondent to prove that its signature was forged. With no
evidence to support its assertion, the respondent cannot
discharge its onus. Therefore, I find that the faxed CPA is
legitimate and is not a product of forgery. As such, I need not
look for the existence of a contract on the basis of the LOI of
23rd June.
59. The question then becomes whether the faxed CPA is
valid under the relevant law. Here, the purported contract
provides that the Arbitration and Conciliation Act, 1996 (26 of
1996) is to be used. [page 3 of faxed CPA dated 22 August
2005]. In the preceding contract the same Act was used.
Therefore, it comes as no surprise that the parties have not
objected to the same in the instant case.
60. Section 7 of the Arbitration and Conciliation Act, 1996
27
(26 of 1996) provides:
(1)In this part, “arbitration agreement” means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.
(2)An arbitration agreement may be in the form of an arbitration clause or in the form of a separate agreement.
(3) An arbitration agreement shall be in writing .
(4) An arbitration agreement is in writing if it is contained in–
(a) a document signed by the parties ;
(b) an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement; or
(c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.
(5)The reference in a contract to a document
containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.
61. Section 7 squarely deals with the present controversy.
This Court has taken note of Section 7(3) & 7(A)(a)’s
requirement that the arbitration agreement be in writing and
28
signed by the parties. According to the learned counsel for the
applicant, affixing a seal under section 7 of the Act is not a
requirement. [See: Bihar State Mineral Development
Corporation & Another v. Encon Builders (1) (P) Ltd.,
(2003) 7 SCC 418 at page 423 para 13 (one of the essential
elements of an arbitration agreement is that “the parties must
agree in writing to be bound by the decision of such tribunal.”)
and K.K. Modi v. K.N. Modi & Others, (1998) 3 SCC 573 at
page 585 para 21 (“there are, of course, the statutory
requirements of a written agreement …. Vide Section 2
Arbitration Act, 1940 and Section 7 Arbitration and
Conciliation Act, 1996.”)
62. The respondent makes much of the fact that the “faxed
CPA” of August 22nd is (1) a copy, not the original; (2) is
stamped by one, not by both parties; (3) one of the parties did
not sign every page; and (4) it was first sent vide fax.
63. Section 7 defeats all four assertions. First, there is no
requirement that the arbitration agreement be an original.
Where the statute has gone to great lengths to define exactly
what is meant by the term “in writing,” we are precluded from
29
adding another term to definition. Indeed, “it is contrary to all
rules of construction to read words into an Act unless it is
absolutely necessary to do so.” [See: Justice G.P. Singh’s
Principles of Statutory Interpretation, 11th Edition, 2008, at page
62.63, citing to Renula Bose (Smt.) v. Rai Manmathnath
Bose, AIR 1945 PC 108, p. 110; Stock v. Frank Jones
(Tiptan) Ltd., (1978) 1 All ER 948, p.951; Assessing
Authority-Cum-Excise and Taxation Officer, Gurgaon &
Another v. East India Cotton Mfg. Co. Ltd., Faridabad
(1981) 3 SCC 531].
64. An exception to this rule can be made. But before
adding words to a statute, “… the Court must be abundantly
clear of three matters: (1) the intended purpose of the statute
or provision in question, (2) that by inadvertence the
draftsman and Parliament failed to give effect to that purpose
in the provision in question; and (3) the substance of the
provision Parliament would have used, had the error in the
Bill been noticed.” [See: Justice G.P. Singh’s Principles of
Statutory Interpretation, 11th Edition, 2008 at page 75 citing to
30
Inco Europe Ltd. v. First Choice Distribution (a firm) (2000) 2 All
ER 109, at page 115 (HL)]. As I mention below, one of the
main objectives of the Arbitration and Conciliation Act, 1996
is to minimise the role of the Court; adding additional
requirements to the Act is antithetical to such a goal.
65. Second, the plain language of Section 7 once again
governs my conclusion. Section 7 does not require that the
parties stamp the agreement. It would be incorrect to disturb
the Parliament’s intention when it is so clearly stated and
when it in no way conflicts with the Constitution.
66. Third, nothing in Section 7 suggests that the parties
must sign every page. Once again, if I take the respondent’s
argument to its logical conclusion, I would have no choice but
to read language into the Act that is not there. Even if the
faxed CPA is construed as a “document,” it need only be
“signed by the parties” pursuant to Section 7(4)(a). Every page
does not need to be signed. If it is considered a “document,”
then this requirement would be met. As established above,
both parties signed the faxed CPA in the signature box at the
31
bottom of Part I. That said, the faxed CPA more closely fits
within Section 7(4)(b)’s requirements.
67. Fourth, Section 7(4)(b) states that an agreement is in
writing if it is contained in “an exchange of letters, telex,
telegrams or other means of telecommunication which provide
a record of the agreement.” This section covers agreements
that are sent via facsimile (“fax”) as they are “other means of
telecommunication”. “Fax” is defined as “a machine that
scans documents electronically and transmits a photographic
image of the contents to a receiving machine by telephone
line” or “a document received by such a machine.” [See:
Chambers 21st Century Dictionary, Allied Publisher’s Limited
(1996)]. This definition clearly provides that a fax falls under
“other means of telecommunication.” Thus, faxed agreements
are acceptable under Section 7 of the Act.
68. Section 7(4)(b) further requires us to ask whether a
record of the agreement is found in the telecommunication, in
this case a fax. What could be a better record of the agreement
than the signatures of the parties themselves? As noted above,
with no evidence to indicate that the respondent’s signature
32
was forged, the faxed CPA stands on its own as the record of
agreement. Likewise, Section 7(4)(b) stands satisfied.
69. The court has to translate the legislative intention
especially when viewed in light of one of the Act’s “main
objectives”: “to minimise the supervisory role of Courts in the
arbitral process. [See: Statements of Objects and Reasons of
Section 4(v] of the Act].
70. If this Court adds a number of extra requirements such
as stamps, seals and originals, we would be enhancing our
role, not minimising it. Moreover, the cost of doing business
would increase. It takes time to implement such formalities.
What is even more worrisome is that the parties’ intention to
arbitrate would be foiled by formality.
71. Such a stance would run counter to the very idea of
arbitration, wherein tribunals all over the world generally
bend over backwards to ensure that the parties’ intention to
arbitrate is upheld. Adding technicalities disturbs the parties’
“autonomy of the will” (l’ autonomie de la volonté), i.e., their
wishes. [For a general discussion on this doctrine see Law and
33
Practice of International Commercial Arbitration, Alan Redfern
and Martin Hunter, Street & Maxwell, London, 1986 at pages
4 and 53].
72. Technicalities like stamps, seals and even signatures are
red tape that have to be removed before the parties can get
what they really want – an efficient, effective and potentially
cheap resolution of their dispute. The autonomie de la volonté
doctrine is enshrined in the policy objectives of the United
Nations Commission on International Trade Law (“UNCITRAL”)
Model Law on International Commercial Arbitration, 1985, on
which our Arbitration Act is based. [See Preamble to the Act].
The courts must implement legislative intention. It would be
improper and undesirable for the courts to add a number of
extra formalities not envisaged by the legislation. The courts
directions should be to achieve the legislative intention. The
courts must implement legislative intention. It would be
improper and undesirable for the courts to add a number of
extra formalities not envisaged by the legislation. The courts
directions should be to achieve the legislative intention.
34
73. One of the objectives of the UNCITRAL Model Law reads
as under:-
“the liberalization of international commercial arbitration by limiting the role of national courts, and by giving effect to the doctrine “autonomy of will,” allowing the parties the freedom to choose how their disputes should be determined.” [See Policy Objectives adopted by UNCITRAL in the preparation of the Model Law, as cited in Law and Practice of International Commercial Arbitration, Alan Redfern and Martin Hunter, Street & Maxwell, London (1986) at page 388 (citing UN doc.A/CN.9/07, paras 16-27].
74. It goes without saying, but in the interest of providing the
parties a comprehensive review of their arguments, I note that
once it is established that the faxed CPA is valid, it follows
that a valid contract and a valid arbitration clause exist. This
contract, the faxed CPA, does not suffer from a conditional
clause, as did the Letter of Intent. Thus, the respondent’s
argument that the parties were not ad idem must fail.
75. I have heard the learned counsel appearing for the
applicant and the respondent at length. I have carefully
reviewed the entire correspondence between the parties. The
charter party agreement that had been signed by the applicant
35
and the respondent clearly indicated that the parties have
entered into a valid and concluded contract. The other
correspondence between the parties also leads to a definite
conclusion: the parties have entered into a valid contract
containing an arbitration clause. Since a dispute has arisen
between the applicant and the respondent, it needs to be
referred to the arbitrator.
76. On consideration of the totality of the facts and
circumstances, I am clearly of the opinion that the applicant is
entitled in law to an order for appointment of a sole arbitrator.
Consequently, I request Hon’ble Justice S.N. Variava, the
retired Judge of the Supreme Court, to accept this arbitration.
The learned arbitrator would be at liberty to fix his own fee. I
direct the parties to appear before the learned arbitrator on 8th
September, 2008 or any date convenient to the learned
arbitrator.
77. Before parting with this arbitration petition, I would like
to make it abundantly clear that the learned arbitrator shall
not be bound by any observations which have been made in
36
this judgment. The observations have been made only to
decide this arbitration petition.
78. The Registry is directed to communicate this order to the
learned arbitrator to enable him to enter upon the reference
and decide the matter as expeditiously as practicable.
79. Consequently, this arbitration petition is allowed and
disposed of. In the peculiar facts and circumstances of this
case, I direct the parties to bear their own costs.
…….……………………..J. (Dalveer Bhandari)
New Delhi;
August 25, 2008.
37